棗莊雙子星城市廣場(chǎng)A1樓、A2樓及地下車庫(kù)工程
外幕墻工程施工方案
編制單位:浙江中南建設(shè)集團(tuán)有限公司
日期:2023.5
目錄
第一章編制依據(jù)..........................................................................................................................................-1-
第二章工程概況..........................................................................................................................................-2-
2.1工程建設(shè)概況表................................................................................................................................................-2-
2.2設(shè)計(jì)概況............................................................................................................................................................-2-
2.3工程施工條件....................................................................................................................................................-4-
第三章施工安排..........................................................................................................................................-4-
3.1項(xiàng)目管理組織....................................................................................................................................................-5-
3.2項(xiàng)目管理目標(biāo)....................................................................................................................................................-7-
3.3各項(xiàng)資源供應(yīng)方式............................................................................................................................................-7-
3.3.1勞務(wù)資源安排一覽表...............................................................................................................................-7-
3.3.2工程用大宗物資供應(yīng)安排一覽表...........................................................................................................-8-
3.3.3大型機(jī)械設(shè)備采購(gòu)供應(yīng)安排一覽表.......................................................................................................-8-
3.4施工流水段的劃分及施工工藝流程................................................................................................................-9-
3.4.1施工流水段的劃分...................................................................................................................................-9-
3.4.2施工工藝流程.........................................................................................................................................-11-
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施..........................................................................................................-11-
3.5.1組織管理重點(diǎn)分析及應(yīng)對(duì)措施.............................................................................................................-11-
3.5.2施工難點(diǎn)分析及應(yīng)對(duì)措施.....................................................................................................................-12-
第四章施工進(jìn)度計(jì)劃.................................................................................................................................-13-
第五章施工準(zhǔn)備與資源配置計(jì)劃..............................................................................................................-18-
5.1施工準(zhǔn)備計(jì)劃..................................................................................................................................................-18-
5.1.1技術(shù)準(zhǔn)備.................................................................................................................................................-18-
5.1.2現(xiàn)場(chǎng)準(zhǔn)備.................................................................................................................................................-21-
5.2資源配置計(jì)劃..................................................................................................................................................-21-
5.2.1勞動(dòng)力配置計(jì)劃.....................................................................................................................................-21-
5.2.2工程用原材料需要量計(jì)劃.....................................................................................................................-22-
5.2.3工程用成品、半成品需要量計(jì)劃.........................................................................................................-22-
5.2.4生產(chǎn)工藝設(shè)備需要量計(jì)劃.....................................................................................................................-22-
第六章施工方法及工藝要求........................................................................................................................-23-
6.1總施工思路......................................................................................................................................................-23-
6.1.1施工順序:.............................................................................................................................................-23-
6.1.2施工方法:.............................................................................................................................................-24-
6.1.3水平運(yùn)輸及垂直運(yùn)輸:.........................................................................................................................-24-
6.2玻璃幕墻部分施工技術(shù)..................................................................................................................................-24-
6.2.1施工準(zhǔn)備.................................................................................................................................................-24-
6.2.2施工措施.................................................................................................................................................-25-
6.2.3工藝流程.................................................................................................................................................-25-
6.2.4技術(shù)參數(shù).................................................................................................................................................-26-
6.2.5施工流程.................................................................................................................................................-27-
6.3鋁板幕墻施工技術(shù)..........................................................................................................................................-35-
6.3.1施工準(zhǔn)備.................................................................................................................................................-35-
6.3.2技術(shù)參數(shù).................................................................................................................................................-35-
6.3.3工藝流程.................................................................................................................................................-36-
6.3.4技術(shù)措施.................................................................................................................................................-37-
6.3.5施工流程.................................................................................................................................................-38-
6.4石材幕墻施工施工技術(shù)..................................................................................................................................-40-
6.4.1施工準(zhǔn)備.................................................................................................................................................-40-
6.4.2技術(shù)參數(shù).................................................................................................................................................-40-
6.4.3工藝流程.................................................................................................................................................-40-
6.4.4施工流程.................................................................................................................................................-41-
6.5驗(yàn)收標(biāo)準(zhǔn).........................................................................................................................................................-43-
6.6驗(yàn)收程序...........................................................................................................................................................-44-
6.7驗(yàn)收內(nèi)容...........................................................................................................................................................-45-
第七章進(jìn)度管理計(jì)劃.................................................................................................................................-50-
7.1確定施工進(jìn)度控制點(diǎn)......................................................................................................................................-50-
7.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工..............................................................................................................-50-
7.3進(jìn)度管理措施..................................................................................................................................................-51-
第八章質(zhì)量管理計(jì)劃.................................................................................................................................-53-
8.1質(zhì)量控制目標(biāo)分解..........................................................................................................................................-53-
8.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工..................................................................................................................-53-
8.3確定質(zhì)量控制點(diǎn)..............................................................................................................................................-54-
8.4質(zhì)量保證措施..................................................................................................................................................-55-
第九章安全管理計(jì)劃.................................................................................................................................-57-
9.1職業(yè)健康安全管理分解目標(biāo)..........................................................................................................................-57-
9.2安全管理組織機(jī)構(gòu)和職責(zé)分工......................................................................................................................-58-
職責(zé)分工..................................................................................................................................................................-58-
9.3職業(yè)健康安全重大危險(xiǎn)源..............................................................................................................................-59-
9.4職業(yè)健康安全資源配置計(jì)劃..........................................................................................................................-60-
9.5安全生產(chǎn)管理制度..........................................................................................................................................-60-
9.6安全生產(chǎn)保證措施..........................................................................................................................................-61-
第十章環(huán)境管理計(jì)劃.................................................................................................................................-66-
10.1環(huán)境管理目標(biāo)................................................................................................................................................-66-
10.2環(huán)境管理組織機(jī)構(gòu)和職責(zé)分工....................................................................................................................-67-
10.3重大環(huán)境因素清單........................................................................................................................................-67-
10.4環(huán)境保護(hù)資源配置計(jì)劃................................................................................................................................-68-
10.5環(huán)境保護(hù)措施................................................................................................................................................-68-
第十一章綠色施工管理計(jì)劃......................................................................................................................-69-
11.1綠色施工組織機(jī)構(gòu)和職責(zé)分工....................................................................................................................-69-
11.2綠色施工實(shí)施措施........................................................................................................................................-69-
11.3綠色施工評(píng)價(jià)................................................................................................................................................-69-
第十二章成品保護(hù)管理計(jì)劃........................................................................................................................-69-
12.1成品保護(hù)管理組織和職責(zé)分工....................................................................................................................-70-
12.2成品保護(hù)計(jì)劃及保證措施............................................................................................................................-70-
第十三章應(yīng)急預(yù)案.....................................................................................................................................-72-
13.1事故類型和危害程度分析............................................................................................................................-72-
13.2組織機(jī)構(gòu)及職責(zé)分工....................................................................................................................................-72-
13.2.1應(yīng)急組織機(jī)構(gòu).......................................................................................................................................-72-
13.2.2應(yīng)急小組職責(zé)分工...............................................................................................................................-72-
13.3預(yù)防與預(yù)警....................................................................................................................................................-73-
13.3.1危險(xiǎn)源監(jiān)控...........................................................................................................................................-73-
13.3.2事故的應(yīng)急準(zhǔn)備...................................................................................................................................-74-
13.4緊急情況發(fā)生和上報(bào)程序.....................................................................................................................-75-
13.5應(yīng)急處置........................................................................................................................................................-75-
13.5.1相應(yīng)分級(jí)...............................................................................................................................................-75-
13.5.2響應(yīng)程序...............................................................................................................................................-75-
13.5.3處置措施...............................................................................................................................................-76-
第十三章疫情管控.......................................................................................................................................-76-
13.1編制依據(jù)..................................................................................................................................................-76-
13.2施工部署..................................................................................................................................................-77-
13.3職責(zé)分工..................................................................................................................................................-77-
13.4防疫物資供應(yīng)安排一覽表......................................................................................................................-78-
13.5主要保證措施..........................................................................................................................................-78-
13.6應(yīng)急救援..................................................................................................................................................-81-
第十四章硬質(zhì)隔離層搭設(shè)方案....................................................................................................................-82-
第十五章防護(hù)棚穩(wěn)定性計(jì)算書(shū)....................................................................................................................-87-
第一章編制依據(jù)
序號(hào)類別文件名稱編號(hào)
1《中華人民共和國(guó)建筑法》國(guó)家主席令第29號(hào)
2《中華人民共和國(guó)安全生產(chǎn)法》國(guó)家主席令第十三號(hào)
國(guó)家行政
3《建設(shè)工程質(zhì)量管理?xiàng)l例》國(guó)務(wù)院令第687號(hào)
文件
4《建設(shè)工程安全生產(chǎn)管理?xiàng)l例》國(guó)務(wù)院令第393號(hào)
5《安全生產(chǎn)許可證條例》國(guó)務(wù)院令第653號(hào)
6建筑節(jié)能工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)GB50411-2023
7玻璃幕墻工程技術(shù)規(guī)范JGJ102-2003
8建筑玻璃應(yīng)用技術(shù)規(guī)程JGJ113-2015
9建筑玻璃點(diǎn)支承裝置JG/T138-2010
10玻璃幕墻工程質(zhì)量檢驗(yàn)標(biāo)準(zhǔn)JGJ/T139-2001
11建筑幕墻氣密、水密、抗風(fēng)壓性能檢測(cè)方法GB/T15227-2007
12建筑幕墻抗震性能振動(dòng)臺(tái)試驗(yàn)方法GB/T18575-2017
13建筑用玻璃與金屬護(hù)欄JG/T342-2012
GB50016-2014(2018
14建筑設(shè)計(jì)防火規(guī)范(2018年版)
國(guó)家標(biāo)準(zhǔn)年版)
15及行業(yè)規(guī)建筑抗震設(shè)計(jì)規(guī)范(2016年版)GB50011-2010
范
16建筑物防雷設(shè)計(jì)規(guī)范GB50057-2010
17工業(yè)建筑防腐蝕設(shè)計(jì)標(biāo)準(zhǔn)GB/T50046-2018
18建筑施工高處作業(yè)安全技術(shù)規(guī)范JGJ80-2016
19混凝土結(jié)構(gòu)后錨固技術(shù)規(guī)程JGJ145-2013
20金屬與石材幕墻工程技術(shù)規(guī)范JGJ133-2001
21工程測(cè)量規(guī)范(附條文說(shuō)明)GB50026-2007
22施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范JGJ46-2005
23建筑施工工具式腳手架安全技術(shù)規(guī)范JGJ202-2010
24建設(shè)工程施工現(xiàn)場(chǎng)環(huán)境與衛(wèi)生標(biāo)準(zhǔn)JGJ146-2013
-1-
25高處作業(yè)吊籃GB19155-2017
26建筑機(jī)械使用安全技術(shù)規(guī)程JGJ33-2012
27建筑工程資料管理規(guī)程JGJ/T185-2009
28鋼結(jié)構(gòu)焊接規(guī)范GB50661-2011
29工業(yè)建筑防腐蝕設(shè)計(jì)標(biāo)準(zhǔn)GB/T50046-2018
地方行政山東省人民政府令第
30山東省建筑安全生產(chǎn)管理規(guī)定
文件311號(hào)
31其他《ZLP系列高處作業(yè)吊籃使用說(shuō)明書(shū)》/
棗莊雙子星城市廣場(chǎng)A1#、A2#及裙樓外幕墻工
32設(shè)計(jì)文件/
程圖紙
第二章工程概況
2.1工程建設(shè)概況表
工程名稱棗莊雙子星城市廣場(chǎng)A1樓、A2樓及裙房外幕墻工程總承包
建筑功能辦公及酒店
建設(shè)規(guī)模幕墻總面積約104030㎡
建筑高度258.7米
建設(shè)單位棗莊市金成置業(yè)有限公司
設(shè)計(jì)單位福建省建筑設(shè)計(jì)研究院
建立單位棗莊市工程建設(shè)監(jiān)理有限公司
總承包單位中建八局第一建設(shè)有限公司
施工單位浙江中南建設(shè)集團(tuán)有限公司
2.2設(shè)計(jì)概況
建筑面積419775㎡幕墻面積104030㎡建筑高度258.7m
層地上標(biāo)準(zhǔn)首層
40層4.1m6m防火等級(jí)一級(jí)
數(shù)層數(shù)層高標(biāo)高
主主樓明龍骨:豎向140系列明框鋁合金立柱,橫向70系列隱框鋁合金橫梁。
要框框架面材:15(雙銀、超白、Low-E)+15A+15中空雙鋼化玻璃,12(雙銀、
幕式大裝超白、Low-E)+12A+12中空雙鋼化玻璃,10(雙銀、超白、Low-E)+12A+10
墻飾線條中空雙鋼化玻璃,8(雙銀、超白、Low-E)+12A+8中空雙鋼化玻璃,6
系玻璃幕(雙銀、超白、Low-E)+12A+6中空雙鋼化玻璃,6+1.14PVB+6(雙銀、
統(tǒng)墻系統(tǒng)Low-E)+12A+6中空鋼化玻璃,外片雙半鋼化,6+1.14PVB+6(雙銀、
Low-E)+12A+8中空鋼化玻璃,外片雙半鋼化,10+1.52PVB+10(雙銀、
Low-E)+12A+12中空鋼化玻璃,外片雙半鋼化,具體后見(jiàn)玻璃規(guī)格選用
表。非透明部分采用6+1.14PVB+6(雙銀、Low-E)+12A+6,6(雙銀、
超白、Low-E)+12A+6中空鋼化玻璃,具體后見(jiàn)玻璃規(guī)格選用表。內(nèi)襯
2mm厚鋁單板(不得采用深灰色噴涂);
-2-
龍骨:采用口80X60x5鋼方通(熱鍍鋅);橫向L50X4熱鍍鋅角鋼。面
鋁板幕
材:3mm厚鋁單板(氟碳噴涂),屋頂采用3mm厚鋁單板(氟碳噴涂),兼
墻系統(tǒng)
做防雷需求與主體電氣防雷裝置相連。
立面圖
-3-
平面圖
標(biāo)準(zhǔn)層平面圖
2.3工程施工條件
建設(shè)氣極端最高溫度及期42.5℃、8
最大雨量及雨季時(shí)間581mm/年、7-8月
地點(diǎn)溫限月
-4-
氣象
極端最低溫度及期8-9級(jí)、北風(fēng)、7-9
狀況-11℃、1月最大風(fēng)力、風(fēng)向及發(fā)生時(shí)間
限月
總包單位根據(jù)分包各單位提供的二級(jí)箱數(shù)量統(tǒng)一配備,項(xiàng)
電力供應(yīng)情況目部根據(jù)最大用電量統(tǒng)一配備三級(jí)箱,以滿足幕墻施工要
求
施工周圍道路市區(qū)內(nèi),運(yùn)輸方便
區(qū)域
環(huán)境材料堆放材料堆放場(chǎng)地由總包統(tǒng)一協(xié)調(diào)
根據(jù)根據(jù)建辦質(zhì)〔2018〕31號(hào)文超過(guò)一定規(guī)模的危險(xiǎn)性較大的分部分項(xiàng)工
程范圍規(guī)定包括:施工高度50m及以上的建筑幕墻安裝工程。本工程需要專家論
證。
第三章施工安排
3.1項(xiàng)目管理組織
項(xiàng)目管理人員及職責(zé)分工
序號(hào)管理職務(wù)姓名職稱(資質(zhì))職責(zé)和權(quán)限
一級(jí)建造師明確項(xiàng)目的各項(xiàng)管理目標(biāo)并分解落實(shí);監(jiān)督檢查
1項(xiàng)目經(jīng)理黃秀峰
高級(jí)工程師項(xiàng)目管理人員履行其職責(zé);組織項(xiàng)目管理和產(chǎn)品
-5-
實(shí)現(xiàn)過(guò)程的策劃,編制項(xiàng)目管理策劃書(shū)、施工組
織設(shè)計(jì)等管理文件;組織進(jìn)行機(jī)械設(shè)備、材料、
周轉(zhuǎn)工具、勞務(wù)人員等資源的配置;做好與業(yè)主、
監(jiān)理等的協(xié)調(diào)與溝通工作;做好分包的協(xié)調(diào)與管
理工作;組織做好項(xiàng)目資金、成本、預(yù)結(jié)算的管
理。
負(fù)責(zé)圖紙審核、設(shè)計(jì)變更、圖紙的深化等工作;
參加編制施工組織設(shè)計(jì)、項(xiàng)目管理策劃文件的編
制,組織施工方案的編制,審核技術(shù)交底;組織
現(xiàn)場(chǎng)的技術(shù)復(fù)核、分部分項(xiàng)工程的驗(yàn)收工作;主
持項(xiàng)目的質(zhì)量管理、施工試驗(yàn)、計(jì)量管理工作。
總體施工進(jìn)度計(jì)劃的安排;施工現(xiàn)場(chǎng)平面管理;
組織協(xié)調(diào)各勞務(wù)分包的現(xiàn)場(chǎng)管理;負(fù)責(zé)施工過(guò)程
二級(jí)建造師
2技術(shù)負(fù)責(zé)人張春勃控制,對(duì)施工過(guò)程中的質(zhì)量、安全、文明施工等
中級(jí)工程師
負(fù)責(zé)負(fù)責(zé)主要機(jī)械設(shè)備、周轉(zhuǎn)工具、勞務(wù)人員的
計(jì)劃與調(diào)配;負(fù)責(zé)制定總進(jìn)度計(jì)劃;積極推廣新
技術(shù)、新工藝,開(kāi)展創(chuàng)優(yōu)活動(dòng)、降低施工成本,
督促、指導(dǎo)項(xiàng)目貫標(biāo)工作的正常進(jìn)行;負(fù)責(zé)審核
項(xiàng)目各種專項(xiàng)技術(shù)方案、技術(shù)變更的上報(bào)并跟蹤
取回業(yè)主、監(jiān)理的審批回文,并追蹤、監(jiān)督及方
案的落實(shí)工作;
負(fù)責(zé)工程質(zhì)量的現(xiàn)場(chǎng)監(jiān)督檢查和分部分項(xiàng)工程
的質(zhì)量驗(yàn)收;負(fù)責(zé)一般不合格品的處置,發(fā)現(xiàn)嚴(yán)
質(zhì)量員
3質(zhì)量負(fù)責(zé)人王建平重不合格品及時(shí)報(bào)告項(xiàng)目總工,并負(fù)責(zé)處置后的
中級(jí)工程師
質(zhì)量驗(yàn)收與評(píng)定;對(duì)各分包和專業(yè)施工班組提出
質(zhì)量獎(jiǎng)罰;質(zhì)量驗(yàn)收文件的記錄與整理。
參與項(xiàng)目危險(xiǎn)源辨識(shí)、風(fēng)險(xiǎn)評(píng)價(jià)與控制策劃,參
與環(huán)境因素的識(shí)別與評(píng)價(jià)。參與項(xiàng)目職業(yè)健康安
全與環(huán)境管理規(guī)劃、管理方案及技術(shù)措施方案的
制定,落實(shí)相關(guān)責(zé)任。
巡回進(jìn)行職業(yè)健康安全/環(huán)境管理檢查,對(duì)關(guān)鍵
特性參數(shù)定期進(jìn)行監(jiān)測(cè),發(fā)現(xiàn)問(wèn)題下達(dá)整改通知
4安全負(fù)責(zé)人任全策安全員、C證
單,并對(duì)整改情況進(jìn)行驗(yàn)證。負(fù)責(zé)職業(yè)健康安全
/環(huán)境應(yīng)急準(zhǔn)備檢查,按應(yīng)急預(yù)案進(jìn)行響應(yīng):1)
負(fù)責(zé)項(xiàng)目安全生產(chǎn)、文明施工和環(huán)境保護(hù)工作;
2)負(fù)責(zé)編制項(xiàng)目職業(yè)健康安全管理計(jì)劃、環(huán)境
管理計(jì)劃和管理制度并監(jiān)督實(shí)施,制定員工安全
培訓(xùn)計(jì)劃,并負(fù)責(zé)組織實(shí)施;3)負(fù)責(zé)每周的全
-6-
員安全生產(chǎn)例會(huì),定期和不定期組織安全生產(chǎn)和
文明施工的檢查,加強(qiáng)安全監(jiān)督管理、消除施工
現(xiàn)場(chǎng)安全隱患;4)負(fù)責(zé)安全目標(biāo)的分解落實(shí)和
安全生產(chǎn)責(zé)任制的考核評(píng)比,5)負(fù)責(zé)項(xiàng)目安全
應(yīng)急預(yù)案編制,進(jìn)行安全應(yīng)急演練,保證項(xiàng)目施
工生產(chǎn)正常進(jìn)行;6)負(fù)責(zé)對(duì)各專業(yè)分包單位的
安全監(jiān)督和管理工作,監(jiān)督專業(yè)分包單位作好安
全防護(hù)工作,消除施工過(guò)程中的安全隱患,確保
安全生產(chǎn)。
1)負(fù)責(zé)具體的施工組織、各級(jí)計(jì)劃安排的執(zhí)行;
2)對(duì)施工企業(yè)形象規(guī)劃、臨時(shí)水電、平面布置
等進(jìn)行管理;3)負(fù)責(zé)每月的工程量統(tǒng)計(jì)報(bào)表上
報(bào),記錄總承包施工日記,定期制作總承包周工
作報(bào)告、總承包月工作報(bào)告;4)對(duì)內(nèi)外各種關(guān)
系、各專業(yè)分包等進(jìn)行統(tǒng)一協(xié)調(diào)、管理;5)負(fù)
責(zé)項(xiàng)目各種進(jìn)度計(jì)劃的上報(bào)并跟蹤取回雇主的
審批回文,并追蹤、監(jiān)督進(jìn)度計(jì)劃的落實(shí)工作。
施工員證書(shū)
5生產(chǎn)經(jīng)理李悅6)負(fù)責(zé)總進(jìn)度計(jì)劃的執(zhí)行,及時(shí)協(xié)調(diào)解決各分
中級(jí)工程師
包管理層、職能部門、施工隊(duì)、專業(yè)分包之間出
現(xiàn)的問(wèn)題矛盾;7)負(fù)責(zé)審核各專業(yè)分包單位的
施工進(jìn)度計(jì)劃,對(duì)各專業(yè)分包單位的進(jìn)度計(jì)劃的
實(shí)施過(guò)程進(jìn)行監(jiān)控,根據(jù)反饋信息發(fā)現(xiàn)問(wèn)題;8)
負(fù)責(zé)提請(qǐng)和安排項(xiàng)目的內(nèi)部生產(chǎn)協(xié)調(diào)例會(huì),協(xié)調(diào)
各專業(yè)分包單位之間的施工問(wèn)題,建立合理完善
的施工秩序;9)負(fù)責(zé)對(duì)各個(gè)專業(yè)分包單位的后
勤管理與協(xié)調(diào)。
1)負(fù)責(zé)項(xiàng)目物資設(shè)備的采購(gòu)和供應(yīng)工作,負(fù)責(zé)
與公司總部后方采購(gòu)供應(yīng)支持的協(xié)調(diào)聯(lián)系工作;
2)負(fù)責(zé)要求各專業(yè)分包單位及時(shí)報(bào)送材料采購(gòu)
7材料工程師張鵬材料員證
計(jì)劃、材料報(bào)審資料,及時(shí)采購(gòu)和進(jìn)場(chǎng)工程所需
的各種材料,并對(duì)材料進(jìn)行檢驗(yàn),保證質(zhì)量;3)
負(fù)責(zé)工程材料采購(gòu)、供應(yīng)管理工作;
3.2項(xiàng)目管理目標(biāo)
項(xiàng)目管理目標(biāo)名稱目標(biāo)值
工期開(kāi)工日期20,竣工日期2023.12.31
工程質(zhì)量達(dá)到合格標(biāo)準(zhǔn),配合甲方品質(zhì)測(cè)評(píng)達(dá)到合
質(zhì)量目標(biāo)
格標(biāo)準(zhǔn),一次性經(jīng)過(guò)政府主管部門竣工驗(yàn)收;
安全目標(biāo)1)保施工期間不出現(xiàn)任何安全事故;
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 全新網(wǎng)絡(luò)游戲開(kāi)發(fā)合同2篇
- 2024-2025學(xué)年新教材高中歷史第八單元20世紀(jì)下半葉世界的新變化第19課資本主義國(guó)家的新變化課時(shí)作業(yè)含解析新人教版必修中外歷史綱要下
- 2025不動(dòng)產(chǎn)登記信息化改造項(xiàng)目合同3篇
- 2025年微信小程序企業(yè)客戶關(guān)系管理系統(tǒng)開(kāi)發(fā)與應(yīng)用合同3篇
- 2024銷售人員職業(yè)發(fā)展保障勞動(dòng)合同3篇
- 二零二五年度醫(yī)療設(shè)施臨時(shí)借款合同參考樣本4篇
- 2025高溫粘合劑產(chǎn)業(yè)鏈金融服務(wù)平臺(tái)合作合同3篇
- 2025年度電信設(shè)備知識(shí)產(chǎn)權(quán)保護(hù)合同3篇
- 2025年度食品行業(yè)退換貨質(zhì)量保證協(xié)議書(shū)
- 二零二五年度高層建筑樓頂廣告位使用權(quán)租賃合同3篇
- 臺(tái)資企業(yè)A股上市相關(guān)資料
- 電 梯 工 程 預(yù) 算 書(shū)
- 羅盤超高清圖
- 參會(huì)嘉賓簽到表
- 機(jī)械車間員工績(jī)效考核表
- 形式發(fā)票格式2 INVOICE
- 2.48低危胸痛患者后繼治療評(píng)估流程圖
- 人力資源管理之績(jī)效考核 一、什么是績(jī)效 所謂績(jī)效簡(jiǎn)單的講就是對(duì)
- 山東省醫(yī)院目錄
- 云南地方本科高校部分基礎(chǔ)研究
- 廢品管理流程圖
評(píng)論
0/150
提交評(píng)論