項(xiàng)目專項(xiàng)施工方案
濟(jì)南東站管鮑大街、龍脊河?xùn)|路、龍脊河西路道路建設(shè)工
程施工一標(biāo)段
路基施工方案
編制:
審核:
審批:
日期:
項(xiàng)目專項(xiàng)施工方案
項(xiàng)目專項(xiàng)施工方案
目錄
第一章編制依據(jù)....................................................................................................................1
第二章工程概況....................................................................................................................2
2.1工程建設(shè)概況一覽表................................................................................................2
2.2工程簡(jiǎn)介....................................................................................................................2
2.3工程施工條件............................................................................................................4
2.3.1地質(zhì)條件.........................................................................................................4
2.3.2水文條件.........................................................................................................5
2.3.3影響施工障礙物情況.....................................................................................6
2.3.4交通條件.........................................................................................................6
2.3.5主要工程數(shù)量.................................................................................................7
第三章施工安排....................................................................................................................7
3.1項(xiàng)目管理組織............................................................................................................7
3.2項(xiàng)目管理目標(biāo)............................................................................................................9
第四章施工進(jìn)度計(jì)劃............................................................................................................9
第五章施工準(zhǔn)備與資源配置計(jì)劃......................................................................................10
5.1施工準(zhǔn)備計(jì)劃..........................................................................................................10
5.1.1技術(shù)準(zhǔn)備.......................................................................................................10
5.1.2現(xiàn)場(chǎng)準(zhǔn)備.......................................................................................................11
5.2資源配置計(jì)劃..........................................................................................................12
5.2.1勞動(dòng)力配置計(jì)劃...........................................................................................12
5.2.2工程用原材料需求量計(jì)劃...........................................................................12
5.2.3工程施工主要周轉(zhuǎn)材料配置計(jì)劃...............................................................13
5.2.4施工機(jī)具配置計(jì)劃.......................................................................................13
5.2.5測(cè)量及試驗(yàn)設(shè)備配置計(jì)劃...........................................................................14
5.2.6防疫物資準(zhǔn)備...............................................................................................14
第六章施工方法及工藝要求..............................................................................................15
6.1振沖碾壓路基施工..................................................................................................15
6.1.1施工工藝流程...............................................................................................15
I
項(xiàng)目專項(xiàng)施工方案
6.1.2施工方法.......................................................................................................15
6.1.3試驗(yàn)工藝方法...............................................................................................16
6.1.4施工要點(diǎn).......................................................................................................18
6.1.5質(zhì)量控制與檢測(cè)...........................................................................................19
6.2填方路基施工..........................................................................................................19
6.2.1施工工藝流程...............................................................................................19
6.2.2施工方法及控制要點(diǎn)...................................................................................20
6.2.3質(zhì)量標(biāo)準(zhǔn).......................................................................................................24
6.3挖方路基施工..........................................................................................................25
6.3.1施工工藝流程...............................................................................................25
6.3.2施工方法及控制要點(diǎn)...................................................................................25
6.3.3質(zhì)量標(biāo)準(zhǔn).......................................................................................................26
6.4石灰土路基施工......................................................................................................27
6.4.1施工工藝流程...............................................................................................27
6.4.2施工方法及控制要點(diǎn)...................................................................................27
6.4.3質(zhì)量標(biāo)準(zhǔn).......................................................................................................33
6.5強(qiáng)夯施工..................................................................................................................33
6.5.1施工工藝流程...............................................................................................33
6.5.2施工準(zhǔn)備.......................................................................................................34
6.5.3試驗(yàn)段施工...................................................................................................34
6.5.4正式施工階段...............................................................................................34
6.5.5檢測(cè)驗(yàn)收.......................................................................................................36
6.5.6質(zhì)量保證措施...............................................................................................36
6.5.7注意事項(xiàng).......................................................................................................37
6.6拋石擠淤..................................................................................................................38
6.6.1施工流程.......................................................................................................38
6.6.2施工準(zhǔn)備.......................................................................................................39
6.6.3施工方法.......................................................................................................39
6.6.4施工質(zhì)量控制...............................................................................................40
II
項(xiàng)目專項(xiàng)施工方案
6.7毛石換填施工..........................................................................................................40
6.7.1材料標(biāo)準(zhǔn).......................................................................................................41
6.7.2運(yùn)輸布料.......................................................................................................41
6.7.3攤鋪整形.......................................................................................................41
6.7.4第一次嵌縫...................................................................................................41
6.7.5穩(wěn)壓...............................................................................................................41
6.7.6第二次嵌縫...................................................................................................42
6.7.7終壓...............................................................................................................42
6.7.8施工質(zhì)量控制...............................................................................................42
第七章進(jìn)度保證措施..........................................................................................................43
7.1以施工準(zhǔn)備的充分性保證工期..............................................................................43
7.2以施工組織的嚴(yán)密性保證工期..............................................................................43
7.3以安全質(zhì)量的平穩(wěn)性保證工期..............................................................................44
第八章質(zhì)量保證措施..........................................................................................................45
8.1項(xiàng)目質(zhì)量管理組織機(jī)構(gòu)..........................................................................................45
8.2質(zhì)量保證措施..........................................................................................................45
8.2.1組織保證措施...............................................................................................45
8.2.2技術(shù)保證措施...............................................................................................49
8.2.3經(jīng)濟(jì)保證措施...............................................................................................50
第九章安全文明施工措施..................................................................................................50
9.1職業(yè)健康安全管理分解目標(biāo)..................................................................................50
9.1.1傷亡控制目標(biāo)...............................................................................................50
9.1.2安全管理達(dá)標(biāo)...............................................................................................50
9.1.3文明施工和環(huán)境管理目標(biāo)...........................................................................51
9.1.4其他目標(biāo).......................................................................................................51
9.2建立安全組織機(jī)構(gòu),明確安全職責(zé)和權(quán)限..........................................................51
9.3施工現(xiàn)場(chǎng)安全生產(chǎn)管理制度..................................................................................54
9.4安全保證措施..........................................................................................................55
9.4.1組織保證.......................................................................................................55
III
項(xiàng)目專項(xiàng)施工方案
9.4.2施工保證.......................................................................................................56
第十章綠色施工措施..........................................................................................................57
10.1環(huán)境保護(hù)措施........................................................................................................57
10.2節(jié)地措施................................................................................................................58
10.3節(jié)水措施................................................................................................................58
10.4節(jié)能措施................................................................................................................59
10.5節(jié)材措施................................................................................................................59
第十一章成品保護(hù)措施......................................................................................................59
11.1成立成品保護(hù)管理機(jī)構(gòu)........................................................................................60
11.2一般規(guī)定................................................................................................................60
11.3成品保護(hù)措施........................................................................................................60
第十二章應(yīng)急預(yù)案..............................................................................................................61
12.1相關(guān)生產(chǎn)風(fēng)險(xiǎn)源的識(shí)別........................................................................................61
12.2組織機(jī)構(gòu)及其職責(zé)................................................................................................61
12.2.1應(yīng)急組織體系.............................................................................................61
12.2.2應(yīng)急處置小組.............................................................................................61
12.2.3應(yīng)急組織管理分工.....................................................................................62
12.3應(yīng)急準(zhǔn)備................................................................................................................63
12.3.1應(yīng)急醫(yī)院.....................................................................................................63
12.3.2應(yīng)急物資、裝備及應(yīng)急資源.....................................................................64
12.4險(xiǎn)情報(bào)告制度及應(yīng)急預(yù)案啟動(dòng)程序....................................................................65
12.4.1險(xiǎn)情報(bào)告制度.............................................................................................65
12.4.2應(yīng)急預(yù)案啟動(dòng)程序.....................................................................................66
12.5應(yīng)急救援預(yù)案實(shí)施................................................................................................67
12.5.1車輛傷害應(yīng)急救援措施.............................................................................67
12.5.2起重機(jī)械事故應(yīng)急救援措施.....................................................................68
12.5.3自然災(zāi)害應(yīng)急措施.....................................................................................69
第十三章疫情防控措施......................................................................................................70
13.1建立疫情防控領(lǐng)導(dǎo)小組........................................................................................70
IV
項(xiàng)目專項(xiàng)施工方案
13.2門禁防疫管理........................................................................................................71
13.2.1硬件設(shè)施管理.............................................................................................71
13.2.2值守人員管理.............................................................................................71
13.2.3防疫物資儲(chǔ)備.............................................................................................72
13.3辦公區(qū)防疫管理....................................................................................................72
13.3.1安全管理.....................................................................................................72
13.3.2防疫管理.....................................................................................................72
13.4生活區(qū)防疫管理....................................................................................................72
13.4.1隔離管理.....................................................................................................72
13.4.2安全管理.....................................................................................................73
13.4.3防疫管理.....................................................................................................73
13.5食堂防疫管理........................................................................................................74
13.5.1人員管理.....................................................................................................74
13.5.2食品管理.....................................................................................................74
13.5.3就餐管理.....................................................................................................74
13.5.4消毒管理.....................................................................................................74
13.6施工現(xiàn)場(chǎng)防疫管理................................................................................................74
13.6.1避免人員工作集中.....................................................................................74
13.6.2佩戴防疫用品.............................................................................................75
13.6.3強(qiáng)化疫情觀察.............................................................................................75
13.6.4安全管理.....................................................................................................75
13.7管理人員入場(chǎng)管理................................................................................................75
13.7.1信息登記.....................................................................................................75
13.7.2入場(chǎng)教育.....................................................................................................75
13.8施工作業(yè)人員入場(chǎng)管理........................................................................................76
13.8.1信息登記.....................................................................................................76
13.8.2信息審核.....................................................................................................76
13.8.3入場(chǎng)教育.....................................................................................................76
13.9外來(lái)人員入場(chǎng)管理................................................................................................76
V
項(xiàng)目專項(xiàng)施工方案
13.9.1入場(chǎng)信息登記.............................................................................................76
13.9.2健康檢查.....................................................................................................77
13.9.3開(kāi)展教育交底.............................................................................................77
13.9.4有序組織入場(chǎng).............................................................................................77
13.10外出人員管理......................................................................................................77
13.10.1外出申請(qǐng)...................................................................................................77
13.10.2申請(qǐng)審批...................................................................................................78
13.10.3回歸手續(xù)...................................................................................................78
13.11會(huì)議管理..............................................................................................................78
13.11.1會(huì)前管理...................................................................................................78
13.11.2會(huì)中管理...................................................................................................78
13.11.3會(huì)后管理...................................................................................................78
13.12防疫物資管理......................................................................................................79
13.12.1防疫物資準(zhǔn)備...........................................................................................79
13.12.2防疫物資儲(chǔ)備量.......................................................................................79
13.12.3防疫物資儲(chǔ)存...........................................................................................79
13.12.4收發(fā)管理...................................................................................................79
13.12.5廢棄處理...................................................................................................80
附件一施工總平面布置圖..................................................................................................81
VI
項(xiàng)目專項(xiàng)施工方案
第一章編制依據(jù)
序號(hào)文件名稱編號(hào)
1《中華人民共和國(guó)建筑法》/
2《中華人民共和國(guó)安全生產(chǎn)法》/
3《中華人民共和國(guó)環(huán)境保護(hù)法》/
4《中華人民共和國(guó)環(huán)境噪聲污染防治法》/
5《中華人民共和國(guó)水污染防治法》/
6《中華人民共和國(guó)大氣污染防治法》/
7《建設(shè)工程安全生產(chǎn)管理?xiàng)l例》/
8《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定》住建部【2018】37號(hào)
9魯建質(zhì)安字【2018】15號(hào)
和城鄉(xiāng)建設(shè)局關(guān)于做好建筑工地開(kāi)(復(fù))工疫情防控工作的通
10濟(jì)建發(fā)【2023】7號(hào)
知》
11《公路土工試驗(yàn)規(guī)程》JTG3430-2023
12《路基工程施工技術(shù)標(biāo)準(zhǔn)》ZJQ08-SGJB016-2018
13《城鎮(zhèn)道路工程施工與質(zhì)量驗(yàn)收規(guī)范》CJJ1-2008
14《公路路基施工技術(shù)規(guī)范》JTG/T3610-2023
15《公路軟土地基路堤設(shè)計(jì)與施工技術(shù)細(xì)則》JTG/TD31-02-2013
16《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
17《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范(附條文說(shuō)明)》JGJ46-2005
18《公路工程施工安全技術(shù)規(guī)范》JTGF90—2015
19《公路工程質(zhì)量檢驗(yàn)評(píng)定標(biāo)準(zhǔn)第一冊(cè)土建工程》JTGF80/1-2017
20《城鎮(zhèn)道路養(yǎng)護(hù)技術(shù)規(guī)范》CJJ36-2016
21《工程測(cè)量規(guī)范》GB50026-2007
22《建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)》GB50300-2013
23《建筑施工場(chǎng)界環(huán)境噪聲排放標(biāo)準(zhǔn)》GB12523-2011
濟(jì)南東站管鮑大街、龍脊河?xùn)|路、龍脊河西路道路建設(shè)工
24/
程施工一標(biāo)段相關(guān)圖紙、勘察報(bào)告及其他相關(guān)設(shè)計(jì)文件
濟(jì)南東站管鮑大街、龍脊河?xùn)|路、龍脊河西路道路建設(shè)工
25/
程施工一標(biāo)段招投標(biāo)文件
現(xiàn)場(chǎng)踏勘調(diào)查所獲得的地質(zhì)水文、資源交通狀況及施工環(huán)
26/
境等資料
《關(guān)于印發(fā)<進(jìn)一步加強(qiáng)2023年春節(jié)后復(fù)工項(xiàng)目新型冠狀
27局工字【2023】6號(hào)
病毒感染肺炎疫情防控工作方案>的通知》
《關(guān)于下發(fā)<基礎(chǔ)設(shè)施公司2023年春節(jié)后復(fù)工項(xiàng)目新型冠
28基司施字【2023】07號(hào)
狀病毒感染肺炎疫情防控工作方案>的通知》
1
項(xiàng)目專項(xiàng)施工方案
第二章工程概況
2.1工程建設(shè)概況一覽表
表2.1工程建設(shè)概況
濟(jì)南東站管鮑大街、龍脊河
工程名稱東路、龍脊河西路道路建設(shè)工程性質(zhì)
工程施工一標(biāo)段
管鮑大街西段西起壩王路,東
管鮑大街西段0.84公里;龍
建設(shè)規(guī)模工程地址至龍脊河?xùn)|路;龍脊河西路北
脊河西路0.8公里
起望華南街,南至管鮑大街
濟(jì)南軌道交通集團(tuán)建設(shè)投資
建設(shè)單位項(xiàng)目承包范圍施工圖紙內(nèi)所有專業(yè)和內(nèi)容
有限公司
道路、交通(土建)、雨水、
設(shè)計(jì)單位主要分包工程污水、管線綜合、照明(土
建)等工程
勘察單位院質(zhì)量合格
合同
監(jiān)理單位工期360日歷天
要求
總承包單位中建八局第一建設(shè)有限公司安全無(wú)安全事故發(fā)生
工程主要功
能或用途
2.2工程簡(jiǎn)介
管鮑大街西段西起壩王路,東至龍脊河?xùn)|路,道路全長(zhǎng)約840m。壩王路至同心路
道路規(guī)劃紅線寬35m,同心路至龍脊河?xùn)|路道路規(guī)劃紅線寬度40m本著以人為本,優(yōu)
先保障慢性空間的原則,同時(shí)兼顧交通功能,充分考慮道路綠化效果,并結(jié)合周邊道路
綜合考慮交通組織,壩王路至同心路道路橫斷面劃分:中央3m分隔帶+兩側(cè)各(機(jī)動(dòng)
車道10.5m+1.5m綠化帶+2.5m非機(jī)動(dòng)車道+1.5m人行道)。同心路至龍脊河?xùn)|路道路橫
斷面劃分:中央3m分隔帶+兩側(cè)各(機(jī)動(dòng)車道10.5m+1.5m綠化帶+3.5m非機(jī)動(dòng)車道+3m
人行道)。
龍脊河西路北起望華南街,南至管鮑大街,道路全長(zhǎng)約800m。道路規(guī)劃紅線寬
30m,次干路。道路橫斷面劃分:機(jī)動(dòng)車道11m+兩側(cè)各(3m綠化帶+3m非機(jī)動(dòng)車道
+3.5m人行道)。
本次工程施工內(nèi)容包括:道路工程、雨水工程、管線綜合工程、污水工程、照明工
程、交通工程等。
本次實(shí)施段全線以挖方為主,無(wú)明顯道路縱向填挖交界,根據(jù)縱斷及巖土工程勘察報(bào)
告,上部主要由黃河沖積成因的粘性土、粉土組成,下部主要由沖洪積成因的黏性土、
2
項(xiàng)目專項(xiàng)施工方案
粉土、卵石組成,場(chǎng)地內(nèi)揭示的特殊性巖土主要為雜填土和素填土,填土堆積時(shí)間較短,
不均勻,結(jié)構(gòu)松散,屬欠固結(jié)土,力學(xué)性質(zhì)差,未經(jīng)有效處理不宜直接作為路基持力層。
擬采取換填、翻曬、摻拌生石灰、振沖碾壓、強(qiáng)夯等措施處理,此外還有部分不良地基
需要進(jìn)行清淤工作。
圖2.2-1填方路基標(biāo)準(zhǔn)橫斷面
圖2.2-2挖方路基標(biāo)準(zhǔn)橫斷面
圖2.2-3半填半挖路基標(biāo)準(zhǔn)橫斷面
3
項(xiàng)目專項(xiàng)施工方案
2.3工程施工條件
2.3.1地質(zhì)條件
1管鮑大街西段施工區(qū)域內(nèi)在鉆探范圍內(nèi)的地層可分為5個(gè)主層及亞層,自上而
下分述如下:
(1)填土:
①素填土:褐黃色,可塑,稍密,稍濕,以粘性土為主,含磚屑,土質(zhì)松散。
①1雜填土:雜色,稍密,主要為塊石、磚塊。
層厚1.80~4.80m,層底標(biāo)高26.71~31.21m。
(2)粉質(zhì)黏土夾粉土,該層以②層粉質(zhì)黏土為主,②1粉土呈透鏡體狀分布,②2粉
質(zhì)黏土在下部分布。
②粉質(zhì)黏土:褐黃色,可塑,粘粒一般,刀切面較光滑,含氧化鐵條紋。
②1粉土:褐黃色,稍密,濕,刀切面粗糙,搖振反應(yīng)迅速,含氧化鐵條紋。
②2粉質(zhì)黏土:灰~灰褐色,可塑,粘粒一般,刀切面較光滑,含有機(jī)質(zhì)。
層厚2.00~5.60m,層底深度6.20~8.20m,層底標(biāo)高23.38~26.01m。
(3)粉質(zhì)粘土:
③粉質(zhì)黏土:灰黃色,可塑,粘粒稍多,零星姜石,局部夾粉土薄層。層厚
1.80~5.30m,層底深度9.80~11.60m,層底標(biāo)高19.18~23.11m。
(4)粉質(zhì)黏土、卵石、粉細(xì)砂:該層④層粉質(zhì)黏土為主,④1卵石、④2粉細(xì)砂層透
鏡體狀分布。
④粉質(zhì)黏土:灰黃色~淺棕黃色,可塑;粘粒一般,含氧化鐵及少量姜石。
④1卵石:雜色,稍~中密,母巖為灰?guī)r,粒徑2~6cm,含量60%,充填淺棕黃粉黏。
④2粉細(xì)砂:灰黃色,稍~中密,很濕,主要成分為石英、長(zhǎng)石、云母,混粉質(zhì)黏土。
僅部分鉆孔揭示,揭示厚度3.40~10.20m。
(5)粉質(zhì)黏土:棕黃色,硬塑,黏粒較多,刀切面較光滑,含鐵錳氧化物。
該層未揭穿,最大揭示深度30.0m。
2龍脊河西路施工區(qū)域內(nèi)在鉆探范圍內(nèi)的地層可分為5個(gè)主層及亞層,自上而下
分述如下:
4
項(xiàng)目專項(xiàng)施工方案
(1)填土:該層主要以素填土為主。
①素填土:褐黃色,可塑;以粘性土為主,含植物根系、少量磚層、碎石、灰渣等。
①1雜填土:雜色,松散~稍密;成分不均勻,主要成分為碎石、磚塊、灰渣等建筑
垃圾。
(2)粉質(zhì)黏土夾粉土:
②粉質(zhì)黏土:褐黃色,可塑;黏粒一般,含鐵錳氧化物。
②1粉土:褐黃色~灰黃色,稍密,稍濕。
②2粉質(zhì)黏土:灰褐色,可塑;黏粒稍多,含碎貝殼。
(3)粉質(zhì)黏土:灰黃色~黃灰色,可塑;粘粒一般,含氧化鐵條紋。
(4)粉質(zhì)黏土夾卵石:該層以④層粉質(zhì)黏土為主,④1層卵石成層狀或透鏡體狀分
布。
④粉質(zhì)黏土:灰黃色,局部成淺棕黃色,可塑,局部硬塑;黏粒一般,局部粘粒稍
少,含氧化鐵,少量姜石。
④1卵石:雜色,稍密;母巖為灰?guī)r,呈亞圓形,粒徑1~4cm,含量40%~60%,充
填灰黃色粘性土。
(5)粉質(zhì)黏土夾卵石:
⑤粉質(zhì)黏土:淺棕黃色,可塑~硬塑;粘粒稍高,含鐵錳氧化物。
⑤1卵石:雜色,稍密;母巖為灰?guī)r,呈亞圓形,粒徑1~4cm,含量50%~60%,充
填淺棕黃色粘性土。
2.3.2水文條件
管鮑大街西段項(xiàng)目受附近工程建設(shè)降水影響,地下水位明顯下降,個(gè)別地段形成較
深的降水漏斗,勘探期間在鉆孔中測(cè)得地下水動(dòng)水位埋深為5.90~7.80m,相應(yīng)標(biāo)高
24.48~25.67m。水位季節(jié)性變化幅度約2.0~3.0m,建議常年最高水位標(biāo)高為29.0~31.0m
(由西向東)。
龍脊河西路項(xiàng)目受附近工程建設(shè)降水影響,地下水位明顯下降。野外勘探期間測(cè)得
地下水動(dòng)水位埋深約為4.90~8.50m,相應(yīng)標(biāo)高為23.26~25.47m。當(dāng)周邊降水工程停止抽
水后,地下水會(huì)回升至自然水位標(biāo)高。水位季節(jié)性變化幅度約3.0~5.0m,建議常年最高
水位標(biāo)高為28.00~30.00m。
5
項(xiàng)目專項(xiàng)施工方案
2.3.3影響施工障礙物
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 機(jī)械勞務(wù)施工合同范本共3篇
- 民事授權(quán)委托書(shū)特別授權(quán)詳解3篇
- 旅游社交媒體管理勞動(dòng)合同模板3篇
- 林業(yè)責(zé)任協(xié)議3篇
- 梅林水庫(kù)的安全保護(hù)3篇
- 法定代表人授權(quán)委托書(shū)寫(xiě)法3篇
- 杠鈴背部訓(xùn)練課程設(shè)計(jì)
- 涂抹果醬課程設(shè)計(jì)
- 攝像頭光學(xué)課程設(shè)計(jì)
- 瓷器收藏課程設(shè)計(jì)
- DB32T 3839-2020 水閘泵站標(biāo)志標(biāo)牌規(guī)范
- 基于西門子S7-200型PLC的消防給水泵控制系統(tǒng)設(shè)計(jì)
- CCEA GC 11-2019 工程造價(jià)咨詢企業(yè)服務(wù)清單
- 農(nóng)業(yè)比較效益低的成因及應(yīng)對(duì)
- 2020年住房和城鄉(xiāng)建設(shè)行業(yè)人員繼續(xù)教育(八大員繼續(xù)教育)土建質(zhì)量員繼續(xù)教育考試題庫(kù)集
- 直觀教具在小學(xué)英語(yǔ)詞匯教學(xué)中的運(yùn)用初探
- 《制冷設(shè)備原理與維修》期末試卷試題及參考答案
- 供水管道工程現(xiàn)場(chǎng)管理辦法
- 酒店委托管理模式下的財(cái)務(wù)治理
- 簡(jiǎn)單員工考勤表
- 新年賀卡模板
評(píng)論
0/150
提交評(píng)論