XX項(xiàng)目總包工程一標(biāo)段
塔吊基礎(chǔ)施工方案
(格式最終版)
編制:
審核:
審批:
中國建筑第x工程局有限公司
2023年8月
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
目錄
第一章編制依據(jù)..........................................................................1
第二章工程概況..........................................................................2
2.1工程概況...........................................................................2
2.2設(shè)計(jì)概況...........................................................................2
2.2.1設(shè)計(jì)概況.......................................................................2
2.2.2塔吊基礎(chǔ)地質(zhì)及塔吊基礎(chǔ)標(biāo)高情況.................................................3
2.3工程施工條件......................................................................6
2.3.1工程現(xiàn)場條件...................................................................7
2.3.2場地工程地質(zhì)條件...............................................................7
2.3.3場地水文地質(zhì)條件...............................................................8
2.4場地情況..........................................................................8
第三章施工安排..........................................................................9
3.1項(xiàng)目管理組織......................................................................9
3.1.1組織機(jī)構(gòu)圖.....................................................................9
3.1.2職責(zé)分工.......................................................................9
3.2項(xiàng)目管理目標(biāo).......................................................................9
3.3各項(xiàng)資源供應(yīng)方式..................................................................10
3.3.1勞務(wù)資源安排一覽表............................................................10
3.3.2工程用大宗物資供應(yīng)安排一覽表..................................................10
3.4施工流水劃分及工藝流程...........................................................10
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對措施.................................................11
第四章施工進(jìn)度計(jì)劃.....................................................................12
第五章施工準(zhǔn)備與資源配置計(jì)劃...........................................................12
5.1施工準(zhǔn)備計(jì)劃......................................................................12
5.2資源配置計(jì)劃......................................................................13
第六章施工方法及工藝要求...............................................................14
6.1方案及技術(shù)參數(shù)....................................................................14
6.1.1塔吊平面定位..................................................................14
6.1.2塔吊基礎(chǔ)設(shè)計(jì)..................................................................17
6.2施工工藝流程......................................................................23
6.3施工要點(diǎn)..........................................................................24
6.3.1土方開挖......................................................................24
6.3.2樁基礎(chǔ)施工....................................................................24
6.3.3墊層澆筑......................................................................25
6.3.4預(yù)埋腳安裝....................................................................25
6.3.5鋼筋綁扎......................................................................26
6.3.6模板安裝......................................................................26
6.3.7混凝土澆筑....................................................................26
6.3.8混凝土試塊制作與留置..........................................................27
6.3.9塔吊防雷接地..................................................................27
6.4驗(yàn)收標(biāo)準(zhǔn).........................................................................27
6.5驗(yàn)收程序..........................................................................27
6.6驗(yàn)收內(nèi)容..........................................................................28
6.7驗(yàn)收人員..........................................................................28
第七章各項(xiàng)管理計(jì)劃.....................................................................29
7.1綠色施工管理計(jì)劃...................................................................29
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
7.1.1資源利用管理計(jì)劃..............................................................29
7.1.2環(huán)境管理計(jì)劃..................................................................30
7.2進(jìn)度管理計(jì)劃......................................................................31
7.2.1確定施工進(jìn)度控制點(diǎn)............................................................31
7.2.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工................................................31
7.2.3進(jìn)度管理措施..................................................................32
7.3質(zhì)量管理計(jì)劃.....................................................................33
7.4安全管理計(jì)劃......................................................................34
7.4.1職業(yè)健康安全管理目標(biāo)..........................................................34
7.4.2現(xiàn)場職業(yè)健康安全管理組織機(jī)構(gòu)和職責(zé)分工........................................34
7.4.3職業(yè)健康安全資源配置計(jì)劃......................................................34
7.5成品保護(hù)計(jì)劃......................................................................35
第八章應(yīng)急救援預(yù)案.....................................................................37
8.1應(yīng)急指揮機(jī)構(gòu)及職責(zé)...............................................................37
8.1.1應(yīng)急組織體系..................................................................37
8.1.2指揮機(jī)構(gòu)及職責(zé)................................................................37
8.2事故風(fēng)險分析.....................................................................38
8.3應(yīng)急救援程序.....................................................................38
8.4應(yīng)急處置措施.....................................................................38
8.4.1應(yīng)急處置總體措施..............................................................38
8.4.2觸電..........................................................................39
8.4.3高空墜落......................................................................40
8.4.4坍塌應(yīng)急預(yù)案..................................................................42
8.4.5機(jī)械傷害應(yīng)急預(yù)案..............................................................44
8.5應(yīng)急物資準(zhǔn)備.....................................................................45
8.6應(yīng)急響應(yīng)、響應(yīng)結(jié)束、演練.........................................................46
第九章計(jì)算書...........................................................................47
9.11#塔吊(TCT7015)矩形板式樁基礎(chǔ)計(jì)算書............................................47
9.1.1計(jì)算依據(jù)......................................................................47
9.1.2塔機(jī)屬性......................................................................47
9.1.3塔機(jī)荷載......................................................................47
9.1.4樁頂作用效應(yīng)計(jì)算..............................................................48
9.1.5樁承載力驗(yàn)算..................................................................49
9.1.6承臺計(jì)算......................................................................51
9.1.7配筋示意圖....................................................................53
9.22#塔吊(STT153)矩形板式樁基礎(chǔ)計(jì)算書...............................................54
9.2.1計(jì)算依據(jù)......................................................................54
9.2.2塔機(jī)屬性......................................................................55
9.2.3塔機(jī)荷載......................................................................55
9.2.4樁頂作用效應(yīng)計(jì)算..............................................................55
9.2.5樁承載力驗(yàn)算..................................................................57
9.2.6承臺計(jì)算......................................................................59
9.2.7配筋示意圖....................................................................61
9.33#塔吊(XGT6015A-8S)矩形板式樁基礎(chǔ)計(jì)算書..........................................62
9.3.1計(jì)算依據(jù)......................................................................62
9.3.2塔機(jī)屬性......................................................................62
9.3.3塔機(jī)荷載......................................................................63
9.3.4樁頂作用效應(yīng)計(jì)算..............................................................63
9.3.5樁承載力驗(yàn)算..................................................................65
9.3.6承臺計(jì)算......................................................................66
9.3.7酉己筋示意圖....................................................................69
9.44#塔吊(XGT6015A-8S)矩形板式樁基礎(chǔ)計(jì)算書..........................................70
2
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
9.4.1計(jì)算依據(jù)......................................................................70
9.4.2塔機(jī)屬性......................................................................70
9.4.3塔機(jī)荷載......................................................................71
9.4.4樁頂作用效應(yīng)計(jì)算..............................................................71
9.4.5樁承載力驗(yàn)算..................................................................73
9.4.6承臺計(jì)算......................................................................74
9.4.7配筋示意圖....................................................................77
9.55#塔吊(XGTT6012)矩形板式樁基礎(chǔ)計(jì)算書.............................................78
9.5.1計(jì)算依據(jù)......................................................................78
9.5.2塔機(jī)屬性......................................................................78
9.5.3塔機(jī)荷載......................................................................79
9.5.4樁頂作用效應(yīng)計(jì)算..............................................................79
9.5.5樁承載力驗(yàn)算..................................................................81
9.5.6承臺計(jì)算......................................................................82
9.5.7配筋示意圖....................................................................85
9.66#塔吊(XGT6015A-8S)矩形板式樁基礎(chǔ)計(jì)算書..........................................86
9.6.1計(jì)算依據(jù)......................................................................86
9.6.2塔機(jī)屬性......................................................................86
9.6.3塔機(jī)荷載......................................................................87
9.6.4樁頂作用效應(yīng)計(jì)算..............................................................87
9.6.5樁承載力驗(yàn)算..................................................................89
9.6.6承臺計(jì)算......................................................................90
9.6.7配筋示意圖....................................................................93
9.77#塔吊(XGT6015A-8S)矩形板式樁基礎(chǔ)計(jì)算書..........................................94
9.7.1計(jì)算依據(jù):....................................................................94
9.7.2塔機(jī)屬性......................................................................94
9.7.3塔機(jī)荷載......................................................................95
9.7.4樁承載力驗(yàn)算..................................................................97
9.7.5承臺計(jì)算......................................................................98
9.7.6配筋示意圖...................................................................101
9.88#塔吊、9#塔吊(TCT5513)矩形板式基礎(chǔ)計(jì)算書.......................................102
9.8.1計(jì)算依據(jù).....................................................................102
9.8.2塔機(jī)屬性.....................................................................102
9.8.3塔機(jī)荷載.....................................................................103
9.8.4基礎(chǔ)驗(yàn)算.....................................................................103
9.8.5配筋示意圖...................................................................109
3
項(xiàng)口總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
第一章編制依據(jù)
序號名稱內(nèi)容編號
1《危險性較大的分部分項(xiàng)工程安全管理辦法》住建部[2018]37號令
住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實(shí)施《危險性較大的
2建辦質(zhì)(2018)31號
分部分項(xiàng)工程安全管理規(guī)定》有關(guān)問題的通知
國家行政文件
《建筑工程五方責(zé)任主體項(xiàng)目負(fù)責(zé)人質(zhì)量終身責(zé)
3建質(zhì)[2014]124號
任追究暫行辦法建質(zhì)》
4《工程質(zhì)量治理兩年行動方案》建質(zhì)[20141130號
《建筑施工塔式起重機(jī)安裝使用、拆卸安全技術(shù)
JGJ196-2010
5規(guī)程》
《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
國家行業(yè)規(guī)范
6《塔式起重機(jī)混凝土基礎(chǔ)工程技術(shù)規(guī)程》JGJ/T187-2019
7《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范(2015版)》GB50010-2010
8《建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范》GB50007-2011
9圖紙“XX項(xiàng)目”工程設(shè)計(jì)圖紙
10圖集《混凝土結(jié)構(gòu)施工圖》(基礎(chǔ)部分)16G101-3
11地質(zhì)報(bào)告XX項(xiàng)目巖土工程勘察技術(shù)報(bào)告
12塔式起重機(jī)使用說明書
其他參考資料
13本企業(yè)有關(guān)規(guī)定
1
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
第二章工程概況
2.1工程概況
表2.17工程概況一覽表
工程名稱XX項(xiàng)目總包工程一標(biāo)段工程性質(zhì)醫(yī)療建筑
建設(shè)規(guī)模地下2層,地上9層工程地址
總占地面積81968.12m2總建筑面積226288.58m2
建設(shè)單位項(xiàng)目承包范圍土建工程、機(jī)電工程等
設(shè)計(jì)單位主要分包工程土建工程、機(jī)電工程等
勘察單位合同質(zhì)量爭創(chuàng)遼寧省優(yōu)質(zhì)結(jié)構(gòu)工程
要求開工日期:2021年9月1日,
監(jiān)理單位工期
竣工日期:2022年10月1日。
爭創(chuàng)“遼寧省安全文明施工標(biāo)準(zhǔn)化工
安全
總承包單位中國建筑第X工程局有限公司地”
科技爭創(chuàng)“遼寧省新技術(shù)應(yīng)用示范工程”
工程主要功
醫(yī)療建筑
能或用途
醫(yī)院主樓整體按使用功能分為住院樓、急診樓、急診住院樓、感染樓和門診樓,涵
蓋核醫(yī)學(xué)、血透、感染病房、婦產(chǎn)科、ICU病房、手術(shù)室等功能性科室房間。
項(xiàng)目地下整體2層,地上最高9層,建筑高度為42.95m。門診樓地上4層,建筑高
度23.5mo
2.2設(shè)計(jì)概況
2.2.1設(shè)計(jì)概況
本工程±0相當(dāng)于絕對標(biāo)高54.900m,塔吊基礎(chǔ)承臺頂標(biāo)高與地下底板頂標(biāo)高一平,
即絕對標(biāo)高44.13m。
本工程塔吊選型及基礎(chǔ)概況如下表所示:
塔吊混凝土
序號型號基礎(chǔ)形式矩形板式基礎(chǔ)尺寸樁基礎(chǔ)尺寸
編號標(biāo)號
中600灌注樁(4根),樁長
11#TCT7015板式樁基礎(chǔ)7.0mX7.0mX1.4mC35
27m,樁心間距4m
①600灌注樁(4根),樁長
22#STT153板式樁基礎(chǔ)6.45mX6.45mX1.7mC35
25m
33#XGT6015A-板式樁基礎(chǔ)5.8mX5.8mxi.2m中600灌注樁(4根),樁長C35
rrrrrrrk
nnrrrrrrr
rrrrrrrrr
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
塔吊混凝土
序號型號基礎(chǔ)形式矩形板式基礎(chǔ)尺寸樁基礎(chǔ)尺寸
編號標(biāo)號
8S25m
XGT601SA-①600灌注樁(4根),樁長
44#板式樁基礎(chǔ)5.8mX5.8mX1.2mC35
SS25m
①600灌注樁(4根),樁長
55#XGTT6012-8板式樁基礎(chǔ)6mX6mX1.5mC35
25m
XGT601SA-①600灌注樁(4根),樁長
66#板式樁基礎(chǔ)5.8mX5.8mX1.2mC35
SS25m
XGT601SA-①600灌注樁(4根),樁長
77#板式樁基礎(chǔ)5.8mX5.8mX1.2mC35
SS25m
88#TCT5513-8F板式基礎(chǔ)7.OmX7.OmX1.5m/C35
99#TCT5513-8F板式基礎(chǔ)7.0mX7.OmX1.5m/C35
本工程各塔吊基礎(chǔ)絕對標(biāo)高及所在持力層情況統(tǒng)計(jì)如下表所示:
板式基礎(chǔ)標(biāo)高樁基礎(chǔ)標(biāo)高
塔吊板式基礎(chǔ)底部樁基礎(chǔ)底部
序號(頂標(biāo)高/底標(biāo)(頂標(biāo)高/底標(biāo)
編號持力層/承載力持力層/承載力
高)高)
11#44.13m/42.73m雜填土/042.73m/17.13m全風(fēng)化花崗巖/300
22#44.13m/42.43m雜填土/042.43m/19.13m圓礫含黏性土/280
33#44.13m/42.93m雜填土/042.93m/19.13m全風(fēng)化花崗巖/3OO
44#44.13m/42.93m雜填土/042.93m/19.13m全風(fēng)化花崗巖/300
55#44.13m/42.63m雜填土/042.63m/19.13m全風(fēng)化花崗巖/300
66#44.13m/42.93m雜填土/042.93m/19.13m全風(fēng)化花崗巖/300
77#44.13m/42.93m雜填土/042.93m/19.13m全風(fēng)化花崗巖/300
88#44.13m/42.63m圓礫/350//
99#44.13m/42.63m圓礫/350//
2.2.2塔吊基礎(chǔ)地質(zhì)及塔吊基礎(chǔ)標(biāo)高情況
根據(jù)廠家提供的基礎(chǔ)圖設(shè)計(jì)圖,所選用的塔吊所需地耐力最低不小于120KPao各塔
吊基礎(chǔ)地質(zhì)情況,及塔吊基礎(chǔ)標(biāo)高位置地質(zhì)情況如下圖所示:
nmrrrrrr
rrrrrrrrr3
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
黜部日森"一"*
塔吊承臺基礎(chǔ)底標(biāo)高位置
(42.73m)
樁基礎(chǔ)底標(biāo)高位置
(17.13m)
+144.00(8.12)+144.00(8.03)
圖2.2-11#塔吊基礎(chǔ)區(qū)域工程地質(zhì)剖面圖
?M3.00(8.72)
圖2.2-22#塔吊基礎(chǔ)區(qū)域工程地質(zhì)剖面圖
4
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
塔吊承臺基礎(chǔ)底標(biāo)高位置
(42.93m)
塔吊樁基礎(chǔ)底標(biāo)高位置
(19.13m)
TMIW一弧>叫碘www一士-
圖2.2-33#塔吊、4#塔吊基礎(chǔ)區(qū)域工程地質(zhì)剖面圖
懸言能黑齡矗
塔吊承臺基礎(chǔ)底標(biāo)高
i塔吊樁基礎(chǔ)底標(biāo)高位
;置(19.13m)
c?
圖2.2-45#塔吊基礎(chǔ)區(qū)域工程地質(zhì)剖面圖
5
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
物li.
$14669
①
塔吊承臺基礎(chǔ)底標(biāo)
「is
局位置(42.93m)
<
塔吊樁基礎(chǔ)底標(biāo)高位
r置(42.93m)
目領(lǐng)麗④
顆血ft與.丁
圖2.2-56#塔吊、7#塔吊基礎(chǔ)區(qū)域工程地質(zhì)剖面圖
55.29見
塔吊承臺基礎(chǔ)底標(biāo)
高位置(42.63m)
2.3工程施工條件
6
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
2.3.1工程現(xiàn)場條件
1場地已封閉完成,基坑土方開挖完成,圍擋內(nèi)場地規(guī)劃已完成,項(xiàng)目西側(cè)、南
側(cè)、東側(cè)為城市主干路。
2正在施工基底清土施工。
圖2.3-1塔吊定位及周邊道路情況
2.3.2場地工程地質(zhì)條件
根據(jù)現(xiàn)場鑒別、原位測試及土分析結(jié)果,將場地土巖性特征自上而下分述如下:
承載力特征壓縮模量Es或變側(cè)阻力特征值端阻力特征值
圖層名稱
值fak(Kpa)形模量Eaqsa(kpa)qpa(kpa)
-7(回填8年)
雜填土///
-10(回填<3年)
粉質(zhì)粘土②100EsO.1-0.2=5.915.0/
中砂②1150Eo=9.219.0/
細(xì)砂②2120Eo=8.814.5/
圓礫③350Eo=18.535.0/
礫砂③1320Eo=21.230.0/
圓礫④450Eo=24.145.0/
礫砂④1400Eo=25.840.0/
粗砂④2300Eo=18.029.5/
粉質(zhì)黏土④3120EsO.1-0.2=5.315.5/
圓礫含黏性土⑤280Eo=15.728.0/
全風(fēng)化花崗巖⑥300Eo=18.130.01700
7
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
承載力特征壓縮模量Es或變側(cè)阻力特征值端阻力特征值
圖層名稱
值fak(Kpa)形模量Eaqsa(kpa)qpa(kpa)
強(qiáng)風(fēng)化花崗巖⑦500Eo=55.52300
中等風(fēng)化花崗巖
1000Eo=200.03500
⑧/
2.3.3場地水文地質(zhì)條件
擬建場區(qū)勘探期間賦存地下水,地下水類型為孔隙潛水,主要含水層為圓礫④及以
下地層。本次勘察期間于鉆孔內(nèi)現(xiàn)場實(shí)測到的地下水初見水位埋深為3.10m?11.00m;
初見水位高程為41.19m?45.24m;穩(wěn)定水位埋深為2.20m?10.60mm。穩(wěn)定水位高程為
44.00m?45.61m。
水位隨季節(jié)變化,變化幅度2?3米左右。同時地下水位變化受人為活動影響較大。
市區(qū)部分工廠搬遷、自備井減少、地下水資源開采實(shí)行統(tǒng)一管理及渾河設(shè)攔水壩提高河
水位等諸多因素綜合作用,沈陽市區(qū)地下水位十多年來總體上呈上升趨勢,2005年豐水
期較上年上升幅度一般在0.5?1.5m之間,部分地區(qū)上升幅度1.5?2.7m。
2.4場地情況
本工程±0.000相當(dāng)于絕對標(biāo)高54.90m,地下室底板頂絕對標(biāo)高為44.13m。
場內(nèi)三個地下分區(qū),分別為A區(qū)、B區(qū)、C區(qū),均為地下二層,基坑平均深度約10m,
1#塔吊、2#塔吊位于A區(qū),3#塔吊、5#塔吊、6#塔吊、7#塔吊位于B區(qū),4#塔吊、8#塔
吊與9#塔吊位于C區(qū)。
場內(nèi)道路位于西、南、東三側(cè),北側(cè)為本工程二、三標(biāo)段施工區(qū)域。地下室施工階
段,在中間設(shè)有25m寬預(yù)留區(qū)域。
什8
項(xiàng)目總包工程一標(biāo)段塔吊基礎(chǔ)施工方案
第三章施工安排
3.1項(xiàng)目管理組織
3.1.1組織機(jī)構(gòu)圖
圖3.1-1組織機(jī)構(gòu)圖
3.1.2職責(zé)分工
表3.1T項(xiàng)目管理人員職責(zé)分工表
序號管理職務(wù)姓名
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 快遞加盟合作協(xié)議書模板
- 公務(wù)車輛維修服務(wù)合同樣本
- 國際法買賣合同范本2024年
- 工程代建委托協(xié)議范本
- 2024工廠轉(zhuǎn)讓協(xié)議書樣式
- 2024年版離婚協(xié)議書怎么寫
- 拖拉機(jī)交易協(xié)議書
- 2024年標(biāo)準(zhǔn)離婚協(xié)議書參考范文
- 專利技術(shù)許可協(xié)議書
- 2024年裝修合同保密協(xié)議模板范本
- 小學(xué)《魔方》校本課程綱要
- 天線測試手冊
- 高中數(shù)學(xué)-圓的標(biāo)準(zhǔn)方程教學(xué)課件設(shè)計(jì)
- 簽訂《商品房買賣合同》業(yè)務(wù)流程圖
- 設(shè)備設(shè)施檢維修及驗(yàn)收記錄表
- cia題庫第二部分
- 純音聽閾測試(曹永茂)
- 喉罩(LMA)-麻醉課件
- 新課標(biāo)背景下高中數(shù)學(xué)大單元教學(xué)的實(shí)施策略
- 中國近代史綱要3
- 無負(fù)壓供水設(shè)備管網(wǎng)疊壓無負(fù)壓變頻供水設(shè)備選型樣本數(shù)據(jù)手冊
評論
0/150
提交評論