




版權(quán)說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請進(jìn)行舉報(bào)或認(rèn)領(lǐng)
文檔簡介
1、Good is good, but better carries it.精益求精,善益求善。pd現(xiàn)場聚氨脂發(fā)泡外保溫施工方案現(xiàn)場聚氨脂發(fā)泡外保溫施工技術(shù)硬質(zhì)聚氨酯、聚苯顆粒保溫漿料復(fù)合外墻外保溫施工方案一、施工概況 該工程為長電臨河風(fēng)景物業(yè)樓,框架結(jié)構(gòu)4層,整個建筑面為3504.2平方米,屋面采用4厚現(xiàn)場硬質(zhì)聚氨酯噴涂保溫,外墻采用2厚現(xiàn)場硬質(zhì)聚氨酯噴涂、聚苯顆粒保溫漿料復(fù)合外保溫,抗裂砂漿復(fù)合耐堿玻纖網(wǎng)格布為保護(hù)增強(qiáng)層,表面為外墻涂料、瓷磚飾面層所組成的新型保溫節(jié)能墻體。二、施工準(zhǔn)備件條1施工用電:采用330V和220V電壓即可滿足施工要求,可用電纜線由總電源箱接出分別引到各樓層處。為了保證
2、機(jī)器設(shè)備的正常運(yùn)行及施工照明的需求,供電電壓不得低于正常電壓的5%。供電所用的導(dǎo)線、開關(guān)等應(yīng)能夠滿足設(shè)備的正常運(yùn)行及安全保護(hù)要求。2施工用腳手架:根據(jù)現(xiàn)場實(shí)際情況,屋面聚氨酯噴涂在層面即可操作,外墻聚氨酯噴涂及保溫漿料抹灰采用外腳手架。 3設(shè)備機(jī)具:配備國外進(jìn)口設(shè)備聚氨酯噴涂機(jī)1臺,氣泵1臺,雙輪推車2臺。三、勞動力組織 人員組織,公司結(jié)合本工程的特點(diǎn),選派有豐富施工和管理經(jīng)驗(yàn)的項(xiàng)目部施工。項(xiàng)目經(jīng)理1名,負(fù)責(zé)整個施工過程中的全面工作。質(zhì)檢員1名,負(fù)責(zé)工程的全面質(zhì)量工作,對工程質(zhì)量負(fù)全責(zé)?,F(xiàn)場選派2名有多年豐富經(jīng)驗(yàn)的聚氨酯噴涂槍手來完成整個噴涂面的工作。1名機(jī)修工,負(fù)責(zé)機(jī)器的維修及保養(yǎng),確保整個
3、施工過程中機(jī)器的正常運(yùn)轉(zhuǎn)。界面噴涂1名,其它人員15名,負(fù)責(zé)施工過程中的基層清理及維護(hù)工作。顆粒保溫及抗裂砂漿面層抹灰部分,設(shè)班組長1名、抹灰技工20名,力工15人,組成外保溫顆料抹灰班組,每一位員工上崗前要經(jīng)過培訓(xùn)。四、現(xiàn)場應(yīng)具備的作業(yè)條件1 首先施工現(xiàn)場應(yīng)具備“三通一平”即水、電、道路暢通,及材料的堆放場地。2 外墻面的垂直度和平整度應(yīng)符合現(xiàn)行國家施工及驗(yàn)收規(guī)范要求。3 外墻面上的雨水管卡、預(yù)埋鐵件等應(yīng)提前安裝完畢,并預(yù)留外保溫厚度。4 施工用腳手架應(yīng)牢固,必須經(jīng)檢驗(yàn)合格后,方可施工。塔吊等機(jī)械設(shè)備應(yīng)能滿足正常施工的要求。5 作業(yè)時環(huán)境溫度不得低于5,風(fēng)力不應(yīng)大于3級,嚴(yán)禁雨天施工,雨期應(yīng)
4、做好防雨措施。五、主要材料采購及性能 1黑、白料采用國外進(jìn)口料,供應(yīng)商由國內(nèi)知名品牌企業(yè)煙臺萬華負(fù)責(zé)供應(yīng),各項(xiàng)性能指標(biāo)穩(wěn)定,符合工程質(zhì)量要求。 2保護(hù)層界面劑、聚苯顆粒漿料、面層抗裂砂漿均由我廠生產(chǎn),采用國內(nèi)先進(jìn)的技術(shù)水平,科學(xué)的合理配方,各項(xiàng)性能指標(biāo)均達(dá)到國家規(guī)范要求。 3.原材料的采購:為確保工程質(zhì)量,在原材料采購方面經(jīng)過了長時間的充分準(zhǔn)備,在全國各地的不同區(qū)域進(jìn)行篩選比較,最后選定了國內(nèi)知名品牌企業(yè)煙臺萬華負(fù)責(zé)供應(yīng),產(chǎn)品無論在質(zhì)量上、數(shù)量上,以及供貨時間等幾方面均能滿足我們工程需求的廠家。 4.材料的儲存:1) 黑、白料:進(jìn)入施工現(xiàn)場的黑、白料應(yīng)分別存放,同時黑料還要避免陽光的直射,用雨
5、布遮擋好,防止結(jié)晶變質(zhì)。施工時可根據(jù)每層樓的實(shí)際噴涂面積,計(jì)算出所需噸數(shù)由上料口采用塔吊將黑、白料分別運(yùn)至每層樓,按要求擺放整齊。2) 界面劑:進(jìn)入施工現(xiàn)場的界面劑,應(yīng)按先后進(jìn)場順序碼放于通風(fēng)良好,干燥的室內(nèi),堆放高度不應(yīng)大于10個包裝袋,先進(jìn)場的應(yīng)先使用。無溶劑硬泡聚氨酯的主要性能指標(biāo)項(xiàng) 目單 位指 標(biāo)干密度/35-36導(dǎo)熱系數(shù)W/mk0025壓縮強(qiáng)度MPa015拉伸強(qiáng)度MPa015燃燒性平均燃燒時間平均燃燒高度S30250聚氨酯界面防潮劑的主要性能指標(biāo)項(xiàng) 目單 位指 標(biāo)容器中狀態(tài)-攪拌后無結(jié)塊,呈均勻狀態(tài)施工性-刷涂無困難低溫貯存穩(wěn)定性-3次試驗(yàn)后,無結(jié)塊,凝聚及組成物的變化拉伸粘結(jié)度與水
6、泥砂漿MPa常溫常態(tài)07耐水05耐凍融05拉伸粘結(jié)度與聚氨酯MPa常溫常態(tài)02聚氨酯破壞耐水02聚氨酯破壞耐凍融02聚氨酯破壞5保溫漿料應(yīng)具有檢測報(bào)告:(導(dǎo)熱系數(shù)達(dá)到0.059W/(mk)、壓縮強(qiáng)度大于250Kpa)、固化后的干密度穩(wěn)定在230/M3以下,保證材料的干密度和導(dǎo)熱系數(shù),檢查單袋重量、及有效期,且嚴(yán)禁曝曬雨淋、兌入其它物料,。 6.耐堿涂塑玻璃纖維網(wǎng)格布應(yīng)滿足施工質(zhì)量、技術(shù)要求。標(biāo)準(zhǔn)網(wǎng)達(dá)到139克/、網(wǎng)距44,耐堿抗拉強(qiáng)度經(jīng)向534N/2.5、緯向535 N/2.5。網(wǎng)格的存放應(yīng)立碼,不宜平堆且應(yīng)防火。7.聚合物抗裂耐水干粉砂漿:包裝應(yīng)為50/袋、保質(zhì)期三個月,應(yīng)存放在陰涼、防水、
7、防潮的地點(diǎn)。符產(chǎn)品標(biāo)準(zhǔn)說明書及出廠合格證。六、主要施工工具、設(shè)備噴涂機(jī)、高壓氣泵、抹子、手持電動攪拌器、多用刀、拉線、靠尺等。7branch network, the Internet, supporting DDN,FR,ISDN,PSTN and satellite data network connections. 2. network management system: the system planning, supervision, design and control of the use of network resources and activities, is achi
8、eve optimal network performance, including the following aspects: performance management: the multifaceted network performance monitoring and management, to ensure that the performance of the Internet to maintain at a high level. Configuration management: monitoring and configuration of network info
9、rmation. Account management: measure the utilization of network resources. Fault management: detection, registration, prompt the user to network failures and, if possible, automatically repair network problems. Safety management: according to the staff of planning to control network access protectio
10、n network will not be easily broken. Remote access management: including equipment management, user rights management, access management for remote users. Network security: network security from the physical layer, network layer, application layer, and many levels of consideration, and have the perf
11、ect virus protection. 3.3.4 system resources of management system in intelligent of factory construction many application of based Shang, to makes all application can smooth, efficient of run, while makes whole factory distribution of computer resources get concentrated, and full and monitoring, mus
12、t for whole computer systems established a perfect of system monitoring platform, makes user can through this platform achieved on whole system of full management, these management including: security management network management event/state/exception management database management detection work f
13、low management Storage management performance and output management services/help desk change and configuration management, inventory and asset management application management 3.3.5 the host system 1. host system performance, can meet the needs of various applications, high performance to price ra
14、tio. 2. the host system has a mechanism for storing backups, needs information stored in the system, as well as key home security needs. 3. critical hosts should take into account multiple aspects of cluster needs. 3.3.6 factory NET 1. goals: broadband multimedia, Office, production and research to
15、provide the best environment and platform, built State of the art network connecting all Department offices, workshops and laboratories. 2. network functions: support for broadband multimedia services; provide advanced platform for production, Commerce, scientific research; provide a good environmen
16、t for academic exchange, and high speed Internet CERNET,CHINANET, quick access to the INTERNET, Exchange information with counterparts at home and abroad, work in concert and exhibition company, factorybranch network, the Internet, supporting DDN,FR,ISDN,PSTN and satellite data network connections.
17、2. network management system: the system planning, supervision, design and control of the use of network resources and activities, is achieve optimal network performance, including the following aspects: performance management: the multifaceted network performance monitoring and management, to ensur
18、e that the performance of the Internet to maintain at a high level. Configuration management: monitoring and configuration of network information. Account management: measure the utilization of network resources. Fault management: detection, registration, prompt the user to network failures and, if
19、possible, automatically repair network problems. Safety management: according to the staff of planning to control network access protection network will not be easily broken. Remote access management: including equipment management, user rights management, access management for remote users. Network
20、 security: network security from the physical layer, network layer, application layer, and many levels of consideration, and have the perfect virus protection. 3.3.4 system resources of management system in intelligent of factory construction many application of based Shang, to makes all application
21、 can smooth, efficient of run, while makes whole factory distribution of computer resources get concentrated, and full and monitoring, must for whole computer systems established a perfect of system monitoring platform, makes user can through this platform achieved on whole system of full management
22、, these management including: security management network management event/state/exception management database management detection work flow management Storage management performance and output management services/help desk change and configuration management, inventory and asset management applica
23、tion management 3.3.5 the host system 1. host system performance, can meet the needs of various applications, high performance to price ratio. 2. the host system has a mechanism for storing backups, needs information stored in the system, as well as key home security needs. 3. critical hosts should
24、take into account multiple aspects of cluster needs. 3.3.6 factory NET 1. goals: broadband multimedia, Office, production and research to provide the best environment and platform, built State of the art network connecting all Department offices, workshops and laboratories. 2. network functions: sup
25、port for broadband multimedia services; provide advanced platform for production, Commerce, scientific research; provide a good environment for academic exchange, and high speed Internet CERNET,CHINANET, quick access to the INTERNET, Exchange information with counterparts at home and abroad, work in
26、 concert and exhibition company, factory七、施工進(jìn)度計(jì)劃施工進(jìn)度計(jì)劃施工進(jìn)度計(jì)劃表工程名稱:臨河風(fēng)景物業(yè)樓聚氨酯噴涂、聚苯顆粒外保溫工程序號分項(xiàng)工程名稱工程量勞 動 計(jì) 劃6月 份7月 份技工力工工作日27293024681012141618202224242628301基層清理552污染防護(hù)5103材料吊運(yùn)5254噴涂防潮劑2105聚酯氨酯噴涂15606噴涂界面劑2107抹顆粒保溫漿料20153508竣工驗(yàn)收八、現(xiàn)場噴涂聚氨酯發(fā)泡及聚苯顆粒保溫漿料施工工藝流程:屋面部分:基層清理污染防護(hù)噴涂界面防潮層開機(jī)噴涂聚氨酯局部修整噴涂界面劑保護(hù)層竣工外墻面部分
27、:基層清理污染防護(hù)噴涂界面防潮層開機(jī)噴涂聚氨酯局部修整噴涂界面劑保護(hù)層抹聚苯顆粒抹聚合物抗裂砂漿壓入玻纖網(wǎng)格布抹面層抗裂砂漿竣工.1、基層清理1) 清理主體施工時墻面遺留的鋼筋頭、廢模板、填堵施工孔洞。2) 清掃墻面的浮灰,清洗油污。3) 墻表面突起物大于或等于10時應(yīng)剔除。2、測量放線1) 在墻的頂部固定膨脹螺栓,作為掛線鐵絲的垂掛點(diǎn)2) 根據(jù)外墻軸線向外返出外保溫抹灰厚度控制點(diǎn),而后固定垂直控制線兩端3) 復(fù)測每層到垂直線的距離是否一致,偏差超過20的,查明原因后做出墻面找平層厚度調(diào)整。4) 根據(jù)垂直控制通線和水平通線做門窗洞口及大陽角處的灰餅.3、噴涂界面劑防潮層 防潮界面劑現(xiàn)場加水?dāng)嚢?/p>
28、均勻后,用噴槍噴在基層墻體上,厚度為2, 噴涂時要均勻、無漏點(diǎn)。4、現(xiàn)場噴涂聚氨脂發(fā)泡1) 開機(jī)噴涂,將聚氨脂保溫隔熱材料均勻地自上而下、自下而上反復(fù)噴涂于墻面之上,每遍厚度宜控制在10之內(nèi),確保聚氨酯層面厚度4、外墻面厚度2,盡量避免流掛象發(fā)生。噴涂硬泡聚氨酯保溫隔熱材料時要注意防風(fēng),施工噴涂應(yīng)多遍完成。2) 噴涂聚氨酯現(xiàn)場發(fā)泡彈性體時,應(yīng)將其壓力調(diào)節(jié)至最高(1000PSI以上)。如果壓力較小,黑白料混合不均勻,會導(dǎo)致反應(yīng)不完全,噴槍持續(xù)噴涂,壓縮空氣壓力會下降,也可能導(dǎo)致噴涂的彈性體表面發(fā)粘。所以,在進(jìn)行彈性體噴涂時,應(yīng)間歇地松動板機(jī),以便維持較高的壓力縮空氣壓力。3) 噴涂聚氨酯現(xiàn)場發(fā)泡
29、彈性體時,將加熱保溫管溫度調(diào)節(jié)至7080,在此條件下將原料預(yù)熱20分鐘,再將主加熱器溫度調(diào)節(jié)6070,即可進(jìn)行噴涂。原料加熱的目的之一是降低黑白料的粘度,使兩種原料的粘度接近,保證黑白料盡可能按設(shè)備要求的比例混合。如果加熱器溫度過低或加熱保溫管溫度過低,會導(dǎo)致在低溫下黑白料粘度較大,混合不均勻,反應(yīng)不完全,致使噴涂的彈性休表面發(fā)粘。4) 操作人員應(yīng)根據(jù)噴涂彈性體顏色的變化來及時判斷黑白料比例是否失調(diào),如果彈性體顏色變淺,表明白料/黑料大于1,如果彈性體顏色變深,表明白料/黑料小于1。5) 如果在噴涂施工過程中出現(xiàn)彈性體發(fā)粘或不固化等現(xiàn)象,可以把不良部分清理掉,然后用溶劑清洗干凈,即可重新進(jìn)行噴
30、涂。6) 用平噴混合頭進(jìn)行噴涂比圓噴混合頭更能精確地控制噴涂的置,使噴涂的彈性體表面更平整、光滑。7) 噴涂彈性一次噴涂厚度約為0. 30.5毫米,應(yīng)根據(jù)所需彈性體的厚度來確定噴涂的次數(shù)。8) 理想的噴涂效果是噴涂彈性體在噴涂后35秒即可硬化,30分鐘后即可進(jìn)行一道工序。5、噴涂界面劑在噴涂完聚氨酯發(fā)泡工序后,用噴槍隨即在上面均勻的刷涂一層界面劑,厚度為2。噴涂時要均勻一致,無漏點(diǎn)現(xiàn)象發(fā)生。6、保溫顆粒抹灰1) 在噴完界面劑的硬質(zhì)聚氨酯上進(jìn)行保溫顆粒漿料抹灰。保溫膠料應(yīng)在每個施工樓層進(jìn)行拌合,需設(shè)專人專職進(jìn)行攪拌,以保證拌合時間和加水量的準(zhǔn)確性,在施工現(xiàn)場攪拌,質(zhì)量可以通過觀察其可操作性、抗滑
31、墜性、膏料狀態(tài)等方法判斷。2) 用保溫顆粒膠料在聚氨酯硬泡上做標(biāo)準(zhǔn)厚度貼餅、沖筋。在打底層抹灰時,保溫漿料厚度不大于20,其平整度要求達(dá)到初步找平的標(biāo)準(zhǔn)。在間隔24小時以上抹面層保溫顆粒漿料,厚度應(yīng)控制在10左右,略高于灰餅的厚度,而后用杠尺刮平,用抹子局部修補(bǔ)平整,待抹完保溫面層30分鐘后,用抹子再趕抹墻面,使平整度達(dá)到規(guī)范要求,其平整度偏差不應(yīng)大于4,為下一步做抗裂漿膠面層打好基礎(chǔ)。保溫漿料應(yīng)在4小時內(nèi)使用完畢,回收的落地灰在4小時內(nèi)回罐攪拌后使用完畢。6、面層施工:保溫層固化干燥后(約24小時左右)方可進(jìn)行施工,廠家已配制好,現(xiàn)場施工時加水用手持電動攪拌機(jī)攪拌,重量比為水:聚合物干粉砂漿
32、等于1:5,即水灰比0.2,可操作時間不大于3小時。在保溫層上抹抗裂面層膠漿,厚度控制在2,所抹面積略大于網(wǎng)片的長,將裁好的耐堿網(wǎng)格布曲面朝向基層壓入抗裂膠漿中,平整不應(yīng)有皺折,網(wǎng)眼膠漿飽滿度應(yīng)為100%,耐堿網(wǎng)格搭接寬度不應(yīng)小于65,耐堿網(wǎng)格布的邊緣嚴(yán)禁干搭接,必須嵌在抗裂膠漿中,在基層大陽角轉(zhuǎn)角處250范圍內(nèi)嚴(yán)禁搭接。面層砂漿施工應(yīng)選擇施工時及施工后24小時沒有雨的天氣進(jìn)行,避免雨水沖刷造成返工。門窗洞口內(nèi)側(cè)周邊及洞口四角均加一層網(wǎng)格布進(jìn)行加強(qiáng),洞口四周網(wǎng)格布尺寸為300200,大墻面粘貼的網(wǎng)格布搭接在門窗口周邊的加強(qiáng)網(wǎng)格布之上,一同埋貼在底層聚合物砂漿內(nèi)。 在預(yù)留孔洞位置處,網(wǎng)格布將斷開
33、,此處面層砂漿的留槎位置應(yīng)考慮后補(bǔ)網(wǎng)格布與原大面網(wǎng)格布搭接長度要求而預(yù)留一定長度。面層聚合物抗裂砂漿應(yīng)留成直槎,砂漿具體留槎位置見圖。7、粘貼外墻面磚:待第一層初步干硬后,即可進(jìn)行外墻面磚的施工:在粘貼面磚前,應(yīng)準(zhǔn)備噴水器對所粘貼的基層進(jìn)行噴水濕潤,以不流淌為宜。在每一分段或分塊內(nèi)的面磚均勻?yàn)樽韵孪蛏险迟N,從最下一層磚下皮的位置線先隱好靠尺,以此托住第一皮面磚,在面磚外皮上口拉水平通線作為粘貼的標(biāo)準(zhǔn)。掛線時,應(yīng)橫豎向均勻甩縫5,豎向縫隙掛雙線,水平向掛單線,但要棱上跟線,在鋪貼過程中及時垂吊,防止出現(xiàn)垂直偏差。超過3m時或中間腰線層高超過3m時,應(yīng)用3m杠檢查。九、質(zhì)量管理措施 1、質(zhì)量控制措
34、施1) 加強(qiáng)人的控制,發(fā)揮“人的因素第一”的主導(dǎo)作用,把人的控制作為全過程控制的重點(diǎn)。管理必須盡職盡責(zé),做好本職工作,同時搞好團(tuán)結(jié)協(xié)作,對施工隊(duì)嚴(yán)格管理,進(jìn)行考核上崗施工,在安排施工計(jì)劃時,全面考慮各種因素對工程質(zhì)量的影響和人與任務(wù)的平衡,防止造成人為事故。2) 加強(qiáng)施工生產(chǎn)和進(jìn)度安排的控制,會同施工班組長合理安排施工進(jìn)度,在進(jìn)度和質(zhì)量發(fā)生矛盾時,進(jìn)度服從于質(zhì)量,合理安排勞動力,科學(xué)地進(jìn)行施工調(diào)度,加強(qiáng)施工機(jī)具、設(shè)備管理、保證施工生產(chǎn)的需要。3) 加強(qiáng)施工物資的質(zhì)量控制,原材料、成品、半成品的采購必須認(rèn)真執(zhí)行公司材料采購制度,凡采購到現(xiàn)場的物資、項(xiàng)目負(fù)責(zé)人必須嚴(yán)格認(rèn)真檢查其質(zhì)量,數(shù)量、品種、規(guī)
35、格等,必要時請施工班組參加。4) 嚴(yán)格檢查制度,所有施工過程都要按規(guī)定認(rèn)真進(jìn)行檢查,檢驗(yàn),未達(dá)到標(biāo)準(zhǔn)要求必須返工,驗(yàn)收合格后才能轉(zhuǎn)入下道工序。5) 自檢:操作工人在施工中按施工成序進(jìn)行自我檢查,并由施工隊(duì)派專職人員進(jìn)行檢查,合格后填寫自檢單報(bào)項(xiàng)目負(fù)責(zé)人,保證本班組完成的施工項(xiàng)目達(dá)到質(zhì)量目標(biāo)的要求,為下一道工序創(chuàng)造良好的施工條件。6) 專檢:在自檢滿足要求的基礎(chǔ)上,項(xiàng)目負(fù)責(zé)人會同有關(guān)專業(yè)施工人員進(jìn)行復(fù)查,合格后報(bào)項(xiàng)目監(jiān)理部驗(yàn)收。檢查中要嚴(yán)格標(biāo)準(zhǔn),一切用數(shù)據(jù)說話,確保每一道工序工程質(zhì)量。7) 堅(jiān)持樣板引路制度,各道工序在施工前必須做樣板,負(fù)責(zé)人員進(jìn)行監(jiān)控指導(dǎo),現(xiàn)場做示范。樣板完成后才能全面施工。8
36、) 加強(qiáng)成品的保護(hù),指定專人負(fù)責(zé),嚴(yán)格執(zhí)行搬運(yùn)、包裝、防護(hù)和交付控制程序,采取“護(hù)、包、蓋、封”的保護(hù)措施,并合理安排施工順序,防止后道工序損壞或污染前道工序。 2、技術(shù)控制措施1) 做好技術(shù)交底,并把交底內(nèi)容傳達(dá)到班組,講解施工工藝、技術(shù)要求、心中有數(shù),掌握關(guān)鍵環(huán)節(jié),避免發(fā)生指導(dǎo)錯誤及操作錯誤。書面交底,應(yīng)強(qiáng)調(diào)采用書面交底的做法,按規(guī)范和規(guī)程的有關(guān)技術(shù)規(guī)定、質(zhì)量標(biāo)準(zhǔn)和安全要求,結(jié)合工程的具體情況寫出書面交底材料,一式兩份?,F(xiàn)場跟班檢查,保證貫徹執(zhí)行,檢查抄平,放線、準(zhǔn)備工作是否符合要求,工人能否按交底要求進(jìn)行施工,一些關(guān)鍵部位是不是合符要求,如有問題提醒工人,注意安全、質(zhì)量等問題。2) 加強(qiáng)材料的
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025年中國電動螺絲刀行業(yè)市場調(diào)查研究及發(fā)展戰(zhàn)略規(guī)劃報(bào)告
- 工業(yè)產(chǎn)品設(shè)計(jì)中的材料學(xué)考核試卷
- 影視錄放設(shè)備的智能聯(lián)網(wǎng)優(yōu)化技術(shù)前景展望考核試卷
- 摩托車運(yùn)動與軌跡控制系統(tǒng)的設(shè)計(jì)與開發(fā)考核試卷
- 2025年美味老抽行業(yè)深度研究分析報(bào)告
- 社交數(shù)據(jù)驅(qū)動的教育創(chuàng)新實(shí)踐
- 2021-2026年中國外用藥行業(yè)發(fā)展前景及投資戰(zhàn)略規(guī)劃研究報(bào)告
- 2021-2026年中國折扣女裝行業(yè)深度分析及投資規(guī)劃研究建議報(bào)告
- 客運(yùn)站安全保障措施加強(qiáng)考核試卷
- 2022-2027年中國周圍血管疾病中成藥行業(yè)市場發(fā)展現(xiàn)狀及投資規(guī)劃建議報(bào)告
- 高三一?!吧媾c強(qiáng)弱關(guān)系思辨”審題立意及范文
- 2025年茂名市高三年級第一次綜合測試(一模)物理試卷(含答案)
- 2025年重癥醫(yī)學(xué)科(ICU)護(hù)理工作計(jì)劃
- 四川省名校2025屆高三第二次模擬考試英語試卷含解析
- 2024各科普通高中課程標(biāo)準(zhǔn)
- 中小學(xué)校園課間時間巡查工作方案
- 《垂體瘤規(guī)范化診治》課件
- 早產(chǎn)臨床防治指南(2024版)解讀
- 艾草種植基地合同(2篇)
- GB/T 30661.10-2024輪椅車座椅第10部分:體位支撐裝置的阻燃性要求和試驗(yàn)方法
- 空調(diào)制冷管道施工協(xié)議
評論
0/150
提交評論