項(xiàng)目專項(xiàng)施工方案
津西體2023-012號(hào)地塊工程
施工電梯基礎(chǔ)及安拆方案
編制單位:
編制人:
日期:
項(xiàng)目專項(xiàng)施工方案
目錄
1編制依據(jù)........................................................................................................................................................1
2工程概況........................................................................................................................................................2
2.1工程建設(shè)概況........................................................................................................................................................2
2.2設(shè)計(jì)概況...............................................................................................................................................................3
2.3工程施工條件........................................................................................................................................................3
3施工安排........................................................................................................................................................5
3.1項(xiàng)目管理組織........................................................................................................................................................5
3.2項(xiàng)目管理目標(biāo)........................................................................................................................................................6
3.3各項(xiàng)資源供應(yīng)方式................................................................................................................................................6
3.4施工流水段的劃分及施工工藝流程....................................................................................................................7
3.4.1施工流水段的劃分.........................................................................................................................................7
3.4.2施工工藝流程.................................................................................................................................................8
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施................................................................................................................8
3.6關(guān)鍵及特殊過程控制............................................................................................................................................9
4施工進(jìn)度計(jì)劃..............................................................................................................................................10
4.1工期進(jìn)度目標(biāo)......................................................................................................................................................10
4.2施工總進(jìn)度計(jì)劃及保證措施..............................................................................................................................10
4.2.1組織管理措施...............................................................................................................................................10
4.2.2技術(shù)措施.......................................................................................................................................................10
4.2.3確保工期的保證措施...................................................................................................................................10
5施工準(zhǔn)備與資源配置計(jì)劃............................................................................................................................11
5.1施工準(zhǔn)備計(jì)劃......................................................................................................................................................11
5.2資源配置計(jì)劃......................................................................................................................................................11
5.2.1勞動(dòng)力配置計(jì)劃...........................................................................................................................................11
5.2.2工程用原材料需要量計(jì)劃...........................................................................................................................12
5.2.3施工機(jī)具配置計(jì)劃.......................................................................................................................................13
5.2.4測(cè)量計(jì)量?jī)x器配置計(jì)劃...............................................................................................................................13
6施工方法及工藝要求...................................................................................................................................14
6.1方案及技術(shù)參數(shù)..................................................................................................................................................14
-1-
項(xiàng)目專項(xiàng)施工方案
6.1.1施工電梯基礎(chǔ)施工方案及技術(shù)參數(shù).........................................................................................................16
6.1.2車庫頂板支撐方案及技術(shù)參數(shù).................................................................................................................18
6.1.3電梯附墻方案及技術(shù)參數(shù).........................................................................................................................18
6.2施工工藝流程......................................................................................................................................................19
6.2.1施工電梯安裝工藝流程.............................................................................................................................19
6.2.2施工電梯拆除工藝流程.............................................................................................................................19
6.3施工電梯安裝控制要點(diǎn)......................................................................................................................................19
6.3.1安裝外籠底盤.............................................................................................................................................19
6.3.2標(biāo)準(zhǔn)節(jié)、吊籠、外籠安裝及調(diào)整.............................................................................................................19
6.3.3導(dǎo)軌架接高.................................................................................................................................................22
6.3.4附著架的安裝.............................................................................................................................................23
6.3.5滑觸線安裝.................................................................................................................................................23
6.3.6調(diào)試.............................................................................................................................................................25
6.3.7安全限位安裝及試運(yùn)行.............................................................................................................................25
6.3.8驗(yàn)收.............................................................................................................................................................25
6.3.9施工電梯防護(hù).............................................................................................................................................31
6.3.10層門安裝...................................................................................................................................................32
6.3.11電梯使用前的檢查...................................................................................................................................33
6.3.12使用...........................................................................................................................................................34
6.3.13過程監(jiān)測(cè)...................................................................................................................................................34
6.4施工電梯拆卸.....................................................................................................................................................36
6.4.1電纜導(dǎo)向裝置的拆卸.................................................................................................................................36
6.4.2導(dǎo)軌架及附墻架的拆卸.............................................................................................................................36
6.4.3上傳動(dòng)機(jī)構(gòu)、吊籠的拆卸.........................................................................................................................36
6.4.4護(hù)欄底架的拆卸.........................................................................................................................................37
6.4.5現(xiàn)場(chǎng)清理.....................................................................................................................................................37
7各項(xiàng)管理計(jì)劃...........................................................................................................................................38
7.1進(jìn)度管理計(jì)劃......................................................................................................................................................38
7.1.1施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工.........................................................................................................38
7.1.2進(jìn)度管理措施.............................................................................................................................................38
7.1.3職責(zé)分工.....................................................................................................................................................39
7.2質(zhì)量管理計(jì)劃......................................................................................................................................................39
7.2.1質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工.............................................................................................................39
7.2.2施工電梯安拆質(zhì)量保證措施.....................................................................................................................39
-2-
項(xiàng)目專項(xiàng)施工方案
7.2.3施工電梯安裝后的質(zhì)量檢查.....................................................................................................................40
7.3安全管理計(jì)劃......................................................................................................................................................40
7.3.1職業(yè)健康安全管理分解目標(biāo).....................................................................................................................40
7.3.2安全管理組織機(jī)構(gòu)和職責(zé)分工.................................................................................................................41
7.3.3職業(yè)健康安全重大危險(xiǎn)源.........................................................................................................................41
7.3.4安全生產(chǎn)保證措施.....................................................................................................................................42
7.4環(huán)境管理計(jì)劃......................................................................................................................................................43
7.4.1環(huán)境管理目標(biāo).............................................................................................................................................43
7.4.2重大環(huán)境因素清單.....................................................................................................................................43
7.5綠色施工管理計(jì)劃..............................................................................................................................................43
7.5.1綠色施工組織機(jī)構(gòu)和職責(zé)分工.................................................................................................................43
7.5.2綠色施工實(shí)施措施.....................................................................................................................................44
7.5.3綠色施工評(píng)價(jià).............................................................................................................................................44
7.6成品保護(hù)管理計(jì)劃..............................................................................................................................................44
7.6.1成品保護(hù)管理組織和職責(zé)分工.................................................................................................................44
7.6.2成品保護(hù)計(jì)劃及保證措施.........................................................................................................................44
8應(yīng)急預(yù)案......................................................................................................................................................45
8.1組織機(jī)構(gòu)及職責(zé)分工..........................................................................................................................................45
8.2預(yù)防與預(yù)警..........................................................................................................................................................46
8.3信息報(bào)告程序......................................................................................................................................................46
8.4應(yīng)急處置.............................................................................................................................................................47
8.4.1相應(yīng)分級(jí).......................................................................................................................................................47
8.4.2響應(yīng)程序.......................................................................................................................................................47
8.4.3處置措施.......................................................................................................................................................47
8.4.4疫情防控處置措施.......................................................................................................................................47
9計(jì)算書..........................................................................................................................................................49
9.1雙籠施工電梯相關(guān)計(jì)算書..................................................................................................................................50
9.2單籠施工電梯相關(guān)計(jì)算書..................................................................................................................................53
-3-
項(xiàng)目專項(xiàng)施工方案
1編制依據(jù)
序號(hào)類別文件名稱編號(hào)
第十三屆中華人民共和國主席
1《中華人民共和國建筑法》
令第二十九號(hào)
第十三屆中華人民共和國主席
2《中華人民共和國安全生產(chǎn)法》
令第八十八號(hào)
國家行政中華人民共和國國務(wù)院令(第
3《建設(shè)工程安全生產(chǎn)管理?xiàng)l例》
文件393號(hào))
中華人民共和國住房和城鄉(xiāng)建
4《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定》
設(shè)部令第37號(hào)
《住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實(shí)施<危險(xiǎn)性較大的
5建辦質(zhì)〔2018〕31號(hào)
分部分項(xiàng)工程安全管理規(guī)定>有關(guān)問題的通知》
6《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范》GB50010-2010
7《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2012
8《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50204-2015
9《電氣裝置安裝工程接地裝置施工及驗(yàn)收規(guī)范》GB50169-2016
10國家行業(yè)《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
11規(guī)范《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
12《建筑施工升降機(jī)安裝、使用、拆卸安全技術(shù)規(guī)程》JGJ215-2010
13《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
14《施工現(xiàn)場(chǎng)機(jī)械設(shè)備檢查技術(shù)規(guī)范》JGJ160-2016
15《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范》(附條文說明)JGJ46-2005
地方規(guī)范
16《天津市建設(shè)工程施工現(xiàn)場(chǎng)安全管理規(guī)程》DB29-113-2011
標(biāo)準(zhǔn)
17合同本工程施工總承包合同/
18本工程藍(lán)圖/
設(shè)計(jì)文件
19本工程施工組織設(shè)計(jì)/
企業(yè)管理
20《安全施工管理手冊(cè)》2023版
文件
21其它《SC型施工升降機(jī)使用說明書》/
1
項(xiàng)目專項(xiàng)施工方案
2工程概況
2.1工程建設(shè)概況
本工程地塊位于天津市河西區(qū),項(xiàng)目東至河西區(qū)中心小學(xué)東湖分校,西至環(huán)湖中路,
南至規(guī)劃紀(jì)莊子北道,北至體院北道。
體院北道
環(huán)湖中路
紀(jì)莊子北道
圖2.1項(xiàng)目效果圖
本工程分為1#~20#住宅樓建筑,公建分為配建1#~4#樓,建筑面積118501.48㎡;地
下共一層,建筑面積50000㎡。小學(xué)綜合樓及附屬用房建筑面積16300㎡。業(yè)態(tài)以精裝修商
品房住宅為主,包含高層、多層住宅、地庫、及配套公建。
工程名稱工程性質(zhì)住宅
建設(shè)規(guī)模833351749.00元工程地址
總占地面積79485.1㎡總建筑面積18.4萬㎡
本工程承包范圍包括地基基礎(chǔ)、土
建工程、裝飾裝修工程、幕墻工程、
采暖通風(fēng)工程、電氣工程、給排水
建設(shè)單位項(xiàng)目承包范圍工程、弱電智能化工程、消防工程、
人防工程、機(jī)電工程、景觀工程、
電梯工程、防雷工程、室外配套工
程及各種管線預(yù)留預(yù)埋工程。
設(shè)計(jì)單位主要分包工程/
2
項(xiàng)目專項(xiàng)施工方案
實(shí)量合格率大于95%,實(shí)測(cè)實(shí)量綜合
勘察單位質(zhì)量得分不低于92分,創(chuàng)天津市“海河
杯”獎(jiǎng)。
監(jiān)理單位工期834日歷天
總承包單位魯能集團(tuán)公司安全性查評(píng)得分不得
合同
低于85分,實(shí)現(xiàn)文明施工標(biāo)準(zhǔn)化
要求100%落地,爭(zhēng)創(chuàng)文明示范工地。確
安全保取得天津市安全文明示范工地。
分包單位
不發(fā)生坍塌、傾覆、高空墜落、觸
電、火災(zāi)、人身傷亡等重大安全事
故。
工程主要功能或
高端住宅,包括高層、多層、洋房
用途
2.2設(shè)計(jì)概況
根據(jù)本工程結(jié)構(gòu)圖紙、結(jié)構(gòu)高度、現(xiàn)場(chǎng)總平面管理情況,為滿足主體結(jié)構(gòu)、二次結(jié)構(gòu)、
裝飾階段施工人員和材料的垂直運(yùn)輸要求,本工程?hào)|半?yún)^(qū)電梯配置情況見下表。
序號(hào)樓座結(jié)構(gòu)形式建筑高度建筑層數(shù)電梯型號(hào)
11#樓剪力墻結(jié)構(gòu)53.7m地上18層/地下1層SC200/200
22#樓剪力墻結(jié)構(gòu)53.7m地上18層/地下1層SC200/200
35#樓剪力墻結(jié)構(gòu)22.15m地上7層/地下1層SC200/200
46#樓剪力墻結(jié)構(gòu)22.15m地上7層/地下1層SC200/200、SC200
57#樓剪力墻結(jié)構(gòu)46.95m地上15層/地下1層SC200
610#樓剪力墻結(jié)構(gòu)46.95m地上15層/地下1層SC200
711#樓剪力墻結(jié)構(gòu)22.15m地上7層/地下1層SC200/200、SC200
812#樓剪力墻結(jié)構(gòu)53.7m地上18層/地下1層SC200/200
913#樓剪力墻結(jié)構(gòu)53.7m地上18層/地下1層SC200/200
1014#樓剪力墻結(jié)構(gòu)53.7m地上18層/地下1層SC200
2.3工程施工條件
1、主體結(jié)構(gòu)需施工至8層及以上。
2、施工電梯安裝施工時(shí),現(xiàn)場(chǎng)設(shè)置塔吊配合施工電梯材料加工、轉(zhuǎn)運(yùn)、安拆施工等。
3、施工電梯基礎(chǔ)混凝土試驗(yàn)報(bào)告需出具,施工電梯安裝告知需報(bào)備完畢。
4、施工電梯基礎(chǔ)底部頂板采用鋼管腳手架回頂加固。
3
項(xiàng)目專項(xiàng)施工方案
3施工安排
3.1項(xiàng)目管理組織
表3.1-1總承包項(xiàng)目管理人員及職責(zé)分工
序號(hào)管理職務(wù)姓名職責(zé)和權(quán)限
負(fù)責(zé)施工電梯工程的全面管理與指揮,認(rèn)真履行合同,負(fù)責(zé)并完成施
1項(xiàng)目經(jīng)理工電梯工程施工方案的順利實(shí)施,簽署各項(xiàng)指令和文件,組織并主持
工程驗(yàn)收。
負(fù)責(zé)指導(dǎo)和處理在施工電梯工程施工過程中所遇到的一切技術(shù)問題,
2項(xiàng)目總工并參與施工過程的管理,負(fù)責(zé)現(xiàn)場(chǎng)施工組織策劃、施工技術(shù)與管理,
以及施工進(jìn)度、成本、質(zhì)量和安全控制等。
負(fù)責(zé)施工電梯工程施工現(xiàn)場(chǎng)安全文明與進(jìn)度總管理,協(xié)調(diào)現(xiàn)場(chǎng)施工組
3生產(chǎn)經(jīng)理
織策劃,以及施工進(jìn)度、成本、質(zhì)量和安全控制等。
直接領(lǐng)導(dǎo)商務(wù)部的各項(xiàng)管理工作;監(jiān)督分包的履約情況,控制工程造
4商務(wù)經(jīng)理
價(jià)和工程進(jìn)度款的支付情況。
加強(qiáng)對(duì)分包單位的質(zhì)量檢查和監(jiān)督,確保分包單位的質(zhì)量符合規(guī)范要
5質(zhì)量總監(jiān)求;
負(fù)責(zé)工程創(chuàng)優(yōu)和評(píng)獎(jiǎng)的策劃、組織、資料準(zhǔn)備和日常管理工作。
負(fù)責(zé)現(xiàn)場(chǎng)安全文明生產(chǎn)、文明施工、施工人員上崗安全教育及安全設(shè)
6安全總監(jiān)
施監(jiān)督檢查與保衛(wèi)工作。
物資工程
7負(fù)責(zé)現(xiàn)場(chǎng)材料儲(chǔ)備進(jìn)場(chǎng)材料驗(yàn)收,確保進(jìn)場(chǎng)所有材料均為合格產(chǎn)品
師
對(duì)現(xiàn)場(chǎng)工程進(jìn)度、質(zhì)量進(jìn)行全面監(jiān)督;貫徹國家及天津市的有關(guān)工程
專業(yè)工程
8施工規(guī)范、工藝規(guī)程、質(zhì)量標(biāo)準(zhǔn),嚴(yán)格執(zhí)行國家施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)
師
準(zhǔn),確保項(xiàng)目總體進(jìn)度、質(zhì)量目標(biāo)和階段質(zhì)量目標(biāo)的實(shí)現(xiàn)。
技術(shù)工程
9負(fù)責(zé)現(xiàn)場(chǎng)測(cè)量復(fù)核、方案報(bào)審等。
師
表3.1-2專業(yè)分包項(xiàng)目管理人員及職責(zé)分工
序號(hào)管理職務(wù)姓名職責(zé)和權(quán)限
負(fù)責(zé)施工電梯工程的全面管理與指揮,認(rèn)真履行合同,負(fù)責(zé)并完成施
1項(xiàng)目經(jīng)理工電梯工程施工方案的順利實(shí)施,簽署各項(xiàng)指令和文件,組織并主持
工程驗(yàn)收。
1)全面負(fù)責(zé)項(xiàng)目的技術(shù)管理工作,負(fù)責(zé)施工電梯施工方案的編制和方
2技術(shù)負(fù)責(zé)案的交底。
2)全面負(fù)責(zé)施工電梯的技術(shù)、質(zhì)量管理及驗(yàn)收工作。
3現(xiàn)場(chǎng)負(fù)責(zé)1)負(fù)責(zé)工程質(zhì)量的現(xiàn)場(chǎng)監(jiān)督檢查和施工電梯施工的質(zhì)量驗(yàn)收。
4
項(xiàng)目專項(xiàng)施工方案
序號(hào)管理職務(wù)姓名職責(zé)和權(quán)限
2)負(fù)責(zé)一般不合格品的處置,發(fā)現(xiàn)嚴(yán)重不合格品及時(shí)報(bào)告技術(shù)負(fù)責(zé)人,
并負(fù)責(zé)處置后的質(zhì)量驗(yàn)收與評(píng)定。
3)對(duì)施工電梯施工班組提出質(zhì)量獎(jiǎng)罰。
4)質(zhì)量驗(yàn)收文件的記錄與整理。
1)參與施工電梯工程危險(xiǎn)源辨識(shí)、風(fēng)險(xiǎn)評(píng)價(jià)與控制策劃,參與環(huán)境因
素的識(shí)別與評(píng)價(jià)。
2)參與施工電梯工程職業(yè)健康安全與環(huán)境管理規(guī)劃、管理方案及技術(shù)
措施方案的制定,落實(shí)相關(guān)責(zé)任。
4安全負(fù)責(zé)
3)巡回進(jìn)行施工電梯工程職業(yè)健康安全/環(huán)境管理檢查,對(duì)關(guān)鍵特性
參數(shù)定期監(jiān)測(cè),發(fā)現(xiàn)問題下達(dá)整改通知單,并對(duì)整改情況進(jìn)行驗(yàn)證。
4)負(fù)責(zé)施工電梯工程職業(yè)健康安全/環(huán)境應(yīng)急準(zhǔn)備檢查,按應(yīng)急預(yù)案
進(jìn)行響應(yīng)。
3.2項(xiàng)目管理目標(biāo)
項(xiàng)目管理目標(biāo)名稱目標(biāo)值
工期管理目標(biāo)2023年11月30日-2023年4月5日,共126日歷天
質(zhì)量管理目標(biāo)符合施工升降機(jī)標(biāo)準(zhǔn)規(guī)范和方案要求,確保一次性驗(yàn)收合格。
零傷亡,無安全事故發(fā)生,無高空墜落事故,觸電事故,無施工升降機(jī)
安全管理目標(biāo)
倒塌事故及重傷事故發(fā)生。
1)符合天津市綠色施工要求,推行“四節(jié)一環(huán)保”
綠色施工目標(biāo)2)在施工過程中減少噪音排放,施工現(xiàn)場(chǎng)噪聲達(dá)標(biāo)排放;
3)施工現(xiàn)場(chǎng)固體廢棄物分類收集安全處置;無環(huán)境問題投訴。
科技目標(biāo)目標(biāo)按時(shí)完成分公司下發(fā)的指標(biāo)任務(wù)
3.3各項(xiàng)資源供應(yīng)方式
1)勞務(wù)資源安排一覽表
專業(yè)施工隊(duì)名開始施工時(shí)建設(shè)工分包商
施工項(xiàng)目名稱資質(zhì)要求分包方式責(zé)任人
稱間期選擇方式
北京天和建筑
施工電梯安拆機(jī)械設(shè)備租賃/2126天專業(yè)分包公司選定
有限責(zé)任公司
2)大型機(jī)械設(shè)備采購供應(yīng)安排一覽表
機(jī)械設(shè)備名稱擬選供應(yīng)商提供方式要求進(jìn)場(chǎng)時(shí)間計(jì)劃出場(chǎng)時(shí)間責(zé)任人
北京天和建筑機(jī)械
施工電梯設(shè)備租賃有限責(zé)任租賃22
公司
5
項(xiàng)目專項(xiàng)施工方案
3.4施工流水段的劃分及施工工藝流程
施工流水段的劃分
根據(jù)平面施工部署及各樓座施工進(jìn)度,施工電梯安裝時(shí)間根據(jù)各樓座施工進(jìn)度及時(shí)穿
插,在各樓座施工至6層時(shí),通知電梯租賃單位準(zhǔn)備進(jìn)場(chǎng),上報(bào)安裝資料審查,確保各樓
座施工至9層時(shí),施工電梯投入使用。
圖3.4.1施工電梯總平面布置圖
3.4.2施工工藝流程
6
項(xiàng)目專項(xiàng)施工方案
施工電梯基礎(chǔ)施工→底架就位→安裝兩個(gè)標(biāo)準(zhǔn)節(jié)→安裝吊籠→安裝標(biāo)準(zhǔn)節(jié)→安裝驅(qū)
動(dòng)裝置→安裝標(biāo)準(zhǔn)節(jié)及頂護(hù)欄→安裝底護(hù)欄→安裝下限位碰塊→安裝附著架→安裝電纜
導(dǎo)向架→安裝樓層通道門→安裝并調(diào)整限位塊→檢測(cè)、驗(yàn)收。
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施
序號(hào)重點(diǎn)和難點(diǎn)具體分析應(yīng)對(duì)措施責(zé)任人
導(dǎo)軌架垂直度及底座的水提前準(zhǔn)備墊片,每道附墻前后必須測(cè)量垂直
底座及導(dǎo)軌
1平度不易控制,電梯廂與外度,預(yù)埋件安裝前進(jìn)行多方復(fù)核,確保電梯
架的安裝
立面間距不易控制。廂與外立面間距符合設(shè)計(jì)要求。
施工電梯安拆屬于危險(xiǎn)性編制與實(shí)際工程密切相符的施工技術(shù)方案,
危險(xiǎn)性較大,
較大分項(xiàng)工程,在安拆過程施工電梯安拆前對(duì)作業(yè)人員進(jìn)行詳細(xì)的安
2安全管理較
中存在傾覆、沖頂、高處墜全技術(shù)交底。施工過程中進(jìn)行旁站監(jiān)督,使
難
落等危險(xiǎn)源。用過程中日、周、月巡檢全覆蓋。
電梯使用過
施工電梯司機(jī)責(zé)任心不強(qiáng),施工電梯司機(jī)必須經(jīng)專門安全技術(shù)培訓(xùn),考
3程過程控制
操作不當(dāng)。試合格,持證上崗。嚴(yán)格酒后作業(yè)。
難度大
3.6關(guān)鍵及特殊過程控制
序號(hào)關(guān)鍵及特殊過程名稱
1施工電梯基礎(chǔ)混凝土澆筑
2施工電梯安裝位置的選擇
3車庫頂板回頂架體搭設(shè)
4施工電梯底座及導(dǎo)軌安裝
7
項(xiàng)目專項(xiàng)施工方案
4施工進(jìn)度計(jì)劃
4.1工期進(jìn)度目標(biāo)
本工程施工電梯計(jì)劃2023年11月30日進(jìn)場(chǎng),2023年4月5日退場(chǎng)。
部位施工內(nèi)容計(jì)劃安裝時(shí)間計(jì)劃拆除時(shí)間責(zé)任人
1#樓電梯安拆2023年12月30日2023年03月15日
2#樓電梯安拆2023年12月30日2023年03月15日
5#樓電梯安拆2023年12月08日2023年03月05日
6#樓電梯安拆2023年12月08日2023年03月05日
7#樓電梯安拆2023年12月08日2023年02月25日
10#樓電梯安拆2023年11月30日2023年02月15日
11#樓電梯安拆2023年12月20日2023年03月10日
12#樓電梯安拆2023年01月15日2023年04月05日
13#樓電梯安拆2023年11月30日2023年02月15日
14#樓電梯安拆2023年11月30日2023年02月15日
4.2施工總進(jìn)度計(jì)劃及保證措施
組織管理措施
項(xiàng)目部全力組織協(xié)調(diào),人員配備齊全,各崗位協(xié)調(diào)一致,確保工程施工;設(shè)備提前組
織進(jìn)場(chǎng),供應(yīng)及時(shí);施工設(shè)備事前做好保養(yǎng)維修,配件購置齊全,以高效率施工設(shè)備投入
到工程施工中去;積極協(xié)調(diào)周邊關(guān)系,配合建設(shè)單位、監(jiān)理單位認(rèn)真及時(shí)地處理施工中出
現(xiàn)的各種問題。
專業(yè)工程師現(xiàn)場(chǎng)值班,跟班作業(yè)隨時(shí)解決現(xiàn)場(chǎng)施工過程中出現(xiàn)的問題。實(shí)行工程例會(huì)
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 農(nóng)村農(nóng)村環(huán)保個(gè)人承包施工協(xié)議
- 建筑規(guī)劃二建專業(yè)人才聘用合同
- 飲料瓶制造地磅租賃協(xié)議
- 教育行業(yè)貨車租賃合同樣本
- 人力資源派遣合同管理指南
- 船舶電力系統(tǒng)維修服務(wù)協(xié)議
- 員工解雇程序規(guī)范化指南
- 聘用合同模板
- 養(yǎng)殖場(chǎng)養(yǎng)殖產(chǎn)品廣告宣傳合同
- 寵物項(xiàng)目部護(hù)理員聘用合同
- 2019-2020學(xué)年上海虹口區(qū)實(shí)驗(yàn)中學(xué)六年級(jí)上學(xué)期英語期末卷及答案
- 2023通勤車輛危險(xiǎn)源評(píng)估標(biāo)準(zhǔn)
- 幼兒園中班科學(xué)《植物過冬有辦法》
- 辦理行政案件程序規(guī)定第七章 調(diào)查取證模板
- 團(tuán)體輔導(dǎo)準(zhǔn)備篇:結(jié)構(gòu)式團(tuán)體練習(xí)及其應(yīng)用
- 大華硬盤錄像機(jī)操作說明
- 結(jié)婚函調(diào)報(bào)告表(帶參考)
- 單位車輛領(lǐng)取免檢標(biāo)志委托書范本
- 2023-2024學(xué)年江蘇省泰州市姜堰市數(shù)學(xué)六年級(jí)第一學(xué)期期末質(zhì)量檢測(cè)試題含答案
- 供銷社建設(shè)項(xiàng)目可行性研究報(bào)告
- 治安案件報(bào)案登記表(標(biāo)準(zhǔn)范本)
評(píng)論
0/150
提交評(píng)論