項(xiàng)目專項(xiàng)施工方案
改造項(xiàng)目吳家山街老舊小區(qū)改造設(shè)計(jì)采購施工總
承包(EPC)工程
落地式腳手架施工方案
編制人:
日期:2023年7月
項(xiàng)目專項(xiàng)施工方案
目錄
第一章編制依據(jù)..........................................................................................................................................-1-
第二章工程概況..........................................................................................................................................-1-
2.1工程建設(shè)概況..............................................................................................................................................-1-
2.2建筑設(shè)計(jì)概況..............................................................................................................................................-3-
2.3外架搭設(shè)概況..............................................................................................................................................-5-
第三章施工安排..........................................................................................................................................-5-
3.1項(xiàng)目組織架構(gòu)................................................................................................................................................-5-
3.2項(xiàng)目管理人員及職責(zé)分工............................................................................................................................-5-
3.3施工流水段劃分............................................................................................................................................-6-
3.4施工重難點(diǎn)分析及應(yīng)對措施......................................................................................................................-7-
第四章施工進(jìn)度計(jì)劃...................................................................................................................................-8-
第五章施工準(zhǔn)備與資源配置計(jì)劃................................................................................................................-8-
5.1施工準(zhǔn)備計(jì)劃................................................................................................................................................-8-
5.1.1技術(shù)準(zhǔn)備...............................................................................................................................................-8-
5.1.2現(xiàn)場準(zhǔn)備...............................................................................................................................................-9-
5.1.3材料選型...............................................................................................................................................-9-
5.2資源配置計(jì)劃............................................................................................................................................-10-
5.2.1勞動力配置.........................................................................................................................................-10-
5.2.2主要周轉(zhuǎn)材料配置計(jì)劃.....................................................................................................................-10-
5.2.3工程施工機(jī)具配置計(jì)劃.....................................................................................................................-10-
5.2.4測量計(jì)量儀器配置計(jì)劃.....................................................................................................................-11-
第六章施工方法及工藝要求......................................................................................................................-11-
6.1方案及技術(shù)參數(shù)........................................................................................................................................-11-
6.2施工工藝流程............................................................................................................................................-12-
6.3施工控制要點(diǎn)............................................................................................................................................-12-
6.3.1定距定位...........................................................................................................................................-12-
6.3.2立桿.....................................................................................................................................................-12-
6.3.3縱向水平桿.......................................................................................................................................-13-
6.3.4橫向水平桿.......................................................................................................................................-14-
6.3.5剪刀撐、橫向斜撐設(shè)置...................................................................................................................-15-
6.3.6連墻件的設(shè)置...................................................................................................................................-16-
6.3.7開口架處理.......................................................................................................................................-17-
項(xiàng)目專項(xiàng)施工方案
6.3.8鋼笆片的鋪設(shè)...................................................................................................................................-17-
6.3.9立面、水平防護(hù)...............................................................................................................................-18-
6.3.10防電避雷措施.................................................................................................................................-18-
6.3.11外架拆除.........................................................................................................................................-18-
6.4現(xiàn)場特殊情況處理....................................................................................................................................-18-
6.5驗(yàn)收標(biāo)準(zhǔn)....................................................................................................................................................-24-
6.5.1驗(yàn)收標(biāo)準(zhǔn)...........................................................................................................................................-24-
6.5.2驗(yàn)收程序...........................................................................................................................................-25-
6.5.3驗(yàn)收人員...........................................................................................................................................-25-
6.6監(jiān)測監(jiān)控措施............................................................................................................................................-26-
第七章進(jìn)度管理計(jì)劃.................................................................................................................................-27-
7.1確定施工進(jìn)度控制點(diǎn)................................................................................................................................-27-
7.2進(jìn)度管理措施............................................................................................................................................-27-
第八章質(zhì)量管理計(jì)劃.................................................................................................................................-28-
8.1質(zhì)量控制目標(biāo)分解......................................................................................................................................-28-
8.2確定質(zhì)量控制點(diǎn)........................................................................................................................................-30-
8.3質(zhì)量保證措施............................................................................................................................................-31-
第九章安全管理計(jì)劃.................................................................................................................................-31-
9.1安全管理組織機(jī)構(gòu)及職責(zé)分工.................................................................................................................-31-
9.2職業(yè)健康安全重大危險(xiǎn)源........................................................................................................................-32-
9.3安全生產(chǎn)管理制度....................................................................................................................................-32-
9.4安全管理措施............................................................................................................................................-33-
9.5文明施工要求............................................................................................................................................-34-
第十章環(huán)境管理計(jì)劃.................................................................................................................................-35-
10.1環(huán)境管理目標(biāo)..........................................................................................................................................-35-
10.2環(huán)境管理組織機(jī)構(gòu)和職責(zé)分工...............................................................................................................-36-
第十一章應(yīng)急預(yù)案.....................................................................................................................................-37-
11.1可能造成重大危害的危險(xiǎn)源進(jìn)行分析...................................................................................................-37-
11.2事前預(yù)控..................................................................................................................................................-38-
11.2.1材料控制.........................................................................................................................................-38-
11.2.2崗前教育.........................................................................................................................................-38-
11.2.3應(yīng)急救援小組.................................................................................................................................-38-
11.2.4應(yīng)急救援措施.................................................................................................................................-39-
項(xiàng)目專項(xiàng)施工方案
11.2.5現(xiàn)場人員傷亡應(yīng)急處置措施.........................................................................................................-40-
11.2.6宣傳與培訓(xùn).....................................................................................................................................-42-
11.2.7應(yīng)急演練.........................................................................................................................................-43-
11.2.8記錄.................................................................................................................................................-43-
11.3應(yīng)急救援..................................................................................................................................................-43-
第十二章肺炎防治預(yù)案.............................................................................................................................-44-
12.1新型冠狀病毒肺炎相關(guān)知識..................................................................................................................-44-
12.1.1新型冠狀病毒.................................................................................................................................-44-
12.1.2傳播途徑.........................................................................................................................................-44-
12.1.3臨床表現(xiàn).........................................................................................................................................-45-
12.2建立疫情防控體系..................................................................................................................................-45-
12.3嚴(yán)格落實(shí)“1234”管理制度.......................................................................................................................-45-
12.3.1一個不得.........................................................................................................................................-45-
12.3.2兩本臺賬.........................................................................................................................................-45-
12.3.3三項(xiàng)教育.........................................................................................................................................-45-
12.3.4四個機(jī)制.........................................................................................................................................-46-
12.4建立員工健康狀況臺賬及疫情防控信息報(bào)告機(jī)制...............................................................................-46-
12.5個人防護(hù)..................................................................................................................................................-46-
12.5.1如何保護(hù)自己遠(yuǎn)離新型冠狀病毒的肺炎傳染..............................................................................-46-
12.5.2正確洗手.........................................................................................................................................-47-
12.5.3正確使用口罩.................................................................................................................................-47-
12.6工作區(qū)防護(hù)知識......................................................................................................................................-48-
12.7出現(xiàn)疑似感染新型冠狀病毒的處置措施...............................................................................................-48-
12.7.1疑似癥狀.........................................................................................................................................-48-
12.7.2就醫(yī)時(shí)注意事項(xiàng).............................................................................................................................-49-
12.7.3確診為新型冠狀病毒感染者后處理措施......................................................................................-49-
12.7.4醫(yī)院聯(lián)系電話及路線圖.................................................................................................................-49-
第十三章計(jì)算書..........................................................................................................................................-50-
項(xiàng)目專項(xiàng)施工方案
第一章編制依據(jù)
序
類別文件名稱編號
號
1《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2012
2《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50204-2015
3《建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范》GB50007-2011
國家標(biāo)
4《鋼管腳手架扣件》GB15831-2006
準(zhǔn)
5《安全網(wǎng)》GB5725-2009
6《鋼結(jié)構(gòu)設(shè)計(jì)標(biāo)準(zhǔn)(附條文說明[另冊])》GB50017-2017
7《建筑施工腳手架安全技術(shù)統(tǒng)一標(biāo)準(zhǔn)》GB51210-2016
8《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
9《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
技術(shù)規(guī)《施工現(xiàn)場臨時(shí)用電安全技術(shù)規(guī)范(附條文說
10JGJ46-2005
范明)》
11《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
12《建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范》JGJ130-2011
13《建設(shè)工程安全生產(chǎn)管理?xiàng)l例》國務(wù)院令第393號
14《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定》住建部第37號
《住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實(shí)施<危險(xiǎn)性較大
行政文建辦質(zhì)(2018)31
15的分部分項(xiàng)工程安全管理規(guī)定>有關(guān)問題的通
件號
知》
武漢市建筑施工現(xiàn)場安全質(zhì)量標(biāo)準(zhǔn)化達(dá)標(biāo)實(shí)施
16/
手冊
第二章工程概況
2.1工程建設(shè)概況
xx改造項(xiàng)目吳家山街老舊小區(qū)改造設(shè)計(jì)采購施工總承包(EPC)工程建設(shè)概況具體內(nèi)
容如表2.1-1所示,社區(qū)分布圖見圖2.1-1所示。
表2.1-1工程建設(shè)概況
序號內(nèi)容
項(xiàng)目名
1xx改造項(xiàng)目吳家山街老舊小區(qū)改造設(shè)計(jì)采購施工總承包(EPC)
稱
標(biāo)段劃
21個標(biāo)段
分
建設(shè)地
3武漢市東西湖吳家山片區(qū)
點(diǎn)
建設(shè)規(guī)吳家山街老舊小區(qū)改造社區(qū)包括:額頭灣小區(qū)、二支溝小區(qū)、富麗雅
4
模小區(qū)、團(tuán)結(jié)樓小區(qū)、陽光院子小區(qū)、東建小區(qū)、中建三局小區(qū)、教校
-1-
項(xiàng)目專項(xiàng)施工方案
小區(qū)、衛(wèi)生局小區(qū)、司法局小區(qū)、防暴隊(duì)小區(qū)、三秀路城建小區(qū)、實(shí)
驗(yàn)小學(xué)宿舍、樂佳1棟、商業(yè)小區(qū)、雅心苑小區(qū)、開屏里小區(qū)、城
管交通小區(qū)、法院宿舍、圓夢佳園、荷花苑、吳北路5號(派出所
院內(nèi))、黃鶴園小區(qū)、東興南(徑河小區(qū))、廣水酒店小區(qū)、科委宿
舍片區(qū)、海景小區(qū)、麗山小區(qū)、四中宿舍,共計(jì)29個小區(qū)。合同估
算價(jià);30964.93萬元。
招標(biāo)內(nèi)項(xiàng)目有關(guān)的設(shè)計(jì)、采購、工程施工總承包服務(wù),其中設(shè)計(jì)為施工圖設(shè)
5
容計(jì)。
6招標(biāo)人武漢市東西湖城市建設(shè)投資發(fā)展有限公司
建設(shè)單
7
位
監(jiān)理單
8
位
聯(lián)合體
9設(shè)計(jì)單
位
建設(shè)周
10210日歷天
期
質(zhì)量目設(shè)計(jì)要求的質(zhì)量標(biāo)準(zhǔn):合格
11
標(biāo)施工要求的質(zhì)量標(biāo)準(zhǔn):合格
安全文
12合格
明目標(biāo)
圖2.1-1社區(qū)分布圖
-2-
項(xiàng)目專項(xiàng)施工方案
表2.1-2小區(qū)分區(qū)情況表
所屬街
序號所屬社區(qū)小區(qū)
道
吳家山
1額頭灣社區(qū)額頭灣小區(qū)、二支溝小區(qū)、富麗雅小區(qū)
街
團(tuán)結(jié)樓小區(qū)、陽光院子小區(qū)、東建小區(qū)、中
吳家山
2恒春里社區(qū)建三局小區(qū)、g教校小區(qū)、衛(wèi)生局小區(qū)、司
街
法局小區(qū)、防暴隊(duì)小區(qū)
三秀路城建小區(qū)、實(shí)驗(yàn)小學(xué)宿舍、樂佳1
吳家山
3開屏里社區(qū)棟、商業(yè)小區(qū)、雅心苑小區(qū)、開屏里小區(qū)、
街
城管交通小區(qū)
吳家山
4文家灣社區(qū)法院宿舍
街
吳家山圓夢佳園、荷花苑、吳北路5號(派出所院
5夢佳社區(qū)
街內(nèi))
吳家山黃鶴園小區(qū)、東興南(徑河小區(qū))、廣水酒
6田園社區(qū)
街店小區(qū)、科委宿舍片區(qū)
吳家山
7怡景社區(qū)海景小區(qū)、麗山小區(qū)、四中宿舍
街
2.2建筑設(shè)計(jì)概況
本項(xiàng)目腳手架作業(yè)范圍內(nèi)施工內(nèi)容主要包括外墻修繕、外墻刷新、外墻清洗、落水管
更換、空調(diào)灰色鋁合金百葉外罩安裝、雨陽棚(鋼結(jié)構(gòu))安裝等。改造小區(qū)情況統(tǒng)計(jì)見表
2.2-1所示。
表2.2-1小區(qū)情況統(tǒng)計(jì)表
建
涉及改涉及樓涉及建筑
序所屬成屋面層
小區(qū)名稱造戶數(shù)棟面積
號社區(qū)時(shí)形式高
(戶)(棟)(萬m2)
間
額頭灣社平屋面、6、
1額頭灣小區(qū)7641619996.89
區(qū)坡屋面7層
額頭灣社平屋面、
2二支溝小區(qū)2251119862.036層
區(qū)坡屋面
6至
額頭灣社平屋面、
3富麗雅小區(qū)164529199817.724
區(qū)坡屋面
層
恒春里社平屋面、
4團(tuán)結(jié)樓小區(qū)96219940.976層
區(qū)坡屋面
6至
恒春里社陽光院子小平屋面、
5125519921.1710
區(qū)區(qū)坡屋面
層
恒春里社
6東建小區(qū)105519921.05平屋面7層
區(qū)
-3-
項(xiàng)目專項(xiàng)施工方案
建
涉及改涉及樓涉及建筑
序所屬成屋面層
小區(qū)名稱造戶數(shù)棟面積
號社區(qū)時(shí)形式高
(戶)(棟)(萬m2)
間
恒春里社中建三局小
7108219911.05平屋面7層
區(qū)區(qū)
恒春里社
8教校小區(qū)30119940.31平屋面6層
區(qū)
恒春里社
9衛(wèi)生局小區(qū)40219950.42平屋面6層
區(qū)
恒春里社
10司法局小區(qū)56219960.63坡屋面7層
區(qū)
恒春里社6、
11防暴隊(duì)小區(qū)107419941.02坡屋面
區(qū)7層
開屏里社三秀路城建平屋面、
12114719890.986層
區(qū)小區(qū)坡屋面
開屏里社實(shí)驗(yàn)小學(xué)宿6、
1342119890.39坡屋面
區(qū)舍7層
開屏里社
14樂佳1棟56119990.42坡屋面7層
區(qū)
開屏里社平屋面、6、
15商業(yè)小區(qū)120419930.91
區(qū)坡屋面7層
開屏里社平屋面、6、
16雅心苑小區(qū)72219970.54
區(qū)坡屋面7層
開屏里社平屋面、6、
17開屏里小區(qū)82319980.63
區(qū)坡屋面7層
開屏里社城管交通小
1836219980.27坡屋面7層
區(qū)區(qū)
文家灣社
19法院宿舍60119980.56坡屋面7層
區(qū)
平屋面、6、
20夢佳社區(qū)圓夢佳園212619991.7
坡屋面7層
21夢佳社區(qū)荷花苑8531919947.4坡屋面7層
吳北路5號
22夢佳社區(qū)(派出所院12119900.12坡屋面3層
內(nèi))
6、
23田園社區(qū)黃鶴園小區(qū)118419941.02坡屋面
7層
東興南(徑平屋面、6、
24田園社區(qū)157519991.4
河小區(qū))坡屋面7層
廣水酒店小平屋面、
25田園社區(qū)179619981.977層
區(qū)坡屋面
科委宿舍片
26田園社區(qū)136519951.28坡屋面7層
區(qū)
-4-
項(xiàng)目專項(xiàng)施工方案
建
涉及改涉及樓涉及建筑
序所屬成屋面層
小區(qū)名稱造戶數(shù)棟面積
號社區(qū)時(shí)形式高
(戶)(棟)(萬m2)
間
6~18
27怡景社區(qū)海景小區(qū)260458200026坡屋面
層
28怡景社區(qū)麗山小區(qū)105420
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 拋荒整治協(xié)議合同
- 2024年生物制藥試劑定制生產(chǎn)合同樣本2篇
- 2025年云南貨運(yùn)資格證題庫在線練習(xí)
- 2025年黃岡貨運(yùn)從業(yè)資格證考試模擬
- 2025年貴港b2貨運(yùn)資格證全題
- 2024年度生物制藥研發(fā)委托技術(shù)合同范本3篇
- 2024年環(huán)保項(xiàng)目實(shí)施方案保密協(xié)議
- 2024年版綜合性勞動協(xié)議范本版
- 2025年北京貨運(yùn)資格證考試70題
- 《工程制圖與CAD(軌道交通)》課件-鐵路線路平面圖認(rèn)識
- 國家糧食和物資儲備局招聘考試試題及答案
- JTG F90-2015 公路工程施工安全技術(shù)規(guī)范
- 松果體區(qū)腫瘤護(hù)理
- 《施工現(xiàn)場安全防護(hù)標(biāo)準(zhǔn)化防高墜篇》測試附有答案
- 流動資金貸款管理辦法培訓(xùn)1
- 血管瘤護(hù)理措施
- 智能穿戴行業(yè)發(fā)展趨勢
- 公共場所的肺結(jié)核消毒措施
- 圓及其在生活中的應(yīng)用
- 春節(jié)晚宴策劃方案1
- 如何制作一個簡易的動物細(xì)胞模型
評論
0/150
提交評論