版權(quán)說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請(qǐng)進(jìn)行舉報(bào)或認(rèn)領(lǐng)
文檔簡(jiǎn)介
中旅成都高新新川項(xiàng)目施工總承包一標(biāo)段工程
臨水用水施工方案
編制單位:中國(guó)建筑第八工程局有限公司
編制人:
編制日期:2023年3月
1
目錄
1編制依據(jù)........................................................................................................................................................1
2工程概況........................................................................................................................................................2
2.1工程建設(shè)概況.....................................................................................................................................2
2.2工程設(shè)計(jì)概況.....................................................................................................................................2
2.3施工條件.............................................................................................................................................2
3施工安排........................................................................................................................................................3
3.1施工管理組織.....................................................................................................................................3
3.1.1管理組織機(jī)構(gòu)..........................................................................................................................3
3.1.2管理人員及職責(zé)權(quán)限..............................................................................................................3
3.2項(xiàng)目管理目標(biāo).....................................................................................................................................3
3.3各項(xiàng)資源安排.....................................................................................................................................4
3.3.1勞務(wù)資源安排一覽表..............................................................................................................4
3.3.2工程用大宗物資供應(yīng)安排一覽表..........................................................................................4
3.4施工流水段的劃分及施工工藝流程.................................................................................................4
3.4.1施工區(qū)域的劃分......................................................................................................................4
3.4.2施工工藝流程..........................................................................................................................5
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施.............................................................................................5
4臨水施工進(jìn)度計(jì)劃........................................................................................................................................6
4.1臨時(shí)用水及消防系統(tǒng).........................................................................................................................6
4.1.1基礎(chǔ)及地下結(jié)構(gòu)施工階段臨時(shí)用水及消防系統(tǒng)...................................................................6
4.1.2各樓層施工用水及消防給水系統(tǒng)..........................................................................................6
5施工準(zhǔn)備與資源配置計(jì)劃............................................................................................................................7
5.1施工準(zhǔn)備計(jì)劃.....................................................................................................................................7
5.1.1組織準(zhǔn)備..................................................................................................................................7
5.1.2技術(shù)準(zhǔn)備..................................................................................................................................7
5.1.3生產(chǎn)準(zhǔn)備..................................................................................................................................7
5.2資源配置計(jì)劃.....................................................................................................................................7
6臨水主要施工方法........................................................................................................................................9
6.1總體概況.............................................................................................................................................9
6.2臨水施工內(nèi)容.....................................................................................................................................9
6.3水量計(jì)算...........................................................................................................................................10
6.4設(shè)備選擇...........................................................................................................................................11
6.5水箱選擇...........................................................................................................................................12
6.6施工要點(diǎn)...........................................................................................................................................12
6.7管線維護(hù)及節(jié)水措施.......................................................................................................................13
6.7.1管線維護(hù)................................................................................................................................13
6.7.2節(jié)水措施................................................................................................................................13
6.8防火和防風(fēng)措施...............................................................................................................................13
6.9設(shè)備防護(hù)措施...................................................................................................................................14
6.10管道支架制作安裝施工措施.........................................................................................................14
6.10驗(yàn)收程序.........................................................................................................................................14
6.11驗(yàn)收內(nèi)容.........................................................................................................................................15
6.12驗(yàn)收人員.........................................................................................................................................15
2
7各項(xiàng)管理計(jì)劃..............................................................................................................................................16
7.1綠色施工管理計(jì)劃...........................................................................................................................16
7.1.1綠色施工管理體系................................................................................................................16
7.1.2綠色施工管理措施................................................................................................................16
7.2消防管理計(jì)劃...................................................................................................................................18
7.2.1消防管理組織體系................................................................................................................18
7.2.2消防管理流程........................................................................................................................18
7.2.3消防安全管理措施................................................................................................................19
7.2.4消防安全事故應(yīng)急預(yù)案........................................................................................................20
7.3進(jìn)度管理計(jì)劃...................................................................................................................................22
7.3.1組織保證措施........................................................................................................................23
7.3.2技術(shù)保證措施........................................................................................................................23
7.3.3人員保證措施........................................................................................................................24
7.3.4材料保證措施........................................................................................................................24
7.3.5機(jī)械保證措施........................................................................................................................24
7.4質(zhì)量管理計(jì)劃...................................................................................................................................24
7.4.1質(zhì)量管理各部門職責(zé)............................................................................................................24
7.4.2質(zhì)量管理制度........................................................................................................................25
7.4.3質(zhì)量保證措施........................................................................................................................25
7.5職業(yè)健康安全管理計(jì)劃...................................................................................................................25
7.5.1職業(yè)健康安全管理目標(biāo)........................................................................................................25
7.5.2現(xiàn)場(chǎng)職業(yè)健康安全管理組織機(jī)構(gòu)和職責(zé)分工.....................................................................26
7.5.3職業(yè)健康安全重大危險(xiǎn)源....................................................................................................27
7.5.4職業(yè)健康安全資源配置計(jì)劃................................................................................................27
7.5.5安全生產(chǎn)管理制度................................................................................................................28
7.5.6職業(yè)健康安全生產(chǎn)保證措施................................................................................................30
7.6成品保護(hù)計(jì)劃...................................................................................................................................31
7.6.1成品和設(shè)備保護(hù)的組織機(jī)構(gòu)職責(zé)分工.................................................................................31
7.6.2臨水過程中自身成品和設(shè)備保護(hù)措施.................................................................................32
8應(yīng)急預(yù)案......................................................................................................................................................33
8.1應(yīng)急指揮機(jī)構(gòu)及職責(zé).......................................................................................................................33
8.1.1應(yīng)急指揮機(jī)構(gòu)........................................................................................................................33
8.1.2應(yīng)急領(lǐng)導(dǎo)小組職責(zé)................................................................................................................33
8.2救援指揮程序...................................................................................................................................34
8.2.1調(diào)集力量................................................................................................................................34
8.2.2搶險(xiǎn)救援基本對(duì)策................................................................................................................34
8.3應(yīng)急救援設(shè)備構(gòu)成...........................................................................................................................34
8.4應(yīng)急預(yù)案的培訓(xùn)和演練...................................................................................................................34
8.5應(yīng)急響應(yīng)...........................................................................................................................................35
8.6應(yīng)急預(yù)案的終止...............................................................................................................................36
9疫情防控管理..............................................................................................................................................37
9.1疫情防控組織機(jī)構(gòu)...........................................................................................................................37
9.1.1疫情防控組織架構(gòu)................................................................................................................37
9.2疫情防控措施...................................................................................................................................38
9.2.1防疫物資................................................................................................................................38
3
9.2.2進(jìn)場(chǎng)管理................................................................................................................................38
9.2.3日常管理和出行報(bào)備............................................................................................................39
9.2.4體溫檢測(cè)管理........................................................................................................................39
9.2.5防疫專項(xiàng)教育........................................................................................................................40
9.2.6防疫宣傳................................................................................................................................40
9.2.7保潔消毒................................................................................................................................41
9.2.8食堂衛(wèi)生管理........................................................................................................................41
9.3疫情應(yīng)急管理...................................................................................................................................42
4
1編制依據(jù)
序號(hào)類別文件名稱編號(hào)
1《建設(shè)工程施工現(xiàn)場(chǎng)消防安全技術(shù)規(guī)范》GB50720-2011
2《消防給水及消火栓系統(tǒng)技術(shù)規(guī)范》GB50974-2014
3《給水排水管道工程施工及驗(yàn)收規(guī)范》GB50268-2008
4行業(yè)規(guī)范《建筑給水排水及供暖工程施工技術(shù)標(biāo)準(zhǔn)》ZJQ08-SGJB242-2017
5《建筑給水排水設(shè)計(jì)標(biāo)準(zhǔn)》GB50015-2023
6《建筑給水排水工程規(guī)范》ZBBZH/GJ15
7《建筑給水排水及采暖工程施工質(zhì)量驗(yàn)收規(guī)范》GB50242-2002
8合同《中旅成都高新新川項(xiàng)目施工總承包工程施工合同》/
9企業(yè)管理《技術(shù)質(zhì)量管理手冊(cè)》2023版
10文件《安全施工管理手冊(cè)》2023版
中旅成都高新新川項(xiàng)目施工總承包工程一標(biāo)段平面布置
11設(shè)計(jì)文件/
圖
1
2工程概況
2.1工程建設(shè)概況
表2.1工程概況
中旅成都高新新川項(xiàng)目施工總承包工程
工程名稱工程性質(zhì)高層民用建筑/多層民用建筑
一標(biāo)段
成都高新區(qū)中和街道龍燈山社
建設(shè)規(guī)模(造
4.02億元工程地址區(qū)12組
價(jià))
(原紅松村2社)
總占地面積40292.42㎡總建筑面積162030.34㎡
土石方開挖、回填土、降排水、
基坑支護(hù)、基礎(chǔ)、主體、屋面、
保溫、防水、人防結(jié)構(gòu)部分、
建設(shè)單位項(xiàng)目承包范圍
裝配式、外墻抹灰、粗裝修、
欄桿、室內(nèi)給排水、電氣及防
雷接地、預(yù)留預(yù)埋等。
門窗安裝工程、地坪及交安設(shè)
施工程、景觀園林、總坪綜合
設(shè)計(jì)單位主要分包工程
管網(wǎng)工程、標(biāo)識(shí)標(biāo)牌、消防工
程、照明、弱電工程等。
勘察單位質(zhì)量四川省結(jié)構(gòu)優(yōu)質(zhì)工程獎(jiǎng)
2023年4月20日至2023年3
監(jiān)理單位工期
月10日,共325日歷天。
合同
四川省省級(jí)安全生產(chǎn)文明施工
總承包單位中國(guó)建筑第八工程局有限公司要求安全
標(biāo)準(zhǔn)化工地
四川省建筑業(yè)新技術(shù)應(yīng)用示范
監(jiān)督單位科技
工地
工程主要功能
住宅
或用途
2.2工程設(shè)計(jì)概況
本項(xiàng)目位于成都高新區(qū)中和街道龍燈山社區(qū)12組,擬新建9#(23F)、10#-1(23F)、
10#-2(25F)、11#(25F)、12#-1(25F)、12#-2(23F)、13#-1(23F)、13#-2(23F)5棟高層住
宅,14#~29#16棟7層疊拼,場(chǎng)內(nèi)地下室東側(cè)為一層、西側(cè)為二層。
2.3施工條件
側(cè),用于生活辦公區(qū)生活用水,并擬于項(xiàng)目東南側(cè),靠近管理人員生活區(qū)設(shè)立1個(gè)臨
時(shí)水泵房,用于生產(chǎn)用水。
2
3施工安排
3.1施工管理組織
3.1.1管理組織機(jī)構(gòu)
圖3.1.1項(xiàng)目管理組織架構(gòu)
3.1.2管理人員及職責(zé)權(quán)限
表3.1.2小組成員及管理職責(zé)
序號(hào)崗位管理職務(wù)姓名職責(zé)
1組長(zhǎng)項(xiàng)目經(jīng)理王凱全面負(fù)責(zé)臨水施工的管理工作。
1負(fù)責(zé)臨水方案等技術(shù)指導(dǎo)工作。
2技術(shù)負(fù)責(zé)人楊偉平2負(fù)責(zé)臨水施工技術(shù)復(fù)核工作。
副組3負(fù)責(zé)相關(guān)技術(shù)資料的收集及整理工作。
長(zhǎng)
3生產(chǎn)經(jīng)理謝文軍負(fù)責(zé)施工現(xiàn)場(chǎng)施工生產(chǎn)、安全文明管理工作。
4商務(wù)經(jīng)理羅天皓負(fù)責(zé)統(tǒng)籌臨水商務(wù)采購(gòu)、資金安排等工作。
5機(jī)電負(fù)責(zé)人鄒星乾全面負(fù)責(zé)臨水施工協(xié)調(diào)管理。
負(fù)責(zé)臨水施工現(xiàn)場(chǎng)質(zhì)量管理,保證現(xiàn)場(chǎng)施工質(zhì)量,組織臨建施工
6質(zhì)量負(fù)責(zé)人何亮
質(zhì)量驗(yàn)收;
全面負(fù)責(zé)臨水安全監(jiān)督管理工作(包括防火、防毒、安全防護(hù)、
7安全負(fù)責(zé)人甘立海
保衛(wèi)、環(huán)境)。
組員負(fù)責(zé)配合機(jī)電負(fù)責(zé)人進(jìn)行施工的現(xiàn)場(chǎng)協(xié)調(diào),組織資源配置全面安
8機(jī)電工程師毛君森
排現(xiàn)場(chǎng)施工,確保工期計(jì)劃
9商務(wù)工程師胡前寬負(fù)責(zé)臨水工程招投標(biāo)和預(yù)結(jié)算工作
負(fù)責(zé)臨水施工階段材料供應(yīng),對(duì)所供應(yīng)的材料質(zhì)量負(fù)責(zé),并按照
10物資工程師蒲炎全國(guó)家標(biāo)準(zhǔn)對(duì)進(jìn)場(chǎng)材料進(jìn)行驗(yàn)收,對(duì)現(xiàn)場(chǎng)材料保管、材料使用、材
料節(jié)約等方面進(jìn)行嚴(yán)格的控制。
3.2項(xiàng)目管理目標(biāo)
表3.2.1項(xiàng)目管理目標(biāo)
項(xiàng)目管理目標(biāo)名稱目標(biāo)值
工期2023年4月20日至2023年3月10日,共計(jì)325天
項(xiàng)目四川省結(jié)構(gòu)優(yōu)質(zhì)工程獎(jiǎng)。
質(zhì)量目標(biāo)
臨水工程目標(biāo):合格。
安全文明目標(biāo)項(xiàng)目總體目標(biāo):安全生產(chǎn)文明施工標(biāo)準(zhǔn)化工地;
3
項(xiàng)目管理目標(biāo)名稱目標(biāo)值
臨水工程施工階段責(zé)任事故死亡率為零,臨時(shí)用水和大型機(jī)械事故為零;
綠色管理目標(biāo)節(jié)約水、電等資源消耗,節(jié)約資源,保護(hù)環(huán)境
科技管理目標(biāo)四川省建筑業(yè)新技術(shù)應(yīng)用示范工地
3.3各項(xiàng)資源安排
3.3.1勞務(wù)資源安排一覽表
表3.3.1勞務(wù)資源安排一覽表
專業(yè)施工資質(zhì)分包商選擇
施工項(xiàng)目名稱開始施工時(shí)間建設(shè)工期分包方式責(zé)任人
隊(duì)名稱要求方式
中旅成都高新新川項(xiàng)西安壹禾
2023年4月20包工及部分
目總承包一標(biāo)段工程建筑工程無325日歷天公司選定羅天皓
日材料
臨時(shí)用水工程有限公司
3.3.2工程用大宗物資供應(yīng)安排一覽表
表3.3.2工程用大宗物資供應(yīng)安排一覽表
物資名稱采購(gòu)單位擬選供應(yīng)商采購(gòu)地點(diǎn)要求進(jìn)場(chǎng)時(shí)間責(zé)任人
鍍鋅鋼管中建八局調(diào)撥四川2023年4月20日蒲焱全
PE管中建八局電商/2023年4月20日蒲焱全
波紋管中建八局電商/2023年4月20日蒲焱全
PVC管中建八局電商/2023年4月20日蒲焱全
3.4施工流水段的劃分及施工工藝流程
3.4.1施工區(qū)域的劃分
臨水隨著臨建施工進(jìn)行布置,根據(jù)總圖施工部署:按照先主管、后支管進(jìn)行施工布置,
投入1家臨水勞務(wù)施工隊(duì)伍,根據(jù)土建施工進(jìn)度進(jìn)行布置,未進(jìn)行豎向分區(qū)。
現(xiàn)場(chǎng)施工區(qū)域劃分如下:A施工區(qū)、B施工區(qū)。施工區(qū)的劃分如下圖3.4.1。
4
圖3.4.1施工區(qū)域劃分圖
3.4.2施工工藝流程
定位放線→預(yù)埋預(yù)留→支架安裝→給水、消防管道制作→管道安裝→管道試壓→管道
清洗→系統(tǒng)驗(yàn)收
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施
表3.5重難點(diǎn)分析及應(yīng)對(duì)措施
序號(hào)重點(diǎn)和難點(diǎn)具體分析應(yīng)對(duì)措施責(zé)任人
下雨天多,工期保障臨水施工正值春夏交替之際,雨根據(jù)天氣預(yù)報(bào),合理規(guī)劃施工時(shí)
1鄒星乾
是重難點(diǎn)水天氣較多,雨天影響施工間,避免雨天施工。
地下室開挖距圍墻,施工道路距重復(fù)確認(rèn)放線精度,管溝開挖時(shí)
場(chǎng)地局限,施工難度
2主體距離較小,施工難度較大,專人看守確保周邊設(shè)施不被破鄒星乾
較大
管道敷設(shè)精度要求較高。壞。
5
4臨水施工進(jìn)度計(jì)劃
4.1臨時(shí)用水及消防系統(tǒng)
本工程臨水用水施工計(jì)劃于2023年4月20日開始施工,于2023年3月10日施工結(jié)
束,總工期325日歷天。
4.1.1基礎(chǔ)及地下結(jié)構(gòu)施工階段臨時(shí)用水及消防系統(tǒng)
本工程基坑周邊臨時(shí)用水及消防主干管施工計(jì)劃于2023年4月20日開始施工,于2023
年4月30日,施工完成。
4.1.2各樓層施工用水及消防給水系統(tǒng)
正負(fù)零結(jié)構(gòu)施工完成,土建回填完成后,場(chǎng)內(nèi)室外消防系統(tǒng)在臨建道路施工前施工完
成,樓層上用水根隨土建結(jié)構(gòu)施工進(jìn)度,于2023年3月10日施工結(jié)束,確保每層施工及
消防用水到位。
6
5施工準(zhǔn)備與資源配置計(jì)劃
5.1施工準(zhǔn)備計(jì)劃
5.1.1組織準(zhǔn)備
項(xiàng)目在臨水施工之前成立臨水施工領(lǐng)導(dǎo)小組,架構(gòu)詳見3.1.1管理組織機(jī)構(gòu)。
5.1.2技術(shù)準(zhǔn)備
1方案、技術(shù)交底
臨水施工前,項(xiàng)目部由項(xiàng)目總工負(fù)責(zé)編制臨水施工方案,并按流程上報(bào)公司、監(jiān)理單
位審批,審批后進(jìn)行方案交底,交底人員面向項(xiàng)目部全體管理人員。
根據(jù)臨水施工特點(diǎn),項(xiàng)目部在施工前提前編制技術(shù)、安全交底,對(duì)所有在施人員進(jìn)行
交底。
2教育培訓(xùn)
3關(guān)注天氣
表5.1.2技術(shù)文件準(zhǔn)備計(jì)劃一覽表
序號(hào)文件名稱文件編號(hào)配備數(shù)量
1《建設(shè)工程施工現(xiàn)場(chǎng)消防安全技術(shù)規(guī)范》GB50720-20112
2《消防給水及消火栓系統(tǒng)技術(shù)規(guī)范》GB50974-20142
3《給水排水管道工程施工及驗(yàn)收規(guī)范》GB50268-20082
4《建筑給水排水及供暖工程施工技術(shù)標(biāo)準(zhǔn)》ZJQ08-SGJB242-20172
5《建筑給水排水設(shè)計(jì)標(biāo)準(zhǔn)》GB50015-20232
6《建筑給水排水工程規(guī)范》ZBBZH/GJ152
7《建筑給水排水及采暖工程施工質(zhì)量驗(yàn)收規(guī)范》GB50242-20022
5.1.3生產(chǎn)準(zhǔn)備
1對(duì)現(xiàn)場(chǎng)施工道路,在臨水期間定期檢查清掃,尤其是大雨過后,及時(shí)清掃防止路
面泥濘塌陷,保證順利通行;
2辦公區(qū)與生活區(qū)用水等都要考慮充分,滿足施工的需要;
3材料庫做好防潮、干燥工作;
4機(jī)械設(shè)備應(yīng)加強(qiáng)維修、保養(yǎng)工作,室外設(shè)備及時(shí)運(yùn)至室內(nèi),避免受潮;
5臨水結(jié)束前,認(rèn)真檢查消防器材,并進(jìn)行調(diào)試;臨時(shí)用水點(diǎn)使用結(jié)束后及時(shí)關(guān)閉
閥門;
6定時(shí)檢查生活區(qū),嚴(yán)禁使用違章電器,嚴(yán)禁私拉亂接,嚴(yán)禁使用明火作業(yè),要堅(jiān)
決杜絕火災(zāi)事故的發(fā)生;
7現(xiàn)場(chǎng)應(yīng)派專人檢查,未經(jīng)許可,不得隨便點(diǎn)火,用火實(shí)行動(dòng)火證申辦制度;
8氧氣瓶、乙炔瓶等也要采取專門措施,派專人看管,電氣焊應(yīng)專人施焊。
5.2資源配置計(jì)劃
表5.2-1勞動(dòng)力配置計(jì)劃
時(shí)間
序號(hào)專業(yè)工種責(zé)任人
2023年4月2023年5月
7
時(shí)間
序號(hào)專業(yè)工種責(zé)任人
1水電工66鄒星乾
2輔助工44鄒星乾
表5.2-2測(cè)量?jī)x器配置計(jì)劃
序號(hào)測(cè)量?jī)?nèi)容儀器、儀表
1大氣溫度測(cè)量自動(dòng)溫度測(cè)定儀、溫度計(jì)
2室內(nèi)外溫度測(cè)量普通溫度計(jì)和干濕溫度計(jì)
表5.2-3主要材料機(jī)具準(zhǔn)備計(jì)劃
序號(hào)名稱單位數(shù)量備注
1水泵臺(tái)2清水排污
2熱熔機(jī)臺(tái)2管道熱熔連接
3電焊機(jī)臺(tái)2支架等焊接
4套絲機(jī)臺(tái)1管道套絲
5干濕溫度計(jì)只2室內(nèi)外測(cè)溫
6臨時(shí)水管m400水泵配套,清水排污
8
6臨水主要施工方法
6.1總體概況
管理人員生活區(qū)設(shè)立1個(gè)臨時(shí)水泵房,泵房?jī)?nèi)掛水表并安裝水箱和穩(wěn)壓設(shè)備保證供水
水壓。
臨時(shí)消防用水與施工用水環(huán)網(wǎng)共用一根DN150主管,施工至主體階段,支管沿樓梯間
進(jìn)入各樓層,保證現(xiàn)場(chǎng)用水及消防用水。
臨時(shí)給水系統(tǒng),每個(gè)用水點(diǎn)設(shè)置一個(gè)DN20給水管并加裝閥門予以控制,各單體室內(nèi)
分層設(shè)置DN20給水閥門,所有分支處均設(shè)置閥門,使區(qū)域范圍用水得到控制,分別供給成
品組裝廁所、自動(dòng)洗車池、標(biāo)養(yǎng)室等生活/生產(chǎn)用水。在塔吊處預(yù)留DN32給水點(diǎn)用于塔吊
霧化噴灑。
圖6.1臨水施工平面布置
6.2臨水施工內(nèi)容
本工程主要用水點(diǎn)為混凝土養(yǎng)護(hù)過程用水、消防用水、沖刷用水、清潔用水、各種加
工用水、生活用水。
室外消防給水系統(tǒng):沿圍墻和道路從臨時(shí)泵房分別布置一根DN150鍍鋅鋼管作為消防
9
用水主管和一根DN100鍍鋅鋼管作為施工用水主管,形成環(huán)狀管網(wǎng)。在施工現(xiàn)場(chǎng)道路旁間
隔不大于60米設(shè)置室外臨時(shí)消火栓。
樓層臨時(shí)消防主管采用DN100鍍鋅鋼管(溝槽連接),高層給水立管采用DN50鍍鋅鋼
管(螺紋連接)。
6.3水量計(jì)算
1施工用水計(jì)算
計(jì)算公式:
q1=K1ΣQ1.N1×K2/(8×3600)
q1——施工用水量(L/S)
K1——未預(yù)計(jì)的施工用水系數(shù)(1.05—1.15),取1.1
Q1——按計(jì)劃每班澆筑高峰混凝土量為400m3
N1——施工用水定額取混凝土350L/m3
K2——用水不均衡系數(shù)取1.5
由于工程結(jié)構(gòu)施工階段相對(duì)于裝修階段施工用水量大,故Q1主要以混凝土工程量為
計(jì)算依據(jù)。
工程用水計(jì)算
q1=K1ΣQ1.N1×K2/(16×3600)
=1.1×(400×350)×1.5/(8×3600)
=8.02L/S
2施工現(xiàn)場(chǎng)生活用水
計(jì)算公式:
q2=(P1N2K3)/(t×8×3600)
其中:q2——施工現(xiàn)場(chǎng)生活用水量(L/S)
P1——施工現(xiàn)場(chǎng)高峰晝夜人數(shù)(擬定800人);
N2——施工現(xiàn)場(chǎng)生活用水定額(40L/人.班)
t——每天工作班數(shù)(班),取1.0班
k3——用水不均衡系數(shù)(1.30—1.50),取1.4
施工現(xiàn)場(chǎng)生活用水計(jì)算
q2=(P1N2K3)/(t×8×3600)
=(800×40×1.4)/(1.0×8×3600)
=1.56L/S
3施工現(xiàn)場(chǎng)機(jī)械用水
施工機(jī)械用水量,因無特殊用水機(jī)械,故從略不計(jì)。
4總用水量計(jì)算
假設(shè)工地同時(shí)發(fā)生火災(zāi)的次數(shù)為一次,則消防用水的定額為15—20L/S,取q4=20L/S
(q4——消防用水施工定額)
10
施工用水Q1=q1+q2=8.02+1.56=9.58L/S
消防用水Q2=q4=20L/S
5干管管徑計(jì)算
計(jì)算公式
4Q
D=1000V
其中:D——水管管徑(m).
Q——耗水量(l/s).
V——管網(wǎng)中水流速度(m/s),取V=1.5m/s.
(1)消防主干管管徑計(jì)算
4Q
D=1000V=√4*20/(1000*3.14*1.5)=0.1303m
(2)生產(chǎn)用水主干管管徑計(jì)算
4Q
D=1000V=√4*9.58/(1000*3.14*1.5)=0.902m
6給水主干管確定
因此,消防供水主管管徑確定為150mm,生產(chǎn)供水主管管徑確定為100mm,以滿足消
防及生產(chǎn)用水使用。
6.4設(shè)備選擇
1水泵揚(yáng)程計(jì)算
計(jì)算公式:H=H1+H2+H3
H——為水泵總揚(yáng)程
H1——為水泵送水到最不利點(diǎn)的高差(m),為80m
H2——為管路水頭損失(m),H2=iL=0.00107v2/d1.3*800=49.34m(L管道長(zhǎng)度,本工
程取800米,i為單位管長(zhǎng)水頭損失,v流速取1.7m/s,d管徑)
H3
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 二零二五年度KTV員工福利與薪酬體系合同3篇
- 《熱電池用FeS2復(fù)合薄膜正極的制備研究》
- 《共享出行對(duì)城市交通擁堵的緩解作用研究》
- 二零二五年度二手吊車租賃合同范本大全及分析2篇
- 《去勢(shì)大鼠BMSCs增殖分化功能與骨組織微結(jié)構(gòu)變化的相關(guān)研究》
- 2025版建筑公司技術(shù)員崗位培訓(xùn)與發(fā)展勞動(dòng)合同3篇
- 2025年度安防設(shè)備研發(fā)與市場(chǎng)推廣合同
- 2025版離婚后夫妻共同財(cái)產(chǎn)分割及子女撫養(yǎng)費(fèi)用支付調(diào)整協(xié)議3篇
- 2025版貸款中介服務(wù)合同范本(金融版)2篇
- 藥物相互作用探討-第1篇-洞察分析
- 2024-2025學(xué)年四年級(jí)科學(xué)上冊(cè)第三單元《運(yùn)動(dòng)和力》測(cè)試卷(教科版)
- 教育用地劃撥流程
- 制造業(yè)智能制造工廠布局方案
- 體外診斷試劑-C反應(yīng)蛋白(CRP)測(cè)定試劑盒(膠乳增強(qiáng)免疫比濁法)臨床評(píng)價(jià)報(bào)告-血清
- 八年級(jí)物理上冊(cè)(滬粵版2024)新教材解讀課件
- 人教版數(shù)學(xué)四上《大數(shù)的認(rèn)識(shí)》說課稿
- 氣胸講課課件
- 2024年典型事故案例警示教育手冊(cè)15例
- 《植物營(yíng)養(yǎng)學(xué)》課件
- 河南省鄭州市鄭東新區(qū)2023-2024學(xué)年五年級(jí)上學(xué)期期末語文試卷
- 貨源保障協(xié)議書
評(píng)論
0/150
提交評(píng)論