片石混凝土擋土墻施工方案資料內(nèi)容僅供參考,如有不當(dāng)或者侵權(quán),請(qǐng)聯(lián)系本人改正或者刪除。合三路滑坡整治工程施工組織設(shè)計(jì)編制日期:二0一二年七月目錄編制說(shuō)明········································編制依據(jù)及原則··································2.1編制依據(jù)·····································2.2編制原則·····································三、工程管理目標(biāo)·····································四、工程概況·········································4.1工程地理位置·································4.2施工場(chǎng)地周圍環(huán)境·····························4.3工程地質(zhì)·····································4.4工程范圍及規(guī)模·······························4.5工程主要特點(diǎn)·································五、設(shè)備、人員動(dòng)員周期及材料組織供應(yīng)··················5.1人員、設(shè)備動(dòng)員周期····························5.2技術(shù)準(zhǔn)備······································5.3材料組織供應(yīng)··································六、施工準(zhǔn)備及臨時(shí)設(shè)施·······························6.1臨時(shí)房屋設(shè)施··································6.2水、電設(shè)施····································施工組織機(jī)構(gòu)的建立·······························7.1組織機(jī)構(gòu)設(shè)置·································7.2施工組織管理機(jī)構(gòu)的運(yùn)作························八、施工計(jì)劃··········································工期進(jìn)度計(jì)劃·································各施工隊(duì)伍人員構(gòu)成···························施工設(shè)備計(jì)劃·································材料供應(yīng)計(jì)劃及措施···························九、施工方法··········································9.1擋土墻構(gòu)造····································9.2填土施工要求··································9.3施工工藝流程··································9.4衡重式擋土墻施工······························十、工程質(zhì)量保證措施···································10.1技術(shù)保證措施·································10.2質(zhì)量管理措施·································10.3施工組織措施·································十一、安全保證措施:····································11.1安全施工主要措施·····························11.2安全保證體系·································十二、文明施工,加強(qiáng)環(huán)保······························12.1文明施工·····································12.2施工現(xiàn)場(chǎng)環(huán)境保護(hù)····························12.3綠化工作措施·································十三、施工進(jìn)度保證措施:································13.1一般保證措施·································13.2組織保證措施·································13.3技術(shù)保證措施·································13.4.經(jīng)濟(jì)保證措施··································13.5.合同保證措施··································十四、雨季施工技術(shù)措施·································十五、采用新工藝新技術(shù)成本節(jié)約措施·····················十六、施工現(xiàn)場(chǎng)平面布置圖·······························16.1施工總平面布置································16.2施工總平面布置······························· 施工組織設(shè)計(jì)編制說(shuō)明在編制本標(biāo)的工程施工組織設(shè)計(jì)的過(guò)程中,我們仔細(xì)閱讀了招標(biāo)文件。在認(rèn)真閱讀和充分理解設(shè)計(jì)意圖的基礎(chǔ)上,結(jié)合我公司的施工經(jīng)驗(yàn),根據(jù)施工場(chǎng)地狀況,以信守合同、確保質(zhì)量工期、安全文明生產(chǎn)、持續(xù)注重環(huán)保、合理控制工程造價(jià)為指導(dǎo)思想,經(jīng)過(guò)細(xì)心研究形成了本施工組織設(shè)計(jì)主要內(nèi)容,其中闡述了本工程實(shí)施時(shí)的施工設(shè)備、施工計(jì)劃安排、施工技術(shù)方案、施工組織實(shí)施方法及順序,確保工程質(zhì)量和工期的主要措施,以及安全、文明、環(huán)境保護(hù)措施。在編制過(guò)程中,擇優(yōu)選擇施工方案,做到科學(xué)合理、經(jīng)濟(jì)方便,為工程施工統(tǒng)籌安排提供技術(shù)支持。編制依據(jù)及原則2.1編制依據(jù)1、擋土墻工程招標(biāo)文件、設(shè)計(jì)圖紙及有關(guān)參考資料。2、我公司的施工現(xiàn)場(chǎng)考察及標(biāo)前有關(guān)會(huì)議精神。3、《公路工程技術(shù)標(biāo)準(zhǔn)》(JTGB01-);《公路路基設(shè)計(jì)規(guī)范》(JTGD30-);《建筑邊坡工程技術(shù)規(guī)范》(GB50330-202);《建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范》(GB50007-);《公路水泥混凝土路面設(shè)計(jì)規(guī)范》(JTGD40-);及現(xiàn)行國(guó)家和相關(guān)標(biāo)準(zhǔn)及規(guī)范。2.2編制原則1、根據(jù)工程特點(diǎn)、自然條件及工期要求,在確保工程質(zhì)量與施工安全的前提下,采用科學(xué)合理的施工作業(yè)方法,籌劃人力安排,調(diào)配所需的機(jī)械設(shè)備,以滿足施工生產(chǎn)的需要,確保人力、物力充分發(fā)揮作用,使績(jī)效最大化。2、詳細(xì)辨別各分項(xiàng)工程之間的施工順序和相互制約關(guān)系,認(rèn)真研究,統(tǒng)籌安排,理清控制因素與被控制因素,形成連貫合理的施工工藝流程。3、對(duì)施工的重點(diǎn)工序和難點(diǎn)工序進(jìn)行科學(xué)分析、采用成熟的施工技術(shù)和經(jīng)驗(yàn),做到切實(shí)可行、合理經(jīng)濟(jì)。4、根據(jù)各級(jí)政府部門質(zhì)量、安全、文明施工、環(huán)境保護(hù)要求,建立各項(xiàng)保證體系前制定完善的保證措施,確保施工生產(chǎn)各項(xiàng)管理目標(biāo)的順利實(shí)現(xiàn)。5、充分利用我公司人力資源、機(jī)具設(shè)備、可動(dòng)員資源以及工程區(qū)域內(nèi)可利用的社會(huì)資源。三、工程管理目標(biāo)工期目標(biāo):90天質(zhì)量目標(biāo):工程一次驗(yàn)收合格率100%,合同履約率達(dá)100%。安全目標(biāo):執(zhí)行國(guó)家頒布的各種施工安全規(guī)程,杜絕傷亡、重大交通、火災(zāi)、機(jī)損等事故。環(huán)境目標(biāo):保護(hù)環(huán)境,文明施工。根據(jù)國(guó)家有關(guān)政策,保護(hù)好沿線自然生態(tài)環(huán)境,滅塵降噪,減少污染。掛牌上崗、文明施工。四、工程概況4.1工程地理位置合三路為雙流至簡(jiǎn)陽(yáng)三岔湖一旅游公路,按三級(jí)公路標(biāo)準(zhǔn)修建;本次滑坡(含路基垮塌)3處工點(diǎn)主要集中在白三路K8+365~K9+133路段范圍內(nèi)。4.2工程范圍及規(guī)模本項(xiàng)目裝置區(qū)域范圍內(nèi)的擋土墻施工將結(jié)合地形,根據(jù)地質(zhì)報(bào)告及埋深構(gòu)造,采用衡重式擋土墻,確定擋土墻的基槽開(kāi)挖的深度和放坡,并最大限度減少土石方工程量。施工單位按照擋土墻的范圍進(jìn)行施工和回填。4.3工程主要特點(diǎn)1、本工程土石方量大,施工作業(yè)面長(zhǎng),工期短,且各段分段施工采用不同類型的擋土墻施工。2、施工時(shí)要充分考慮在施工過(guò)程中對(duì)相鄰工廠生產(chǎn)和場(chǎng)平施工單位的影響,做好安全防范措施。3、本工程擋土墻分為衡重式C20片石擋土墻。4、施工時(shí)需組織好基槽開(kāi)挖、堆放、運(yùn)輸、工程測(cè)量等作業(yè),做到安全文明施工。5、在擋土墻施工過(guò)程中要與場(chǎng)平施工單位密切配合,確保擋土墻后填料對(duì)稱、均勻回填和場(chǎng)平回填質(zhì)量。五、設(shè)備、人員動(dòng)員周期及材料組織供應(yīng)5.1人員、設(shè)備動(dòng)員周期1、我司有成套的施工設(shè)備,有豐富的工程施工經(jīng)驗(yàn),擁有各類工程技術(shù)人員、施工管理人員和熟練的機(jī)械操作手和熟練的勞工隊(duì)伍。在簽署合同協(xié)議后在業(yè)主規(guī)定的進(jìn)場(chǎng)時(shí)間內(nèi),組織人員、施工機(jī)械及設(shè)備進(jìn)場(chǎng)并展開(kāi)作業(yè)。進(jìn)場(chǎng)后主要工作是清理現(xiàn)場(chǎng)、接通施工點(diǎn)的水電、通訊,安裝機(jī)械、搭建臨時(shí)房屋、水池、作好混凝土、砂漿施工配合比等。2、各種專用設(shè)備、材料進(jìn)場(chǎng)采用汽車運(yùn)輸?shù)姆绞竭M(jìn)行,并安裝、調(diào)試完畢,能及時(shí)投入生產(chǎn)使用。3、在施工設(shè)備進(jìn)場(chǎng)的同時(shí),組織所有進(jìn)入該項(xiàng)目的工程技術(shù)人員和工程管理人員分批進(jìn)入施工現(xiàn)場(chǎng),開(kāi)始項(xiàng)目經(jīng)理部的籌建工作。4、人員安排表序號(hào)人員人數(shù)備注1管理人員42技術(shù)人員63施工人員505.2技術(shù)準(zhǔn)備人員進(jìn)場(chǎng)后立即開(kāi)展技術(shù)準(zhǔn)備工作,技術(shù)準(zhǔn)備工作分為內(nèi)業(yè)準(zhǔn)備工作和外業(yè)準(zhǔn)備工作。1、內(nèi)業(yè)準(zhǔn)備1)、審核、分析設(shè)計(jì)圖紙,提供實(shí)施性施工圖紙。2)、臨時(shí)工程的設(shè)計(jì)與施工,包括料場(chǎng)建設(shè)、臨時(shí)用房修建、臨時(shí)施工便道的修建等。3)、編寫(xiě)實(shí)施性施工組織設(shè)計(jì),對(duì)施工具體人員安排、機(jī)械設(shè)備配備、場(chǎng)地布置、施工工序、施工進(jìn)度都做具體周密的說(shuō)明。4)、編制質(zhì)量計(jì)劃,落實(shí)質(zhì)量管理體系、提出質(zhì)量管理標(biāo)準(zhǔn)、明確保障措施。5)、編制施工工藝標(biāo)準(zhǔn)及保證措施,一切要以技術(shù)規(guī)范、設(shè)計(jì)圖紙為準(zhǔn)則。6)、制定技術(shù)管理辦法和實(shí)施細(xì)則,盡量作到細(xì)而準(zhǔn)。7)、進(jìn)行崗前培訓(xùn),著重培訓(xùn)員工的崗位職業(yè)技能、工程質(zhì)量意識(shí)、安全生產(chǎn)意識(shí)。2、外業(yè)準(zhǔn)備1)、租賃項(xiàng)目部辦公和生活用房。2)、平整臨時(shí)場(chǎng)地,清理施工現(xiàn)場(chǎng)。3)、測(cè)量控制體系的建立。4)、各類實(shí)驗(yàn)儀器的配備。5)、各類施工設(shè)備的安裝和調(diào)試。5.3材料組織供應(yīng)1、水泥:擬采用水泥廠生產(chǎn)的合格水泥進(jìn)行施工,用汽車運(yùn)至施工現(xiàn)場(chǎng)。2、鋼材(鋼筋)擬從市區(qū)或就近購(gòu)買,用汽車運(yùn)至施工現(xiàn)場(chǎng)。3、碎石、砂:擬從沿線各料場(chǎng)購(gòu)買,用汽車運(yùn)至施工現(xiàn)場(chǎng)。其余小型材料就近組織購(gòu)買,運(yùn)抵施工現(xiàn)場(chǎng)。六、施工準(zhǔn)備及臨時(shí)設(shè)施6.1臨時(shí)房屋設(shè)施項(xiàng)目經(jīng)理部準(zhǔn)備在現(xiàn)場(chǎng)附近租用民房。以方便與業(yè)主、監(jiān)理、當(dāng)?shù)卣嚷?lián)系。6.2水、電設(shè)施1、施工用水、用電沿線水源豐富,在工地修建蓄水池,經(jīng)過(guò)潛水泵、輸水管送至施工點(diǎn)的方法解決。2、生產(chǎn)、生活用電生產(chǎn)用電采用化工園區(qū)內(nèi)的高壓電源。生活用電可取自當(dāng)?shù)鼐用裼秒娋W(wǎng)。生活用水則取自當(dāng)?shù)仫嬘盟c(diǎn)。在施工區(qū),生活用電可下接高壓線或自備發(fā)電機(jī)組供給,生活用水則取自當(dāng)?shù)仫嬘盟c(diǎn)或自備井供應(yīng)。混凝土拌和場(chǎng)混凝土由商混站用商混車運(yùn)送至現(xiàn)場(chǎng)。4、交通、通訊項(xiàng)目經(jīng)理部安裝電話、傳真機(jī),以便于和業(yè)主、監(jiān)理及當(dāng)?shù)卣3致?lián)系。每個(gè)施工隊(duì)用手機(jī)于與經(jīng)理部保持聯(lián)系,協(xié)調(diào)工作,保持項(xiàng)目部與施工隊(duì)統(tǒng)一指揮、協(xié)調(diào)。充分利用電腦、電子信箱,與外界進(jìn)行信息交換與溝通,獲取對(duì)本項(xiàng)目有用的信息。項(xiàng)目部配備行政車、材料采購(gòu)車、生活用車各一臺(tái),解決各施工隊(duì)的交通、材料及平時(shí)生活問(wèn)題。施工組織機(jī)構(gòu)的建立7.1組織機(jī)構(gòu)設(shè)置1、我公司高度重視本工程,一旦中標(biāo)本工程將列為我公司的重點(diǎn)工程,為優(yōu)質(zhì)按期完成本工程施工任務(wù),在全公司范圍內(nèi)抽調(diào)管理水平高、具有豐富施工經(jīng)驗(yàn)的人員組成施工項(xiàng)目經(jīng)理部。項(xiàng)目經(jīng)理部下設(shè)六個(gè)職能部門,配備足夠數(shù)量且具有施工管理和施工經(jīng)驗(yàn)的技術(shù)及各專業(yè)骨干,負(fù)責(zé)工程建設(shè)全過(guò)程的管理、組織、協(xié)調(diào),以確保各項(xiàng)工程管理目標(biāo)的實(shí)現(xiàn),按對(duì)項(xiàng)目法人的要求控制工程進(jìn)度、質(zhì)量、安全和文明施工等。2、項(xiàng)目經(jīng)理部設(shè)項(xiàng)目經(jīng)理一人,總工程師一人,調(diào)度指揮一人,副經(jīng)理一人,項(xiàng)目部?jī)?nèi)設(shè)施工技術(shù)科、安全質(zhì)量科、計(jì)劃財(cái)務(wù)科、物資設(shè)備科、測(cè)試中心、綜合辦公室六個(gè)職能部門。7.2施工組織管理機(jī)構(gòu)的運(yùn)作1、主要管理人員配備、項(xiàng)目經(jīng)理部的項(xiàng)目經(jīng)理由本公司具有豐富施工經(jīng)驗(yàn)、承擔(dān)過(guò)類似工程建設(shè)的工程師擔(dān)任,負(fù)責(zé)施工生產(chǎn)過(guò)程的組織、指揮及協(xié)調(diào)工作。項(xiàng)目經(jīng)理部的副經(jīng)理和總工程師按各自分管責(zé)任,指派有豐富經(jīng)驗(yàn)的人員擔(dān)任。、專業(yè)技術(shù)負(fù)責(zé)人,按照相關(guān)專業(yè),配備多人配合項(xiàng)目總工程師做好施工技術(shù)管理工作。2、管理職能部門及工作1)、項(xiàng)目經(jīng)理部的管理機(jī)構(gòu)為施工技術(shù)科、安全質(zhì)量科、計(jì)劃財(cái)務(wù)科、物資設(shè)備科、測(cè)試中心、綜合辦公室六個(gè)職能部門。每個(gè)部門按責(zé)任制執(zhí)行,有條不紊開(kāi)展工作。2)、項(xiàng)目經(jīng)理部的施工技術(shù)科、安全質(zhì)量科等部門派專人指導(dǎo)現(xiàn)場(chǎng)的相關(guān)工作,并與業(yè)主、監(jiān)理、設(shè)計(jì)院及有關(guān)單位、部門保持有效聯(lián)系,及時(shí)解決施工中出現(xiàn)的各種問(wèn)題。八、施工計(jì)劃工期進(jìn)度計(jì)劃1、本工程施工總工期為90天日歷天。2、開(kāi)工日期以甲方下達(dá)的開(kāi)工令為準(zhǔn),在規(guī)定的施工日歷天之內(nèi),全部工程應(yīng)完成,并經(jīng)過(guò)驗(yàn)收。3、施工工期進(jìn)度計(jì)劃:根據(jù)業(yè)主的要求,我公司將該工程的工期定為90天:1)、施工準(zhǔn)備期:在接到業(yè)主的中標(biāo)通知書(shū)后一周內(nèi),我公司將組織人員進(jìn)入施工現(xiàn)場(chǎng)開(kāi)始施工前期工作,作施工前的各項(xiàng)準(zhǔn)備工作。預(yù)計(jì)在5天內(nèi)完成。2)、施工期:在準(zhǔn)備工作完成后,將展開(kāi)全面施工作業(yè),采用流水作業(yè)分隊(duì)分段施工,將按照事前制定的計(jì)劃有條不紊的進(jìn)行各項(xiàng)工作,預(yù)計(jì)在77天內(nèi)完成。3)、施工收尾及交驗(yàn)期:主體工程完工后,在最后8天內(nèi)應(yīng)加緊其余零星工程的施工和工程的全面清理工作,以達(dá)到業(yè)主要求的工程交工條件。4、我公司就上述工期節(jié)點(diǎn)要求,結(jié)合施工現(xiàn)場(chǎng)實(shí)際情況,對(duì)本工程施工計(jì)劃進(jìn)行了科學(xué)合理的安排,根據(jù)我公司以往施工經(jīng)驗(yàn),我們完全有能力在甲方指定的工期內(nèi)順利完成本工程。施工設(shè)備計(jì)劃1、為滿足施工生產(chǎn),落實(shí)施工機(jī)械配置計(jì)劃,以單位主要領(lǐng)導(dǎo)掛帥,快速抽調(diào)足夠數(shù)量性能良好的機(jī)械設(shè)備運(yùn)抵施工現(xiàn)場(chǎng)。對(duì)于個(gè)別類型的機(jī)械,數(shù)量不足的,將采取新購(gòu)或租賃的辦法補(bǔ)齊。2、主要機(jī)械設(shè)備配制序號(hào)機(jī)械名稱規(guī)格單位數(shù)量1內(nèi)燃空壓機(jī)V-3.5/3臺(tái)62混凝土振動(dòng)棒ZN35臺(tái)43混凝土攪拌機(jī)J500臺(tái)24抽水機(jī)ф100mm臺(tái)35履帶式挖掘機(jī)1m3臺(tái)16自動(dòng)翻斗車5t臺(tái)47鋼筋切割機(jī)HGQ40臺(tái)28鋼筋彎曲機(jī)HGW40臺(tái)29全站儀NTS-202臺(tái)210經(jīng)緯儀M310378臺(tái)211水準(zhǔn)儀M214516臺(tái)212電焊機(jī)BX1-500臺(tái)28.3各施工隊(duì)伍人員構(gòu)成1、項(xiàng)目經(jīng)理部在選擇施工隊(duì)伍時(shí),注重進(jìn)場(chǎng)隊(duì)伍的施工信譽(yù)、人員的技術(shù)素質(zhì)、配套情況及近階段的實(shí)際表現(xiàn),施工能力和施工質(zhì)量能否滿足需要。2、對(duì)進(jìn)場(chǎng)的隊(duì)伍實(shí)施動(dòng)態(tài)管理,不允許擅自擴(kuò)充和隨意抽調(diào),以確保施工隊(duì)伍的素質(zhì)和人員相對(duì)穩(wěn)定。3、未經(jīng)有關(guān)質(zhì)量、安全方面培訓(xùn)的操作工人不許上崗。凡進(jìn)場(chǎng)的隊(duì)伍必須配備一定數(shù)量的專職協(xié)調(diào)質(zhì)量、安全的管理人員。材料供應(yīng)計(jì)劃及措施1、本工程材料供應(yīng)由項(xiàng)目經(jīng)理部統(tǒng)一負(fù)責(zé)。材料供應(yīng)將采取統(tǒng)一采購(gòu)、統(tǒng)一調(diào)運(yùn)的原則進(jìn)行,所有材料的供應(yīng)均應(yīng)符合業(yè)主提出的要求,并得到監(jiān)理工程師的同意。2、所有用于本工程的材料、貨物和各種類型的物品,無(wú)論是天然狀態(tài)的、經(jīng)過(guò)加工的或者是制造出來(lái)的均應(yīng)該是新的,并符合合同要求的類型和質(zhì)量。3、作為用于正式工程中的材料和制成品的樣品(包括材料樣品和工地現(xiàn)場(chǎng)制成品的樣品),經(jīng)監(jiān)理工程師批準(zhǔn)后,由施工單位妥善保存至監(jiān)理工程師準(zhǔn)許其自行處理時(shí)為止。4、當(dāng)技術(shù)規(guī)范或有關(guān)的參照標(biāo)準(zhǔn)要求有材料生產(chǎn)商和供應(yīng)商的測(cè)試證明書(shū)時(shí),施工單位將提供每份證明書(shū)的原件或復(fù)印件。證明書(shū)對(duì)被證明的材料采用系列編號(hào)或參考編號(hào),使人一目了然。證明書(shū)中包括有關(guān)參考標(biāo)準(zhǔn)和技術(shù)規(guī)定條款所要求的內(nèi)容。5、施工單位將對(duì)全部材料的取樣和測(cè)試,施工工藝,設(shè)備和量測(cè)裝置進(jìn)行日常檢查,以控制其質(zhì)量并保證它們與技術(shù)規(guī)定和批準(zhǔn)的試樣相一致。6、施工單位做材料與試樣的試驗(yàn),委托由監(jiān)理工程師批準(zhǔn)的、具有相應(yīng)資質(zhì)的試驗(yàn)單位來(lái)承擔(dān)。7、材料質(zhì)量是工程質(zhì)量的生命,為此必須嚴(yán)格控制材料進(jìn)貨渠道,把好材料質(zhì)量關(guān),做好質(zhì)量自檢工作。九、施工組織①、施工準(zhǔn)備1.1圖紙審核及原地貌復(fù)測(cè),發(fā)現(xiàn)圖紙有誤或現(xiàn)場(chǎng)與設(shè)計(jì)不符的及時(shí)上報(bào)相關(guān)人員進(jìn)行復(fù)查。1.2擋墻片石選用質(zhì)地堅(jiān)實(shí)、無(wú)風(fēng)化剝落及抗壓強(qiáng)度不低于MU30片石。1.3選用C20混凝土。1.4修建臨時(shí)施工便道、布置材料堆放場(chǎng)地及備料。2、施工工藝流程(見(jiàn)下圖)施工準(zhǔn)備測(cè)量放線流水導(dǎo)流挖除換填機(jī)械碾壓夯實(shí)基槽開(kāi)挖地基承載力檢測(cè)立模加固安裝泄水孔做濾水層澆筑混凝土并人工擺片石拆除模板養(yǎng)護(hù)3、施工方案3.1施工場(chǎng)地準(zhǔn)備3.1.1測(cè)量放線,定出樁位中心線及開(kāi)挖邊界線。3.1.2清除擋墻用地范圍內(nèi)的樹(shù)樁、雜草、垃圾等所有障礙物;在基槽周圍挖設(shè)排水溝,排除地表水。3.2開(kāi)挖
3.2.1基槽開(kāi)挖采用1.2m3斗容量的日立液壓挖掘機(jī)一臺(tái)進(jìn)行基槽開(kāi)挖,開(kāi)挖長(zhǎng)度根據(jù)現(xiàn)場(chǎng)地質(zhì)情況進(jìn)行分段開(kāi)挖,每段15或20米。機(jī)械開(kāi)挖至基底設(shè)計(jì)標(biāo)高以上10cm時(shí),重新進(jìn)行測(cè)量放樣,確定開(kāi)挖正確不偏位的情況下改用人工進(jìn)行基底清理,確保基底符合設(shè)計(jì)及相關(guān)規(guī)范要求。3.3基礎(chǔ)施工3.3.1片石混凝土采用沿槽澆筑,澆筑過(guò)程中,選用高性能砼,嚴(yán)格控制配合比,砼中片石的摻量控制在25%范圍以內(nèi)。片石用人工擺放,分散布置。
3.3.2采用插入式50型振動(dòng)棒進(jìn)行振搗,砼振搗密實(shí),振搗過(guò)程中快插慢抽。無(wú)漏振,無(wú)蜂窩麻面等。3.3.3砼澆筑完成后及時(shí)養(yǎng)護(hù),防止由于內(nèi)外溫差過(guò)大而產(chǎn)生砼收縮開(kāi)裂。3.3.4在片石砼澆筑過(guò)程中,現(xiàn)場(chǎng)取樣制作砼試件,標(biāo)準(zhǔn)養(yǎng)護(hù)28天后送中心試驗(yàn)室檢測(cè)。3.4墻身澆筑
3.4.1基礎(chǔ)澆筑完成后,根據(jù)設(shè)計(jì)圖及現(xiàn)場(chǎng)高程放出擋墻澆筑邊線。3.4.2模板安裝.(1)模板采用膠合木模板,禁止使用有缺角、破損的模板。(2)保證混凝土結(jié)構(gòu)和構(gòu)件各部分設(shè)計(jì)形狀尺寸和相互間位置正確;(3)具有足夠的強(qiáng)度、剛度和穩(wěn)定性,能承受新澆筑混凝土的重力側(cè)壓力及施工中可能產(chǎn)生的各項(xiàng)負(fù)荷。(4)模板的接縫不得漏漿;在澆筑砼前,木模板應(yīng)澆水濕潤(rùn),但模板內(nèi)不應(yīng)有積水(5)模板與砼的接觸面應(yīng)清理干凈并涂刷脫膜劑,但不得影響模板結(jié)構(gòu)性能。模板使用后應(yīng)按規(guī)定修整保存。(6)模板之間粘貼雙面不干膠帶,以減小模板縫防止漏漿,以保證砼面的觀感質(zhì)量。(7)模板采用M14×500螺栓與預(yù)埋鋼筋拉結(jié)配D48×3.5鋼架管橫、豎龍骨加固,并配以大號(hào)蝶形卡緊固,對(duì)拉螺桿按1000×500的間距布置,設(shè)置時(shí)將泄水孔位置與螺桿緊貼布置,以防扔填片石碰壞PVC管.緊貼模板的豎向龍骨間距不得大于300㎜。3.4.3澆筑砼(1)混凝土澆筑前應(yīng)做好如下準(zhǔn)備工作:a)制定澆筑工藝,明確結(jié)構(gòu)分段分塊的間隔澆筑順序,先澆筑基礎(chǔ)混凝土,由于墻身較高,因此決定墻身混凝土分兩次澆筑完成,施工縫接茬采用片石連接,片石規(guī)格不得小于15cm,間距不得小于15cm,且距模板邊緣的距離不得小于25cm。b)根據(jù)結(jié)構(gòu)截面尺寸大小研究確定必要的防溫防裂措施。c)施工前應(yīng)仔細(xì)檢查模版、預(yù)埋件的緊固程度。(2)澆筑混凝土?xí)r應(yīng)符合下列要求:a)混凝土應(yīng)分層進(jìn)行澆筑,不得隨意留置施工縫。b)混凝土澆筑應(yīng)連續(xù)進(jìn)行。當(dāng)因故間歇時(shí),其間歇時(shí)間應(yīng)小于前層混凝土的初凝時(shí)間或能重塑的時(shí)間。不同混凝土的允許間歇時(shí)間應(yīng)根據(jù)環(huán)境溫度、水泥性能。水膠比和外加劑類型等條件經(jīng)過(guò)試驗(yàn)確定。d)新澆混凝土與鄰接的已硬化混凝土或巖土介質(zhì)間的溫差不得大于15℃。f)在澆筑混凝土過(guò)程中或澆筑完成時(shí),如混凝土表面泌水較多,須在不擾動(dòng)已澆筑混凝土的條件下,采取措施減少泌水。g)澆筑混凝土期間,應(yīng)設(shè)專人檢查模板穩(wěn)定情況,發(fā)現(xiàn)有松動(dòng)、變形、移位時(shí)應(yīng)及時(shí)處理。h)澆筑混凝土?xí)r,應(yīng)填寫(xiě)混凝土施工記錄。i)自高處向模板內(nèi)傾卸混凝土?xí)r,為防止混凝土離析,一般應(yīng)滿足下列要求:從高處直接傾卸時(shí),混凝土傾落高度不宜超過(guò)2m,以不發(fā)生離析為度。g)在混凝土施工縫處接續(xù)澆筑新混凝土?xí)r,一般應(yīng)滿足下列要求:抗?jié)B要求的混凝土結(jié)構(gòu),施工縫宜做成凹型、凸型。(3)混凝土振搗a)混凝土澆筑過(guò)程中,應(yīng)隨時(shí)對(duì)混凝土進(jìn)行振搗并使其均勻密實(shí)。振搗宜采用插入式振搗器垂直點(diǎn)振b).混凝土振搗過(guò)程中,應(yīng)避免重復(fù)振搗,防止過(guò)振。應(yīng)加強(qiáng)檢查模板支撐的穩(wěn)定性和接縫的密合情況,防止在振搗混凝土過(guò)程中產(chǎn)生漏漿。c).采用機(jī)械振搗混凝土?xí)r,應(yīng)符合下列規(guī)定:1)采用插入式振搗器振搗混凝土?xí)r,插入式振搗器的移動(dòng)間距不宜大于振搗器作用半徑的1.5倍,且插入下層混凝土內(nèi)的深度宜未50~100mm,與側(cè)模應(yīng)保持50~100mm的距離。2)當(dāng)振搗完畢需要變換振搗棒在混凝土拌和物中的水平位置時(shí),應(yīng)邊振動(dòng)邊豎向緩慢提出振動(dòng)棒,不得將振動(dòng)棒放在拌和物內(nèi)平拖。不得用振動(dòng)棒驅(qū)趕混凝土。3)表面振動(dòng)器的移動(dòng)距離應(yīng)能覆蓋已振動(dòng)部分的邊緣。4)應(yīng)避免碰撞模板、鋼筋及其它預(yù)埋件。5)每一振點(diǎn)的振搗延續(xù)時(shí)間宜為20~30s,以混凝土不再沉落、不出現(xiàn)氣泡、表面呈現(xiàn)浮漿為度,防止過(guò)振、漏振。d)混凝土振搗完成后,應(yīng)及時(shí)修整、抹平混凝土裸露面,待定漿后再抹第二遍并壓光。抹面時(shí)嚴(yán)禁灑水,并應(yīng)防止過(guò)渡操作影響表面層混凝土的質(zhì)量。特別要注意施工抹面工序的質(zhì)量保證。(4)填放于混凝土中的片石應(yīng)符合以下要求:a)片石的強(qiáng)度等級(jí)不應(yīng)小于MU30。b)片石的最大尺寸不應(yīng)大于結(jié)構(gòu)最小尺寸的1/4,最小尺寸不應(yīng)小于15cm。c)片石在填放前應(yīng)用水沖洗干凈。d)片石應(yīng)均勻分布安放穩(wěn)妥,片石間凈間距不得小于15cm,片石與模板間的凈間距不宜小于25cm。e)最上層片石頂面應(yīng)覆蓋不小于25cm的混凝土層。f)片石采用人工擺放的方式進(jìn)行,注意片石不能碰傷模板及PVC管。g)澆筑完成后,在砼初凝前,在砼接茬面栽少量片石。h)片石體積不得超過(guò)片石混凝土總體積的25%。3.5墻背回填及泄水孔,沉降縫設(shè)置3.5.1最低一排泄水孔以下用黏土進(jìn)行回填,每層填土厚度15cm,回填30cm,用人工分層夯實(shí)。3.5.2當(dāng)墻身片石混凝土達(dá)到設(shè)計(jì)強(qiáng)度70%以上時(shí)進(jìn)行擋墻墻背回填,以確保片石混凝土墻體的質(zhì)量。3.5.3墻背回填材料采用B組填料,按45cm一層分層填筑夯實(shí)。3.5.4墻身于地面以上部分,每隔2米上、下、左、右交錯(cuò)設(shè)置泄水孔。應(yīng)嚴(yán)格控制泄水孔位置,保證其位置準(zhǔn)確,橫平豎直??變?nèi)預(yù)埋φ10cmPVC管伸入墻背10cm,端部20cm處用土工布包裹。最底排泄水孔下部及墻頂以下0.5米的范圍內(nèi)設(shè)夯填黏土防滲層。同時(shí)施工過(guò)程中嚴(yán)格控制泄水孔4%的流水坡度,并保證泄水孔向外排水順暢。3.5.5擋墻沿墻身方向結(jié)合墻高每隔15m或20m設(shè)一道伸縮縫,縫寬0.02m,擋土墻沿墻頂內(nèi)外三邊填塞瀝青麻筋,填塞深度20cm。3.6混凝土養(yǎng)護(hù):3.6.1.混凝土養(yǎng)護(hù)期間,應(yīng)重點(diǎn)加強(qiáng)混凝土的濕度和溫度控制,及時(shí)對(duì)混凝土暴露面進(jìn)行灑水養(yǎng)護(hù),并保持暴露面持續(xù)濕潤(rùn),直至混凝土終凝為止。3.6.2.混凝土帶模養(yǎng)護(hù)期間,應(yīng)采取帶模包裹、澆水。經(jīng)過(guò)噴淋灑水措施進(jìn)行保濕、潮濕養(yǎng)護(hù),保證模板接縫處不至失水干燥。為了保證順利拆模,可在混凝土澆筑24~48h后略微松開(kāi)模板,并繼續(xù)澆水養(yǎng)護(hù)至拆模后。3.6.3.在任意養(yǎng)護(hù)時(shí)間,若淋注于混凝土表面的養(yǎng)護(hù)水溫度低于混凝土表面溫度,二者間溫差不得大于15℃。3.6.4.在任意養(yǎng)護(hù)時(shí)間,若淋注于混凝土表面的養(yǎng)護(hù)水溫度低于混凝土表面溫度,二者間溫差不得大于15℃。3.6.5.混凝土養(yǎng)護(hù)期間,對(duì)混凝土的養(yǎng)護(hù)過(guò)程做詳細(xì)記錄,并建立嚴(yán)格的崗位責(zé)任制。3.7.混凝土拆?;炷敛鹉r(shí)的強(qiáng)度應(yīng)符合設(shè)計(jì)要求。當(dāng)設(shè)計(jì)未提出要求時(shí),應(yīng)符合下列規(guī)定:3.7.1側(cè)模應(yīng)在混凝土強(qiáng)度達(dá)到2.5Mpa以上,且表面季棱角不因拆模而損失,方可拆除。3.7.2混凝土的拆模時(shí)間除需考慮拆模時(shí)的混凝土強(qiáng)度應(yīng)滿足上一條的規(guī)定外,還應(yīng)考慮拆模時(shí)混凝土的溫度(由水泥水化熱引起)不能過(guò)高,以免混凝土接觸空氣時(shí)降溫過(guò)快而開(kāi)裂,更不能在此時(shí)澆注涼水養(yǎng)護(hù)?;炷羶?nèi)部開(kāi)始降溫以前以及混凝土內(nèi)部溫度最高時(shí)不得拆模。3.7.3拆模宜按立模順序逆向進(jìn)行,不得損傷混凝土,并減少模板破損。當(dāng)模板與混凝土脫離后,方可拆卸、調(diào)運(yùn)模板。3.7.4拆除臨時(shí)埋設(shè)與混凝土中她預(yù)埋部件時(shí),不得損傷混凝土。3.7.5拆除模板時(shí),不得影響或中斷混凝土的養(yǎng)護(hù)工作。3.7.6拆除后的混凝土結(jié)構(gòu)應(yīng)在混凝土達(dá)到100%的設(shè)計(jì)強(qiáng)度后,方可承受全部設(shè)計(jì)荷載。3.8混凝土缺陷處理3.8.1混凝土拆模后,如表面由粗糙、不平整、蜂窩、孔洞、疏松麻面和卻棱角等缺陷或不良外觀時(shí),應(yīng)認(rèn)真分析缺陷產(chǎn)生的原因,及時(shí)報(bào)告監(jiān)理和業(yè)主,不得自行處理。3.8.2當(dāng)混凝土表面缺陷修補(bǔ)后,修補(bǔ)或填充的混凝土應(yīng)與本體混凝土表面緊密結(jié)合,在填充、養(yǎng)護(hù)、和干燥后,所有填充物應(yīng)堅(jiān)固、物收縮縫或產(chǎn)生膨形區(qū),表面平整且與相鄰表面平齊,達(dá)到工程技術(shù)規(guī)范要求的相應(yīng)等級(jí)及標(biāo)準(zhǔn)的要求。修補(bǔ)后混凝土的耐久性能應(yīng)不低于本體混凝土。3.8.3除監(jiān)理工程師批準(zhǔn)外,用模板成型的混凝土表面不允許粉刷。3.8.4模板的拆除順序應(yīng)按設(shè)計(jì)的順序進(jìn)行。設(shè)計(jì)物規(guī)定時(shí),應(yīng)遵循先支后拆、后支先拆的順序進(jìn)行。3.8.5拆模時(shí)嚴(yán)禁拋扔模板。3.8.6模板拆除后應(yīng)及時(shí)對(duì)其進(jìn)行維修整理,并分類妥善保存。3.9腳手架搭設(shè)3.9.1采用雙排扣件式鋼管腳手架,鋼管為Φ48×3.5,Q235鋼,距1.2米,縱距1.8米,步距1.8米,每12-15米設(shè)剪刀撐一道.立桿底設(shè)墊木,面積不小于0.1m縱向掃地桿距底座下皮200mm,并需按規(guī)范要求搭設(shè)密目安全網(wǎng)。3.9.2單管立柱上的對(duì)接扣件應(yīng)交錯(cuò)布置,兩個(gè)相鄰立柱接頭不應(yīng)設(shè)在同步同跨內(nèi),在高度方向錯(cuò)開(kāi)不小于500mm,各接頭中心距主節(jié)點(diǎn)的距離不應(yīng)大于步距的1/3。搭接長(zhǎng)度≥1m,不小于兩個(gè)旋轉(zhuǎn)扣件固定端部扣件蓋板的邊緣至桿端距離不應(yīng)小于100mm。。十.安全措施1、嚴(yán)格按照”安全標(biāo)準(zhǔn)工地”實(shí)施辦法建設(shè)標(biāo)準(zhǔn)化工地,進(jìn)行文明施工。2、建立健全安全生產(chǎn)崗位責(zé)任制,由專職人員進(jìn)行安全技術(shù)監(jiān)督。3、施工現(xiàn)場(chǎng)的材料、機(jī)具堆放必須整齊,實(shí)行文明施工,對(duì)臟、亂、差的工地要嚴(yán)肅處理。4、定期或不定期抽查工地安全情況,發(fā)現(xiàn)安全隱患堅(jiān)決制止。5、定期進(jìn)行安全知識(shí)教育,做好安全技術(shù)交底。6、現(xiàn)場(chǎng)施工人員必須佩戴安全帽,必須持證上崗。十一.質(zhì)量控制措施1、組織學(xué)習(xí)各種有針對(duì)性的規(guī)則、規(guī)范,嚴(yán)格掌握工程質(zhì)量驗(yàn)收標(biāo)準(zhǔn)。2、抓開(kāi)挖質(zhì)量關(guān),勤測(cè)量復(fù)核??刂瞥?杜絕欠挖。3、抓好原材料及工程試驗(yàn)關(guān),不合格的原材料嚴(yán)禁使用。4、抓好立模支護(hù)關(guān),控制好中線、水平、結(jié)構(gòu)尺寸。5、抓好砼的澆灌、搗固關(guān)、砼嚴(yán)格按配合比施工,搗固密實(shí),以內(nèi)實(shí)為根本,外表平整美觀,線條接縫整齊。8、單位工程質(zhì)量8.1地基承載試驗(yàn)結(jié)果與設(shè)計(jì)一致,坑底表面無(wú)松軟巖土。8.2墻趾處巖土層盡量少受施工擾動(dòng),斜面地基平整無(wú)補(bǔ)貼。8.3基礎(chǔ)周邊大致平順整齊或基坑壁貼緊。8.4回填分層夯實(shí)8.5沉降縫、伸縮縫位置、縫的填塞符合設(shè)計(jì)規(guī)定。8.6泄水孔位置,孔距符合設(shè)計(jì)要求,孔內(nèi)通暢。8.7反濾層及時(shí)設(shè)置、并隔水,其材料符合設(shè)計(jì)要求,厚度不小于設(shè)計(jì)規(guī)定。8.8墻面平順、整齊。墻頂及兩端面與路基邊坡連接應(yīng)密貼封嚴(yán)。十二、質(zhì)量檢驗(yàn)1.基本要求(1)石料規(guī)格和質(zhì)量應(yīng)符合有關(guān)規(guī)定。(2)地基與基礎(chǔ)必須滿足圖紙要求。(3)混凝土的配合比應(yīng)符合試驗(yàn)規(guī)定。(4)混凝土表面應(yīng)平整、密實(shí)、無(wú)蜂窩麻面現(xiàn)象。(5)墻背填料符合圖紙要求。(6)沉降縫、泄水孔的位置和數(shù)量應(yīng)符合圖紙要求。2.外觀鑒定(1)混凝土表面平整,無(wú)蜂窩、麻面。(2)泄水孔坡度向外,無(wú)堵塞現(xiàn)象。(3)沉降縫整齊垂直,上下貫通。十三、環(huán)保措施環(huán)境保護(hù)是為了保護(hù)和改進(jìn)當(dāng)?shù)氐纳瞽h(huán)境與生態(tài)環(huán)境,防止給當(dāng)?shù)卦斐晌廴竞推渌?保障人體健康,促進(jìn)生產(chǎn)。因此,必須把環(huán)境保護(hù)工作納入計(jì)劃,建立環(huán)境保護(hù)責(zé)任制度,采取有效的措施,防止生產(chǎn)建設(shè)過(guò)程中產(chǎn)生的廢水、廢渣物、粉塵、噪聲等對(duì)當(dāng)?shù)丨h(huán)境造成污染和危害。1、在集鎮(zhèn)和村莊附近施工時(shí),噪聲較大的機(jī)械避免在夜間施工;非施工的噪聲要盡力避免。并經(jīng)過(guò)有效的管理和采取相應(yīng)的技術(shù)手段將噪聲控制到最低程度。2、施工和生產(chǎn)中的污水和廢水排放至指定地點(diǎn),不得隨意亂棄,并根據(jù)具體情況修建防護(hù)設(shè)施,防止水土流失。3、沿路線兩側(cè)路界外視線500m范圍內(nèi)不開(kāi)采石料,也不收購(gòu)該范圍內(nèi)開(kāi)采的石料或人工砂,以保護(hù)沿線的生態(tài)環(huán)境。4、工程完工后,清除所有占用場(chǎng)地的雜物,對(duì)原地面進(jìn)行平整、恢復(fù)為耕地或植被覆蓋;所租用的臨時(shí)用地,無(wú)償?shù)鼗謴?fù)原貌或達(dá)到復(fù)墾要求。所有公路用地范圍內(nèi)的雜物,廢棄物品都清除干凈。凡損壞的水利渠道、地方道路、排水溝、沿線通訊、電力設(shè)施等將與當(dāng)?shù)赜嘘P(guān)部門協(xié)商后進(jìn)行恢復(fù)或加以改移。6、光纜、電纜保護(hù)對(duì)于合同段內(nèi)的通訊電纜、光纜及高壓線設(shè)置,必須會(huì)同主管部門采取保護(hù)措施,施工前要求業(yè)主指明所有地下光纜、電纜的位置,設(shè)置明顯標(biāo)志。臨時(shí)設(shè)施的布置應(yīng)盡量避開(kāi)。在施工中一旦遇到預(yù)先不明的光纜、電纜,應(yīng)立即停止施工,保護(hù)好現(xiàn)場(chǎng),報(bào)告業(yè)主、工程師和主管部門處理。十四、安全文明施工措施1、堅(jiān)持”安全第一、預(yù)防為主”的基本方針在施工過(guò)程中要始終把安全,特別是從業(yè)人員和其它人員人身安全放在首要位置,實(shí)行”安全優(yōu)先”的原則。在確保安全的前提下,努力實(shí)現(xiàn)生產(chǎn)的質(zhì)量和進(jìn)度目標(biāo)是一致的,是生產(chǎn)經(jīng)營(yíng)活動(dòng)順利進(jìn)行的保證,我施工隊(duì)將按照”生產(chǎn)必須安全,安全為了生產(chǎn)”的原則進(jìn)行安全管理,建立的項(xiàng)目負(fù)責(zé)為首的領(lǐng)導(dǎo)小組,定期組織安全檢查,(附安全組織機(jī)構(gòu)圖和安全保證體系圖),發(fā)現(xiàn)事故隱患及時(shí)排除。2、保證措施(1)對(duì)參戰(zhàn)員工進(jìn)行安全教育培訓(xùn),特種作業(yè)人員必須持證上崗,做到安全生產(chǎn)、人人有責(zé),從而提高全體員工的安全意識(shí)。(2)建立健全生產(chǎn)安全管理制度,落實(shí)各級(jí)部門安全責(zé)任制。(3)幾個(gè)特殊環(huán)節(jié)的預(yù)防保證措施。a、場(chǎng)地建設(shè)必須按施工總平面圖布置,符合安全技術(shù)規(guī)則,設(shè)備、材料、臨時(shí)設(shè)施,臨時(shí)水電線路,生活設(shè)施等場(chǎng)地布置標(biāo)準(zhǔn)化。b、在施工過(guò)程中做到”三定一堅(jiān)持”即一定人員,專人負(fù)責(zé)設(shè)備的安裝,拆卸、檢修、操作、指揮。二定責(zé)任,對(duì)以上各種人員都應(yīng)明確職責(zé),健全安全生產(chǎn)責(zé)任制。三定制度,建立保障安全作業(yè)的規(guī)章制度。作業(yè)區(qū)域內(nèi)掛醒目的標(biāo)志;嚴(yán)禁作業(yè)過(guò)程中下方有人穿行;電機(jī)作業(yè)設(shè)緊急自動(dòng)開(kāi)關(guān),作業(yè)人員不得離崗或與她人說(shuō)笑聊天,分工明確,緊密配合。作業(yè)人員系安全帶,戴安全帽,禁止穿拖鞋作業(yè)和酒后上崗,特殊危險(xiǎn)區(qū)域設(shè)置防護(hù)欄和明顯標(biāo)志。(4)安全用電措施①采用通用的安全配電箱,實(shí)行一機(jī)一閘一漏電保護(hù)置。主要配電箱均作接地以防止感應(yīng)電傷人。②照明線路不能與動(dòng)力線路混用,鋼筋木工機(jī)械、振搗棒等電動(dòng)機(jī)械使用的電纜必須嚴(yán)格檢查,不能使用絕緣性差的或有破損的電纜。③機(jī)械設(shè)備移位、電器檢修時(shí)必須斷電操作,嚴(yán)禁帶電作業(yè),并掛上警示牌。移位時(shí)必須有專人指揮。④移動(dòng)電器修理電器由專業(yè)電工操作。(5)施工操作安全措施①嚴(yán)格執(zhí)行各種安全操作規(guī)程和安全規(guī)章制度。②加強(qiáng)安全生產(chǎn)的宣傳教育工作,做到”人人講安全,事事計(jì)安全,時(shí)時(shí)講安全”。③執(zhí)行崗位責(zé)任制,加強(qiáng)特種作業(yè)人員的上崗培訓(xùn)。(6)交通安全措施①本路段車輛出入口由專人指揮,避免施工段交通事故的發(fā)生。②重型運(yùn)輸機(jī)械的施工通道要及時(shí)養(yǎng)護(hù),避免車輛傾覆。十五、技術(shù)管理體系框圖工程監(jiān)理工程監(jiān)理總工程師總工程師測(cè)量組技術(shù)組質(zhì)檢組試測(cè)量組技術(shù)組質(zhì)檢組試驗(yàn)霜組土石方施工負(fù)責(zé)人施工負(fù)責(zé)人附屬結(jié)構(gòu)施工負(fù)責(zé)人道路及排水土石方施工負(fù)責(zé)人施工負(fù)責(zé)人附屬結(jié)構(gòu)施工負(fù)責(zé)人道路及排水
、管理措施1)、全面開(kāi)展質(zhì)量管理2)、積極開(kāi)展勞動(dòng)競(jìng)賽3)、嚴(yán)格執(zhí)行監(jiān)理工程師指令4)、嚴(yán)把材料關(guān)8、技術(shù)措施1)、建立每個(gè)分項(xiàng)工程,每道工序,每個(gè)施工環(huán)節(jié)的質(zhì)量標(biāo)準(zhǔn)和技術(shù)標(biāo)準(zhǔn),并在施工中嚴(yán)格執(zhí)行。加強(qiáng)職工隊(duì)伍培訓(xùn),提高職工安全質(zhì)量和技術(shù)素質(zhì)。2)、嚴(yán)格履行技術(shù)復(fù)核和質(zhì)量管理檢查制,對(duì)測(cè)量放樣應(yīng)進(jìn)行復(fù)核,測(cè)量資料及其它施工技術(shù)資料由專人保管、收集、整理,和施工同步。3)、組織強(qiáng)有力的施工隊(duì)伍及具有經(jīng)驗(yàn)的工程技術(shù)人員及訓(xùn)練有素的技術(shù)人員參加施工。4)、開(kāi)工前認(rèn)真審閱圖紙及各種技術(shù)文件,及時(shí)編制施工組織設(shè)計(jì)與質(zhì)量計(jì)劃,進(jìn)行分項(xiàng)、分部工程劃分,分解創(chuàng)優(yōu)指標(biāo),提出創(chuàng)優(yōu)計(jì)劃的實(shí)施期限。5)、編制各分項(xiàng)、分部工程施工實(shí)施細(xì)則,規(guī)范施工工期、方法、質(zhì)量標(biāo)準(zhǔn),檢測(cè)手段并嚴(yán)格實(shí)施。6)、嚴(yán)格履行技術(shù)復(fù)核和質(zhì)量管理檢查制,對(duì)測(cè)量進(jìn)行復(fù)核,符合制度方能放線。測(cè)量資料及其它施工技術(shù)資料必須有專人保管、收集、整理,且和施工同步。7)、認(rèn)真進(jìn)行工程技術(shù)、質(zhì)量及施工安全技術(shù)交底,施工順序進(jìn)度安排均要作交底,并作好書(shū)面記錄備查。8)、嚴(yán)格按照有關(guān)的施工規(guī)范及設(shè)計(jì)圖紙施工,工程質(zhì)量評(píng)定及隱蔽工程驗(yàn)收,必須經(jīng)監(jiān)理工程師評(píng)定簽認(rèn)后,方可進(jìn)行下步工序施工。9)、施工中,如對(duì)結(jié)構(gòu)和其它原因需進(jìn)行設(shè)計(jì)修改,必須在辦理工程聯(lián)系單、設(shè)計(jì)修改通知單后方可施工。10)、在保證建設(shè)監(jiān)理工程師充分履行職責(zé)和行使權(quán)力的前提下,建立項(xiàng)目經(jīng)理部?jī)?nèi)部監(jiān)理工程師制,各班組設(shè)質(zhì)量檢查員,實(shí)行質(zhì)量否決制度。與工程監(jiān)理密切配合搞好質(zhì)量管理工作,做好事前質(zhì)量控制,施工過(guò)程質(zhì)量控制,竣工驗(yàn)收等工作。十六、施工組織措施1、以合同文件要求和設(shè)計(jì)圖紙為依據(jù),以技術(shù)規(guī)范為標(biāo)準(zhǔn),制定項(xiàng)目創(chuàng)優(yōu)規(guī)劃,確定各分項(xiàng)目的質(zhì)量管理目標(biāo)和各工序的質(zhì)量管理標(biāo)準(zhǔn),以工序質(zhì)量標(biāo)準(zhǔn)的實(shí)現(xiàn)來(lái)保證分項(xiàng)目質(zhì)量目標(biāo)的實(shí)現(xiàn),以分項(xiàng)質(zhì)量目標(biāo)的實(shí)現(xiàn)來(lái)保證工程項(xiàng)目質(zhì)量創(chuàng)優(yōu)目標(biāo)的實(shí)現(xiàn)。2、實(shí)行項(xiàng)目經(jīng)理質(zhì)量負(fù)責(zé)制和技術(shù)質(zhì)量雙向承包責(zé)任制,逐層簽定技術(shù)質(zhì)量責(zé)任狀,以激發(fā)全體參與項(xiàng)目施工人員的創(chuàng)優(yōu)積極性,促進(jìn)工程質(zhì)量的提高。3、加強(qiáng)教育,貫徹制度,科學(xué)管理,促進(jìn)創(chuàng)優(yōu)。在整個(gè)工程施工中力求做到”五不施工”(施工圖未復(fù)核、測(cè)量未復(fù)核、材料未實(shí)驗(yàn)或無(wú)合格證、技術(shù)未交底、隱蔽工程未簽證不施工);”三不交接”(無(wú)自檢記錄、無(wú)施工記錄、無(wú)專職質(zhì)檢人員簽字不交接);”三教育”(工前培訓(xùn)、工中指導(dǎo)、工后講評(píng))。4、加強(qiáng)現(xiàn)場(chǎng)質(zhì)量控制和質(zhì)量檢查。按照合同文件和技術(shù)規(guī)范的規(guī)定,設(shè)立工地試驗(yàn)站和質(zhì)量監(jiān)測(cè)站,配備滿足檢測(cè)需要的各種測(cè)試儀器設(shè)備,對(duì)工程所用的各種材料、設(shè)備和施工的各工序進(jìn)行有效的檢測(cè)控制。5、施工中采用先進(jìn)的施工工藝和精良的施工設(shè)備,不斷優(yōu)化施工組織設(shè)計(jì)方案,推廣應(yīng)用”四新”成果,突破創(chuàng)優(yōu)難點(diǎn),采用先進(jìn)的技術(shù)和科學(xué)的管理相結(jié)合。大力組織”兩化”施工,使工程質(zhì)量一次成優(yōu)。6、虛心聽(tīng)取和接受工程師及其代表的指導(dǎo)和監(jiān)督,堅(jiān)決執(zhí)行工程師及其代表的指示,及時(shí)落實(shí)工程師及代表的改進(jìn)意見(jiàn)。提供滿足工程師及其代表在現(xiàn)場(chǎng)檢測(cè)需要的人員和儀器設(shè)備,搞好與工程師及其代表的配合工作,同心協(xié)力創(chuàng)優(yōu)。7、作好各種試驗(yàn)、檢測(cè)記錄,為施工提供準(zhǔn)確可靠的各種數(shù)據(jù),收集整理工程質(zhì)量和施工技術(shù)資料,及時(shí)編制竣工文件。8、建立施工與建設(shè)、監(jiān)理、設(shè)計(jì)各方組成的質(zhì)量監(jiān)控網(wǎng)絡(luò),使整個(gè)工程在施工過(guò)程中始終處于受控狀態(tài)。9、工程預(yù)驗(yàn)收前,承包商組織有關(guān)人員按設(shè)計(jì)施工圖和施工標(biāo)準(zhǔn)的要求對(duì)其施工工程進(jìn)行全面的檢查,如有不符立即進(jìn)行整改。
10、當(dāng)全部工程完工并符合合同規(guī)定時(shí),承包商應(yīng)向業(yè)主或監(jiān)理申請(qǐng)交工驗(yàn)收。
11、承包商對(duì)業(yè)主或監(jiān)理組織的預(yù)驗(yàn)收提出的問(wèn)題,應(yīng)在業(yè)主或監(jiān)理規(guī)定的期限內(nèi)整改完,再次提出交工申請(qǐng)。
12、交工資料由業(yè)主或監(jiān)理組織驗(yàn)收,驗(yàn)收后辦理交工資料交接手續(xù)。十七、安全保證措施①、安全施工主要措施1、成立環(huán)境保護(hù)領(lǐng)導(dǎo)機(jī)構(gòu):項(xiàng)目部成立環(huán)境保護(hù)委員會(huì),指定一名副經(jīng)理負(fù)責(zé)環(huán)境保護(hù)工作的組織領(lǐng)導(dǎo)、規(guī)章制度的制訂和檢查落實(shí)。各工程隊(duì)成立環(huán)境保護(hù)領(lǐng)導(dǎo)小組,隊(duì)主管領(lǐng)導(dǎo)任小組組長(zhǎng),各施工工長(zhǎng)及后勤保障部門負(fù)責(zé)人為成員,負(fù)責(zé)日常性的環(huán)境保護(hù)工作的檢查和落實(shí)。2、積極與所在地聯(lián)成環(huán)境保護(hù)網(wǎng)絡(luò),認(rèn)真聽(tīng)取地方環(huán)保部門的意見(jiàn),虛心接受其監(jiān)督和落實(shí)。3、根據(jù)本工程項(xiàng)目的作業(yè)特點(diǎn),制訂如下保護(hù)措施:1)、在砌筑操作之前必須檢查操作環(huán)境是否符合安全要求,道路是否暢通,機(jī)具是否完好、牢固,安全設(shè)施和防護(hù)用品是否齊全,經(jīng)檢查符合要求后才可施工。2)、砌筑基礎(chǔ)時(shí),應(yīng)經(jīng)常檢查和注意基坑邊坡的土體變化情況,有無(wú)開(kāi)裂、位移現(xiàn)象。堆放石材料應(yīng)離槽(坑)邊1m以上。3)、砌筑高度超過(guò)施工操作面1.2m以上時(shí)應(yīng)搭設(shè)腳手架。腳手架上堆放材料不得超過(guò)規(guī)定荷載值,同一塊腳手板上操作人員不得超過(guò)兩人。不準(zhǔn)用放不穩(wěn)固的工具或物品在腳手板上墊高操作,更不準(zhǔn)在未經(jīng)計(jì)算和加固的情況下,在腳手板上再隨意疊搭一層腳手板。應(yīng)按規(guī)定搭設(shè)安全網(wǎng)。4)、在腳手架施工時(shí),堆放材料、施工機(jī)具等物品不得超過(guò)使用荷載,否則,必須經(jīng)過(guò)驗(yàn)算并采取有效的加固措施后,方可堆放和施工。5)、不準(zhǔn)站在墻頂面上劃線、磚砌、刮縫、清理墻面和檢查大腳垂直度等工作;修石時(shí)應(yīng)面向墻面砍,并要注意防止碎石跳出傷人,垂直往上、往下人工投遞石料時(shí),要支搭站人用的寬度不小于0.6m的專用腳手架,并認(rèn)真?zhèn)鬟f,以防傷人。6)、不準(zhǔn)在墻頂上或腳手架上修鑿石材,以免墻體受到振動(dòng),影響墻體質(zhì)量或石塊掉下傷人。不準(zhǔn)勉強(qiáng)在超過(guò)胸部的墻上砌筑片石,以免不宜控制墻面垂直度、碰撞石墻或上石時(shí)失手掉下造成事故。不用的石塊不得由上往下投擲,運(yùn)石上下的坡道要加固定牢,并訂設(shè)防滑條、欄桿扶手等。7)、已砌好的山墻應(yīng)用臨時(shí)系桿(如檀條等)放置在各跨山墻上,使其連接穩(wěn)定,或采用其它加固措施,雨期每天下班前應(yīng)用防雨材料遮蓋,以防雨水沖掉砂漿,致使砌體倒塌。4、進(jìn)出場(chǎng)便道,經(jīng)常灑水養(yǎng)護(hù),避免造成塵土飛揚(yáng),污染周圍環(huán)境。5、施工設(shè)備停置有序,材料堆放井井有條,環(huán)境衛(wèi)生專人打掃,施工營(yíng)區(qū)、生活區(qū)干凈整齊。6、施工管理人員及現(xiàn)場(chǎng)施工人員均掛牌上崗。7、質(zhì)量員對(duì)現(xiàn)場(chǎng)所進(jìn)行的與質(zhì)量有關(guān)的活動(dòng)進(jìn)行觀察、監(jiān)督與檢查。檢查現(xiàn)場(chǎng)的施工工作是否按已批準(zhǔn)的程序進(jìn)行。8、現(xiàn)場(chǎng)檢查活動(dòng)是隨機(jī)的,無(wú)特殊原因,原則上每天都要進(jìn)行,對(duì)觀察發(fā)現(xiàn)的不足或缺陷要作出記錄,并將不足或缺陷按重要性的不同以書(shū)面或口頭形式通知責(zé)任方。9、每周末,技術(shù)部要總結(jié)檢查情況,進(jìn)行講評(píng)和通報(bào),保證重點(diǎn)項(xiàng)目和重要過(guò)程不漏檢。10、項(xiàng)目工地每月召開(kāi)一次由各部門和項(xiàng)目經(jīng)理參加的質(zhì)量小結(jié)會(huì)。技術(shù)部在會(huì)上向大家匯報(bào)當(dāng)月質(zhì)量體系運(yùn)行情況,及時(shí)找出存在的問(wèn)題,督促有問(wèn)題的部門積極采取糾正措施,抓緊整改。11、現(xiàn)場(chǎng)發(fā)現(xiàn)的所有質(zhì)量問(wèn)題,其改正行動(dòng)都要按程序文件規(guī)定的格式記錄下來(lái),且隨著工程進(jìn)展,逐步向下一階段移交,作為竣工狀態(tài)證明質(zhì)量達(dá)到要求的記錄文件。12、項(xiàng)目工地對(duì)質(zhì)量體系運(yùn)行中出現(xiàn)與質(zhì)量管理文件有沖突或無(wú)法執(zhí)行的情況時(shí),要及時(shí)向公司報(bào)告,以求得問(wèn)題的及時(shí)解決。13、施工現(xiàn)場(chǎng)平面布置符合有關(guān)安全衛(wèi)生規(guī)定,機(jī)具擺放整齊有序,各種標(biāo)志、標(biāo)識(shí)正確醒目,達(dá)到文明施工標(biāo)準(zhǔn)。14、如出現(xiàn)危及或可能傷及人員的危險(xiǎn)時(shí),所有相關(guān)的工作應(yīng)停止直至危險(xiǎn)狀態(tài)得到消除。15、任何表現(xiàn)出不安全因素的設(shè)備和工具必須立即停止使用,直至處于安全狀態(tài)或從施工區(qū)域移出或更換。16、若現(xiàn)場(chǎng)發(fā)生事故,應(yīng)立即采取應(yīng)急措施并在第一時(shí)間向業(yè)主提交書(shū)面報(bào)告,按業(yè)主和監(jiān)理的相關(guān)規(guī)定及本公司《事故處理程序》進(jìn)行事故的調(diào)查和處理。17、施工現(xiàn)場(chǎng)主要道路應(yīng)符合標(biāo)準(zhǔn)要求,特殊地況設(shè)蓋板、安全護(hù)欄。18、施工現(xiàn)場(chǎng)根據(jù)消防要求配置消防設(shè)施和器具,保持消防通道暢通。19、晚上施工時(shí),在獲監(jiān)理認(rèn)可后,項(xiàng)目部提供具有足夠照明強(qiáng)度的設(shè)備,確保安全生產(chǎn)。20、控制箱電氣開(kāi)關(guān)、閘刀等須放置在防雨棚或防雨罩,設(shè)漏電保護(hù)器以防漏電。21、作業(yè)現(xiàn)場(chǎng)應(yīng)經(jīng)常打掃并保持清潔,垃圾應(yīng)集中堆放并及時(shí)清理、運(yùn)送至指定地點(diǎn)。22、熟悉與安全和健康有關(guān)的法律責(zé)任和義務(wù),熟悉項(xiàng)目部全面的、綜合的安全和健康程序的細(xì)節(jié)。23、對(duì)違反安全程序的有關(guān)人員將依據(jù)項(xiàng)目部相關(guān)規(guī)定,采取適當(dāng)?shù)膽土P性措施。違反安全規(guī)定并危及生命和財(cái)產(chǎn)安全的人員將被從施工隊(duì)伍中清除出去。24、施工人員工作前應(yīng)按規(guī)定穿戴好與作業(yè)相適應(yīng)的防護(hù)用品,檢查作業(yè)場(chǎng)地、施工機(jī)具及設(shè)備的完好情況,記錄每次檢查的日期、發(fā)現(xiàn)的問(wèn)題、所采取的補(bǔ)救措施等。25、施工人員工作中應(yīng)遵守崗位安全技術(shù)操作規(guī)程,做到文明施工。26、施工人員在工作前和工作中均不得食用酒精類飲料,不應(yīng)在禁止煙火的場(chǎng)所吸煙。27、在施工區(qū)域應(yīng)走指定通道,不應(yīng)跨越危險(xiǎn)區(qū),不應(yīng)在行駛的機(jī)動(dòng)車上爬上跳下和攀登起重機(jī)吊鉤和吊運(yùn)中的物件。28、應(yīng)注意各種安全標(biāo)志,不應(yīng)隨便拆除或占用各種照明、信號(hào)、防雷等安全防護(hù)裝置、安全標(biāo)志和檢測(cè)儀表等。29、發(fā)生事故應(yīng)及時(shí)搶救人員、財(cái)產(chǎn),保護(hù)現(xiàn)場(chǎng)并向有關(guān)人員報(bào)告。執(zhí)行交接班制度。30、施工現(xiàn)場(chǎng)電氣作業(yè),由專職電工按規(guī)范操作。并負(fù)責(zé)作業(yè)區(qū)內(nèi)各種帶電設(shè)備及電線的漏電檢查,發(fā)現(xiàn)問(wèn)題立即整改。31、電氣設(shè)備操作人員,必須穿合格勞保服裝,戴標(biāo)準(zhǔn)絕緣手套,使用前必須對(duì)電氣設(shè)備進(jìn)行漏電試驗(yàn)。32、雨雪或潮濕天氣,一般不在露天使用電氣設(shè)備,必要時(shí)采取適當(dāng)?shù)陌踩秒姶胧?3、施工現(xiàn)場(chǎng)用電設(shè)施應(yīng)在設(shè)備負(fù)荷線的首端處設(shè)置漏電保護(hù)裝置。漏電保護(hù)器應(yīng)裝設(shè)在開(kāi)關(guān)箱內(nèi)。34、施工現(xiàn)場(chǎng)的配電室應(yīng)通風(fēng)良好,并采取防止雨雪和動(dòng)物入內(nèi)的措施。35、用電設(shè)備的金屬外殼(安全電壓除外)應(yīng)作保護(hù)接地或保護(hù)接零。潮濕或條件特別惡劣的施工現(xiàn)場(chǎng)的電氣設(shè)備應(yīng)采用保護(hù)接零。36、配電屏(盤)上的各種配電線路應(yīng)有編號(hào)并標(biāo)明用途。配電線路維修時(shí)應(yīng)懸掛”禁止合閘,有人操作”警告標(biāo)志。停、送電必須有專人負(fù)責(zé)。37、搬運(yùn)石塊時(shí)要注意配合,步調(diào)協(xié)調(diào)一致,互相用力均勻,保證安全。38、石籠制作時(shí)注意安全,綁扎鐵絲時(shí)注意不要滑傷皮膚,鉤破衣服。39、修筑施工便道應(yīng)保證足夠的寬度和強(qiáng)度,確保運(yùn)輸安全。40、人工開(kāi)挖基槽時(shí)注意不要滑傷管子防腐層,人工鑿巖時(shí)要防止石塊崩傷操作人員。41、修筑圍堰導(dǎo)流時(shí)圍堰應(yīng)有足夠的強(qiáng)度,防止被水沖垮。42、漿砌石護(hù)坡時(shí)應(yīng)把坡上的石塊清理干凈,防止石塊清理不凈滑落傷人。43、攪拌機(jī)操作時(shí)應(yīng)遵守操作規(guī)程,嚴(yán)禁非崗位人員違章操作44、進(jìn)料便道、堆料場(chǎng)盡量利用施工作業(yè)帶或已有的鄉(xiāng)村砂石路等,沒(méi)有植被的砂石場(chǎng)和植被已被破壞的場(chǎng)地。45、施工時(shí)采取適當(dāng)措施保證現(xiàn)場(chǎng)道路、斜坡和其它對(duì)地面不會(huì)形成障礙,造成水災(zāi),破壞植被。46、作業(yè)帶外被不慎砍伐的樹(shù)木要立即補(bǔ)救,只要安全性和可施工性允許,平整場(chǎng)地的工作人員應(yīng)盡量不破壞場(chǎng)地表面,不觸及原有的根系,植物能夠從地面切斷,為以后重新萌芽生長(zhǎng)創(chuàng)造條件。47、開(kāi)挖管溝時(shí)要把表層土和底層土分開(kāi)堆放,設(shè)置合適的溝渠排水和保持跨躍管溝的安全通道,以一種不影響其它土地使用的方式把管溝里過(guò)多的水抽到臨近的地區(qū)。48、回填管溝時(shí),應(yīng)盡量作到恢復(fù)地表的原來(lái)形狀,使表面能正常排水。49、下層土和表層土回填應(yīng)與管溝內(nèi)兩側(cè)的土層匹配,保存的表土不可在下層土回填之前填到管溝里面。50、在回填堆放挖出的土壤時(shí),不可把表層的草皮或表土除去。51、壓實(shí)管溝中的回填土,壓實(shí)程度要大致相當(dāng)于施工前狀態(tài),以盡量減少下沉。在管溝與水道交叉處和中斷的排水溝的兩岸壓實(shí)填土?xí)r注意,必要時(shí)采取適當(dāng)?shù)拇胧?確保施工安全。52、在回填前需對(duì)大開(kāi)挖的管溝用肉眼檢查,如發(fā)現(xiàn)有動(dòng)物,則應(yīng)把它們弄出來(lái),對(duì)于較大的動(dòng)物,可在夠壁挖一個(gè)斜坡,以便讓它能夠爬出來(lái)。53、取料場(chǎng)與任何水域保持最低限度的植被緩沖帶。54、取料場(chǎng)擴(kuò)展過(guò)程中移走的表土層必須適當(dāng)堆放,采取措施防止水土流失,把侵蝕局限在取料場(chǎng)范圍內(nèi),不得擅自擴(kuò)大作業(yè)面。55、除了指定的料場(chǎng),未經(jīng)當(dāng)?shù)赜嘘P(guān)部門許可在施工中不能隨意從河床或岸邊傾倒或挖取卵石、采砂及廢棄物。56、毀壞、遷移或清理樹(shù)木、植被不得超過(guò)工程施工所需的范圍,不得亂砍亂伐。
57、施工時(shí)臨時(shí)加寬加固的道路,施工完畢應(yīng)結(jié)合當(dāng)?shù)貙?shí)際情況,對(duì)影響環(huán)境的予以恢復(fù)原貌。58、對(duì)于違反環(huán)保規(guī)章造成環(huán)境破壞,應(yīng)立即報(bào)告項(xiàng)目監(jiān)理,按照項(xiàng)目監(jiān)理的指示負(fù)責(zé)清理、回收和(或)采取復(fù)原措施。地表徑流向聚集,沖溝上部設(shè)置環(huán)向節(jié)流排水溝,邊坡處沿管溝砌筑截水墻。59、穩(wěn)定性差的沖溝邊坡,軟土地基采用漿砌條(塊)石護(hù)坡。
60、在施工作業(yè)前,經(jīng)過(guò)對(duì)風(fēng)險(xiǎn)和危害分析以及當(dāng)?shù)爻R?jiàn)病、傳染病和醫(yī)院狀況調(diào)查的基礎(chǔ)上,針對(duì)有毒蛇出沒(méi)的環(huán)境、使用機(jī)械設(shè)備、發(fā)電機(jī)排水等危險(xiǎn)因素,編制應(yīng)急預(yù)案和應(yīng)急程序,成立應(yīng)急小組,準(zhǔn)備應(yīng)急物資,保證每位員工都熟悉應(yīng)急預(yù)案和緊急情況下的應(yīng)急行動(dòng)。61、如電源開(kāi)關(guān)在附近、應(yīng)迅速關(guān)閉電源,否則用絕緣物體挑開(kāi)電線或分離電器,使患者脫離電源;呼吸停止者,立即進(jìn)行人工呼吸;
心臟停跳者,進(jìn)行胸外心臟按壓;送醫(yī)院急救處理。62、處理?yè)p傷的原則是首先搶救傷員的生命,對(duì)呼吸、心跳停止的傷員,應(yīng)就地立即進(jìn)行復(fù)蘇術(shù)。63、治療窒息。如遇嚴(yán)重失血或胸部開(kāi)放性損傷,應(yīng)盡快止血或封閉胸部傷口;
64、治療休克和骨折固定。運(yùn)送四肢骨折傷員,必須用夾板固定傷肢,脊椎骨折須臥硬板床;
65、如動(dòng)脈出血,要上止血帶,每隔1小時(shí)放松一次,每次1—2分種,轉(zhuǎn)運(yùn)途中應(yīng)保持呼吸道暢通;
66、送醫(yī)院,預(yù)防感染,糾正電解質(zhì)代謝失調(diào),注射破傷風(fēng)抗毒素。67、急性中毒者,立即終止接觸毒物,毒物由呼吸道或皮膚侵入時(shí),要立即將病人撤離中毒現(xiàn)場(chǎng),移到空氣新鮮的地方,污染的衣服必須立即脫去,清洗接觸部位的皮膚;采取催吐、洗胃、導(dǎo)瀉等方法清除體內(nèi)尚未被吸收的毒物;清除皮膚上的毒物,脫去污染衣服,用大量溫水清洗皮膚毛發(fā);清除眼內(nèi)毒物,用清水徹底清洗;清除傷口毒物;使用解毒劑并送醫(yī)院。十八、安全保證體系安全保證體系框圖安全安全法規(guī)技術(shù)負(fù)責(zé)人項(xiàng)目經(jīng)理(安全責(zé)任人)技術(shù)負(fù)責(zé)人項(xiàng)目經(jīng)理(安全責(zé)任人)項(xiàng)目安全規(guī)程技術(shù)措施項(xiàng)目安全規(guī)程技術(shù)措施現(xiàn)場(chǎng)安全負(fù)責(zé)人現(xiàn)場(chǎng)安全負(fù)責(zé)人各施工區(qū)各施工區(qū)糾正、整改糾正、整改1、建立安全生產(chǎn)責(zé)任制2、建立安全保證體系,健全各級(jí)各部門生產(chǎn)責(zé)任制,責(zé)任落實(shí)到人;3、各項(xiàng)施工任務(wù)都有明確的安全指標(biāo)和包括獎(jiǎng)懲辦法在內(nèi)的保證措施,簽訂各級(jí)安全生產(chǎn)責(zé)任制。4、加強(qiáng)安全意識(shí)和技術(shù)教育1)、剛進(jìn)施工現(xiàn)場(chǎng)施工人員必須進(jìn)行安全技術(shù)教育;2)、工人變工種,必須進(jìn)行新工種的安全技術(shù)教育;3)、工人掌握本工種操作技能,熟悉本工種安全技術(shù)操作規(guī)程;4)、認(rèn)真建立”職工勞動(dòng)保護(hù)記錄卡”,及時(shí)做好記錄。5、安全保證的指導(dǎo)思想本工程施工現(xiàn)場(chǎng)和工程規(guī)模較大,施工人員多,專業(yè)交叉施工頻繁,不安全因素多。為切實(shí)保證施工過(guò)程安全無(wú)事故,將”安全第一,預(yù)防為主”指導(dǎo)思想落到實(shí)處,為實(shí)現(xiàn)這一指導(dǎo)思想,安全生產(chǎn)將在組織保證管理制度及防止傷害事故、培訓(xùn)和教育等方面采取切實(shí)可行的相應(yīng)措施。6、建立以項(xiàng)目經(jīng)理部及安全監(jiān)察部門為主的安全領(lǐng)導(dǎo)組織,強(qiáng)調(diào)”管生產(chǎn)必須管安全”的生產(chǎn)原則,推行全員安全生產(chǎn)責(zé)任制.7、本項(xiàng)目設(shè)專職安全監(jiān)察部門,配合工班長(zhǎng)進(jìn)行施工過(guò)程中的安全管理工作。8、施工工班設(shè)兼職安全員,配合工班長(zhǎng)進(jìn)行施工過(guò)程中的安全管理工作.9、管理制度措施建立健全各項(xiàng)安全生產(chǎn)管理制度,在進(jìn)行施工技術(shù)交底時(shí),同時(shí)進(jìn)行安全交底。特種作業(yè)人員必須經(jīng)過(guò)有關(guān)部門培訓(xùn),考試合格后持證上崗、建立定期安全檢查制度,建立相應(yīng)的考核措施,施工管理人員及各工種操作人員要佩戴不同的崗位標(biāo)識(shí);嚴(yán)禁違章指揮、違章作業(yè)、野蠻施工。10、施工過(guò)程安全措施施工過(guò)程中對(duì)安全教育、執(zhí)證上崗以及用電、樁基開(kāi)挖的通風(fēng)、防坍塌、高空作業(yè)等嚴(yán)格按安全規(guī)程執(zhí)行,保證安全生產(chǎn)。11、消防安全保證措施為加強(qiáng)工程消防安全管理,貫徹”預(yù)防為主,防消結(jié)合”的消防方針,確保工程順利進(jìn)行,采取以下措施確保消防安全。12、重點(diǎn)防范的安全措施在本工程施工中,各環(huán)節(jié)的安全管理不容忽視,隨時(shí)采取措施改進(jìn)。本工程重點(diǎn)防護(hù)措施有以下幾項(xiàng),這在開(kāi)工之前,必須完善安全措施。1)、防止觸電事故的發(fā)生,電工應(yīng)經(jīng)常檢查電器及線路安全,線路均配備標(biāo)準(zhǔn)配電箱。2)、為維護(hù)行人和交通安全,施工現(xiàn)場(chǎng)出入口及重要部位實(shí)行封閉施工。采用鋼圍欄將施工現(xiàn)場(chǎng)封閉,既有利于文明施工,又減少相互干擾。3)、作好機(jī)械設(shè)備的安全防護(hù)措施。4)、做好防洪、防火、防盜、防爆炸事故等”四防”工作。防洪:施工場(chǎng)地開(kāi)挖臨時(shí)排水溝,備好抽水設(shè)備。防火:電力線路和照明線路按規(guī)定布設(shè);生產(chǎn)和生活臨時(shí)用房除特殊情況(試驗(yàn))一律不得使用電爐;不得亂丟煙頭;組建防火組織,定期檢查;在施工現(xiàn)場(chǎng)安放各種滅火器具。防盜:現(xiàn)場(chǎng)派專人保衛(wèi),加強(qiáng)與地方公安、聯(lián)防機(jī)關(guān)聯(lián)系,確保施工安全。防爆:易燃、易爆物品必須派專人管理,且與其它物品分開(kāi)儲(chǔ)存;乙炔、氧氣瓶的存放應(yīng)設(shè)立單間儲(chǔ)存,并照防火規(guī)定距離及要求修建儲(chǔ)存庫(kù)房,庫(kù)房周圍應(yīng)設(shè)立明顯的防火標(biāo)志。一切無(wú)關(guān)人員嚴(yán)禁動(dòng)用乙炔、氧氣及進(jìn)入儲(chǔ)存庫(kù)房。13、其它需重點(diǎn)防范的安全措施1)、施工現(xiàn)場(chǎng)設(shè)置安全標(biāo)志,場(chǎng)內(nèi)的溝、坑等邊緣設(shè)安全護(hù)欄。場(chǎng)地狹小,行人和運(yùn)輸繁忙的路段設(shè)專人指揮交通。2)、工地上較高的建(構(gòu))筑物、臨時(shí)設(shè)施及重要庫(kù)房均應(yīng)架設(shè)避雷裝置。3)、施工測(cè)量釘樁要注意周圍行人的安全,不得對(duì)面使錘。鋼釬和其它工具不得隨意拋擲。4)、場(chǎng)內(nèi)道路應(yīng)經(jīng)常維護(hù),保持暢通,場(chǎng)內(nèi)道路應(yīng)平坦順直。5)、現(xiàn)場(chǎng)架設(shè)的臨時(shí)線路必須用絕緣物支撐,不得將電線纏繞在鋼筋、樹(shù)木或腳手架上。6)、各種電器設(shè)備應(yīng)配有專用開(kāi)關(guān),室外使用的開(kāi)關(guān)、插座應(yīng)外裝防水箱并加鎖,在操作處加設(shè)絕緣墊層。7)、在三相五線制供電系統(tǒng)中,電器設(shè)備的金屬外殼應(yīng)作接地保護(hù),其接地電阻應(yīng)不大于4。8)、各種電器設(shè)備的檢查維修,應(yīng)停電作業(yè);如必須帶電作業(yè)時(shí),應(yīng)有可靠的安全措施并派專人監(jiān)護(hù)。9)、工地安裝變壓器必須符合電業(yè)部門的要求,并設(shè)專人管理,施工用電要盡量保持三相平衡。10)、現(xiàn)場(chǎng)的變(配)電設(shè)備處,必須備有滅火器材和高壓安全用具,非電工人員嚴(yán)禁接近帶電設(shè)備。11)、施工現(xiàn)場(chǎng)的臨時(shí)照明:室內(nèi)照明線路應(yīng)用瓷夾固定;電線接頭應(yīng)牢固,并用絕緣膠帶包扎,保險(xiǎn)絲應(yīng)按用電負(fù)荷量裝設(shè)。12)、檢修電氣設(shè)備時(shí)應(yīng)按下列要求進(jìn)行:電氣設(shè)備的檢修必須由電工進(jìn)行,她人不得任意操作。工作中如遇停電應(yīng)拉下開(kāi)關(guān),切斷電源;檢修結(jié)束必須仔細(xì)檢查各項(xiàng)設(shè)備的情況,沒(méi)有異常,方可合閘。大型電氣設(shè)備檢修應(yīng)在切斷電源,設(shè)好防護(hù)后進(jìn)行,并在開(kāi)關(guān)處設(shè)置警示標(biāo)牌,工作完成后方可拆除;如需進(jìn)行送電試驗(yàn)時(shí),必須在認(rèn)真檢查并與有關(guān)部門聯(lián)系后,方可進(jìn)行。13)、操作人員在工作中不得擅離崗位,不得操作與操作證不相符合的機(jī)械;不得將機(jī)械設(shè)備交給無(wú)本機(jī)種操作證的人員操作。14)、機(jī)械設(shè)備在施工現(xiàn)場(chǎng)停放時(shí),應(yīng)選擇安全的停放地點(diǎn),關(guān)閉好駕駛室(操作室),要拉上駐車制動(dòng)閘。十九、文明施工,加強(qiáng)環(huán)保①、文明施工在施工現(xiàn)場(chǎng)管理中,采取各種措施,按現(xiàn)代化施工的客觀要求組織施工,使施工現(xiàn)場(chǎng)保持良好的施工環(huán)境和施工秩序。主要措施有:
1、組織管理措施1)、建立健全管理組織機(jī)構(gòu)。施工現(xiàn)場(chǎng)應(yīng)成立以項(xiàng)目負(fù)責(zé)人為組長(zhǎng),生產(chǎn)、技術(shù)質(zhì)量、安全、消防、保衛(wèi)、材料、行政衛(wèi)生管理人員為成員的文明施工管理組織。2)、健全管理制度。包括:個(gè)人崗位責(zé)任制、經(jīng)濟(jì)責(zé)任制、檢查制度、獎(jiǎng)懲制度、會(huì)議制度和各項(xiàng)專業(yè)管理制度等;3)、健全管理資料。加強(qiáng)教育培訓(xùn)工作;推廣應(yīng)用新技術(shù)、新工藝、新設(shè)備和現(xiàn)代化管理方法,提高機(jī)械化作業(yè)程度。2、現(xiàn)場(chǎng)管理措施1)、對(duì)施工現(xiàn)場(chǎng)各生產(chǎn)要素(主要是物的要素)的所處狀態(tài),不斷地進(jìn)行整理、整頓、清掃、清潔,并培養(yǎng)員工的素質(zhì)及技術(shù),實(shí)現(xiàn)文明施工。2)、合理定置。將全工地施工期間所需要的物在空間上合理布置,實(shí)現(xiàn)人與物、人與場(chǎng)所、物與場(chǎng)所、物與物之間的最佳結(jié)合,使施工現(xiàn)場(chǎng)秩序化、標(biāo)準(zhǔn)化、規(guī)范化,體現(xiàn)文明施工水平。3)、目視管理。目視管理就是用眼睛看的管理,亦可稱之為”看得見(jiàn)的管理”。它是利用形象直觀,色彩適宜的各種視覺(jué)感知信息來(lái)組織現(xiàn)場(chǎng)施工生產(chǎn)活動(dòng),達(dá)到提高勞動(dòng)生產(chǎn)率,保證工程質(zhì)量,降低工程的成本。目視管理是一種簡(jiǎn)便適用,透明度高,便于員工自主管理,自我控制,科學(xué)組織生產(chǎn)的一種有效的管理方式。4)、其主要內(nèi)容與形式如下:①施工現(xiàn)場(chǎng)各項(xiàng)管理制度、操作規(guī)程、工作標(biāo)準(zhǔn)、施工現(xiàn)場(chǎng)管理實(shí)施細(xì)則等布告等應(yīng)用墻報(bào)、掛板等形式,展示清楚。②在定置過(guò)程中,以清晰的、標(biāo)準(zhǔn)化的視覺(jué)顯示信息落實(shí)定置設(shè)計(jì),實(shí)現(xiàn)合理定置。③施工現(xiàn)場(chǎng)的管理崗位責(zé)任人采用標(biāo)牌顯示,以更好地落實(shí)崗位責(zé)任制,激發(fā)崗位人員的責(zé)任心,并有利于群眾監(jiān)督。④在施工現(xiàn)場(chǎng)合理利用各種色彩、安全色、安全標(biāo)志等,并實(shí)行標(biāo)準(zhǔn)化管理,有利于生產(chǎn)和員工的安全。⑤將施工現(xiàn)場(chǎng)管理的各項(xiàng)檢查結(jié)果張榜公布。二十、施工現(xiàn)場(chǎng)環(huán)境保護(hù)1、環(huán)境保護(hù)是中國(guó)的一項(xiàng)基本國(guó)策。在施工過(guò)程中,采取措施,按照國(guó)家、地方法規(guī)和行業(yè)、企業(yè)要求,采取措施控制施工現(xiàn)場(chǎng)的各種粉塵、廢水、廢氣、固體廢棄物以及噪聲、振動(dòng)等對(duì)環(huán)境的污染和危害,同時(shí)要防止水土流失。保護(hù)和改進(jìn)施工環(huán)境,保證人們身體健康,消除外部干擾,保證順利進(jìn)行。2、環(huán)境保護(hù)的措施及具體做法:1)、實(shí)行環(huán)保目標(biāo)責(zé)任制2)、加強(qiáng)檢查和監(jiān)控工作3)、對(duì)要保護(hù)和改進(jìn)的施工現(xiàn)場(chǎng)環(huán)境,進(jìn)行綜合治理4)、嚴(yán)格執(zhí)行國(guó)家的法律、法規(guī),統(tǒng)籌安排,合理布置,綜合治理。5)、施工前應(yīng)制定施工期間環(huán)境保護(hù)措施,防止大氣污染、水源污染和噪聲污染。6)、施工廢棄物采取措施集中外運(yùn)到指定地點(diǎn),避免阻塞河溝、污染水源。如無(wú)法及時(shí)處理或運(yùn)走,則必須設(shè)法防止散失。7)、施工中所產(chǎn)生的污水或廢水,集中處理,不能隨意排放。8)、在運(yùn)輸和貯存施工材料時(shí),采取覆蓋、倉(cāng)貯等措施防止漏失。9)、當(dāng)路線經(jīng)過(guò)農(nóng)田灌溉區(qū)時(shí),采取必要臨時(shí)措施。如接邊溝,安設(shè)水管等以保證不影響或中斷農(nóng)田的排灌作業(yè)。10)、對(duì)工程范圍以外的土地及植被應(yīng)注意保護(hù),未經(jīng)工程師批準(zhǔn),不得隨意堆置廢方和挖掘。3、保持作業(yè)帶范圍內(nèi)不遺留施工產(chǎn)生的垃圾和碎片。4、工現(xiàn)場(chǎng)的食物垃圾應(yīng)每天清楚掉。5、垃圾應(yīng)運(yùn)到施工場(chǎng)地以外適當(dāng)?shù)睦幚韴?chǎng)妥善處理。6、不得將垃圾處理到溝渠里,表土或土堆上。7、清理人員收拾垃圾、碎片、切斷的殘枝和施工預(yù)料進(jìn)行處理。把固體廢料和垃圾(非生物可降解的垃圾)收集起來(lái)在一個(gè)場(chǎng)外地點(diǎn)進(jìn)行處理。8、把固體廢料和垃圾(非塵物可降解的垃圾)收集起來(lái)在一個(gè)場(chǎng)外地點(diǎn)進(jìn)行處理。9、各種油料應(yīng)在容器內(nèi)存放,廢油應(yīng)及時(shí)回收集中儲(chǔ)存,嚴(yán)禁就地傾倒,油料對(duì)地面造成污染時(shí)應(yīng)采取措施進(jìn)行清理。10、清理時(shí)被切斷的樹(shù)木可運(yùn)出作業(yè)帶范圍或在作業(yè)帶范圍內(nèi)進(jìn)行切片、切碎、或堆在一個(gè)可接近的地方,可供公眾加以利用。
二十一、綠化工作措施1、工地附近的樹(shù)木、花草盡可能進(jìn)行保護(hù)。2、施工期間對(duì)綠化地區(qū)進(jìn)行管理養(yǎng)護(hù)。二十二、施工進(jìn)度工期保證措施本項(xiàng)工程施工我們將按照”高效、優(yōu)質(zhì)、有序”的原則均衡進(jìn)行,根據(jù)工期、質(zhì)量、安全等要求,合理安排,精心施工,在確保質(zhì)量、安全的前提下采取如下措施以保證預(yù)定工期的實(shí)現(xiàn)。本工程施工不受外圍交通影響,現(xiàn)場(chǎng)采用局部封閉圍蔽施工,全路段進(jìn)行統(tǒng)籌安排施工,控制好施工的進(jìn)度,能夠安排晚間施工。關(guān)鍵工序擬定全天候施工,管理人員分為三班和作業(yè)人員分為四班進(jìn)行施工。在施工安排中要充分的考慮雨季施工時(shí)候的特點(diǎn),認(rèn)真做好雨季施工的質(zhì)量保證工作。二十三、一般措施我公司的技術(shù)力量雄厚,設(shè)備齊全,特別善于組織打大仗、打硬仗,在建設(shè)單位中具有良好的信譽(yù)。具有良好及廣泛的社會(huì)關(guān)系,這些條件為工程的順利進(jìn)行奠定了基礎(chǔ)。工程開(kāi)工后,立即根據(jù)施工進(jìn)度計(jì)劃進(jìn)行各項(xiàng)工作的落實(shí),使工程一開(kāi)始施工就有組織、有步驟地進(jìn)行。1、從機(jī)構(gòu)組織、人員配備,管理上保證。配備高級(jí)技術(shù)人才組成精干的項(xiàng)目經(jīng)理部。詳見(jiàn)工程項(xiàng)目管理機(jī)構(gòu)。按部門、單位、崗位為主體制訂嚴(yán)格的責(zé)任制度,做到人人有責(zé)可負(fù)。制定嚴(yán)密的規(guī)章制度,任何人都須毫無(wú)例外地遵守。2、從計(jì)劃安排上保證。按照施工進(jìn)度總計(jì)劃的工期要求,精心制定分項(xiàng)施工計(jì)劃和各項(xiàng)實(shí)施方案,重要工序做好施工組織專項(xiàng)設(shè)計(jì),合理安排各分項(xiàng)工程的施工順序、全面覆蓋施工的全過(guò)程和所有方面。確保關(guān)鍵線路上的各工序按時(shí)完成,充分利用有利條件和時(shí)間,縮短作業(yè)流程,從各個(gè)環(huán)節(jié)上加快施工進(jìn)度。計(jì)劃按周按日進(jìn)行細(xì)分,計(jì)劃的執(zhí)行和檢查落實(shí)到人。預(yù)先解決后續(xù)工作中可能會(huì)出現(xiàn)的問(wèn)題,為后續(xù)工作順利進(jìn)行創(chuàng)造有利條件。3、從材料管理和機(jī)械設(shè)備管理上保證。材料進(jìn)行分層管理,明確材料管理制度,使整個(gè)施工過(guò)程的材料周轉(zhuǎn)順利。其中鋼板校等支護(hù)材料的投入是關(guān)鍵,為確保施工進(jìn)度,支護(hù)材料均按周轉(zhuǎn)2次的數(shù)量投入。編制詳細(xì)的施工項(xiàng)目材料計(jì)劃與材料供應(yīng)計(jì)劃,合理指導(dǎo)與組織施工項(xiàng)目材料的管理,確保材料的及時(shí)供應(yīng),在材料供應(yīng)計(jì)劃的執(zhí)行過(guò)程中,定期或不定期地檢查。堅(jiān)決杜絕停工待料的現(xiàn)象發(fā)生。本工程的土方施工機(jī)械和土方運(yùn)輸車輛是控制施工進(jìn)度的關(guān)鍵設(shè)備,因此施工期間必須保證按施工機(jī)械設(shè)備表中的機(jī)械及時(shí)進(jìn)場(chǎng)施工。機(jī)械設(shè)備管理中,做到人機(jī)固定,實(shí)行機(jī)械使用、保養(yǎng)責(zé)任制,將機(jī)械設(shè)備的使用效益與個(gè)人經(jīng)濟(jì)利益聯(lián)系起來(lái),進(jìn)而提高機(jī)械的生產(chǎn)效率,確保各工序按時(shí)完成。組織好機(jī)械設(shè)備的流水施工,搞好機(jī)械設(shè)備的綜合利用,為機(jī)械設(shè)備的施工創(chuàng)造良好的條件,大力提高其使用率,縮短作業(yè)時(shí)間。4、從技術(shù)上保證。本標(biāo)項(xiàng)目技術(shù)負(fù)責(zé)人全面負(fù)責(zé)該標(biāo)段的施工技術(shù)管理,與各級(jí)技術(shù)人員建立技術(shù)管理小組,負(fù)責(zé)各項(xiàng)專利技術(shù)問(wèn)題的解決,施工方案的編制與監(jiān)督執(zhí)行。建立技術(shù)責(zé)任制,對(duì)各級(jí)技術(shù)人員建立明確的職責(zé)和范圍,以達(dá)到各負(fù)其責(zé),各司其職,充分調(diào)動(dòng)各級(jí)技術(shù)人員的積極性和創(chuàng)造性,及時(shí)解決施工中的技術(shù)問(wèn)題,以方案指導(dǎo)施工,防止出現(xiàn)返工現(xiàn)象而影響工期。各技術(shù)管理小組及時(shí)總結(jié)施工中出現(xiàn)的問(wèn)題與經(jīng)驗(yàn),把易于施工、保證質(zhì)量、加快進(jìn)度的各項(xiàng)措施加以推廣,以更好地指導(dǎo)后續(xù)作業(yè)。5、從施工組織與管理上保證。在施工生產(chǎn)過(guò)程中,合理支排各工序的交接與搭接,確保每道工序的施工順利進(jìn)行。各工序施工前均進(jìn)行詳細(xì)的施工技術(shù)交底,統(tǒng)一施工工藝,加強(qiáng)過(guò)程控制,出專職質(zhì)檢員負(fù)責(zé)施工全過(guò)程的工序質(zhì)量檢查。確保各工序達(dá)到規(guī)定的質(zhì)量目標(biāo),防止出現(xiàn)不合格工序返工而影響工期的現(xiàn)象。在施工時(shí)如果因客觀原因而延誤工期時(shí),經(jīng)監(jiān)理工程師同意后,利用多加夜班,集中人力物力搶回關(guān)鍵線路工期。6、從安全生產(chǎn)上保證。加強(qiáng)職工法規(guī)、安全制度的學(xué)習(xí)與教育,增強(qiáng)安全生產(chǎn)觀念。對(duì)于新工人進(jìn)行崗位教育,對(duì)于特種操作人員,除接受一般性的安全教育外,還進(jìn)行專門的安全操作技術(shù)教育訓(xùn)練。在施工生產(chǎn)過(guò)程中,進(jìn)行經(jīng)常性在施工生產(chǎn)中,對(duì)安全生產(chǎn)進(jìn)行監(jiān)督檢查。并結(jié)合季節(jié)的特點(diǎn),做好防水、防觸電、防墜落、防坍塌、防火等各項(xiàng)措施和制度。項(xiàng)目經(jīng)理部成立安全小組,設(shè)專職人員負(fù)責(zé)日常的安全檢查、監(jiān)督,保證施工順利進(jìn)行。7、從后勤供應(yīng)上保證。加強(qiáng)機(jī)械設(shè)備和車輛保養(yǎng)、維修,保障施工正常運(yùn)轉(zhuǎn)。搞好職工食堂,防病治病,保障職工身體健康,保證正常的出勤率,確保工期。8、從工作關(guān)系及其協(xié)調(diào)上保證。根據(jù)不同工作關(guān)系的客觀性采取不同的處理方法。比如企業(yè)內(nèi)的經(jīng)濟(jì)協(xié)作關(guān)系經(jīng)過(guò)企業(yè)內(nèi)部分工、分責(zé)、分權(quán)、分利來(lái)解決。9、加強(qiáng)與工作各方的聯(lián)系,做好與當(dāng)?shù)鼐用竦膮f(xié)調(diào)工作,取得她們的支持與配合,使工程得以順利進(jìn)行。。二十四、組織保證措施1、快速進(jìn)場(chǎng),快速展開(kāi)我單位中標(biāo)后,迅速成立以項(xiàng)目經(jīng)理、總工程師為首的施工領(lǐng)導(dǎo)小組,根據(jù)工程各工序工種,合理組織勞動(dòng)力,配足人員、機(jī)具設(shè)備,統(tǒng)一指揮,統(tǒng)一調(diào)度,統(tǒng)一安排。主要施工人員、施工機(jī)械設(shè)備做到”三快”,即”進(jìn)場(chǎng)快、施工準(zhǔn)備快、開(kāi)工快”。2、準(zhǔn)備工作有條不紊進(jìn)場(chǎng)后,積極配合業(yè)主加強(qiáng)征地拆遷,創(chuàng)造良好的施工外部環(huán)境;施工便道、施工用水、用電及施工臨時(shí)設(shè)施本著先通后善的原則,在一個(gè)月內(nèi)全部完成,保證主體工程順利開(kāi)工。3、科學(xué)組織,合理安排加強(qiáng)施工計(jì)劃管理的科學(xué)性,突出重點(diǎn)、兼顧一般,運(yùn)用統(tǒng)籌學(xué)、網(wǎng)絡(luò)技術(shù)、系統(tǒng)工程進(jìn)行實(shí)施性施工組織設(shè)計(jì)編制;并在實(shí)施過(guò)程中針對(duì)實(shí)際情況不斷充實(shí)調(diào)整。4、人員保障組建強(qiáng)有力的項(xiàng)目經(jīng)理部,選派富有經(jīng)驗(yàn)、并具有敢打敢拼精神的工程師擔(dān)任項(xiàng)目經(jīng)理;并選派具有豐富施工經(jīng)驗(yàn)的專業(yè)化施工隊(duì)伍。5、設(shè)備保障本項(xiàng)目設(shè)備投入量大,施工前期一定要按計(jì)劃上足設(shè)備,并留有余地,加強(qiáng)保養(yǎng)和維修,保證設(shè)備的完好率。二十五、技術(shù)保證措施1、編制網(wǎng)絡(luò)計(jì)劃項(xiàng)目經(jīng)理部進(jìn)場(chǎng)后,將根據(jù)技術(shù)文件和合同文件要求及現(xiàn)場(chǎng)實(shí)際情況重新編制實(shí)施性網(wǎng)絡(luò)計(jì)劃,并以此進(jìn)行施工組織、調(diào)度、同時(shí)以此為依據(jù)編排月、旬、日作業(yè)計(jì)劃,特別對(duì)控制性工程和重點(diǎn)工程的施工必須制訂單項(xiàng)作業(yè)計(jì)劃,并具體采取如下措施進(jìn)行工期控制:2、按總體計(jì)劃工期90%的日歷天數(shù),制訂各單位工程目標(biāo)計(jì)劃和相應(yīng)措施。3、全面編制各項(xiàng)總工期、階段工期和工序作業(yè)工期三級(jí)網(wǎng)絡(luò)計(jì)劃,并向所設(shè)計(jì)工期的直接、間接施工隊(duì)伍分解落實(shí)。4、強(qiáng)化施工過(guò)程中的勞動(dòng)力、機(jī)械設(shè)備、材料供應(yīng)等資源平衡協(xié)調(diào)、監(jiān)督指導(dǎo)工作。5、預(yù)先制訂網(wǎng)
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 二零二五年度特殊功能性內(nèi)墻涂料研發(fā)與應(yīng)用合同3篇
- 二零二五年度公司對(duì)公司智能化辦公租賃合同3篇
- 2025上海市國(guó)有土地使用權(quán)出讓合同范本
- 二零二五年度能源企業(yè)公司掛靠能源供應(yīng)合同3篇
- 2025年度內(nèi)部承包合同協(xié)議書(shū):XX部門內(nèi)部承包銷售業(yè)績(jī)提成協(xié)議3篇
- 二零二五年度全款購(gòu)車車輛認(rèn)證合同模板3篇
- 二零二五年度農(nóng)村房屋贈(zèng)與合同附帶農(nóng)用設(shè)備配套協(xié)議
- 2025年度土地流轉(zhuǎn)承包與農(nóng)村金融服務(wù)合作協(xié)議3篇
- 二零二五年度解除勞動(dòng)合同經(jīng)濟(jì)補(bǔ)償金及員工心理咨詢服務(wù)合同3篇
- 2025年度辦公室租賃合同(含企業(yè)活動(dòng)策劃與執(zhí)行)3篇
- 2021-2022學(xué)年山東省濟(jì)寧市高一上學(xué)期期末考試英語(yǔ)試題(解析版)(不含聽(tīng)力音頻)
- T-PPAC 402-2022 企業(yè)專利密集型產(chǎn)品評(píng)價(jià)方法
- 配電自動(dòng)化終端運(yùn)行維護(hù)管理規(guī)定
- 監(jiān)護(hù)人考試試題
- 中醫(yī)醫(yī)療技術(shù)相關(guān)性感染預(yù)防與控制
- 2024年工貿(mào)重點(diǎn)企業(yè)有限空間作業(yè)專家指導(dǎo)服務(wù)專題培訓(xùn)
- 2024年注冊(cè)安全工程師考試題庫(kù)及參考答案【完整版】
- 第十二章 全等三角形 作業(yè)設(shè)計(jì)-2023-2024學(xué)年人教版八年級(jí)數(shù)學(xué)上冊(cè)
- 建筑結(jié)構(gòu)荷載規(guī)范DBJ-T 15-101-2022
- 制藥專業(yè)畢業(yè)設(shè)計(jì)開(kāi)題報(bào)告
- 普通心理學(xué)智慧樹(shù)知到期末考試答案2024年
評(píng)論
0/150
提交評(píng)論