目錄
1編制依據...............................................................................1
1.1編制目的...........................................................................1
1.2編制依據..........................................................................1
2工程概況...............................................................................1
2.1工程位置..........................................................................1
2.2工程規(guī)模..........................................................................2
2.3資源配置情況......................................................................3
2.3.1設備配置...............................................................................................................................................3
2.3.2人力資源配置......................................................................................................................................6
2.4工程地質及水文地質.................................................................7
2.4.1地形地貌..............................................................................................................................................7
2.4.2氣象特征..............................................................................................................................................7
2.4.3工程地質及水文地質概況.................................................................................................................8
2.5沿線環(huán)境..........................................................................13
2.5.1盾構穿越沿線建構筑物.....................................................................................................................13
2.5.2地下管線............................................................................................................................................13
3工程重難點............................................................................14
3.1盾構穿越沿線建構筑物多、施工難度較大..............................................14
3.2盾構下穿沙河及駟馬橋..............................................................14
3.3盾構下穿北新高架..................................................................14
3.4盾構下穿荷花池社區(qū)(成鐵生活區(qū))..................................................14
3.5盾構始發(fā)及到達....................................................................14
3.6盾構開倉換刀作業(yè).................................................................15
3.7沿線建(構)筑物監(jiān)測工作量大......................................................15
4盾構隧道施工風險分析...................................................................15
4.1風險源識別.......................................................................15
4.2風險分析..........................................................................16
4.2.1盾構始發(fā)與到達..............................................................................................................................16
4.2.2盾構掘進.........................................................................................................................................16
4.2.3盾構穿越沙河及駟馬橋.................................................................................................................17
4.2.3盾構穿越城北賓館.........................................................................................................................18
4.2.4穿越隧道沿線地下管線.................................................................................................................20
4.2.5開倉換刀.........................................................................................................................................20
4.2.6隧道施工事故..................................................................................................................................20
4.3風險評價..........................................................................21
5專項施工方案..........................................................................25
5.1盾構始發(fā)與到達....................................................................25
5.1.1端頭加固.............................................................................................................................................25
5.1.2始發(fā)軸線控制.................................................................................................................................30
5.1.3基座及反力架加固.........................................................................................................................30
5.1.4洞門封固.........................................................................................................................................31
5.1.5掘進控制............................................................................................................................................32
5.1.6監(jiān)控量測.........................................................................................................................................34
5.2盾構掘進方案......................................................................37
5.2.1盾構機選型及改造............................................................................................................................37
5.2.2施工前準備........................................................................................................................................38
5.2.3盾構參數設定及優(yōu)化........................................................................................................................39
5.2.4盾構試掘進........................................................................................................................................42
5.2.5渣土改良.............................................................................................................................................44
5.2.6盾構掘進方向控制與調整................................................................................................................45
5.2.7出土量控制.........................................................................................................................................47
5.2.8管片拼裝..........................................................................................................................................47
5.2.9同步注漿.........................................................................................................................................49
5.2.10洞內二次注漿加固.........................................................................................................................50
5.2.10盾構管片加強..................................................................................................................................51
5.2.11滯后沉降的控制及應急措施..........................................................................................................51
5.2.12數據采集、傳遞與分析..................................................................................................................53
5.2.13監(jiān)測技術...........................................................................................................................................54
5.3盾構下穿沙河及駟馬橋方案.........................................................54
5.3.1施工措施.........................................................................................................................................54
5.3.2掘進參數.........................................................................................................................................57
5.3.3出土量..............................................................................................................................................57
5.3.4同步注漿.....................................................................................................................................57
5.3.5監(jiān)控量測.....................................................................................................................................57
5.3.6做好“保頭護尾”............................................................................................................................58
5.3.7設備檢查和保養(yǎng)................................................................................................................................58
5.4盾構穿越城北賓館加固措施..........................................................58
5.4.1施工前準備........................................................................................................................................58
5.4.2施工加固措施方案...........................................................................................................................58
5.5盾構穿越民房地面加固方案..........................................................60
5.5.1施工前準備.........................................................................................................................................60
5.5.2地面注漿加固施工方案...................................................................................................................60
5.5.3洞內深孔注漿...................................................................................................................................61
5.6盾構穿越管線方案..................................................................62
5.6.1施工前準備.........................................................................................................................................62
5.6.2管線加固處理措施..........................................................................................................................62
5.6.3二次注漿.........................................................................................................................................63
5.6.4洞內注漿加固..................................................................................................................................63
5.6.5YDK2+402碎污水管處理措施........................................................................................................64
5.7開倉換刀施工方案..................................................................65
5.7.1開倉作業(yè)組織架構..........................................................................................................................65
5.7.2開倉總體部署....................................................................................................................................67
5.7.3常壓換刀施工方案............................................................................................................................69
6施工監(jiān)控量測..........................................................................72
6.1監(jiān)測實施細則......................................................................72
6.1.1監(jiān)測的必要性....................................................................................................................................72
6.1.2監(jiān)測目的............................................................................................................................................72
6.1.3監(jiān)測項目及精度要求........................................................................................................................73
6.1.4監(jiān)測重點............................................................................................................................................73
6.1.5監(jiān)測頻率............................................................................................................................................74
6.2監(jiān)測內容及方法....................................................................74
6.2.1地表沉降監(jiān)測.....................................................................................................................................74
6.2.2建(構)筑物沉降與傾斜監(jiān)測........................................................................................................77
6.2.3地下管線沉降監(jiān)測...........................................................................................................................80
6.2.4地下水位監(jiān)測...................................................................................................................................81
6.2.5地中位移監(jiān)測...................................................................................................................................82
6.3監(jiān)測預警等級劃分、報告、處置、消警................................................86
6.4監(jiān)測數據的處理、分析與信息反饋....................................................87
6.4.1監(jiān)控量測流程.................................................................................................................................87
6.4.2數據采集.........................................................................................................................................88
6.4.3數據整理.........................................................................................................................................89
6.4.4數據分析.........................................................................................................................................89
6.4.5信息的反饋和預警報告.................................................................................................................89
6.4.6成果提交..........................................................................................................................................90
7安全應急預案..........................................................................91
7.1安全管理保障體系..................................................................91
7.1.1建立健全安全管理組織..................................................................................................................92
7.1.2完善各項安全生產管理制度.........................................................................................................93
7.1.3建立安全生產崗位責任制度.........................................................................................................93
7.1.4堅持安全教育.................................................................................................................................93
7.1.5強化技術安全管理.........................................................................................................................93
7.1.6日常安全管理..................................................................................................................................93
7.2.應急管理組織機構................................................................94
7.2.1應急組織機構..................................................................................................................................94
7.2.2事故應急小組職責..........................................................................................................................94
7..........................................................................................................................................2.3應急聯(lián)絡電話.97
7..................................................................................................................................................2.4預防預警.98
7.3應急準備及應急響應...............................................................98
7.3.1應急物資..........................................................................................................................................98
7.3.2應急響應程序..................................................................................................................................99
7.4應急救援措施....................................................................103
7.4.1地表沉陷事故應急措施................................................................................................................103
7.4.2管線應急措施................................................................................................................................103
7.4.3建筑物應急措施...........................................................................................................................104
7.5培訓、應急演練和預案評價及修改...................................................104
7.5.1培訓工作....................................................................104
7.5.2預案評價與修改..............................................................105
7.5.3應急救援預案的維護.........................................................105
1編制依據
1.1編制目的
為做好成都地鐵7號線一期工程土建1標盾構區(qū)間風險管理工作,全面地考慮在施
工中所能遇到的各種風險的狀況,進行盾構施工各階段的風險識別和評估,制定相應的
風險控制措施、專項方案以及應急預案,從而進一步加強對盾構施工危險性較大的分部
分項工程的安全管理,積極防范和遏制施工生產安全事故的發(fā)生,保證盾構施工的自身
安全和社會公共安全。特編制本方案。
1.2編制依據
(1)《危險性較大的分部分項工程安全管理辦法》(建質[2009]87號);
(2)《關于完善施工現場管理人員配備的實施意見》(成建委[2008]101號);
(3)《成都地鐵投融資項目重大危險源安全管理辦法》(成地鐵建[2012]24號);
(4)《成都地鐵工程安全生產及文明施工管理考核辦法》(成地鐵發(fā)[2012]210
號);
(5)《關于進一步加強盾構施工安全管理工作的通知》(成地鐵建[2013]67號);
(6)《地下鐵道工程施工及驗收規(guī)范》(GB50299T9992003版);
(7)《盾構法隧道施工與驗收規(guī)范》(GB50446-2008);
(8)《建筑與市政降水技術規(guī)程》(JGJ/T111-98);
(9)國家、四川省、成都市及成都市安監(jiān)站、成都地鐵公司出臺的相關法規(guī)、文
件等;
(10)《成都地鐵7號線一期工程火車北站?駟馬橋站巖土工程詳細勘察報告》;
(11)成都地鐵7號線一期工程火車北站?駟馬橋站區(qū)間施工圖紙;
(12)成都地鐵7號線一期工程土建1標盾構區(qū)間沿線建筑物基礎施工圖紙;
(13)《成都地鐵7號線一期工程土建1標段實施性施工組織設計》;
(14)成都地區(qū)盾構施工技術積累和經驗總結,我公司在盾構施工領域積累的技術
和管理經驗。
2工程概況
2.1工程位置
區(qū)間隧道由駟馬橋站始發(fā),沿駟馬橋路西行下穿沙河,沿云景灣項目旁小路穿過一
片空地后下穿成都鐵路局工務大修段家屬樓,出工務大修段家屬樓后下穿北新高架、荷
花池停車場及城北賓館,后穿過北站東二路后進入荷花池社區(qū),出荷花池社區(qū)后沿站前
路到達火車北站東端頭。
圖2.1-1火駟區(qū)間線路平面圖
2.2工程規(guī)模
火車北站-駟馬橋站起止里程為Y(Z)DKO+773.267-Y(Z)DK2+545.063,其中左線長
1770.866m(其中短鏈0.93m),右線長1771.796m,為雙孔圓形隧道,主要附屬工程包
括3個聯(lián)絡通道(2個含泵房)、4個洞門。
本工程主要內容見下表:
主要工程內容表表2.2-1
序號工程項目及費用名稱單位數量
1盾構主體工程項1
2盾構區(qū)間隧道工程延長米3542.662
3盾構掘進延長米3542.662
4管片襯砌制安延長米3540
5管片制作延長米3540
6聯(lián)絡通道項3
7洞門個4
主要工程進度計劃表表2.2-2
聯(lián)絡通道及泵
序號區(qū)間盾構始發(fā)時間盾構到達時間
房完成時間
左線2014.8.202015.4.25
1火車北站?駟馬橋站2015.7.30
右線2014.9.202015.5.25
2.3資源配置情況
2.3.1設備配置
1)本工程采用兩臺中鐵裝備盾構機,編號為63號、64號。本工程編號右線3號、
左線4號盾構機,盾構機主要參數如下:
盾構機主要參數表表2.3-1
序號參數列表單位
1使用項目成都地鐵
標段名稱7號線一期工程土建1標
區(qū)間里程Y(Z)DK0+773.267-Y(Z)DK2+545.063
主要地質條件卵石土
項目管片規(guī)格(外徑/內徑-寬度/分度)①6000/5400-1500/36°inm
最小曲線半徑400m
2整機
型號CTE6250
開挖直徑*6280mm
刀盤轉速0-3.35r/min
最大推進速度-80mm/min
最大推力3700T
最大工作壓力0.3MPa
水平轉彎半徑250m
縱向爬坡能力±50%o
3刀盤
刀盤規(guī)格(直徑X長度)06280X1580mm
刀盤開口率36%
結構總重約50(不含刀具)T
泡沫口數量4個
4刀具
17寸中心雙聯(lián)滾刀4把
18寸單刃滾刀31把
切刀32把
邊刮刀8把
焊接撕裂刀29把
保徑刀8把
大圓環(huán)耐磨保護整圈
5主驅動
驅動型式液壓驅動
驅動組數量9組
驅動總功率945KW
轉速范圍0-3.35rpm
額定扭矩6650KNm
脫困扭矩8100KNm
主軸承直徑3061mm
6盾體
型式被動較接式
前盾規(guī)格(直徑)66250mm
前盾重量約90T
中盾規(guī)格(直徑)66240mm
中盾重量約95T
尾盾規(guī)格(直徑)@6230mm
尾盾重量約24T
尾盾密封刷排數3排
盾尾安裝間隙30mm
7人倉
型式雙倉并聯(lián)
工作壓力0.3MPa
設計壓力0.5MPa
8螺旋輸送機
螺旋軸型式軸式
規(guī)格(直徑X長度)4)800X12500mm
最大通過粒徑4)290X560mm
最大出渣能力3357m3/h
驅動功率315kW
最大扭矩210kN?m
轉速范圍0-25r/min
總重約25T
9管片安裝機
型式中心回轉式
抓舉頭型式機械式
縱向移動行程2000mm
自由度數量6個
旋轉角度±200O
提升力120kN
扭矩150kN?m
10管片運輸小車
規(guī)格(長X寬X高)5220X1660X545mm
承載管片數量3后
負載管片能力15T
縱向滑動行程1760mm
11推進系統(tǒng)
油缸規(guī)格(①缸徑/桿徑)0220/180mm
推進行程2150mm
最大推進速度80mm/min
最大工作壓力34MPa
最大推力3700T
12校接系統(tǒng)
油缸規(guī)格(缸徑/桿徑-行程)6180/80-150mm
油缸數量18根
總拉力約12000KN
13單液同步注漿系統(tǒng)
注漿泵型式雙活塞注漿泵
注漿泵數量2個
注漿泵功率30kW
注漿能力10X27m3/h
注漿泵出口最大壓力6MPa
砂漿罐容量87m3
14膨潤土注入系統(tǒng)
改良膨潤土泵型式軟管泵
改良膨潤土泵功率18.5kW
注入能力167m3/h
膨潤土罐容量
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經權益所有人同意不得將文件中的內容挪作商業(yè)或盈利用途。
- 5. 人人文庫網僅提供信息存儲空間,僅對用戶上傳內容的表現方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
- 6. 下載文件中如有侵權或不適當內容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 物聯(lián)網與智能交通系統(tǒng)的結合
- 《數據網組建與維護》課件-3.1任務1 靜態(tài)路由實現網絡互聯(lián)
- 胎心監(jiān)護臨床意義
- 2025年征信數據挖掘技術與應用題庫:征信數據分析考試
- 2025年小學教師資格考試《綜合素質》教育案例反思策略與試題試卷
- 2025年安全生產考試題庫:水上交通事故案例分析試題卷
- 2025年消防安全知識培訓考試題庫:消防設施設備選型與消防設施驗收流程標準試題
- 2025年茶藝師職業(yè)技能競賽茶葉茶藝表演技巧與創(chuàng)新試題試卷
- 2025年SAT語法知識測試卷:語法知識點鞏固與測試試題
- 安全游泳講課
- 高等教育數字化轉型心得體會
- 2025年安徽財貿職業(yè)學院單招職業(yè)技能測試題庫及答案1套
- 2025年安徽職業(yè)技術學院單招職業(yè)技能測試題庫及答案1套
- 典范英語6-12玉米片硬幣英文原文及重點短語和句子演示教學
- 日式保潔培訓課件大全
- 2025年廣東省深圳市高考語文一模試卷
- 2025年陜西工商職業(yè)學院單招職業(yè)技能測試題庫學生專用
- 2025年福建省高職單招職業(yè)適應性測試題庫及答案解析
- 自媒體運營實戰(zhàn)教程(抖音版) 課件 第7章 短視頻運營-自媒體中級
- 2025時事政治必考題庫含參考答案
- 保潔管理安全培訓課件
評論
0/150
提交評論