項(xiàng)目專項(xiàng)施工方案
鐵路工程ZQSG-3標(biāo)
西林隧道二次襯砌施工方案
編制:
審核:
審批:
日期:
項(xiàng)目專項(xiàng)施工方案
目錄
第一章編制說明....................................................................................................................1
1.1編制依據(jù)....................................................................................................................1
1.2編制范圍....................................................................................................................2
第二章工程概況....................................................................................................................2
2.1隧道概況....................................................................................................................2
2.2地質(zhì)條件....................................................................................................................3
2.3水文狀況....................................................................................................................3
2.4二襯及仰拱設(shè)計(jì)情況................................................................................................3
第三章施工進(jìn)度計(jì)劃............................................................................................................4
第四章施工準(zhǔn)備與資源配置計(jì)劃........................................................................................4
4.1施工原則....................................................................................................................4
4.2施作時機(jī)....................................................................................................................4
4.3施工準(zhǔn)備....................................................................................................................4
第五章施工工藝及方法........................................................................................................6
5.1二襯施工總體施工安排............................................................................................6
5.2施工順序....................................................................................................................7
5.3施工工藝流程............................................................................................................7
5.2.1隧道初支斷面凈空量測.................................................................................8
5.2.2清底和基面處理.............................................................................................8
5.2.3仰拱及仰拱填充施工...................................................................................10
5.2.4二襯鋼筋施工...............................................................................................14
5.2.5臺車使用.......................................................................................................20
5.2.6二襯混凝土澆筑...........................................................................................24
5.4防排水施工..............................................................................................................32
5.4.1排水盲管施工...............................................................................................33
5.4.2防水板施工...................................................................................................35
5.4.3施工縫變形縫防水施工...............................................................................38
5.5綜合接地設(shè)置..........................................................................................................43
I
項(xiàng)目專項(xiàng)施工方案
5.5.1綜合接地整體方案.......................................................................................43
5.5.2初期支護(hù)綜合接地(含明洞仰拱)...........................................................43
5.5.3二次襯砌綜合接地.......................................................................................45
5.5.4過軌管線.......................................................................................................49
5.6水溝電纜槽..............................................................................................................49
5.7預(yù)埋槽道..................................................................................................................52
5.8質(zhì)量驗(yàn)收標(biāo)準(zhǔn)..........................................................................................................56
第六章管理措施..................................................................................................................59
6.1標(biāo)準(zhǔn)化管理..............................................................................................................59
6.1.1標(biāo)準(zhǔn)化管理體系...........................................................................................59
6.1.2四化要求.......................................................................................................60
6.2安全生產(chǎn)保證措施..................................................................................................61
6.2.1安全目標(biāo).......................................................................................................61
6.2.2安全生產(chǎn)管理制度.......................................................................................61
6.2.3安全保證措施...............................................................................................63
6.3質(zhì)量管理措施..........................................................................................................65
6.3.1質(zhì)量目標(biāo).......................................................................................................65
6.3.2質(zhì)量保證體系...............................................................................................65
6.3.3質(zhì)量保證措施...............................................................................................66
6.4文明施工管理措施..................................................................................................68
6.4.1文明施工目標(biāo)...............................................................................................68
6.4.2文明施工措施...............................................................................................68
6.5施工環(huán)保、水土保持目標(biāo)......................................................................................70
6.5.1揚(yáng)塵治理和大氣環(huán)境保護(hù)...........................................................................70
6.5.2減小生態(tài)環(huán)境破壞.......................................................................................71
6.5.3噪聲、光污染控制.......................................................................................71
6.5.4水環(huán)境保護(hù)...................................................................................................72
6.5.5固體廢棄物處理...........................................................................................72
6.6綠色施工管理措施..................................................................................................74
II
項(xiàng)目專項(xiàng)施工方案
6.6.1綠色施工管理目標(biāo)及方針...........................................................................74
6.6.2綠色施工“五節(jié)”實(shí)施措施...........................................................................74
6.7工期控制措施..........................................................................................................76
6.7.1保證工期的管理措施...................................................................................76
6.7.2保證工期的組織措施...................................................................................76
6.7.3保證工期的技術(shù)措施...................................................................................77
6.7.4保證工期的資源保證措施...........................................................................77
6.8文物保護(hù)..................................................................................................................78
6.8.1文物保護(hù)目標(biāo)...............................................................................................78
6.8.2文物保護(hù)措施...............................................................................................78
6.9冬季施工措施..........................................................................................................79
6.9.1混凝土拌制...................................................................................................79
6.9.2鋼筋加工.......................................................................................................80
6.9.3養(yǎng)生溫度監(jiān)控...............................................................................................81
6.10雨季施工措施........................................................................................................82
6.10.1施工現(xiàn)場排水及道路通暢保證措施.........................................................82
6.10.2用電、防雷措施.........................................................................................82
6.10.3原材料及半成品的保護(hù).............................................................................82
6.10.4雨季施工資源配備計(jì)劃.............................................................................83
第七章預(yù)警機(jī)制和應(yīng)急預(yù)案..............................................................................................83
7.1應(yīng)急組織體系與職責(zé)..............................................................................................83
7.2應(yīng)急準(zhǔn)備..................................................................................................................87
7.3應(yīng)急響應(yīng)..................................................................................................................89
7.4信息報告..................................................................................................................90
7.5先期處置..................................................................................................................91
7.6應(yīng)急結(jié)束..................................................................................................................91
7.7后期處置..................................................................................................................91
7.8信息發(fā)布..................................................................................................................91
7.9培訓(xùn)與演練..............................................................................................................92
III
項(xiàng)目專項(xiàng)施工方案
7.10應(yīng)急事態(tài)及處理....................................................................................................93
7.10.1機(jī)械傷害事故應(yīng)急處理.............................................................................93
7.10.2交通事故應(yīng)急處理.....................................................................................93
7.10.3高處作業(yè)發(fā)生高處墜落的應(yīng)急處理.........................................................94
7.10.4觸電事故的應(yīng)急處理.................................................................................95
7.10.5隧道坍塌、涌水應(yīng)急處理.........................................................................96
7.10.6爆炸事故應(yīng)急處理.....................................................................................97
7.11應(yīng)急保障措施........................................................................................................99
7.11.1應(yīng)急演練.....................................................................................................99
7.11.2醫(yī)療保障.....................................................................................................99
7.11.3治安保障...................................................................................................100
第八章新型冠狀病毒肺炎疫情防控預(yù)案........................................................................100
8.1疫情響應(yīng)對策........................................................................................................100
8.2防控領(lǐng)導(dǎo)小組及職責(zé)............................................................................................100
8.2.1防控領(lǐng)導(dǎo)小組.............................................................................................100
8.2.2疫情防護(hù)應(yīng)急領(lǐng)導(dǎo)小組主要職責(zé).............................................................101
8.2.3疫情防護(hù)應(yīng)急辦公室職責(zé).........................................................................102
8.2.4工作小組主要職責(zé).....................................................................................102
8.3預(yù)防疫情防控措施................................................................................................104
8.4應(yīng)急響應(yīng)................................................................................................................105
8.5防疫物資準(zhǔn)備........................................................................................................106
8.6應(yīng)急路線................................................................................................................107
IV
項(xiàng)目專項(xiàng)施工方案
第一章編制說明
1.1編制依據(jù)
表1.1編制依據(jù)
序號類別文件名稱編號
中華人民共和國主席
1中華人民共和國安全生產(chǎn)法
令第十三號
中華人民共和國主席
2中華人民共和國環(huán)境保護(hù)法
國家法律令第九號
法規(guī)、行
中華人民共和國國務(wù)
3政文件建設(shè)工程安全生產(chǎn)管理?xiàng)l例
院令(第393號)
中華人民共和國國務(wù)
4建設(shè)工程質(zhì)量管理?xiàng)l例
院令(第714號)
5高速鐵路隧道工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)TB10753-2018
6高速鐵路隧道工程施工技術(shù)規(guī)程Q/CR9604-2015
7鐵路工程測量規(guī)范TB10101-2018
8鐵路隧道超前地質(zhì)預(yù)報技術(shù)規(guī)程Q/CR9217-2015
9鐵路隧道監(jiān)控量測技術(shù)規(guī)程Q/CR9218-2015
10鐵路隧道施工搶險救援指南Q/CR9219-2015
11鐵路工程沉降變形觀測與評估技術(shù)規(guī)程Q/CR9230-2016
12鐵路混凝土工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)TB10424-2018
行業(yè)標(biāo)準(zhǔn)
13鐵路混凝土強(qiáng)度檢驗(yàn)評定標(biāo)準(zhǔn)TBl0425-2019
規(guī)范
14鐵路工程結(jié)構(gòu)混凝土強(qiáng)度檢測規(guī)程TB10426-2019
15鐵路混凝土工程施工技術(shù)規(guī)程Q/CR9207-2017
16鐵路工程基本作業(yè)施工安全技術(shù)規(guī)程TB10301-2021
17鐵路隧道工程施工安全技術(shù)規(guī)程TB10304-2021
18鐵路混凝土TB/T3275-2018
19鐵路混凝土結(jié)構(gòu)耐久性設(shè)計(jì)規(guī)范TB10005-2010
20鐵路隧道工程施工機(jī)械配置技術(shù)規(guī)程Q/CR9226-2015
21鐵路建設(shè)項(xiàng)目現(xiàn)場管理規(guī)范Q/CR9202-2015
1
項(xiàng)目專項(xiàng)施工方案
序號類別文件名稱編號
22鐵路隧道襯砌質(zhì)量無損檢測規(guī)程TB10223-2004
鐵總建設(shè)(2017)
23鐵路建設(shè)項(xiàng)目質(zhì)量安全紅線管理規(guī)定
310號
新建鐵路萊西至榮成鐵路施工圖西林隧道設(shè)計(jì)
24榮萊施(隧道)10
圖
時速350公里客運(yùn)專線鐵路雙線隧道復(fù)合式襯
25通隧(2008)0301
砌
設(shè)計(jì)文件
26時速350km雙線隧道復(fù)合式襯砌萊榮隧參01
時速350km雙線隧道預(yù)支護(hù)措施、防排水
27萊榮隧參04
及施工方法
28鐵路綜合接地系統(tǒng)通號(2016)9301
山東省突發(fā)公共衛(wèi)生事件應(yīng)急響應(yīng)
29地方文件/
(實(shí)時更新響應(yīng)等級)
關(guān)于明確濰煙、萊榮鐵路隧道工程開挖進(jìn)尺濰煙高鐵工【2022】
30其他文件
及安全步距的通知20號
1.2編制范圍
xx鐵路站前工程ZQSG-3標(biāo)段西林隧道二次襯砌施工(含水溝電纜槽)。
第二章工程概況
2.1隧道概況
西林隧道位于山東省威海市乳山市大孤山鎮(zhèn)內(nèi),進(jìn)出口均有土路,交通較為方便。
隧址區(qū)剝蝕丘陵區(qū),地形起伏較大,相對高差31m,自然坡度約15°~40°,植被發(fā)育,
辟為茂密灌木。地層表層為全風(fēng)化花崗閃長巖,隧道洞身為強(qiáng)風(fēng)化~弱風(fēng)化花崗閃長巖,
強(qiáng)風(fēng)化層厚約3.5~9.8m,巖心呈塊狀,節(jié)理裂隙發(fā)育,巖體破碎;弱風(fēng)化層巖心呈柱
狀,巖體較完整,巖質(zhì)較堅(jiān)硬。
隧道里程DK117+880~DK118+344.22,該隧為設(shè)計(jì)時速350km單洞雙線隧道。隧
道全段位于半徑為9000m的右偏曲線上。隧道內(nèi)設(shè)置坡度為3.5‰的單面上坡。隧道最
大埋深27.6m。全長464.22m,其中Ⅴ級圍巖253m,Ⅳ級圍巖140m,明洞37.22m,進(jìn)、
出口洞門均采用17m斜切式洞門,隧道進(jìn)口明暗分界里程DK117+897,出口明暗分界
2
項(xiàng)目專項(xiàng)施工方案
里程為DK118+290。
2.2地質(zhì)條件
西林隧道隧址區(qū)為剝蝕丘陵地貌區(qū),地形起伏較大,地表植被較發(fā)育,相對高度約
31m,坡角15°~40°大部分區(qū)域基巖埋深較淺,隧址區(qū)頂部基巖直接出露,層間節(jié)理
裂隙發(fā)育,局部表層覆蓋殘破積物,谷底堆積有較厚的洪積物、坡積物。隧道出口地段
地勢較低;進(jìn)、出口段覆蓋層較薄,局部基巖出露。隧道最大標(biāo)高約96.5m,隧道最大
埋深約27.6m。
3
西林隧道隧址區(qū)表層為震旦期垛崮山超單元(dDγδ2)花崗閃長巖,全風(fēng)化,黃褐
色,主要分布在隧道山坡表層,厚3.0~6.3m不等,隧道洞身圍巖為震旦期垛崮山超單
3
元(dDγδ2),青灰色~灰白色,強(qiáng)風(fēng)化~弱風(fēng)化,強(qiáng)風(fēng)化層厚約3.5~9.8m,巖心呈塊
狀,節(jié)理裂隙發(fā)育,巖體破碎,弱風(fēng)化,巖芯呈柱狀,巖體較完整,巖質(zhì)較堅(jiān)硬。
線路所經(jīng)大地構(gòu)造單元屬于華北地臺膠北地塊,位于新華夏系巨型構(gòu)造的第二隆起
帶,由膠萊坳陷和威海隆起組成,隧址區(qū)屬于威海隆起,區(qū)內(nèi)巖漿巖面積出露,主要為
垛崮山超單元大孤山單元弱片麻狀、斑狀中粒含綠簾花崗閃長巖,呈巖基產(chǎn)出。
隧址區(qū)內(nèi)斷裂構(gòu)造不發(fā)育,無活動性斷裂通過。
2.3水文狀況
西林隧道地表水不發(fā)育;地下水弱發(fā)育,主要為基巖裂隙水,受大氣降水及地表水
補(bǔ)給。地下水無化學(xué)性侵蝕,無鹽類結(jié)晶破壞,僅根據(jù)氯離子含量判定,無氯鹽侵蝕性。
2.4二襯及仰拱設(shè)計(jì)情況
1Ⅳ級圍巖
Ⅳ級圍巖段采用Ⅳ型復(fù)合式襯砌,拱墻厚40cm、仰拱厚度50cm,主筋Φ18鋼筋、
a
鋼筋間距20cm,混凝土標(biāo)號為C35,防水等級P10,仰拱填充每延米7.365m3,混凝土
為C20素混凝土。
2Ⅴ級圍巖
Ⅴ級圍巖段采用Ⅴ型復(fù)合式襯砌,拱墻厚50cm、仰拱厚60cm,主筋Φ22鋼筋、
b
鋼筋間距20cm,混凝土標(biāo)號為C35,防水等級P10,仰拱填充每延米7.365m3,混凝土
3
項(xiàng)目專項(xiàng)施工方案
為C20素混凝土。
第三章施工進(jìn)度計(jì)劃
隧道防排水及二襯施工受隧道開挖進(jìn)度的影響,根據(jù)隧道開挖進(jìn)度情況對隧道防排
水及二襯施工作業(yè)時間進(jìn)行規(guī)劃。仰拱施工計(jì)劃于2022年6月20日開始,2022年12
月23日完成,工期為187天;二襯施工計(jì)劃于2022年7月25日開始,2022年1月27
日完成,工期為187天。水溝電纜槽施計(jì)劃工于2022年1月28日開始,2022年3月8
日完成,工期40天。
第四章施工準(zhǔn)備與資源配置計(jì)劃
4.1施工原則
軟弱圍巖及不良地質(zhì)隧道的二襯襯砌應(yīng)及時施作,Ⅳ級圍巖不得大于150m,Ⅴ級
圍巖不得大于120m。如超出此距離應(yīng)根據(jù)監(jiān)控量測情況減緩或暫停掌子面施工。
隧道襯砌要遵循“仰拱超前、拱墻整體襯砌”的原則。
4.2施作時機(jī)
二此襯砌根據(jù)圍巖及初期支護(hù)的變形監(jiān)控量測資料綜合分析后確定施作時機(jī)。淺埋
及地質(zhì)條件較差地段仰拱應(yīng)緊跟開挖面施作并與拱墻及早封閉成環(huán)。深埋隧道二次襯砌
在圍巖和初期支護(hù)基本穩(wěn)定后施作,初期支護(hù)變形基本穩(wěn)定條件如下:
1隧道水平凈空變化速度及拱頂垂直位移速度明顯下降。水平收斂(拱腳附近7d
平均值)小于0.2mm/d、拱部下沉速度小于0.15mm/d。
2隧道位移相對值已達(dá)到總相對位移量的90%以上。
圍巖變形過大或初期支護(hù)不收斂,又難以及時補(bǔ)強(qiáng)時,可設(shè)置臨時仰拱或橫撐以封
閉開挖面,必要時可提前施作二次襯砌,以改善施工結(jié)構(gòu)的受力狀態(tài),并輔以必要的加
強(qiáng)措施。
4.3施工準(zhǔn)備
1管理人員配備情況
為了保證隧道施工順利進(jìn)行,配置施工管理人員負(fù)責(zé)隧道施工的組織管理和協(xié)調(diào)。
4
項(xiàng)目專項(xiàng)施工方案
根據(jù)整個施工組織劃分,隧道施工為一工區(qū)施工范圍,隧道施工管理人員配置詳見表
4.3-1。
表4.3-1西林隧道施工主要管理人員
序號姓名崗位任務(wù)分工
1生產(chǎn)經(jīng)理負(fù)責(zé)隧道施工過程的現(xiàn)場統(tǒng)籌管理
2技術(shù)負(fù)責(zé)人負(fù)責(zé)現(xiàn)場施工過程的技術(shù)支持
3安全負(fù)責(zé)人負(fù)責(zé)施工過程對人、機(jī)的安全監(jiān)督管理
4技術(shù)員負(fù)責(zé)現(xiàn)場技術(shù)工作,及時記錄施工過程中的各種數(shù)據(jù)
5測量員負(fù)責(zé)隧道放樣及監(jiān)控量測工作
6質(zhì)量員負(fù)責(zé)隧道施工過程中的質(zhì)量檢測
7地質(zhì)工程師負(fù)責(zé)隧道施工過程中的超前地質(zhì)預(yù)報工作
8材料員負(fù)責(zé)隧道施工過程中材料采購及管理工作
9試驗(yàn)員負(fù)責(zé)隧道施工過程中的試驗(yàn)檢測工作
2勞動力配備情況
根據(jù)施工任務(wù),結(jié)合隧道洞身襯砌施工要求,選用專業(yè)隧道施工隊(duì)伍,針對洞身二
次襯砌配備防水班、鋼筋班、仰拱班、二襯班,合計(jì)35人。施工隊(duì)伍安排及勞力配置
詳見表4.3-2。
表4.3-2施工隊(duì)伍安排及勞力
序號施工隊(duì)伍司機(jī)/勞力配備擔(dān)負(fù)主要任務(wù)
1防排水班6清理巖面、預(yù)埋排水管、掛設(shè)土工布、防水板
2鋼筋班15二襯鋼筋加工、綁扎
3仰拱班6仰拱支模、澆筑仰拱及填充混凝土
4二襯班8二襯支模、澆筑二襯混凝土
3機(jī)械設(shè)備配備情況
根據(jù)二砌施工需要配備施工機(jī)械如表4.3-3所示。
表4.3-3二襯施工機(jī)械
序號機(jī)械設(shè)備名稱單位數(shù)量備注
1挖掘機(jī)PC220-6臺2帶破碎錘
2通風(fēng)機(jī)55kw臺2
5
項(xiàng)目專項(xiàng)施工方案
序號機(jī)械設(shè)備名稱單位數(shù)量備注
3發(fā)電機(jī)500GF臺1
4電焊機(jī)BX-200臺4
5鋼筋彎曲機(jī)GW50臺1
6鋼筋切斷機(jī)GQ50臺1
7砼輸送泵HBT60SE臺1
8仰拱棧橋自制套1
9爬焊機(jī)JIT-810臺2
10插入式振搗器ZN35臺8
11附著式振動器YZS-50-4臺20
12砼運(yùn)輸車YC4D130輛3
13襯砌臺車定制(12.1m)臺1
14裝載機(jī)柳工ZL50C輛4
15鋼筋臺車定制臺1
16養(yǎng)護(hù)臺車自制臺1
17水準(zhǔn)儀DSZ3臺1
測量
18全站儀萊卡臺1
儀器
19GPS海星達(dá)iRTK2臺1
4測量儀器配置情況見表4.3-4。
表4.3-4測量儀器
序號名稱單位數(shù)量備注
1水準(zhǔn)儀DSZ3臺1
2全站儀萊卡臺1
3GPS海星達(dá)iRTK2臺1
第五章施工工藝及方法
5.1二襯施工總體施工安排
總體施工見二襯施工工藝流程圖。
模板臺車施工:二襯采用定制二襯臺車施工,根據(jù)設(shè)計(jì)圖紙要求,二襯每版12m,
本隧道臺車長度選用12.1m(搭接部分長10cm)。臺車橫坡調(diào)節(jié)采用在主油缸底部設(shè)置
6
項(xiàng)目專項(xiàng)施工方案
加高塊的方式。
隧道防水施工:隧道內(nèi)采用簡易臺架鋪設(shè)防水材料。
隧道鋼筋施工:在加工廠集中加工,再運(yùn)輸至隧道二襯鋼筋施工部位,采用防水板
簡易臺架作為鋼筋綁扎施工平臺進(jìn)行鋼筋施工。環(huán)向主筋采用擠壓套筒連接和綁扎法共
同操作,縱向鋼筋采用綁扎連接,鋼筋節(jié)點(diǎn)采用綁扎。
隧道二襯砼施工:混凝土在1#拌合站集中拌合,混凝土罐車運(yùn)輸至隧道內(nèi),由砼輸
送泵至地面泵送至模板臺車內(nèi),振搗以插入式振搗棒為主,附著式振搗器輔助振搗。
5.2施工順序
二次襯砌施工順序:仰拱與矮邊墻同時施工,仰拱、矮邊墻超前30m,仰拱施做完
成后,利用多功能作業(yè)平臺人工鋪設(shè)防水板,綁扎鋼筋后,采用液壓整體式襯砌臺車進(jìn)
行二次襯砌,采用拱墻一次性整體灌注施工,最后完成整體道床施工。如圖5.2所示。
圖5.2二次襯砌施工順序
5.3施工工藝流程
二次襯砌施工流程見圖5.3。
7
項(xiàng)目專項(xiàng)施工方案
施工準(zhǔn)備
自動計(jì)量拌合站建立仰拱開挖襯砌斷面檢查
原材料進(jìn)場檢驗(yàn)鋪設(shè)軌道
棧橋就位
設(shè)計(jì)混凝土配比不臺車就位
合基底處理
格
混凝土試驗(yàn)拱墻施工縫接茬處理
鋼筋綁扎、安裝仰拱模板
合格
模板清理,臺車校正、固定
混凝土攪拌
隱蔽工程檢查
運(yùn)送混凝土
擋止預(yù)
合格基鋼
頭水墊埋
倉塊筋
板帶保件
泵送入模澆筑仰拱混凝土清安
安安護(hù)安
理裝
裝裝層裝
混凝土養(yǎng)護(hù)不
合
格
安裝填充及鋪底模板臺車安裝檢查
不
合合格
格
模板安裝檢查澆筑拱墻混凝土
合格
澆筑混凝土混凝土養(yǎng)護(hù)
混凝土養(yǎng)護(hù)脫模移動臺車
強(qiáng)度滿足機(jī)械行走結(jié)束
結(jié)束拱墻襯砌施工工藝流程
仰拱和填充施工工藝流程
圖5.3二次襯砌施工工藝流程
5.2.1隧道初支斷面凈空量測
隧道二襯施工之前,先由測量班對隧道初支斷面凈空進(jìn)行測量,對隧道凈空進(jìn)行檢
查,完成后將測量成果上報。提前對侵限部分進(jìn)行處理,處理完成后進(jìn)行復(fù)測,并經(jīng)監(jiān)
理檢查合格后方可進(jìn)行下一道工序。
初支凈空斷面間距:Ⅴ級圍巖5m,Ⅳ級圍巖10m。
8
項(xiàng)目專項(xiàng)施工方案
5.2.2清底和基面處理
1清底采用人工配合挖機(jī),清底過程中應(yīng)注意對隧道初支的保護(hù)。
2初支基面集中漏水部位進(jìn)行注漿堵水,滲水部位施作防水砂漿剛性防水層或堵
漏王,做到無滴水、漏水、淌水、線流或泥砂流出,保證基面干燥、清潔。
3自拱頂向兩側(cè)將基面外露的鋼筋頭、鐵絲、錨管、錨桿等尖銳物切除錘平,并
用砂漿抹平順,不得出現(xiàn)尖銳物。
4對基面凹凸不平處修鑿及用砂漿抹平順,初支表面平整度應(yīng)符合D/L≤1/10的
要求(D為初期支護(hù)基面相鄰兩凸面凹進(jìn)去的深度;L為基面相鄰兩凸面間的距離,且
L≤1m)。將基面陰、陽角處和棱角部位須用砂漿抹成圓弧,圓弧半徑為100mm。
5基面處理完,并經(jīng)檢查驗(yàn)收合格后,方可進(jìn)行下一道工序施工。
仰拱采用移動式棧橋施工,仰拱填充不與仰拱同時灌注,拱墻襯砌采用液壓鋼模襯
砌臺車施工,襯砌后注漿采用帶模注漿,最后施工水溝電纜槽。洞內(nèi)混凝土襯砌施工順
序見圖。
9
項(xiàng)目專項(xiàng)施工方案
圖5.2.2洞內(nèi)混凝土襯砌施工順序
5.2.3仰拱及仰拱填充施工
為保證隧道施工平行作業(yè),仰拱施工采用自制仰拱棧橋。每幅棧橋采用3根I40a工
字鋼,三根并排間距40cm設(shè)置,頂部用Φ22螺紋鋼筋連成整體,縱向
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 外匯預(yù)收貨款合同范例
- 種牛租賃合同范例
- 鄉(xiāng)村居民個人借款合同范例
- 二手轉(zhuǎn)讓房屋買賣合同范例
- 正規(guī)送貨合同范例
- 聘請兼職律師合同范例
- 吹填砂合同范例
- 注冊地址合同范例
- 公司領(lǐng)導(dǎo)承攬工程合同范例
- 聘用司機(jī)勞務(wù)合同范例
- 三級醫(yī)院醫(yī)療設(shè)備配置標(biāo)準(zhǔn)
- 合法離婚協(xié)議書(2篇)
- 水輪發(fā)電機(jī)組大修質(zhì)量標(biāo)準(zhǔn)
- 項(xiàng)目主要技術(shù)方案計(jì)劃表
- 汽車零部件開發(fā)質(zhì)量管理課件
- 20m29.6m30.4m20m鋼箱梁橋?qū)嵗O(shè)計(jì)內(nèi)容與表達(dá)
- 冀教版四年級上冊英語Unit 4單元測試卷(含聽力音頻)
- 【真題】北京市西城區(qū)六年級語文第一學(xué)期期末試卷 2021-2022學(xué)年(有答案)
- VMWare Horizon7平臺集成指南
- 口腔專科護(hù)理知識考核試題與答案
- 音響工作總結(jié)共3篇(劇院音響工作個人總結(jié))
評論
0/150
提交評論