項(xiàng)目專項(xiàng)施工方案
標(biāo)段二勘察設(shè)計(jì)施工總承包工程
懸挑式腳手架施工方案
編制單位:中國(guó)建筑第八工程局有限公司
編制人:
日期:2023.10.10
項(xiàng)目專項(xiàng)施工方案
目錄
1編制依據(jù).......................................................................................................................................................1
2工程概況.......................................................................................................................................................3
2.1工程建設(shè)概況一覽表........................................................................................................................3
2.2設(shè)計(jì)概況............................................................................................................................................3
2.2.1建筑設(shè)計(jì)概況.........................................................................................................................3
2.2.2懸挑式腳手架設(shè)計(jì)概況.........................................................................................................4
2.3項(xiàng)目施工條件....................................................................................................................................6
3施工安排.......................................................................................................................................................7
3.1項(xiàng)目管理組織....................................................................................................................................7
3.2項(xiàng)目管理目標(biāo)....................................................................................................................................8
3.3各項(xiàng)資源供應(yīng)方式............................................................................................................................8
3.4施工流水段的劃分及施工工藝流程................................................................................................9
3.4.1施工流水段劃分.....................................................................................................................9
3.4.2施工工藝流程.........................................................................................................................9
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施............................................................................................9
3.6新技術(shù)應(yīng)用......................................................................................................................................10
3.7關(guān)鍵及特殊過(guò)程控制......................................................................................................................10
4施工進(jìn)度計(jì)劃.............................................................................................................................................11
5施工準(zhǔn)備與資源配置計(jì)劃.........................................................................................................................16
5.1施工準(zhǔn)備計(jì)劃..................................................................................................................................16
5.1.1技術(shù)準(zhǔn)備...............................................................................................................................16
5.1.2現(xiàn)場(chǎng)準(zhǔn)備...............................................................................................................................17
5.2資源配置計(jì)劃..................................................................................................................................17
5.2.1勞動(dòng)力配置計(jì)劃...................................................................................................................17
5.2.2工程用原材料需用量計(jì)劃...................................................................................................18
5.2.3施工機(jī)具配置計(jì)劃...............................................................................................................19
5.2.4測(cè)量設(shè)備配置計(jì)劃...............................................................................................................19
6施工方法及工藝要求.................................................................................................................................20
6.1方案及技術(shù)參數(shù)..............................................................................................................................20
6.2施工工藝流程..................................................................................................................................20
6.2.1搭設(shè)工藝流程.......................................................................................................................20
6.2.2拆除工藝流程.......................................................................................................................22
6.3施工要點(diǎn)..........................................................................................................................................23
6.3.1焊接鋼筋頭...........................................................................................................................23
6.3.2預(yù)埋U型鋼筋拉環(huán)...............................................................................................................23
6.3.3固定工字鋼...........................................................................................................................24
6.3.4拉結(jié)鋼絲繩...........................................................................................................................27
6.3.5掃地桿...................................................................................................................................29
6.3.6立桿.......................................................................................................................................29
6.3.7水平桿...................................................................................................................................30
6.3.8剪刀撐...................................................................................................................................31
6.3.9腳手板...................................................................................................................................32
6.3.10連墻件.................................................................................................................................33
6.3.11安全防護(hù)措施.....................................................................................................................34
6.3.12開(kāi)口部位外架構(gòu)造.............................................................................................................37
6.3.13外架在卸料平臺(tái)處的處理.................................................................................................37
6.3.14塔司通道設(shè)置.....................................................................................................................38
6.3.15監(jiān)測(cè)監(jiān)控措施.....................................................................................................................39
6.3.16腳手架拆除.........................................................................................................................41
I
項(xiàng)目專項(xiàng)施工方案
6.4驗(yàn)收標(biāo)準(zhǔn)..........................................................................................................................................42
6.5驗(yàn)收程序..........................................................................................................................................44
6.6驗(yàn)收內(nèi)容..........................................................................................................................................44
6.7驗(yàn)收人員..........................................................................................................................................46
7各項(xiàng)管理計(jì)劃.............................................................................................................................................47
7.1綠色施工管理計(jì)劃..........................................................................................................................47
7.1.1綠色施工管理目標(biāo)...............................................................................................................47
7.1.2綠色施工組織機(jī)構(gòu)和職責(zé)分工...........................................................................................47
7.1.3綠色施工實(shí)施措施...............................................................................................................48
7.2進(jìn)度管理計(jì)劃..................................................................................................................................48
7.2.1施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工...................................................................................48
7.2.2進(jìn)度管理措施.......................................................................................................................48
7.3質(zhì)量管理計(jì)劃..................................................................................................................................49
7.3.1質(zhì)量控制目標(biāo)分解...............................................................................................................49
7.3.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工.......................................................................................50
7.3.3確定質(zhì)量控制點(diǎn)...................................................................................................................51
7.3.4質(zhì)量保證措施.......................................................................................................................52
7.4安全管理計(jì)劃..................................................................................................................................52
7.4.1職業(yè)健康安全管理分解目標(biāo)...............................................................................................52
7.4.2安全管理組織機(jī)構(gòu)和職責(zé)分工...........................................................................................53
7.4.3職業(yè)健康安全重大危險(xiǎn)源...................................................................................................54
7.4.4職業(yè)健康安全資源配置計(jì)劃...............................................................................................55
7.4.5安全生產(chǎn)管理制度...............................................................................................................55
7.4.6安全生產(chǎn)保證措施...............................................................................................................56
7.5成品保護(hù)管理計(jì)劃..........................................................................................................................58
7.5.1成品保護(hù)目標(biāo).......................................................................................................................58
7.5.2成品保護(hù)管理組織和職責(zé)分工...........................................................................................58
7.5.3成品保護(hù)計(jì)劃及保證措施...................................................................................................59
8應(yīng)急預(yù)案.....................................................................................................................................................60
8.1應(yīng)急指揮機(jī)構(gòu)及職責(zé)......................................................................................................................60
8.2事故風(fēng)險(xiǎn)分析..................................................................................................................................62
8.3應(yīng)急知識(shí)培訓(xùn)..................................................................................................................................62
8.4事故報(bào)告............................................................................................................................................62
8.5現(xiàn)場(chǎng)應(yīng)急處置措施..........................................................................................................................63
8.5.1施工現(xiàn)場(chǎng)防高空墜落安全防護(hù)措施...................................................................................63
8.5.2觸電事故應(yīng)急預(yù)案...............................................................................................................63
8.5.3食物中毒事故應(yīng)急預(yù)案.......................................................................................................63
8.5.4施工現(xiàn)場(chǎng)防物體打擊安全防護(hù)措施...................................................................................64
8.5.5腳手架坍塌事故...................................................................................................................64
8.5.6傾覆事故...............................................................................................................................64
8.5.7起重機(jī)起吊作業(yè)應(yīng)急預(yù)案...................................................................................................65
8.5.8火災(zāi)應(yīng)急預(yù)案.......................................................................................................................65
8.5.9中暑事故應(yīng)急預(yù)案...............................................................................................................66
8.6應(yīng)急物資準(zhǔn)備..................................................................................................................................66
8.7應(yīng)急響應(yīng)、響應(yīng)結(jié)束、演練..........................................................................................................67
8.7.1應(yīng)急響應(yīng).................................................................................................................................67
8.7.2響應(yīng)結(jié)束.................................................................................................................................67
8.7.3演練.........................................................................................................................................68
9疫情防控.....................................................................................................................................................71
9.1疫情防控管理組織..........................................................................................................................71
II
項(xiàng)目專項(xiàng)施工方案
9.2疫情防控原則..................................................................................................................................72
9.3防控措施..........................................................................................................................................72
9.3.1復(fù)工前的排查工作...............................................................................................................72
9.3.2復(fù)工許可...............................................................................................................................73
9.3.3復(fù)工后日常防控措施...........................................................................................................73
9.3.4全員實(shí)名制登記及健康排查制度.......................................................................................73
9.3.5防疫宣貫及個(gè)人防護(hù)制度...................................................................................................74
9.3.6人員分流制度.......................................................................................................................74
9.3.7信息報(bào)送制度.......................................................................................................................74
9.3.8防控物資保障制度...............................................................................................................74
9.4突發(fā)疫情應(yīng)急流程..........................................................................................................................74
10附件...........................................................................................................................................................77
10.1計(jì)算書(shū)............................................................................................................................................77
10.1.1懸挑27m計(jì)算書(shū)................................................................................................................77
10.1.2懸挑28m計(jì)算書(shū)................................................................................................................90
10.2陽(yáng)角處聯(lián)梁計(jì)算書(shū)......................................................................................................................103
10.2.124m懸挑計(jì)算書(shū)...............................................................................................................103
10.2.228m懸挑計(jì)算書(shū)...............................................................................................................117
10.3附圖(詳見(jiàn)附件)......................................................................................................................131
III
項(xiàng)目專項(xiàng)施工方案
1編制依據(jù)
序號(hào)類(lèi)別文件名稱編號(hào)
第十二屆中華人民共和國(guó)主
1《中華人民共和國(guó)安全生產(chǎn)法》
席令第八十八號(hào)
第十三屆中華人民共和國(guó)主
2《中華人民共和國(guó)建筑法》
席令第二十九號(hào)
第十二屆中華人民共和國(guó)主
3《中華人民共和國(guó)環(huán)境保護(hù)法》
席令第九號(hào)
中華人民共和國(guó)國(guó)務(wù)院令
4國(guó)家行政文件《建設(shè)工程質(zhì)量管理?xiàng)l例》
(第714號(hào))
中華人民共和國(guó)國(guó)務(wù)院令
5《建設(shè)工程安全生產(chǎn)管理?xiàng)l例》
(第393號(hào))
中華人民共和國(guó)住房和城鄉(xiāng)
6《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定》
建設(shè)部令第37號(hào)
住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實(shí)施《危險(xiǎn)性較大的分部分項(xiàng)工程安
7建辦質(zhì)[2018]31號(hào)
全管理規(guī)定》有關(guān)問(wèn)題的通知
8《建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范》JGJ130-2011
9《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
10《建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)》GB50300-2013
11《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
12《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
13國(guó)家行業(yè)規(guī)范《鋼管腳手架扣件》GB15831-2006
14《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范》(附條文說(shuō)明)JGJ46-2005
15《建筑物防雷設(shè)計(jì)規(guī)范》GB50057-2010
16《建筑施工模板安全技術(shù)規(guī)范》JGJ162-2008
17《建筑施工腳手架安全技術(shù)統(tǒng)一標(biāo)準(zhǔn)》GB51210-2016
18《安全網(wǎng)》GB5725-2009
19《工程質(zhì)量安全監(jiān)督數(shù)據(jù)標(biāo)準(zhǔn)》DBJ/T15-85-2011
地方規(guī)范標(biāo)準(zhǔn)
20《廣東省建筑結(jié)構(gòu)荷載規(guī)范》DBJ15-101-2014
1
項(xiàng)目專項(xiàng)施工方案
廣東省住房和城鄉(xiāng)建設(shè)廳關(guān)于印發(fā)房屋市政工程危險(xiǎn)性較大的分
21粵建規(guī)范[2023]2號(hào)
部分項(xiàng)工程安全管理實(shí)施細(xì)則的通知
《珠海市房屋市政工程腳手架及高大模板支撐系統(tǒng)監(jiān)督管理辦法
22珠規(guī)建質(zhì)〔2012〕79號(hào)
(試行)》
23地方行政文件《珠海市建筑施工腳手架搭設(shè)安全技術(shù)要點(diǎn)》珠建安監(jiān)[2004]06號(hào)
24《關(guān)于進(jìn)一步加強(qiáng)腳手架及模板支撐系統(tǒng)搭設(shè)管理的通知》珠規(guī)建質(zhì)〔2014〕53號(hào)
25《珠海經(jīng)濟(jì)特區(qū)防臺(tái)風(fēng)條例》/
26合同xx標(biāo)段二勘察設(shè)計(jì)施工總承包合同/
27中建八局《建筑工程施工技術(shù)標(biāo)準(zhǔn)》/
28企業(yè)技術(shù)標(biāo)準(zhǔn)《中建八局第一建設(shè)有限公司標(biāo)準(zhǔn)化管理手冊(cè)》/
29《施工組織設(shè)計(jì)編制與管理標(biāo)準(zhǔn)》ZJQ08-SGJB001-2017
30PKPM計(jì)算軟件/
《廣東省住房和城鄉(xiāng)建設(shè)廳關(guān)于切實(shí)做好房屋市政工程復(fù)工前后
31/
新型冠狀病毒感染肺炎疫情防控的通知》
其他
《關(guān)于印發(fā)珠海市建筑工地新型冠狀病毒感染的肺炎預(yù)防控制工
32/
作指引的通知》
33《中建八局一公司華南公司防疫工作方案》華南辦字(2023)7號(hào)
2
項(xiàng)目專項(xiàng)施工方案
2工程概況
2.1工程建設(shè)概況一覽表
工程名稱工程性質(zhì)辦公/商業(yè)
建設(shè)規(guī)模34.1億元工程地址
總占地面積6.65萬(wàn)㎡總建筑面積45.8萬(wàn)㎡
用地紅線范圍內(nèi)的所有工程、紅線外所有
相關(guān)配套設(shè)施工程,包括但不限于塔樓、
建設(shè)單位項(xiàng)目承包范圍樣板區(qū)、部分道路、地下通道、連橋,與
科學(xué)城一期、三期銜接、穿過(guò)環(huán)島西路的
云平臺(tái)等。
設(shè)計(jì)單位主要分包工程土方工程、支護(hù)工程
勘察單位質(zhì)量合格
監(jiān)理單位工期絕對(duì)工期1465天
合同確?!爸楹J薪ㄖこ贪踩a(chǎn)文明施工
總承包單位要求安全優(yōu)良樣板工地”,爭(zhēng)創(chuàng)“廣東省建筑工程
安全生產(chǎn)文明施工優(yōu)良樣板工地”
分包單位科技/
工程主要功能
辦公/商業(yè)
或用途
2.2設(shè)計(jì)概況
2.2.1建筑設(shè)計(jì)概況
地下建筑面積94635.5m2地上建筑面積350854.5m2裙房建筑面積12510㎡
地上1~39層地下6000、4900、2950、2850抗震設(shè)防烈度7度
層數(shù)地下2層層高首層5000、4800抗震設(shè)防類(lèi)別乙類(lèi)
裙房1~3層標(biāo)準(zhǔn)層5100防火等級(jí)一級(jí)
細(xì)石混凝土樓地面/水泥砂漿樓地面/地磚樓地面/地坪涂料樓地面/防靜電架空活動(dòng)地板樓面/花崗
樓地面
巖地面
裝飾墻面涂料外墻/面磚外墻/石材幕墻外墻/金屬板幕墻外墻/玻璃幕墻外墻
裝修涂料頂棚/輕鋼龍骨水泥纖維板/穿孔水泥纖維吸音板吊頂/鋁穿孔吸聲板吊頂/防火吊頂/鋁扣板吊
頂棚
頂/隔聲吊頂
樓梯地磚樓地面,涂料墻面,涂料頂棚
3
項(xiàng)目專項(xiàng)施工方案
電梯廳地面:待定墻面:待定頂棚:待定
底板:1.5mm厚非瀝青基高分子自粘膠膜防水卷材+1.5mm厚水泥基滲透結(jié)晶防
地下防水等級(jí):一級(jí)水涂料
側(cè)壁:1.5mm厚水泥基滲透結(jié)晶防水涂料+1.5mm厚合成高分子自粘防水卷材
非種植區(qū):1.5mm厚水泥基滲透結(jié)晶防水涂料+3厚聚酯胎基(PY)類(lèi)自粘聚合物
防水
改性瀝青卷材
屋面防水等級(jí):一級(jí)
種植區(qū):1.5mm厚水泥基滲透結(jié)晶防水涂料+3厚聚酯胎基(PY)類(lèi)自粘聚合物改
性瀝青卷材+4厚耐根穿刺聚酯胎基(PY)類(lèi)自粘聚合物改性瀝青卷材(SBSⅡ型)
廚衛(wèi)間聚合物水泥防水涂料聚氨酯防水涂料
幕墻工程面積(待定)龍骨(待定)面材(玻璃)
智能化系統(tǒng)
保溫節(jié)能屋面:燃燒性能等級(jí)B1級(jí)的擠塑聚苯乙烯泡沫塑料板墻體:/
綠化植被
2.2.2懸挑式腳手架設(shè)計(jì)概況
懸挑腳手架僅搭設(shè)至屋面層1.5m高度,機(jī)房外架采用落地式腳手架、裝飾構(gòu)架外腳手架單獨(dú)編制
方案。
表-1懸挑腳手架概況情況一覽表
腳手架型式(開(kāi)口型、
懸挑工字鋼所在的錨固樓層/支撐樓板厚度/單次懸挑高度(樓層
樓棟號(hào)最大懸挑長(zhǎng)度封閉型、是否設(shè)置馬
是否存在懸挑構(gòu)件承力強(qiáng)度數(shù))
道)
4F/否110mm/C3018m2.05m封閉型
SB1
8F/否110mm/C3019.5m2.05m封閉型
3F/否110mm/C3022.5m2.05m封閉型
8F/否110mm/C3022.5m2.05m封閉型
13F/否110mm/C3022.5m2.05m封閉型
SA1
18F/否110mm/C3022.5m2.05m封閉型
23F/否110mm/C3022.5m2.05m封閉型
28F/否110mm/C3022.5m
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025年度大豆產(chǎn)業(yè)鏈信息化建設(shè)合同8篇
- 2025版城市消防站滅火器更新采購(gòu)合同模板4篇
- 二零二五版農(nóng)業(yè)大棚溫室氣體減排技術(shù)服務(wù)合同
- 二零二五年度教育培訓(xùn)機(jī)構(gòu)師資免責(zé)協(xié)議4篇
- 二零二五版門(mén)牌制作安裝與文化旅游推廣合同4篇
- 二零二五年度電器產(chǎn)品展示與銷(xiāo)售體驗(yàn)中心建設(shè)合同4篇
- 2025年度苗木種植與生態(tài)農(nóng)業(yè)示范區(qū)合作合同2篇
- 2025年度個(gè)人帶車(chē)庫(kù)帶健身房別墅買(mǎi)賣(mài)合同書(shū)
- 2025年度個(gè)人抵押車(chē)借款信用擔(dān)保合同范本
- 二零二五年度特色餐飲店供應(yīng)鏈優(yōu)化與銷(xiāo)售合同3篇
- 2024年社區(qū)警務(wù)規(guī)范考試題庫(kù)
- 2024年食用牛脂項(xiàng)目可行性研究報(bào)告
- 2024-2030年中國(guó)戶外音箱行業(yè)市場(chǎng)發(fā)展趨勢(shì)與前景展望戰(zhàn)略分析報(bào)告
- GB/T 30306-2024家用和類(lèi)似用途飲用水處理濾芯
- 家務(wù)分工與責(zé)任保證書(shū)
- 消防安全隱患等級(jí)
- 溫室氣體(二氧化碳和甲烷)走航監(jiān)測(cè)技術(shù)規(guī)范
- 2023山東春季高考數(shù)學(xué)真題(含答案)
- 為加入燒火佬協(xié)會(huì)致辭(7篇)
- 職業(yè)衛(wèi)生法律法規(guī)和標(biāo)準(zhǔn)培訓(xùn)課件
- 高二下學(xué)期英語(yǔ)閱讀提升練習(xí)(二)
評(píng)論
0/150
提交評(píng)論