總目錄目錄································································1第一章工程概況····················································2第一節(jié)工程名稱、性質(zhì)、規(guī)模和地理位置··························2第二節(jié)相關(guān)單位················································2第三節(jié)工程承包范圍及內(nèi)容······································2第二章幕墻設(shè)計(jì)簡(jiǎn)介················································2第一節(jié)各立面幕墻設(shè)計(jì)簡(jiǎn)介······································2第二節(jié)幕墻使用部位及工程量····································2第三節(jié)幕墻節(jié)能設(shè)計(jì)的節(jié)能構(gòu)造和采用的節(jié)能材料··················3第三章編制依據(jù)····················································3第四章施工部署和施工計(jì)劃··········································4第一節(jié)施工條件················································4第二節(jié)項(xiàng)目管理班子············································4第三節(jié)施工設(shè)備計(jì)劃···········································10第五節(jié)施工現(xiàn)場(chǎng)布置···········································10第六節(jié)垂直運(yùn)輸、施工設(shè)備·····································10第五章幕墻施工方法···············································11第一節(jié)玻璃幕墻施工工藝·······································11第二節(jié)鋁板幕墻施工工藝·······································16第三節(jié)預(yù)埋件、轉(zhuǎn)接件和龍骨的制作和安裝施工方法···············19第四節(jié)幕墻板塊制作、安裝及隱蔽驗(yàn)收···························21第五節(jié)幕墻的防火要求·········································23第六節(jié)幕墻防雷···············································23第七節(jié)節(jié)能隔熱、中空玻璃加工等技術(shù)措施·······················26第八節(jié)幕墻開(kāi)啟扇防墜、面板運(yùn)輸、安裝、清洗措施···············27第六章安全文明施工、消防及環(huán)保措施·······························28第一節(jié)施工現(xiàn)場(chǎng)安全管理·······································28第二節(jié)安全保證措施···········································29第三節(jié)安全技術(shù)措施···········································30第四節(jié)文明施工措施···········································35第七章質(zhì)量管理···················································40第一節(jié)質(zhì)量管理的控制·········································40第二節(jié)生產(chǎn)管理措施···········································40第三節(jié)材料加工及質(zhì)量控制·····································42第四節(jié)材料管理措施···········································43第八章應(yīng)急預(yù)案···················································46第一節(jié)安全意外事故處理及事故責(zé)任·····························46第二節(jié)項(xiàng)目應(yīng)急預(yù)案書(shū)·········································47第九章勞動(dòng)力計(jì)劃·················································49第一章工程概況第一節(jié)工程名稱、性質(zhì)、規(guī)模和地理位置1、工程名稱:名企廣場(chǎng)高層SOHO商務(wù)用房2、工程性質(zhì):綜合建筑。3、規(guī)模:該項(xiàng)目建筑面積為137700㎡,其中地下一層,地上15~27層,框架剪力墻結(jié)構(gòu),抗震設(shè)防烈度為6度,耐火要求達(dá)到1級(jí),節(jié)能要求滿足《公用建筑節(jié)能設(shè)計(jì)標(biāo)準(zhǔn)》GB50189-2005的規(guī)定要求。4、項(xiàng)目地址:杭州蕭山聞堰鎮(zhèn)第二節(jié)相關(guān)單位1、工程建設(shè)單位:杭州正江房地產(chǎn)開(kāi)發(fā)有限公司2、建筑設(shè)計(jì)單位:中國(guó)美術(shù)學(xué)院風(fēng)景建筑設(shè)計(jì)研究院3、幕墻設(shè)計(jì)單位:浙江大學(xué)建筑設(shè)計(jì)研究院4、監(jiān)理單位:浙江中潤(rùn)建設(shè)監(jiān)理有限公司5、總包單位:天偉建設(shè)集團(tuán)有限公司第三節(jié)工程承包范圍和內(nèi)容名企廣場(chǎng)高層SOHO商務(wù)用房門窗幕墻工程主樓、裙樓的玻璃幕墻、鋁板幕墻、玻璃雨蓬、鋁合金百葉、鋁合金門窗;第二章幕墻設(shè)計(jì)簡(jiǎn)介第一節(jié)、各立面幕墻設(shè)計(jì)簡(jiǎn)介該工程為地下一層,地上15~27層,局部裙房六~七層。共分二個(gè)區(qū),二個(gè)區(qū)幕墻設(shè)計(jì)要求和分布基本一致,分別含有玻璃幕墻、鋁板幕墻、鋁合金門窗等工程范圍。第二節(jié)、幕墻使用部位及工程量1、按施工方法分:該項(xiàng)目為構(gòu)件式幕墻。2、按面板材料分:該項(xiàng)目幕墻包含玻璃幕墻、鋁板幕墻、鋁合金門窗等。3、按構(gòu)造和支撐方式分(1)、幕墻為明框玻璃幕墻。(2)、鋁板幕墻以鋼材為龍骨,面板為2.5㎜氟碳噴涂鋁單板,硅酮耐候膠封閉。(3)、鋁合金門窗采用斷橋隔熱56系列鋁合金型材。第三節(jié)幕墻節(jié)能設(shè)計(jì)的節(jié)能構(gòu)造和采用的節(jié)能材料玻璃幕墻采用斷橋隔熱鋁合金型材,隔熱條滿足規(guī)范要求。并要求對(duì)隔熱條進(jìn)行抗拉抗剪的現(xiàn)場(chǎng)復(fù)測(cè)。第三章編制依據(jù)1、由設(shè)計(jì)單位提供的幕墻施工圖。2、現(xiàn)行國(guó)家和有關(guān)主管部門制定的有關(guān)方針、政策、法律、法規(guī)、規(guī)章、規(guī)范及其強(qiáng)制性條文、規(guī)程、標(biāo)準(zhǔn)、定額。《玻璃幕墻工程技術(shù)規(guī)范》JGJ102-2003*《建筑幕墻》GB/T21086-2007*《金屬及石材幕墻工程技術(shù)規(guī)范》JGJ133-2001*《建筑幕墻氣密、水密、抗風(fēng)壓性能檢測(cè)方法》GB/T15227-2007*《建筑幕墻平面內(nèi)變形性能檢測(cè)方法》GB/T18250-2000*《玻璃幕墻工程質(zhì)量驗(yàn)收標(biāo)準(zhǔn)》JGJ/T139-2001*《建筑外窗氣密、水密、抗風(fēng)壓性能現(xiàn)場(chǎng)檢測(cè)方法》JG/T

211-2007*《建筑外窗抗風(fēng)壓性能分級(jí)及檢測(cè)方法》GB/T7106-2002*《建筑外窗氣密性能分級(jí)及檢測(cè)方法》GB/T7107-2002*《建筑外窗水密性能分級(jí)及檢測(cè)方法》GB/T7108-2002*《建筑外窗保溫性能分級(jí)及檢測(cè)方法》GB/T8484-2002*《建筑外窗空氣隔聲性能分級(jí)及檢測(cè)方法》GB/T8485-2002*《建筑外門的風(fēng)壓變形性能分級(jí)及檢測(cè)方法》GB/T13685-92*《建筑外門的空氣滲透和雨水滲漏性能分級(jí)及檢測(cè)方法》GB/T13686-92*《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2001(2006年版)*《建筑設(shè)計(jì)防火規(guī)范》GB50016-2006*《建筑物防雷設(shè)計(jì)規(guī)范》GB50057-94(2000版)*《建筑用鋁型材、鋁板氟碳涂層》JG/T133-2000*《建筑用隔熱鋁合金型材穿條式》JG/T175-2005*《鋁及鋁合金硬質(zhì)陽(yáng)極氧化膜規(guī)范》GB/T19822-2005*《鋁幕墻板氟碳噴漆鋁單板》YS/T429.2-2000*《建筑玻璃應(yīng)用技術(shù)規(guī)程》JGJ113-2003*《中空玻璃》GB/T11944-2002*《建筑鋼結(jié)構(gòu)焊接技術(shù)規(guī)程》JGJ81-2002*《建筑用硅酮結(jié)構(gòu)密封膠》GB16776-20053、我公司制定的ISO9001-2000程序文件、企業(yè)標(biāo)準(zhǔn)、以及公司制定的各種規(guī)章制度。4、工程目標(biāo)。(1)施工總工期:計(jì)劃總工期為240天(日歷天)。(2)施工目標(biāo):嚴(yán)格按規(guī)范要求設(shè)計(jì),按設(shè)計(jì)施工。接受業(yè)主和設(shè)計(jì)師、監(jiān)理、總包單位的管理。(3)目標(biāo)工程質(zhì)量:達(dá)到國(guó)家現(xiàn)行施工質(zhì)量驗(yàn)收合格標(biāo)準(zhǔn)。(4)安全目標(biāo):安全施工無(wú)事故,達(dá)到文明施工工地要求。第四章施工部署和施工計(jì)劃第一節(jié)施工條件1、總包方已完成工程主體結(jié)構(gòu)。2、現(xiàn)場(chǎng)已按圖紙要求完成預(yù)埋件的預(yù)埋工作,經(jīng)現(xiàn)場(chǎng)復(fù)測(cè),符合圖紙預(yù)埋要求。3、幕墻施工前期采用總包現(xiàn)場(chǎng)腳手架,在總包腳手架拆除后幕墻施工采用吊蘭。4、幕墻施工所用的臨時(shí)水、電均采用總包方現(xiàn)有設(shè)施,總包方已按要求將二級(jí)配電箱安裝至樓層。5、其他設(shè)施如道路、臨舍等均符合幕墻施工要求。第二節(jié)項(xiàng)目管理班子項(xiàng)目管理人員包括項(xiàng)目經(jīng)理1名,技術(shù)主管1名,質(zhì)檢員1名,安全員1名、施工主管1名及其它施工管理人員。實(shí)施對(duì)該項(xiàng)目施工全過(guò)程的管理職能,對(duì)工程中的材料管理運(yùn)輸、安裝操作、質(zhì)量控制、施工安全直至竣工驗(yàn)收進(jìn)行全方位管理。項(xiàng)目管理機(jī)構(gòu)配備情況表職務(wù)姓名證書(shū)名稱證號(hào)項(xiàng)目經(jīng)理李廣文職稱證書(shū)粵建安B(2008)0004377技術(shù)負(fù)責(zé)人張宏職稱證書(shū)951310安全員湯東泉資格證書(shū)0913B0035施工員來(lái)傳夫資格證書(shū)0913A0015質(zhì)檢員沈丹資格證書(shū)0913B0007資料員丁瑜資格證書(shū)0903C00316材料員來(lái)永明資格證書(shū)1013C0021項(xiàng)目經(jīng)理部組織機(jī)構(gòu)圖。1、項(xiàng)目經(jīng)理職責(zé)(1)、負(fù)責(zé)工程施工組織方案編制及總體進(jìn)度計(jì)劃編制。(2)、負(fù)責(zé)對(duì)工程的質(zhì)量、設(shè)計(jì)、工期、安全等進(jìn)行監(jiān)督管理,履行合同條款。(3)、負(fù)責(zé)工程施工安全,質(zhì)量及進(jìn)度(工期)控制;負(fù)責(zé)協(xié)調(diào)甲方、總包、監(jiān)理公司、公司內(nèi)部各部門的關(guān)系,保證工程順利進(jìn)行。(4)、負(fù)責(zé)項(xiàng)目組織機(jī)構(gòu)設(shè)置及各成員的工作安排,對(duì)各成員工作情況進(jìn)行監(jiān)督和考核。(5)、負(fù)責(zé)項(xiàng)目部管理人員及施工隊(duì)伍管理,做到安全施工、文明施工。要求辦公室、庫(kù)房整潔有序各類標(biāo)識(shí)清晰醒目。(6)、負(fù)責(zé)工程施工過(guò)程中各種資料報(bào)表、文件、函件收發(fā)存檔。文件管理按公司ISO9001質(zhì)量體系程序文件要求進(jìn)行。(7)、負(fù)責(zé)召開(kāi)項(xiàng)目管理工作會(huì)議。(8)、負(fù)責(zé)按時(shí)上報(bào)每月工程進(jìn)度計(jì)劃表及工程進(jìn)度完成量報(bào)表。(9)、負(fù)責(zé)工程項(xiàng)目施工統(tǒng)計(jì)和協(xié)調(diào)預(yù)算部門編制工程結(jié)算書(shū);負(fù)責(zé)工程現(xiàn)場(chǎng)交工資料收集整理,協(xié)助質(zhì)安部做好竣工資料移交工作。(10)、參加工程施工過(guò)程中各種協(xié)調(diào)會(huì)及工程例會(huì)。(11)、對(duì)甲方提出的設(shè)計(jì)和合同內(nèi)容變更,及時(shí)反饋公司相關(guān)部門并及時(shí)向甲方或監(jiān)理單位辦理簽證手續(xù)。(12)、參加處理安裝過(guò)程中出現(xiàn)的重大安全及質(zhì)量問(wèn)題會(huì)議。負(fù)責(zé)組織工程中間驗(yàn)收及竣工驗(yàn)收。2、項(xiàng)目技術(shù)負(fù)責(zé)人職責(zé)(1)、在項(xiàng)目經(jīng)理的領(lǐng)導(dǎo)下,具體主持本工程的施工圖、加工圖設(shè)計(jì)工作。(2)、負(fù)責(zé)本工程技術(shù)管理工作,組織重大技術(shù)方案的審核,解決施工過(guò)程中出現(xiàn)的重大技術(shù)問(wèn)題。(3)、負(fù)責(zé)施工全過(guò)程技術(shù)指導(dǎo)與監(jiān)控,負(fù)責(zé)監(jiān)督執(zhí)行ISO9001質(zhì)量體系,組織施工圖紙會(huì)審和技術(shù)交底工作。(4)、負(fù)責(zé)主持項(xiàng)目技術(shù)例會(huì),處理設(shè)計(jì)變更有關(guān)工作。(5)負(fù)責(zé)工程施工的全面質(zhì)量管理。(6)、與業(yè)主、設(shè)計(jì)單位、監(jiān)理公司保持經(jīng)常溝通,保證設(shè)計(jì)、監(jiān)理的要求與指令在各工種中貫徹落實(shí)。(7)組織技術(shù)骨干對(duì)本項(xiàng)目的關(guān)鍵技術(shù)難題進(jìn)行科研攻關(guān),落實(shí)加工制作、施工安裝工藝,確保施工順利進(jìn)行。(8)負(fù)責(zé)組織門窗、幕墻各項(xiàng)性能指標(biāo)檢測(cè)材料試驗(yàn)等工作。3、安全員職責(zé)(1)、認(rèn)真執(zhí)行本企業(yè)的領(lǐng)導(dǎo)和安全部門在安全、文明、防火防汛生產(chǎn)方面的批示和規(guī)定,對(duì)本項(xiàng)目的職工在生產(chǎn)中安全健康負(fù)全面責(zé)任。(2)、在計(jì)劃、布置、檢查、總結(jié)和評(píng)比安全、文明生產(chǎn)工作的同時(shí)計(jì)劃、布置、檢查、總結(jié)和評(píng)比安全、文明生產(chǎn)工作。(3)、經(jīng)常檢查施工現(xiàn)場(chǎng)的機(jī)械設(shè)備及其安全裝置、鋼管架、工夾具、半成品堆放以及生活設(shè)施等是否符合安全文明要求。(4)、按時(shí)提出本工程安全技術(shù)措施計(jì)劃項(xiàng)目,經(jīng)上級(jí)批準(zhǔn)后負(fù)責(zé)對(duì)措施項(xiàng)目的實(shí)施。(5)、制定和修訂本項(xiàng)目的安全、文明、防火防汛管理制度,經(jīng)上級(jí)批準(zhǔn)后負(fù)責(zé)執(zhí)行。(6)、經(jīng)常對(duì)本項(xiàng)目職工進(jìn)行安全生產(chǎn)思想和技術(shù)教育,對(duì)新調(diào)入項(xiàng)目的工人進(jìn)行安全生產(chǎn)現(xiàn)場(chǎng)教育;對(duì)特種作業(yè)的工人,必須嚴(yán)格訓(xùn)練,經(jīng)考試合格,并持有操作合格證,方可獨(dú)立操作。(7)、發(fā)生事故時(shí),應(yīng)及時(shí)向主管領(lǐng)導(dǎo)和安全部門報(bào)告,并協(xié)助安全部門進(jìn)行事故的調(diào)查、登記和分析處理工作。(8)、開(kāi)展各項(xiàng)安全、文明、防火防汛管理工作,制定具體的安全、文明、防火防汛管理措施。4、質(zhì)量員職責(zé)(1)、收集整理質(zhì)量資料,對(duì)現(xiàn)場(chǎng)情況隨時(shí)隨地進(jìn)行監(jiān)控,及時(shí)填報(bào)分項(xiàng)工程質(zhì)量檢查評(píng)定報(bào)表,協(xié)助建立質(zhì)量檔案。(2)、按質(zhì)量標(biāo)準(zhǔn)及時(shí)對(duì)工程質(zhì)量進(jìn)行驗(yàn)評(píng),對(duì)不合格的有權(quán)責(zé)令返工或停工,并將發(fā)生的質(zhì)量事故及經(jīng)濟(jì)損失如實(shí)上報(bào)。(3)、參加質(zhì)量會(huì)議及質(zhì)量檢查,參加工程質(zhì)量事故的分析、調(diào)查和處理。(配合項(xiàng)目工程質(zhì)監(jiān)站的現(xiàn)場(chǎng)質(zhì)監(jiān)工作)負(fù)責(zé)各項(xiàng)試驗(yàn)和檢測(cè)。(4)、積極協(xié)助領(lǐng)導(dǎo)開(kāi)展全面質(zhì)量管理,嚴(yán)格掌握質(zhì)量標(biāo)準(zhǔn),對(duì)檢驗(yàn)評(píng)定的工程質(zhì)量負(fù)責(zé),認(rèn)真實(shí)行目標(biāo)管理和全面質(zhì)量管理。(5)、嚴(yán)格按設(shè)計(jì)圖紙、施工規(guī)范、施工程序組織施工,按照質(zhì)量檢驗(yàn)評(píng)定標(biāo)準(zhǔn)主持檢查。(6)、嚴(yán)格掌握質(zhì)量標(biāo)準(zhǔn),堅(jiān)持原則,正確及時(shí)反映質(zhì)量情況。(7)、認(rèn)真開(kāi)展工程創(chuàng)優(yōu)工作,隨機(jī)抽查工序質(zhì)量,不合格的責(zé)令返工,確認(rèn)工程全優(yōu)。5、施工員職責(zé)(1)、具體負(fù)責(zé)工程項(xiàng)目的施工管理,負(fù)責(zé)對(duì)本工程構(gòu)件制作和安裝的各立面的主控點(diǎn)進(jìn)行測(cè)量放線工作,確保結(jié)構(gòu)的精確定位。(2)、參與圖紙會(huì)審及技術(shù)交底工作,解決施工現(xiàn)場(chǎng)出現(xiàn)的技術(shù)問(wèn)題。(3)、指導(dǎo)和檢查施工人員按圖、按規(guī)范施工,對(duì)結(jié)構(gòu)和板塊的吊裝,轉(zhuǎn)運(yùn)嚴(yán)格按計(jì)劃實(shí)施,確保進(jìn)度,使施工做到有序進(jìn)行。(4)、嚴(yán)格按施工程序施工,及時(shí)填寫施工日志、收集質(zhì)量原始記錄,隨時(shí)掌握工程質(zhì)量情況。(5)、對(duì)成品和半成品認(rèn)真保護(hù),作好醒目標(biāo)記,加設(shè)圍欄,不允許二次污染。(6)、對(duì)違反操作規(guī)程造成質(zhì)量不合格的要及時(shí)返工,發(fā)生質(zhì)量事故要及時(shí)上報(bào)。(7)、認(rèn)真組織貫徹落實(shí)安全生產(chǎn)規(guī)章制度,對(duì)所承擔(dān)的工程全生產(chǎn)工作直接負(fù)責(zé)。(8)、根據(jù)進(jìn)度計(jì)劃跟蹤工程進(jìn)度。(9)、調(diào)整進(jìn)度計(jì)劃,安排各工序的施工順序和節(jié)奏速度。(10)、根據(jù)施工進(jìn)度調(diào)配資源配置,做好人、財(cái)、物的優(yōu)化配置工作。(11)、做好里程碑工作的按時(shí)實(shí)現(xiàn)工作。(12)、有效控制關(guān)鍵工作的開(kāi)始結(jié)束時(shí)間,保證關(guān)鍵線路工作的按時(shí)完成。6、材料員職責(zé)(1)、負(fù)責(zé)編制材料采購(gòu)計(jì)劃,及時(shí)聯(lián)系供應(yīng)廠高,跟蹤材料質(zhì)量檢測(cè),確保工程材料質(zhì)量。(2)、根據(jù)工程的進(jìn)度計(jì)劃,調(diào)配施工機(jī)械與設(shè)備。(3)、組織材料二次運(yùn)輸及材料保管、倉(cāng)儲(chǔ)。認(rèn)真做好倉(cāng)庫(kù)的收發(fā)登記,按倉(cāng)儲(chǔ)管理要求,分類擺放各類工程材料,達(dá)到堆放有序,帳物相符。(4)、負(fù)責(zé)驗(yàn)收、收集、保管所提供產(chǎn)品的質(zhì)保書(shū)、標(biāo)準(zhǔn)文件及相關(guān)技術(shù)資料。(5)、接受對(duì)口上級(jí)職責(zé)部門指導(dǎo)、監(jiān)督檢查。第三節(jié)施工設(shè)備計(jì)劃主要施工設(shè)備表機(jī)械名稱規(guī)格型號(hào)數(shù)量用途電焊機(jī)WS-30020臺(tái)鐵件施工電子經(jīng)緯儀DT202C1臺(tái)測(cè)量放線水準(zhǔn)儀DZS3-11臺(tái)測(cè)量放線第五節(jié)施工現(xiàn)場(chǎng)的布置現(xiàn)場(chǎng)材料的堆放、施工用主要設(shè)備、加工場(chǎng)地等已按總包及監(jiān)理的要求合理布置完畢,幕墻施工臨時(shí)用電總包方已按要求將二級(jí)配電箱安裝至樓層,滿足幕墻施工要求。第六節(jié)垂直運(yùn)輸、施工設(shè)備等情況介紹及采取的措施幕墻施工材料運(yùn)輸采用總包方的外用提升機(jī)及塔吊,幕墻安裝前期采用總包現(xiàn)有腳手架,在總包腳手架拆除后采用吊蘭,并與總包方簽訂了配合協(xié)議。第五章幕墻施工方法第一節(jié)玻璃幕墻施工工藝施工工藝流程幕墻性能檢測(cè)試驗(yàn)現(xiàn)場(chǎng)準(zhǔn)備施工準(zhǔn)備材料準(zhǔn)備幕墻性能檢測(cè)試驗(yàn)現(xiàn)場(chǎng)準(zhǔn)備施工準(zhǔn)備材料準(zhǔn)備技術(shù)準(zhǔn)備技術(shù)準(zhǔn)備測(cè)量放線測(cè)量放線人員機(jī)械準(zhǔn)備人員機(jī)械準(zhǔn)備預(yù)埋件、連接件安裝連接件加工預(yù)埋件、連接件安裝連接件加工防雷接地防雷接地成品玻璃安裝固化、檢驗(yàn)型材加工檢驗(yàn)鋁框安裝防火棉成品玻璃安裝固化、檢驗(yàn)型材加工檢驗(yàn)鋁框安裝防火棉玻璃打膠制作玻璃打膠制作隱蔽驗(yàn)收隱蔽驗(yàn)收鋁板安裝鋁板安裝打耐候膠打耐候膠清理清理竣工驗(yàn)收竣工驗(yàn)收1、施工準(zhǔn)備(1)現(xiàn)場(chǎng)準(zhǔn)備1)臨時(shí)設(shè)施的搭設(shè)①充分利用現(xiàn)場(chǎng)現(xiàn)有的臨時(shí)設(shè)施,保證人員、設(shè)備能按計(jì)劃順利進(jìn)入施工現(xiàn)場(chǎng)。進(jìn)場(chǎng)后了解現(xiàn)場(chǎng)的具體情況,安裝好加工車間和打膠車間及施工作業(yè)面的水源(含消防水源)、電源的供用。②接通施工臨時(shí)水源和電源,并檢查漏電保護(hù)器和觸電保護(hù)器的靈敏度情況。(2)腳手架1)利用現(xiàn)有的腳手架,局部妨礙施工的請(qǐng)總包方處理。2)鋁板幕墻依靠腳手架施工,根據(jù)幕墻骨架設(shè)計(jì)圖紙規(guī)定的高度和寬度,調(diào)整腳手架。3)由于施工程序中的不同需要,施工中搭建的腳手架要求如下:①放線和制作承重鋼結(jié)構(gòu)支架時(shí),應(yīng)搭建在幕墻面玻璃的兩側(cè),方便工人在不同位置進(jìn)行焊接和安裝等作業(yè)。②安裝玻璃幕墻時(shí),應(yīng)搭建在幕墻的內(nèi)側(cè)。要便于玻璃吊裝斜向伸入時(shí)不碰腳手架,又要使站立在腳手架上下各部位的工人都能很方便地能握住手動(dòng)吸盤,協(xié)助吊車使玻璃準(zhǔn)確就位。③玻璃安裝就位后注膠和清洗階段,這時(shí)需在室外另行搭建一排腳手架,由于全玻璃幕墻連續(xù)面積較大,使室外腳手架無(wú)法與主體結(jié)構(gòu)拉接,所以要特別注意腳手架的支撐和穩(wěn)固,可以用地錨,纜繩和用斜撐的支柱拉接。在正式施工前,應(yīng)對(duì)施工范圍的場(chǎng)地進(jìn)行整平填實(shí),做好場(chǎng)地的清理,保證吊車行走暢通。(3)技術(shù)準(zhǔn)備1)在施工前組織設(shè)計(jì)院、監(jiān)理、現(xiàn)場(chǎng)施工班組等進(jìn)行圖紙會(huì)審,將存在的問(wèn)題及早處理。針對(duì)確定的設(shè)計(jì)和施工方案。在對(duì)玻璃幕墻進(jìn)行設(shè)計(jì)分隔時(shí),除要考慮外形的均勻美觀外,還應(yīng)注意盡量減少玻璃的規(guī)格型號(hào)。由于各類建筑的室外設(shè)計(jì)都不盡相同,對(duì)有室外大雨棚、行車坡道等項(xiàng)目,更應(yīng)注意協(xié)調(diào)好總體施工順序和進(jìn)度,防止由于其他室外設(shè)施的建設(shè),影響吊車行走和玻璃幕墻的安裝。2)編制詳細(xì)的施工技術(shù)交底,并向職工進(jìn)行交底,使施工人員都了解設(shè)計(jì)意圖和施工方法及質(zhì)量標(biāo)準(zhǔn)。3)技術(shù)資料收集。現(xiàn)場(chǎng)土建設(shè)計(jì)資料收集和土建結(jié)構(gòu)尺寸測(cè)量。由于土建施工時(shí)可能會(huì)有一些變動(dòng),實(shí)際尺寸不一定都與設(shè)計(jì)圖紙符合。玻璃幕墻對(duì)土建結(jié)構(gòu)相關(guān)的尺寸要求料高。所以在設(shè)計(jì)前必須到現(xiàn)場(chǎng)量測(cè),取得第一手資料數(shù)據(jù)。然后才能根據(jù)業(yè)主要求繪制切實(shí)可行的幕墻分隔圖。對(duì)于有大門出入的部位,還必須與制作自動(dòng)旋轉(zhuǎn)門、全玻門的單位配合,使玻璃幕墻在門上和門邊都有可靠的收口。同時(shí)也需滿足自動(dòng)旋轉(zhuǎn)門的安裝和維修要求。詳細(xì)核查施工圖紙和現(xiàn)場(chǎng)實(shí)測(cè)尺寸,以確保設(shè)計(jì)加工的完善,同時(shí)認(rèn)真與結(jié)構(gòu)圖紙及其他專業(yè)圖紙進(jìn)行核對(duì),以及時(shí)發(fā)現(xiàn)其不相符部位,盡早采取有效措施修正。鋁板幕墻在制作前應(yīng)對(duì)建筑設(shè)計(jì)施工圖進(jìn)行核對(duì),最好是參考竣工圖,并對(duì)已建建筑物進(jìn)行復(fù)測(cè),按實(shí)測(cè)結(jié)果調(diào)整幕墻并經(jīng)設(shè)計(jì)單位同意后,方可加工組裝。施工前,對(duì)照鋁板幕墻的骨架設(shè)計(jì),復(fù)檢主體結(jié)構(gòu)的質(zhì)量。依照以往的經(jīng)驗(yàn),因?yàn)橹黧w結(jié)構(gòu)質(zhì)量的好壞,對(duì)幕墻骨架的排列位置影響較大。特別是墻面垂直度、平整度的偏差,將會(huì)影響整個(gè)幕墻的水平位置。此外,對(duì)主體結(jié)構(gòu)的預(yù)留孔洞及表面的缺陷,應(yīng)做好檢查記錄,及時(shí)與有關(guān)方面協(xié)商解決。4)測(cè)量準(zhǔn)備工作①根據(jù)所建立一級(jí)測(cè)量控制網(wǎng)的水準(zhǔn)點(diǎn),經(jīng)反復(fù)核對(duì)并簽證后作為引測(cè)放線的依據(jù)。②測(cè)量?jī)x器在使用前進(jìn)行檢測(cè)、校正以確保施工測(cè)設(shè)精度。5)組織樣板墻的施工。6)對(duì)測(cè)量、試驗(yàn)儀器進(jìn)行校正和檢查。(4)材料及機(jī)具準(zhǔn)備框料:采用斷橋鋁合金料,。鋁板幕墻:材料采用氟碳鋁板。鋁板板幕墻施工前應(yīng)按設(shè)計(jì)要求,準(zhǔn)確提出所需材料的規(guī)格及各種配件的數(shù)量,以便于加工訂做。鋁板幕墻所采用的材料、零附件應(yīng)符合有關(guān)規(guī)定,并應(yīng)有出廠合格證。加工幕墻構(gòu)件所采用的設(shè)備、機(jī)具應(yīng)能達(dá)到幕墻構(gòu)件加工精度的要求,其量具應(yīng)定期進(jìn)行計(jì)量檢定。不得使用過(guò)期的材料。1)主要材料質(zhì)量檢查①玻璃的尺寸規(guī)格是否正確,特別要注意檢查玻璃在儲(chǔ)存、運(yùn)輸過(guò)程中有無(wú)受到損傷,發(fā)現(xiàn)有裂紋、崩邊的玻璃決不能安裝,并應(yīng)立即通知工廠盡快重新加工補(bǔ)充。②金屬結(jié)構(gòu)構(gòu)件的材質(zhì)是否符合設(shè)計(jì)要求,構(gòu)件是否平直,加工尺寸、精度、孔洞位置是否滿足設(shè)計(jì)要求。要刷好第一道防銹漆,所有構(gòu)件編號(hào)要標(biāo)注明顯。2)主要施工機(jī)具檢查①玻璃吊裝和運(yùn)輸機(jī)具及設(shè)備的檢查,特別是對(duì)吊車的操作系統(tǒng)和電動(dòng)吸盤的性能檢查。②各種電動(dòng)和手動(dòng)工具的性能檢查。③根據(jù)施工進(jìn)度計(jì)劃,編制詳細(xì)的機(jī)具使用計(jì)劃,并提前七天組織進(jìn)場(chǎng),并對(duì)進(jìn)場(chǎng)的機(jī)械設(shè)備進(jìn)行檢修、保養(yǎng)④做好型材加工車間和玻璃打膠車間的設(shè)備安裝和調(diào)試。(5)人員組織1)根據(jù)施工進(jìn)度計(jì)劃,提前二天組織勞動(dòng)力進(jìn)場(chǎng)。2)組織進(jìn)場(chǎng)職工學(xué)習(xí)合同文件和技術(shù)規(guī)范,熟悉圖紙,和技術(shù)交底,增強(qiáng)參全體職工的質(zhì)量意識(shí)和合同意識(shí)。3)做好新工人、新技術(shù)人員的上崗培訓(xùn)工作,加強(qiáng)遵紀(jì)守法、安全意識(shí)和合同意識(shí)。2、測(cè)量放線(1)、測(cè)量放線對(duì)幕墻施工來(lái)說(shuō)是最關(guān)鍵的工作。其精度的高低直接影響到幕墻的安裝成敗和成本的控制。因此在施工中應(yīng)引起高度重視。1)、測(cè)量依據(jù):幕墻施工圖,土建方提供的各方向軸線,標(biāo)高及部份土建平面圖。2)、測(cè)量?jī)x器和工具:經(jīng)緯儀,水平儀,鋼卷尺,30kg吊線錘。?1.5鋼絲等。施工軸線控制網(wǎng)的建立為了對(duì)大樓建筑作整體控制和幕墻細(xì)部測(cè),本工程布設(shè)兩級(jí)控制網(wǎng)點(diǎn)即主體主控點(diǎn)和墻面控制網(wǎng)點(diǎn)。并先布設(shè)控制軸線網(wǎng)后局部測(cè)設(shè)定位。(2)、建立平面位置控制線及控制點(diǎn)1)、主控制網(wǎng)點(diǎn):按原土建施工所建立的軸線控制網(wǎng)建立4個(gè)控制點(diǎn),測(cè)設(shè)到一層墻面(±0.000)為主控網(wǎng)點(diǎn),并以此建立四條墻面主控制網(wǎng)軸線(基準(zhǔn)線),。依據(jù)主控制軸線,用經(jīng)緯儀和鋼卷尺,彈出與外墻有關(guān)的軸線邊線。建立平面位置控制軸線。2)、平面控制點(diǎn):根據(jù)本工程的平面特征,結(jié)合幕墻分格大樣圖和土建主體控制網(wǎng)點(diǎn)給出的標(biāo)高控制點(diǎn),軸線位置。采用重錘、鋼絲線、測(cè)量器具及水平儀等測(cè)量工具在主體結(jié)構(gòu)上彈出幕墻平面、立柱、分格及轉(zhuǎn)角基準(zhǔn)線,并用經(jīng)緯儀進(jìn)行調(diào)校、復(fù)核后,建立幕墻平面分格及幕墻主型材外邊位置控制點(diǎn)。(3)、水平標(biāo)高控制線的確定根據(jù)該大樓的絕對(duì)標(biāo)高(土建方提供),實(shí)行分段設(shè)點(diǎn)控制,再根據(jù)控制點(diǎn)投測(cè)到每根柱子及墻上,各控制層及標(biāo)高采用50m鋼卷尺進(jìn)行精確測(cè)量復(fù)核,在施工過(guò)程中,在每一翼第一層墻面的兩端以墻面控制點(diǎn),標(biāo)定水平控制點(diǎn)要特別注意,應(yīng)先定兩端點(diǎn),后定中間點(diǎn)),然后根據(jù)幕墻與墻面260㎜的間隙用水準(zhǔn)儀或用鋼絲標(biāo)定出水平控制線并在墻面彈出灰線。其余各樓層以此水平控制線為依據(jù)。分別測(cè)設(shè)。(4)、調(diào)節(jié)板快的設(shè)定:1)、水平方向,分別與四個(gè)大角包角鋁板相連玻璃為調(diào)節(jié)板塊。2)、垂直方向:以頂部鋁板為調(diào)節(jié)板塊。(5)、其它細(xì)節(jié)尺寸定位分格依據(jù)控制軸線,控制點(diǎn)、控制線及標(biāo)高采用鋼卷尺,水平儀進(jìn)行精確量距確定,并彈出墨線作好測(cè)量成果記錄。3、測(cè)量時(shí)應(yīng)注意的事項(xiàng)(1)、分格軸線的測(cè)量放線應(yīng)與主體結(jié)構(gòu)測(cè)量放線相配合,測(cè)量放線時(shí)應(yīng)控制分配誤差,不使誤差積累。水平標(biāo)高要逐層從地面引上,以免誤差累積。誤差大于規(guī)定的允許偏差時(shí),包括垂直偏差值,應(yīng)適當(dāng)調(diào)整幕墻的軸線,使其符合幕墻的構(gòu)造需要。(2)、測(cè)量檢驗(yàn)人員應(yīng)及時(shí)對(duì)測(cè)量放線情況進(jìn)行檢查,并將其查驗(yàn)情況填入記錄表。(3)、在測(cè)量放線的同時(shí),應(yīng)對(duì)預(yù)埋件的偏差進(jìn)行檢驗(yàn),其上、下、左、右偏差值不應(yīng)超過(guò)±45mm,超差的預(yù)埋件必須進(jìn)行適當(dāng)?shù)奶幚砗蠓娇蛇M(jìn)行安裝施工。(4)、檢驗(yàn)人員應(yīng)對(duì)預(yù)埋件的偏差情況進(jìn)行抽樣檢查,抽檢量應(yīng)為幕墻預(yù)埋件總數(shù)量的5%以上且不少于5件,所檢測(cè)點(diǎn)不合格數(shù)不超過(guò)10%,可判為合格。(5)、對(duì)于由橫豎桿件組成的幕墻骨架,一般先彈出豎向桿件的位置,然后再將豎向桿件的錨點(diǎn)確定。再將橫向桿件彈到豎向桿件上。第二節(jié)鋁板幕墻施工工藝打膠打膠測(cè)量放線預(yù)埋件位置檢驗(yàn)安放預(yù)埋件復(fù)測(cè)預(yù)埋件位置尺寸安裝固定角碼鍍鋅角碼加工鋼型材加工鋼型材安裝幕墻工程隱蔽驗(yàn)收安裝質(zhì)量驗(yàn)收防火棉安裝安裝質(zhì)量檢查防火棉安裝安裝質(zhì)量檢查鋁板安裝安裝質(zhì)量檢查清理1、幕墻鋁板安裝(1)、鋁板的加工:采用工廠制作。板的加應(yīng)在凈的門車間進(jìn)行加工的序主為鋁裁、刨和固。板儲(chǔ)存以0o傾斜置,板需厚木墊,才致于生彎現(xiàn)象搬運(yùn)時(shí)需人取,將面朝,切推,以擦傷板材切勿置重物或踏,防產(chǎn)彎曲凹陷現(xiàn)象。如果手工裁切,在裁切前先將工作臺(tái)清潔干凈,以免板材受損。(2)、鋁板與副框及加強(qiáng)筋的固定1)鋁板與副框及加強(qiáng)筋的固定。板材邊緣彎折以后,就要同副框固定成形,同時(shí)根據(jù)板材的性質(zhì)及具體分格尺寸的要求,在板材背面適當(dāng)?shù)奈恢迷O(shè)置加強(qiáng)筋。通常采用鋁合金方管作為加強(qiáng)筋。加強(qiáng)筋的數(shù)量要根據(jù)設(shè)計(jì)而定。一般情況下,當(dāng)板材的長(zhǎng)度小于1m時(shí)可設(shè)置一根加強(qiáng)筋:①當(dāng)板材的長(zhǎng)度小于2m時(shí)可設(shè)置2根加強(qiáng)筋;②當(dāng)板材的長(zhǎng)度大于2m時(shí),應(yīng)按設(shè)計(jì)要求增加加強(qiáng)筋的數(shù)量。2)、副框與板材的側(cè)面可用抽芯鋁鉚釘緊固,抽釘間距應(yīng)在250mm左右。①板的正面與副框的接觸面間由于不能用鉚釘緊固,所以要在副框與板材間用結(jié)構(gòu)膠粘接。②轉(zhuǎn)角處要用角碼將兩根副框連接牢固。③加強(qiáng)筋(鋁方管)與副框間也要用角碼連接緊固,加強(qiáng)筋與板材間要用結(jié)構(gòu)膠粘接牢固。3副框通常有兩種形狀組裝后應(yīng)將每塊板的對(duì)角接縫處用密封膠密封,防止?jié)B水。這里的鋁板組框中采用雙面膠帶,只適合于較低建筑的鋁板幕墻。對(duì)于高層建筑,副框及加強(qiáng)筋與鋁板正面接觸處必須采用結(jié)構(gòu)膠粘接,而不能采用雙面膠帶。(2)、鋁板安裝1)、安裝技術(shù)要求①鋁板須放置于干燥通風(fēng)處,并避免與電火花、油污及混凝土等腐蝕物質(zhì)接觸,以防板表面受損。②鋁板件搬運(yùn)時(shí)應(yīng)有保護(hù)措施,以免損壞鋁板。③注膠前,一定要用清潔劑將鋁板及鋁合金(型鋼)框表面清潔干凈,清潔后的材料須在1h內(nèi)密封,否則重新清洗。④密封膠須注滿,不能有空隙或氣泡。⑤清潔用擦布須及時(shí)更換以保持干凈。⑥應(yīng)遵守標(biāo)簽上的說(shuō)明使用溶劑,使用溶劑場(chǎng)所嚴(yán)禁煙火。⑦注膠之前,應(yīng)將密封條或防風(fēng)雨膠條安放于鋁板與鋁合金(鋼)型材之間。根據(jù)密封膠的使用說(shuō)明注膠寬度與注膠深度之最合適尺寸比率為2:1。注密封膠時(shí),應(yīng)用膠紙保護(hù)膠縫兩側(cè)的材料,使之不受污染。鋁板安裝完畢在易受污染部位用膠紙貼蓋或用塑料薄膜覆蓋保護(hù);易被劃碰的部位,應(yīng)設(shè)安全護(hù)欄保護(hù)。清潔中所使用的清潔劑應(yīng)對(duì)鋁板膠及鋁合(鋼型材料無(wú)任何腐蝕。2)、安裝施工要點(diǎn)鋁板與副框組合完成后,開(kāi)始在主體框架上進(jìn)行安裝。①鋁板幕墻的主體框架(鋁框)通常有兩種形狀。其中第一種副框與第二種主框都可搭配使用但第二種副框只能與第二種主框配合使用。②板間接縫寬度按設(shè)計(jì)而定,安裝板前要在豎框上拉出兩根通線,定好板間接縫的位置按線的位置安裝板材拉線時(shí)要使用彈性小的線,以保證板縫整齊。③副框與主框接觸處應(yīng)加設(shè)一層膠墊,不允許鋼性連接。如果采用第二種主框是將膠條安裝在兩邊的凹槽內(nèi),如果采用方管做主框,則應(yīng)交膠條粘接到主框上,當(dāng)采用第二種主框,在安裝時(shí)就將壓片及螺栓安裝到主框上了。螺栓的螺母端在主框中間的凹槽里。④板材定位以后,將壓片的兩腳插到板上副框的凹槽里,將壓片上的螺栓緊固就可以了。壓片的個(gè)數(shù)及間距要根據(jù)設(shè)計(jì)而定。⑤當(dāng)?shù)诙N副框與方管配合使用時(shí),鋁板定位以后,用自攻螺絲將壓片固定到主框上就可以了。當(dāng)采用第一種副框時(shí),主框必然是方管,副框與副框間采用搭接互壓的方式,用自攻螺絲將副框固定到主框上就可以了。⑥鋁板與板之間的縫隙一般為10~20mm,用硅酮密封膠或橡膠條等彈性材料封堵。在垂直接縫內(nèi)放置襯墊。在安裝時(shí),兩塊板之間有20mm的間隙,用一條擠壓成型的橡膠帶進(jìn)行密封處理。兩塊板用一塊5mm的鋁合金板壓住連接件的兩端,然后用螺絲擰緊。螺絲的間距300mm左右。第三節(jié)預(yù)埋件、轉(zhuǎn)接件和龍骨的制作和安裝施工方法幕墻與建筑主體結(jié)構(gòu)連接的埋件已在主體結(jié)構(gòu)施工過(guò)程中埋設(shè)完畢,并經(jīng)復(fù)測(cè)基本符合幕墻施工圖紙的要求。對(duì)于個(gè)別漏埋或埋錯(cuò)的埋件,必須采用后補(bǔ)。后不埋件的錨固件將采用定型化學(xué)(錨固)螺栓,作為設(shè)置連接件來(lái)替代預(yù)埋件。并要求通過(guò)威權(quán)檢測(cè)部門的現(xiàn)場(chǎng)抗拉拔試驗(yàn)?,F(xiàn)場(chǎng)后補(bǔ)埋件的有關(guān)規(guī)范要求:1、后埋件埋設(shè)方法后埋件的埋設(shè)螺桿與藥劑要充分混合,待強(qiáng)度達(dá)到要求時(shí),再將預(yù)埋板與螺桿連在一起,然后點(diǎn)焊螺母,防止松脫。(1)、材料錨板:8mm厚鍍鋅鋼板。錨固膠:錨固樹(shù)脂膠。錨筋:M12×160通長(zhǎng)螺桿,表面不得有銹斑、油污、漆點(diǎn)。每根螺桿配一個(gè)螺母、一個(gè)4mm厚限位鋼板。(2)、操作步驟用沖擊鉆在砼結(jié)構(gòu)上鉆Φ14mm的孔,孔深不小于115mm。用毛刷或風(fēng)筒將孔清理干凈,孔內(nèi)不得有余灰或積水。將藥劑包放進(jìn)孔內(nèi),并將螺桿插入孔中并輕輕旋轉(zhuǎn),使螺桿與膠充分接觸,等膠固化后將錨板罩在砼結(jié)構(gòu)面上。將每根螺桿套上4mm厚限位鋼板、螺母,將錨板固定在正確的位置。檢查錨板位置合適后,將4mm厚限位鋼板與錨板點(diǎn)焊,以防錨扳沿條孔移位。不允許對(duì)螺桿進(jìn)行焊接。(3)、注意事項(xiàng)1)、與錨扳相接的砼墻面應(yīng)平整,錨板安裝定位后表面應(yīng)豎直,以便錨板受壓時(shí)受力均勻。墻面如不平整需剔鑿?fù)可皾{。2)、為保證螺桿與砼之間的粘接力,要求孔內(nèi)清潔干凈,孔壁上不得有浮灰、積水、碎石。3)、為保證螺桿與藥劑之間的粘接力,要求螺桿表面無(wú)鍍鋅、無(wú)油漆、無(wú)銹斑污漬。4)、螺桿的錨固深度必須滿足要求,螺桿端頭伸出螺母5-7mm為宜。錨筋長(zhǎng)度在滿足以上兩點(diǎn)的前提下可根據(jù)現(xiàn)場(chǎng)情況調(diào)整。5)、緊固錨板、焊接定位鋼板需在藥劑完全固化后進(jìn)行,以防影響藥劑的性能。一般在30分鐘左右。6)、在插入螺桿時(shí),應(yīng)盡量使溢出的藥劑分布在錨板與砼墻面之間的縫隙內(nèi)。2、結(jié)構(gòu)與預(yù)埋件位置檢查及偏差處理方案(1)、結(jié)構(gòu)與預(yù)埋件位置檢查1)、在彈線放樣過(guò)程中,預(yù)埋件位置的檢查與結(jié)構(gòu)檢查的工作相繼展開(kāi),依據(jù)某一軸線為檢查起始點(diǎn),進(jìn)行預(yù)埋件位置與結(jié)構(gòu)的檢查,并記錄檢測(cè)結(jié)果。2)、對(duì)照預(yù)埋件的編號(hào)圖,依次逐個(gè)進(jìn)行檢查,將每一編號(hào)處的結(jié)構(gòu)偏差,與埋件的偏差值記錄下來(lái),提交反饋給設(shè)計(jì)進(jìn)行分析,對(duì)偏位>45mm以上埋件進(jìn)行補(bǔ)救措施,同時(shí)記錄結(jié)構(gòu)偏差大于設(shè)計(jì)標(biāo)準(zhǔn)的,請(qǐng)總承包單位配合進(jìn)行處理。3)若預(yù)埋件結(jié)構(gòu)偏差較大,已超出施工圖范圍或垂直度達(dá)不到國(guó)家和地方標(biāo)準(zhǔn)的,則應(yīng)將報(bào)告以及檢查數(shù)據(jù),呈報(bào)給業(yè)主、監(jiān)理、總包,并提出建議性方案供有關(guān)部門參考,待業(yè)主、監(jiān)理、設(shè)計(jì)同意后再進(jìn)行施工。4)若偏差在范圍內(nèi),則依據(jù)施工圖進(jìn)行施工。3、預(yù)埋件的偏差處理(1)、預(yù)埋件位置偏差過(guò)大或未預(yù)設(shè)埋件時(shí),應(yīng)制訂補(bǔ)救措施或可靠連接方案,經(jīng)與業(yè)主、土建設(shè)計(jì)單位洽商同意后,方可實(shí)施。當(dāng)預(yù)埋件偏差在45~150mm時(shí),應(yīng)采用與預(yù)埋件等厚度,同材料的鋼板,一端與預(yù)埋件焊接,依據(jù)設(shè)計(jì)要求進(jìn)行周邊焊,焊接質(zhì)量應(yīng)符合現(xiàn)行國(guó)家標(biāo)準(zhǔn)《鋼結(jié)構(gòu)工程施工及驗(yàn)收規(guī)范》,另一端采用設(shè)計(jì)所規(guī)定化學(xué)螺栓進(jìn)行固定。(2)、化學(xué)螺栓施工之前首先請(qǐng)監(jiān)理取樣,化學(xué)螺栓呈送有關(guān)部門做物理性能測(cè)試以及化學(xué)螺栓的拉拔試驗(yàn),待各項(xiàng)數(shù)據(jù)合格后進(jìn)行現(xiàn)場(chǎng)施工。(3)、預(yù)埋件表面沿垂直方向傾斜誤差大時(shí),應(yīng)采用厚度合適的鋼板墊平后焊牢,嚴(yán)禁用鋼筋等不規(guī)則金屬件作墊焊或搭接焊。(4)、因結(jié)構(gòu)向內(nèi)偏移引起支座長(zhǎng)度不夠,無(wú)法正常施工時(shí),則采用加長(zhǎng)支座的辦法解決,在預(yù)埋件上焊接鋼板或槽鋼加墊的方法解決。4、預(yù)埋件偏位采用化學(xué)螺栓錨固,但施工過(guò)程中必須嚴(yán)格按照廠家的標(biāo)準(zhǔn)要求進(jìn)行施工?;瘜W(xué)螺栓施工步驟及要求:安裝程序:鉆孔——清孔——置入藥劑管——鉆入螺栓——凝膠過(guò)程——硬化過(guò)程——固定物體。如下圖所示:化學(xué)螺栓施工流程示意圖1)、.確認(rèn)打化學(xué)螺栓位置,測(cè)量組進(jìn)行放樣。2)、施工人員按照定位十字線進(jìn)行打孔。3)、打孔深度,孔徑依據(jù)標(biāo)準(zhǔn)進(jìn)行。沖擊鉆上設(shè)立標(biāo)尺確??咨?。4)、打孔完畢吹清孔內(nèi)灰塵。5)、放入藥劑包。6)、.放入螺桿進(jìn)行攪拌,轉(zhuǎn)速為1400轉(zhuǎn)/分。7)、待孔口有少量混合物外露后即完成。8)、待30分鐘凝固后方能進(jìn)行施工安裝。第四節(jié)幕墻板塊制作、安裝及隱蔽驗(yàn)收1、玻璃板塊的制作該工程玻璃幕墻為框架式豎明橫隱玻璃幕墻。玻璃板塊的特點(diǎn)是:玻璃在鋁框外部,通過(guò)用硅酮結(jié)構(gòu)膠進(jìn)行鋁框和玻璃間的粘接結(jié)合。所有隱框玻璃幕墻的玻璃板塊必須加鋁合金托塊(包括隱框開(kāi)啟窗)。硅酮結(jié)構(gòu)膠的厚度與寬度通過(guò)計(jì)算取得,雙面貼膠條是臨時(shí)支撐玻璃待硅酮結(jié)構(gòu)膠固化,鋁框是與幕墻橫梁和立柱連接的重要構(gòu)件。(1)、玻璃質(zhì)量控制措施:①、鋼化玻璃應(yīng)符合規(guī)范要求。②、玻璃到貨后應(yīng)從外觀、性能要求、尺寸偏差等幾方面按照規(guī)范要求進(jìn)行檢驗(yàn)。不得有妨礙透視的污點(diǎn)。③、不合格不許使用,相應(yīng)做好記錄及歸類存放,不得與合格品混雜放置。④、檢查玻璃尺寸的偏差是否在允許偏差內(nèi)。⑤、檢查玻璃的產(chǎn)地證書(shū)、型號(hào)及厚度、狀態(tài)是否與訂貨合同相同。⑥、校對(duì)出廠合格證書(shū),物理性能檢測(cè)報(bào)告是否符合購(gòu)貨合同要求。(2)、結(jié)構(gòu)膠與耐侯膠:①、檢查膠的生產(chǎn)廠家、型號(hào)及規(guī)格、出廠合格證和性能報(bào)告是否與訂貨合同相同。②、檢查膠筒上的出廠日期及有效期是否在施工期內(nèi)用完,有無(wú)過(guò)期膠混入產(chǎn)品之中。(3)、膠縫處基材的清潔清潔是保證隱框幕墻板塊粘接力的關(guān)鍵工序,也是隱框幕墻的安全性、可靠性的主要技術(shù)措施之一。本工程采用二甲苯為清潔劑。清潔時(shí),將二甲苯倒在清潔布上,不得將清潔布蘸入二甲苯的容器中,應(yīng)順一個(gè)方向依次清洗;然后用第二塊干布擦去未揮發(fā)的溶劑,第二塊布臟了應(yīng)立即更換。清潔后30分鐘內(nèi)必須注膠,否則就要進(jìn)行第二次清潔。清潔后的表面,在搬運(yùn)時(shí)不要用手觸摸,要防止第二次污染。(4)、粘貼雙面貼膠條玻璃必須按設(shè)計(jì)位置固定在鋁框上,在平面內(nèi)鋁框與玻璃要按基準(zhǔn)線確定定位,定位采用定位夾具來(lái)確定其準(zhǔn)確位置,要求其偏差在±0.5mm以內(nèi)。鋁框安置完畢后,在其上粘貼雙面貼膠條。雙面貼膠條保證膠縫的厚度和寬度。雙面貼膠條厚度應(yīng)比膠縫計(jì)算厚度大1mm,因?yàn)榉胖貌AШ笥捎诓Aе亓磕z條被壓縮10%。粘貼雙面貼膠條時(shí),應(yīng)使膠條保持直線,用力下按使膠條貼緊鋁框,但手不能觸及粘膠面,因而在放玻璃前,不要撕下膠條的隔離紙,以防膠面被污染。玻璃放在雙面膠條上應(yīng)一次成功定位,不得來(lái)回移動(dòng)玻璃。否則不干膠粘在玻璃上將難以保證打注結(jié)構(gòu)膠后粘貼的牢固性。萬(wàn)一不干膠粘在玻璃面上,應(yīng)重新清潔。(5)、注膠幕墻玻璃板塊的硅酮結(jié)構(gòu)膠必須用機(jī)械注膠,注膠要順序進(jìn)行,以排出空隙內(nèi)的空氣,并要涂布均勻避免氣泡出現(xiàn)。注膠后用刮刀刮去多余的膠,并修光整平外露表面。(6)、靜置和養(yǎng)護(hù)注膠后的板塊應(yīng)在靜置場(chǎng)靜置養(yǎng)護(hù)。雙組份膠靜置3天后,單組份膠靜置7天后才能運(yùn)輸,所以要準(zhǔn)備足夠面積的靜置場(chǎng)地。靜置場(chǎng)地環(huán)境溫度為18℃~28℃,濕度為65~75%。否則會(huì)影響結(jié)構(gòu)膠的固化效果。靜置采用在架子上疊放,疊方時(shí)一般為4~7塊,每塊間必須防止四塊等邊立方體墊塊,墊塊采用泡沫塑料或其他彈性材料,其尺寸偏差不大于0.5mm,以免玻璃不平而壓碎。要判斷固化程度,可利用混膠時(shí)留下的切口實(shí)驗(yàn)樣品,切口膠體表面如果閃閃發(fā)光,非常平滑說(shuō)明尚未完全固化;反之切口表面平整、顏色發(fā)暗則說(shuō)明完全固化,可以搬運(yùn)。未完全固化的板塊不能搬運(yùn),以免粘接力下降。完全固化的板塊需繼續(xù)存放14~21天,使達(dá)到其粘接強(qiáng)度后才可以安裝施工。21天達(dá)到強(qiáng)度后,可用剝離試驗(yàn)檢驗(yàn)其粘接力,試驗(yàn)時(shí)拉住膠樣品一端,用刀在膠條中面切開(kāi)50mm,再用手拉住切口的膠條向后撕扯,如果沿膠體中撕開(kāi)則為合格;反之,如果在基材表面剝離,而膠體未破壞則說(shuō)明粘接力不足,這批材料不合格。2、玻璃板塊的安裝玻璃框在安裝前應(yīng)對(duì)玻璃及四周的鋁框進(jìn)行必要的清潔,保證嵌縫耐候膠能可靠粘結(jié)。安裝前玻璃的鍍膜面應(yīng)粘貼保護(hù)膜加以保護(hù),交工前再全部揭去。(1)、玻璃的品種、規(guī)格與色彩應(yīng)與設(shè)計(jì)要求相符,若有不符設(shè)計(jì)圖紙的現(xiàn)象,應(yīng)及時(shí)向有關(guān)部門反映,得到處理后方可安裝。(2)、玻璃框在安裝時(shí)應(yīng)注意保護(hù),避免碰撞、損傷或跌落;當(dāng)玻璃框面積較大或自身質(zhì)量較大時(shí),可采用機(jī)械安裝,或用真空吸盤提升安裝。(3)、玻璃幕墻組裝允許偏差及檢查方法應(yīng)符合有關(guān)規(guī)定。(4)、用于固定玻璃框的勾塊、壓塊或其他連接件,應(yīng)嚴(yán)格按設(shè)計(jì)要求或有關(guān)規(guī)范執(zhí)行,嚴(yán)禁少裝或不裝緊固螺釘。(5)、分格玻璃拼縫應(yīng)豎直橫平,縫寬均勻,并符合設(shè)計(jì)及偏差要求。每塊玻璃框初步定位后,應(yīng)與相鄰玻璃框進(jìn)行協(xié)調(diào),保證拼縫符合要求。對(duì)不符合要求的應(yīng)進(jìn)行調(diào)校修正,自檢合格后報(bào)質(zhì)檢人員進(jìn)行抽檢,每幅幕墻抽檢5%的分格,且不得小于5個(gè)分格。允許偏差項(xiàng)目中有80%抽檢實(shí)測(cè)值合格,其余抽檢實(shí)測(cè)值不影響安全和使用,則可判定為合格。抽檢合格后方可進(jìn)行固定和打耐候硅酮密封第五節(jié)幕墻的防火要求幕墻防火主要包括各樓層間、隔墻外沿和外墻保溫的防火。1、各樓層間該工程采用1.5㎜鍍鋅鐵皮封堵,內(nèi)填充100㎜厚防火巖棉,鍍鋅鐵皮與幕墻結(jié)構(gòu)和主體結(jié)構(gòu)間用密封膠封堵。2、外墻保溫采用燃燒性能達(dá)到A級(jí)的保溫材料。第六節(jié)幕墻防雷根據(jù)設(shè)計(jì)院提供的主體結(jié)構(gòu)避雷引下線及節(jié)點(diǎn),在混泥土澆筑前,采用Φ12mm鍍鋅圓鋼與避雷引下線的主筋焊接,并將鍍鋅圓鋼接至結(jié)構(gòu)外側(cè)。避雷引下線的焊接應(yīng)符合國(guó)家規(guī)范要求。幕墻避雷接地均勻連接,嚴(yán)格按照?qǐng)D紙?jiān)O(shè)計(jì)要求進(jìn)行焊接。1、幕墻工程防雷措施

防雷裝置有三部分:接閃器、引下線和接地裝置。在玻璃幕墻的防雷設(shè)計(jì)中,應(yīng)充分利用建筑物的這些裝置,將幕墻豎向龍骨、橫向龍骨和建筑物防雷網(wǎng)接通,連成一個(gè)防雷整體,把玻璃幕墻獲得的巨大雷電能量,通過(guò)建筑物的接地系統(tǒng),迅速地輸送到地下,保護(hù)玻璃幕墻和建筑物免遭雷電破壞的作用。

幕墻頂部的女兒墻的蓋板,是人為地設(shè)立的良好導(dǎo)體,它沿建筑物女兒墻的頂部分布,其電場(chǎng)強(qiáng)度很大。雷電先驅(qū)很自然地被吸引過(guò)來(lái),是雷擊率最大的部位。作為防止雷擊的直擊措施,可將蓋板設(shè)計(jì)成直接接受雷擊的裝置,起到引雷作用的接閃器。其作用在于接受雷電流,同時(shí)又安全地把雷電流與建筑物防雷網(wǎng)接通,并導(dǎo)通入地達(dá)到避雷作用。

幕玻璃墻頂部的接閃器,不能防止電流的側(cè)面橫向發(fā)展繞擊作用。目前防止側(cè)擊雷的常見(jiàn)做法是在30m以上的高層建筑玻璃幕墻部位,每三層設(shè)置一圈均壓環(huán),并和建筑物防雷網(wǎng)及玻璃幕墻自身的防雷體系接通。

2、玻璃幕墻的防雷接地要求及施工方法

根據(jù)有關(guān)防雷接地的技術(shù)資料并結(jié)合以往竣工工程的經(jīng)驗(yàn),我們認(rèn)為玻璃幕墻防雷必須在以下幾個(gè)重要方面滿足要求:

(1)玻璃幕墻的防雷設(shè)計(jì)應(yīng)符合現(xiàn)行國(guó)家標(biāo)準(zhǔn)《建筑物防雷設(shè)計(jì)規(guī)范》(GB500057-2000)的有關(guān)規(guī)定。

(2)引下線截面應(yīng)符合要求

玻璃幕墻豎向主龍骨應(yīng)視為引下線,豎向主龍骨的跨接用扁鋼制品時(shí)截面必須滿足要求。

(3)滿足機(jī)械強(qiáng)度的要求除焊接方式以外,采用壓接方式其金屬材料厚度應(yīng)達(dá)到4mm。

(4)采用焊接方式要滿足施工規(guī)范的要求

圓鋼搭接長(zhǎng)度為其直徑的6倍,且雙面施焊;扁鋼搭接長(zhǎng)度為其寬度的2倍,且三面施焊;焊接處做防腐處理。

(5)不同金屬壓接,要做防電化腐蝕處理。如:鋼與鋁連接時(shí),鋼要鍍錫;或在鋼、鋁之間加不銹鋼墊片。

(6)施工完成后,要有權(quán)威檢測(cè)機(jī)構(gòu)進(jìn)行檢測(cè),必須達(dá)到設(shè)計(jì)和規(guī)范要求的接地電阻值。

3、玻璃幕墻防雷接地的作法

該大廈地上15~27層,高91米,外墻使用玻璃幕墻及鋁單板板。下面說(shuō)明其玻璃幕墻防雷接地具體作法:

(1)、從十層開(kāi)始,每三層在建筑物四周結(jié)構(gòu)樓板表面敷設(shè)一根(Φ12)鍍鋅圓鋼,并與建筑物四周防雷引下線的引出鋼筋(Φ12)焊接,焊接長(zhǎng)度為圓鋼直徑的6倍,雙面施焊、焊接處刷兩道防銹漆(以后焊接處均刷兩道防銹漆),從而形成一道均壓環(huán)。為使玻璃幕墻豎向鋁合金主龍骨保持接地的貫通,用40×5鍍鋅扁鋼一端與均壓環(huán)焊接,焊接長(zhǎng)度應(yīng)為其寬度的2倍,并三面施焊,另一端用兩個(gè)M8不銹鋼對(duì)穿螺栓與豎向主龍骨進(jìn)行壓接,為防止鍍鋅扁鋼與鋁合金的電化學(xué)腐蝕,在其間加墊1mm厚不銹鋼墊片,并加不銹鋼平墊和彈簧墊。

(2)、所有豎向主龍骨的連接處采用40×5鋁合金制成的可伸縮的“歐姆彎”進(jìn)行壓接,連接處上下各用兩個(gè)M8不銹鋼對(duì)穿螺栓進(jìn)行壓接,并加不銹鋼平墊和彈簧墊。

(3)、設(shè)置均壓環(huán)的樓層所有豎向主龍骨與橫向龍骨的連接處,通過(guò)40×5鋁角碼兩端各用兩個(gè)M6不銹鋼對(duì)穿螺栓進(jìn)行壓接,并加不銹鋼平墊和彈簧墊。

(4)、幕墻頂部女兒墻的蓋板是起到引雷作用的接閃器。用φ12鍍鋅圓鋼沿女兒墻周圈安裝,并與主體結(jié)構(gòu)防雷引下線焊接。在蓋板內(nèi)側(cè)安裝40×4×4鍍鋅角鋼,每塊鋁板安裝兩段角鋼(每段長(zhǎng)300mm),兩段之間用φ12鍍鋅圓鋼焊接連通。并用φ12鍍鋅圓鋼一端與女兒墻頂φ12鍍鋅圓鋼焊接,另一端與角鋼焊接。每段角鋼與鋁板之間用四個(gè)M6×20不銹鋼自攻螺絲壓接(角鋼與鋁板之間加墊1mm厚不銹鋼墊片),并加不銹鋼平墊和彈簧墊。

總之,幕墻結(jié)構(gòu)應(yīng)自上而下與建筑物結(jié)構(gòu)的防雷裝置可靠連接。當(dāng)幕墻與屋面女兒墻平齊時(shí),其所有金屬主構(gòu)架必須與避雷帶(網(wǎng))進(jìn)行可靠連接,還必須與高層建筑的均壓環(huán)進(jìn)行可靠連接,在幕墻底部亦應(yīng)與防雷裝置連接。

4、通過(guò)實(shí)施上述的技術(shù)質(zhì)量安全措施,使玻璃幕墻與大廈的防雷系統(tǒng)成為一個(gè)整體,較好地完成了玻璃幕墻防雷系統(tǒng)的全部工作。后經(jīng)實(shí)地檢測(cè),在大廈設(shè)置的測(cè)試點(diǎn)實(shí)測(cè),接地電阻值均在0.4~0.8Ω之間,完全滿足設(shè)計(jì)(R≤1Ω)及規(guī)范要求。5、連廊鋼結(jié)構(gòu)由安裝資質(zhì)的企業(yè)施工。第七節(jié)節(jié)能隔熱、中空玻璃加工等技術(shù)措施1、節(jié)能隔熱技術(shù)措施影響幕墻門窗保溫節(jié)能的因素主要是門窗樞扇及玻璃,因此,我們希望框扇和玻璃能夠具有相同的抗風(fēng)強(qiáng)度、隔聲能力、熱阻抗能力和裝飾效果等。但是隨著玻璃工業(yè)的發(fā)展,應(yīng)用于門窗幕墻玻璃在熱工、光學(xué)性能上有了顯著的改善,這與框扇導(dǎo)熱系數(shù)過(guò)大而產(chǎn)生的熱橋(冷橋)現(xiàn)象形成很大的反差,從而促進(jìn)了門窗幕墻設(shè)計(jì)、制造廠家在型材斷面上不斷改進(jìn)和提高。

(1)、

幕墻及門窗框扇斷熱型材

在鋁合金型材斷面之中,使用熱橋(冷橋)技術(shù)使型材分為內(nèi)、外兩部,目前有兩種工藝:一種是注膠式斷熱技術(shù)(即澆注切橋技術(shù)),這種技術(shù)既可以生產(chǎn)對(duì)稱型斷熱型材,也可以生產(chǎn)非對(duì)稱型材。由于利用澆注式處理,流體填補(bǔ)成型空間原理,其成品精度可以達(dá)到非常高的要求。另一種是斷熱條嵌人技術(shù),就是采用由聚酞胺66加25%玻璃纖維(PA66GF25)合成斷熱條與鋁合金型材在外力擠壓下嵌合組成斷熱鋁型材。這種型材不僅強(qiáng)度高(接近鋁合金),而且它的性能主要是機(jī)械性能和隔熱性能。由于隔熱條的加人使型材形成多種斷面形式,有良好的強(qiáng)度,另外隔熱條中的玻璃纖維排列有序,能夠長(zhǎng)時(shí)問(wèn)承受高拉應(yīng)力和高剪切應(yīng)力,隔熱條的線形膨脹系數(shù)接近鋁,有非常好的加工性能;同時(shí)內(nèi)、外型材可以由不同顏色和表面處理方式的型材組成,增強(qiáng)了裝飾效果。并且可抗多種酸、堿化學(xué)物質(zhì)的腐蝕;另外可在200攝時(shí)度的氣氛中接受表面處理。隔熱條的主要規(guī)格有多種,所以可以廣泛地應(yīng)用。

2、玻璃的選用

現(xiàn)代建筑不但對(duì)建筑物適用性提出要求,而且對(duì)建筑物的采光節(jié)能性能提出更多的要求。在采用大面積玻璃門窗時(shí),對(duì)節(jié)能性能應(yīng)給予足夠的重視。從節(jié)能的要求考慮,門窗玻璃應(yīng)能夠控制太陽(yáng)輻射和黑體輻射。太陽(yáng)輻射分為紫外光、可見(jiàn)光、近紅外光,其能量主要集中在0.4-0.7μm。的可見(jiàn)光和0.7一2.5μm的近紅外光,分別占總太陽(yáng)輻射能量的43%和41%。我們?cè)谶@里所提的黑體輻射,通常講的就是溫度較高的物體散發(fā)的熱,如冬季暖氣設(shè)備發(fā)出的熱、溫?zé)岬膲Ρ诎l(fā)出的熱等。溫度越高的物體發(fā)出的熱量越大。也就是黑體輻射強(qiáng)度越高。在討論門窗玻璃的節(jié)能問(wèn)題時(shí),最大的黑體輻射源是取暖設(shè)備,另外還有周圍環(huán)境物體散發(fā)的熱最。黑體散發(fā)的熱除了稱作黑體輻射外,還稱作熱輻射、遠(yuǎn)紅外輻射,三者的含義相同。太陽(yáng)輻射一旦被物體吸收,就會(huì)改變輻射波長(zhǎng),變成熱輻射,所以進(jìn)人室內(nèi)的太陽(yáng)輻射會(huì)提高室溫。

(1)玻璃是如何節(jié)能的要使門窗玻璃達(dá)到最佳的節(jié)能效果,必須有效地控制太陽(yáng)能輻射和熱輻射,但是不同的地區(qū)、不同的季節(jié)有著不同的側(cè)面。在炎熱夏季的南方地區(qū),采用鍍膜玻璃有效地阻擋熾熱的太陽(yáng)能輻射,以減少降溫所消耗的空調(diào)費(fèi)用,熱反射鍍膜玻璃具有這種功能。在寒冷冬季的北方地區(qū),也采用鍍膜玻璃有效地阻擋室內(nèi)取暖設(shè)備發(fā)出的熱量通過(guò)玻璃門窗向室外泄漏,同時(shí)還要求把太陽(yáng)輻射能引人室內(nèi),低輻射鍍膜玻璃(簡(jiǎn)稱LOW一E玻璃)具有這種功能。還有一種折中的要求,即夏季要求有效地阻擋熾熱的太陽(yáng)能輻射,冬季要求有效地阻擋室內(nèi)取暖設(shè)備發(fā)出的熱量,某些透過(guò)率較低的低輻射鍍膜玻璃具有這種功能。對(duì)于中、低緯度地區(qū)夏季要求有效地阻擋熾熱的太陽(yáng)能輻射,冬季要求有效地阻擋室內(nèi)取暖設(shè)備發(fā)出的熱量,某些透過(guò)率較低的低輻射鍍膜玻璃具有這種功能,希望鍍膜玻璃在夏季主要起阻擋太陽(yáng)輻射及室外的熱輻射的作用,冬季主要起阻擋室內(nèi)熱輻射的作用,這種鍍膜玻璃不同于前面所述的典型的創(chuàng)反射鍍膜玻璃或低輻射膜玻璃,要求具有低輻射膜玻璃性能的基礎(chǔ)上兼顧熱反射鍍膜玻璃性能。在保留原有的低輻射膜層的前提下,通過(guò)改變其它膜層的厚度適當(dāng)降低太陽(yáng)光(特別是其中近紅外光)的透過(guò)率、提高太陽(yáng)光(特別是其中近紅外光)的反射,得到低輻射率、低遮陽(yáng)系數(shù)的鍍膜玻璃。如果選擇的適當(dāng),這種低輻射鍍膜玻璃的綜合節(jié)能效果相當(dāng)不錯(cuò)。

(2)中空玻璃玻璃占門窗面積的70%-80%左右,固此控制熱量和隔音便成為主要問(wèn)題,中空玻璃相比單層玻璃具有明顯的阻隔熱量的功能,中空層在A12時(shí),K值在3.5以下,因此中空玻璃的組成對(duì)節(jié)能效果的影響很大,如果中空層充氫氣和氟氣隔熱效果會(huì)更好。如果采用LOW-E中空玻璃將會(huì)大幅提高門窗的整體性能,中空玻璃另有一個(gè)顯著特點(diǎn)是防結(jié)露特性,不會(huì)在隔層出現(xiàn)露水,而且玻璃朝向室內(nèi)一側(cè)不易結(jié)露,中空玻璃的隔音效果也很好,一般情況下可降低噪音數(shù)十分貝。

綜上所述,我們可以看出只要解決好門窗幕墻型材斷熱問(wèn)題和選配玻璃的應(yīng)用,就能使它具有高強(qiáng)度、高氣密性、高水密性、高精度性、優(yōu)異的個(gè)隔熱、隔音性能。完全可以設(shè)計(jì)、制造出適應(yīng)保溫節(jié)能要求的門窗幕墻。第八節(jié)幕墻開(kāi)啟扇防墜、面板運(yùn)輸、安裝、清洗措施1、為了防止開(kāi)啟窗墜落,在安裝過(guò)程中要求室內(nèi)外都要有安裝人員同時(shí)進(jìn)行,室外的施工人員扶牢開(kāi)啟窗,室內(nèi)人員進(jìn)行固定,將緊固件上緊,同時(shí)在調(diào)試過(guò)程中,室外的施工人員也要時(shí)刻扶牢開(kāi)啟窗,直到調(diào)試禁錮完畢。同時(shí),在安裝的開(kāi)啟扇下方要有木板,防止墜落。2、面板運(yùn)輸可分為長(zhǎng)途和短途。長(zhǎng)途就是由生產(chǎn)廠家運(yùn)輸?shù)焦さ噩F(xiàn)場(chǎng),短途就是施工現(xiàn)場(chǎng)安裝過(guò)程中的搬運(yùn)。長(zhǎng)途運(yùn)輸要求:玻璃板塊完成后用木箱包裝,裝箱要規(guī)整,不歪斜,立靠裝箱,木箱四周用泡沫塞緊,板面相貼,間隔泡沫紙,框面相對(duì),封箱后成品在箱內(nèi)應(yīng)無(wú)竄動(dòng)或擠折,木箱須打鋼帶,便于吊運(yùn)也不易被碰壞。安裝過(guò)程中的搬運(yùn),要將洗盤用好,同時(shí)人員要足夠,同時(shí)要將施工現(xiàn)場(chǎng)的腳手架的架板放好放牢,做好安全防護(hù)工作。3、幕墻清洗:整體外裝工程,應(yīng)在施工完畢后,進(jìn)行一次室外全面徹底清洗,保證工程能圓滿達(dá)到竣工驗(yàn)收優(yōu)良等級(jí)。①清洗順序按照由上至下、先室后外的順序清洗。②清洗方法板塊清洗時(shí),用中性清洗劑,鋁合金型材用型材清洗劑,清洗劑間不能互相產(chǎn)生反應(yīng),不能錯(cuò)用,清洗前須先以清洗劑作檢查,證明對(duì)鋁合金無(wú)腐蝕作用之后方可使用,清洗后用清水沖洗干凈。③清洗時(shí)的注意安全事項(xiàng)清洗前做好工人安全技術(shù)交底;對(duì)清洗的輔助器械要做到安全可靠無(wú)故障,確保操作工人安全;遇大風(fēng)天(4級(jí)以上),雨天不進(jìn)行外墻清洗工作;外墻清洗時(shí),建筑物周圍設(shè)有警界線,防止閑雜人等入清洗范圍;高處清洗操作工人需配安全帶,工人安全帶須與牢固結(jié)構(gòu)相連接。第六章安全文明施工、消防及環(huán)保措施第一節(jié)施工現(xiàn)場(chǎng)安全管理1、堅(jiān)持“安全第一,預(yù)防為主”的安全施工方針,根據(jù)國(guó)家現(xiàn)行的《建筑施工安全檢查標(biāo)準(zhǔn)》要求,建立完整系統(tǒng)的安全管理體系,杜絕事故發(fā)生,確保安全生產(chǎn),實(shí)現(xiàn)安全施工達(dá)標(biāo)的管理目標(biāo)。參加施工的全體人員,必須樹(shù)立“安全第一,預(yù)防為主”和“安全為生產(chǎn),生產(chǎn)必須安全”的思想,從工程開(kāi)工到竣工,都必須嚴(yán)格執(zhí)行國(guó)家有關(guān)安全法規(guī)及集團(tuán)公司和建設(shè)單位的安全生產(chǎn)規(guī)章制度,必須認(rèn)真執(zhí)行企業(yè)的有關(guān)安全規(guī)定和要求,施工作業(yè)人員要按照集團(tuán)公司制定的《安裝工人安全技術(shù)操作規(guī)程》進(jìn)行施工作業(yè)。不違章作業(yè),消除一切事故。2、認(rèn)真貫徹“打防并舉,標(biāo)本兼治,重在治本”的綜治方針,切實(shí)搞好本項(xiàng)目現(xiàn)場(chǎng)社會(huì)治安綜治的管理,保障項(xiàng)目施工安全、有序、順利,根據(jù)本項(xiàng)目的特點(diǎn)和特定環(huán)境制定相應(yīng)的綜合治理目標(biāo)和保證措施,納入項(xiàng)目安全管理體系。3、作為項(xiàng)目安全管理體系內(nèi)容的環(huán)境保護(hù),項(xiàng)目部嚴(yán)格遵照市政府頒布的有關(guān)安全文明施工和環(huán)境保護(hù)的有關(guān)法規(guī)、規(guī)章執(zhí)行實(shí)施,切實(shí)抓好施工現(xiàn)場(chǎng)的文明衛(wèi)生和環(huán)境保護(hù)。4、現(xiàn)場(chǎng)建立安全消防領(lǐng)導(dǎo)小組,健全防火安全崗位責(zé)任制,項(xiàng)目負(fù)責(zé)人親自動(dòng)手抓,一級(jí)抓一級(jí),一級(jí)包一級(jí),一抓到底,層層落實(shí),全體動(dòng)員,把防火安全責(zé)任落到實(shí)處,杜絕火險(xiǎn)隱患。第二節(jié)安全保證措施1、建立以安全生產(chǎn)責(zé)任制為中心的安全管理制度,根據(jù)“管理生產(chǎn)必須管安全”、“安全生產(chǎn)人人有責(zé)”的原則,明確項(xiàng)目經(jīng)理各職能部門負(fù)責(zé)人、作為工長(zhǎng)和班長(zhǎng)在施工活動(dòng)中應(yīng)負(fù)的責(zé)任。2、項(xiàng)目經(jīng)理:認(rèn)真貫徹和國(guó)家有關(guān)安全生產(chǎn)的方針、政策、法規(guī)和企業(yè)安全生產(chǎn)的各項(xiàng)規(guī)章制度;嚴(yán)格執(zhí)行安全考核指標(biāo)和安全生產(chǎn)獎(jiǎng)懲辦法,嚴(yán)格執(zhí)行安全技術(shù)措施審批和施工安全技術(shù)措施交底制度,定期組織安全生產(chǎn)檢查和分析,針對(duì)可能產(chǎn)生的安全隱患制定相應(yīng)的預(yù)防措施。3、安全員:落實(shí)安全設(shè)施的設(shè)置;對(duì)施工全過(guò)程的安全進(jìn)行監(jiān)督,糾正違章作業(yè),配合有關(guān)部門排除安全隱患,組織安全教育和全員安全活動(dòng),監(jiān)督勞保用品的質(zhì)量和正確使用。4、班組長(zhǎng):向本工種作業(yè)人員進(jìn)行安全措施交底;嚴(yán)格執(zhí)行本工種安全技術(shù)操作規(guī)程,拒絕違章作業(yè);對(duì)本次作業(yè)所使用的機(jī)具、設(shè)備、防護(hù)用具及作業(yè)環(huán)境進(jìn)行安全檢查,消除安全隱患,組織班組開(kāi)展安全活動(dòng),召開(kāi)崗位安全生產(chǎn)會(huì),每周進(jìn)行安全講評(píng)。5、建立二級(jí)安全檢查制度。由企業(yè)安全生產(chǎn)監(jiān)察部門或項(xiàng)目經(jīng)理部對(duì)貫徹國(guó)家安全生產(chǎn)法律、法規(guī)的情況、安全生產(chǎn)情況、勞動(dòng)條件、事故隱患等進(jìn)行檢查,項(xiàng)目經(jīng)理定期對(duì)施工項(xiàng)目的安全生產(chǎn)責(zé)任制、安全保證計(jì)劃、安全組織機(jī)構(gòu)、安全組織機(jī)構(gòu)、安全保證措施、安全技術(shù)交底、安全教育、安全持證上崗、安全設(shè)施、安全標(biāo)識(shí)、操作行為、違章管理、安全紀(jì)錄進(jìn)行檢查,確保項(xiàng)目安全計(jì)劃的實(shí)施。6、安全生產(chǎn)實(shí)行總包負(fù)責(zé)制,對(duì)分包單位進(jìn)行統(tǒng)一領(lǐng)導(dǎo)、綜合管理。吸收分包單位負(fù)責(zé)人參加現(xiàn)場(chǎng)安全領(lǐng)導(dǎo)小組,統(tǒng)籌、協(xié)調(diào)、管理施工現(xiàn)場(chǎng)的安全管理,分包單位的安全管理工作須服從總包單位的監(jiān)督檢查。7、建立施工安全生產(chǎn)教育制度,定期對(duì)施工人員進(jìn)行安全知識(shí)、安全技能、設(shè)備性能、操作規(guī)程、安全法規(guī)的安全教育輪訓(xùn),對(duì)新技術(shù)、新工藝、新設(shè)備的采用和調(diào)換工作崗位時(shí),也要進(jìn)行安全教育,未經(jīng)安全教育培訓(xùn)的施工人員一律不得上崗操作。使全體施工人員真正認(rèn)識(shí)到安全施工的重要性和必然性,懂得安全生產(chǎn)和文明施工的科學(xué)知道,牢固樹(shù)立安全第一的思想,在施工中自覺(jué)遵守各項(xiàng)安全施工法律、法規(guī)和規(guī)章制度。8、認(rèn)真執(zhí)行安全技術(shù)交底制度,安全技術(shù)交底與施工技術(shù)交底同時(shí)進(jìn)行,由項(xiàng)目技術(shù)負(fù)責(zé)人將本施工項(xiàng)目的施工作業(yè)特點(diǎn)和危險(xiǎn)點(diǎn)及其危險(xiǎn)點(diǎn)的具體預(yù)防措施,應(yīng)注意的安全事項(xiàng),相應(yīng)的安全操作規(guī)程和標(biāo)準(zhǔn),發(fā)生事故后應(yīng)及時(shí)采取的應(yīng)急措施向安全員、施工班組長(zhǎng)和相關(guān)人員進(jìn)行全面詳細(xì)的安全技術(shù)交底,并保存交底雙方簽字確認(rèn)的安全技術(shù)交底記錄。第三節(jié)安全技術(shù)措施1、現(xiàn)場(chǎng)安全措施(1)、管理人員和施工人員進(jìn)入施工現(xiàn)場(chǎng)一律佩戴工作卡、無(wú)佩戴工作卡者一律不得進(jìn)入現(xiàn)場(chǎng)上崗施工。(2)、落入“三寶、四口”保護(hù)措施,頭戴安全帽,身穿工作服,高空作業(yè)系安全帶,并做到三緊:領(lǐng)口、袖口扣緊、衣下擺緊、腳穿合適軟底鞋的鞋帶緊,對(duì)電梯口、樓梯口、預(yù)留洞口、管道井口圍護(hù)設(shè)施,須驗(yàn)收合格和有明顯的警示標(biāo)志。(3)、施工現(xiàn)場(chǎng)嚴(yán)禁赤膊、赤腳、穿背心、穿拖鞋和穿高跟鞋。(4)、各項(xiàng)安全設(shè)施、防護(hù)裝置如確因施工工序而需要臨時(shí)拆除或移動(dòng)時(shí),必須以有關(guān)主管部門負(fù)責(zé)人批準(zhǔn)后方可拆除,在拆移時(shí)有安全監(jiān)護(hù),并采取相應(yīng)的防范措施。2、安全消防措施(1)、加強(qiáng)現(xiàn)場(chǎng)消防安全、綜合保衛(wèi)管理,建立義務(wù)消防隊(duì)員和定期進(jìn)行消防訓(xùn)練演習(xí)。配備專職治安保衛(wèi)人員。(2)、施工現(xiàn)場(chǎng)備足一定的消防器材,指定專人維護(hù)管理,定期更新,保持有效使用,并加強(qiáng)施工人員的消防安全教育,“應(yīng)知、應(yīng)會(huì)”消防器材。(3)、加強(qiáng)法制教育和精神文明教育,提高職工“知法、守法”的法制意識(shí),開(kāi)展有益身心、文明健康的娛樂(lè)活動(dòng),禁止聚眾賭博、酗酒斗毆等擾亂生產(chǎn)、工作、生活正常秩序的不良行業(yè)。配合公安部門搞好現(xiàn)場(chǎng)治安工作。3、文明施工、環(huán)境保護(hù)措施(1)、現(xiàn)場(chǎng)實(shí)行封閉施工。制定工地現(xiàn)場(chǎng)的環(huán)境衛(wèi)生制度,注重現(xiàn)場(chǎng)綠化,改善環(huán)境。(2)、施工現(xiàn)場(chǎng)的材料定場(chǎng)分類有序。(3)、保持做到施工“落手清”,工完場(chǎng)清,垃圾袋裝,集中運(yùn)至指定地點(diǎn),做到作業(yè)面無(wú)積存垃圾,無(wú)積存污水,無(wú)散落材料。(4)、嚴(yán)禁往電梯井、管道井傾倒垃圾和拋扔雜物。(5)、施工區(qū)派專人負(fù)責(zé)清理和打掃,保持場(chǎng)地整潔,道路暢通,確保門前墻外無(wú)垃圾、無(wú)建筑材料、無(wú)污水,無(wú)蟲(chóng)且少臭?,F(xiàn)場(chǎng)嚴(yán)禁大小便,在每個(gè)層樓面作業(yè)層設(shè)置小便桶,每天完工后由專人負(fù)責(zé)清運(yùn)。(6)、控制施工噪音,采取隔絕消聲措施,將施工噪音分貝控制在國(guó)家規(guī)定的范圍內(nèi)。4、施工現(xiàn)場(chǎng)防火措施施工中對(duì)火警隱患,嚴(yán)格控制火源和執(zhí)行動(dòng)火過(guò)程的安全焊接措施:(1)、電焊操作人員,須進(jìn)行專門培訓(xùn),掌握焊接安全技術(shù)、操作規(guī)程,經(jīng)考試取得合格證后方準(zhǔn)操作。徒工學(xué)習(xí)期間,須在師傅的監(jiān)護(hù)下進(jìn)行操作。(2)、嚴(yán)格執(zhí)行用火審批程序和制度。操作前須辦理用火申請(qǐng)手續(xù),經(jīng)單位領(lǐng)導(dǎo)同意和消防保衛(wèi)或安全技術(shù)部門批準(zhǔn),領(lǐng)用火許可證后方可進(jìn)行操作。(3)、進(jìn)行電焊前,應(yīng)由施工員或班組長(zhǎng)向操作,看火人員進(jìn)行消防安全技術(shù)措施交底,所有交、直流電的金屬外殼,都必須采取保護(hù)接地或接零,焊接的金屬設(shè)備、結(jié)構(gòu)本身要接地;任何領(lǐng)導(dǎo)不能以任何借口縱容焊工進(jìn)行冒險(xiǎn)作業(yè),焊接時(shí),必須設(shè)接火斗,防火看護(hù)人。(4)、裝過(guò)或有易燃、可燃液體、氣體及化學(xué)危險(xiǎn)品的容器、管道各設(shè)備,在未徹底清洗干凈前,不得進(jìn)行焊接。(5)、遇有五級(jí)以上大風(fēng)氣候時(shí),施工現(xiàn)場(chǎng)的高空各露天焊接作業(yè)應(yīng)停止,雨雪天后應(yīng)先清除施工地點(diǎn)的積水、積雪后方可施焊。(6)、領(lǐng)導(dǎo)及生產(chǎn)技術(shù)人員,要合理安排工藝和編排施工進(jìn)度程序,在有可燃材料保溫的部位,不準(zhǔn)進(jìn)行焊割接作業(yè)。必要時(shí),應(yīng)在工藝安排各施工方法上采取嚴(yán)格的防火措施。焊接作業(yè)不準(zhǔn)與油漆、噴漆、脫漆、木工等易燃操作同時(shí)間、同部位上下交叉作業(yè)。(7)、焊接結(jié)束或離開(kāi)操作現(xiàn)場(chǎng)時(shí),必須切斷電源、氣源。赤熱的焊嘴、焊鉗以及焊條頭等,禁止在易燃、易燃物品和可燃物上。(8)、禁止使用不合格的焊接工具設(shè)備。各種用電設(shè)備,照明設(shè)備在露天使用時(shí)時(shí)必須設(shè)有防水防雨措施,各種設(shè)備的防護(hù)罩必須齊全。電焊導(dǎo)線不能與裝有氣體的氣瓶接觸,也不能與氣焊的軟管或氣體的導(dǎo)管放在一起。(9)、焊接現(xiàn)場(chǎng)、臨時(shí)庫(kù)房須配備滅火器材,危險(xiǎn)性較大的應(yīng)有專人到現(xiàn)場(chǎng)監(jiān)護(hù)。(10)、看火(監(jiān)護(hù))人員作業(yè)指導(dǎo)書(shū):1)、清理焊接部位附近的易燃、可燃物品;對(duì)不能清除的易燃、可燃物品要用水澆濕或蓋上石棉布等非燃材料,以隔絕火星。2)、要堅(jiān)守崗位,不能兼顧其他工作,要與電焊地工密切配合,隨時(shí)注視焊接周圍的情況,一旦起火及時(shí)撲救。3)、在高空焊接時(shí),要用非燃材料做成接火盤和風(fēng)檔(即接火斗),以接住和控制火花的濺落。4)、在焊接過(guò)程中,要隨時(shí)進(jìn)行檢查,操作結(jié)束后,要對(duì)焊接地點(diǎn)進(jìn)行仔細(xì)檢查,確認(rèn)無(wú)危險(xiǎn)后方可離開(kāi)。在隱蔽場(chǎng)所或部位焊接操作完畢后,0.5至4小時(shí)內(nèi)要反復(fù)檢查,以防陰燃起火。5)、要根據(jù)情況,備好適用的滅火器材的防火設(shè)備(石棉布、接火盤、風(fēng)檔等),做好滅火設(shè)備。6)、發(fā)現(xiàn)電焊操作人員違反電焊防火管理規(guī)定、操作規(guī)程或動(dòng)火部位有火災(zāi)、爆炸危險(xiǎn)時(shí),有權(quán)責(zé)令停止操作,收回動(dòng)火許可證及操作證,并及時(shí)向領(lǐng)導(dǎo)或保衛(wèi)部門匯報(bào)。7)、沒(méi)有品牌的電氣設(shè)備不得隨意接通電源,各種電氣設(shè)備的出廠證,合格證應(yīng)齊全。8)、手電鉆、沖擊鉆、電動(dòng)改錐等電動(dòng)工具須作檢驗(yàn),檢驗(yàn)合格后方事使用。9)、施工現(xiàn)場(chǎng)嚴(yán)禁吸煙。10)、五級(jí)風(fēng)以上禁止動(dòng)電氣焊。(11)、電焊工的操作作業(yè)指導(dǎo)書(shū)。1)、焊工在操作前,要嚴(yán)格檢查所用工具(包括電焊機(jī)設(shè)備、線路敷設(shè)、電纜線的接點(diǎn)等),使用的均應(yīng)符合標(biāo)準(zhǔn),保持完好狀態(tài);2)、電焊機(jī)應(yīng)有單獨(dú)開(kāi)關(guān),裝在防火、防雨的閘箱內(nèi),電焊機(jī)設(shè)防雨棚(罩),開(kāi)關(guān)的保險(xiǎn)絲容量應(yīng)為該機(jī)的1.5倍,保險(xiǎn)絲不準(zhǔn)用銅絲或鐵絲代替;3)、焊接部位必須與氧氣瓶、乙炔瓶、乙炔發(fā)生器及各種易烯、可烯材料隔離,二瓶之間不得小于5mm,與明火之間不得小于10m。(12)、電焊機(jī)必須設(shè)有專用接地線,直接放在焊件上,接地線不準(zhǔn)接在建筑物,機(jī)械設(shè)備、各種管道,避雷引下線和金屬架上借路使用,防止接觸火花,造成起火事故。(13)、電焊機(jī)一、二次線應(yīng)用線鼻子壓接牢固,同時(shí)應(yīng)加裝防護(hù)罩,防止松動(dòng),短路放弧、引燃可燃物。(14)、嚴(yán)格執(zhí)行防火規(guī)定和操作規(guī)程,操作時(shí)采取相應(yīng)的措施,與看火人員密切配合,防止引起火災(zāi)。5、施工機(jī)械安全使用措施(1)、安裝幕墻用的施工機(jī)具在使用前進(jìn)行嚴(yán)格檢驗(yàn),包括各種安全保護(hù)裝置的運(yùn)轉(zhuǎn)試驗(yàn);手電鉆、電動(dòng)改錐、焊釘槍等電動(dòng)工具的絕緣電壓試驗(yàn);電焊機(jī)二次側(cè)把,地線需接長(zhǎng)使用時(shí),應(yīng)保證搭接面積,接點(diǎn)處用絕緣膠帶包裹好,地線良好不能有破皮裂口存在,手持玻璃吸盤和玻璃吸盤機(jī),須檢查吸附重量和作吸附持續(xù)時(shí)間試驗(yàn);(2)、在高層建筑幕墻安裝交叉作業(yè)時(shí),結(jié)構(gòu)施工層下方須安排人員看守并設(shè)有醒目的標(biāo)示牌;(3)、施工中的吊蘭應(yīng)安全、穩(wěn)定,能滿足施工應(yīng)承受的荷載與氣候條件,在荷載作用下不變形、傾斜,工作完后將吊籃離開(kāi)工作面2米以外;(4)、木制、鋼制及竹制跳板施工前都必須檢查,跳板本身有無(wú)不安全因素存在,如裂紋、殘邊等;(5)、橫桿卡扣要牢固,無(wú)松動(dòng),脫落,打滑等現(xiàn)象,與樓體拉線點(diǎn)要牢固;(6)、為了防止密封材料在施工中的溶劑中毒,對(duì)溶劑進(jìn)行嚴(yán)格的保管制度;(7)、施工人員進(jìn)入現(xiàn)場(chǎng),執(zhí)行地盤規(guī)章制度,執(zhí)行國(guó)家及地方有關(guān)建安條例;(8)、施工人員進(jìn)場(chǎng)施工必須服裝整齊統(tǒng)一,安全帽、安全帶、工具袋等勞保用品齊全,持證上網(wǎng),焊接操作人員在工作時(shí)應(yīng)穿戴好所有防護(hù)用具;(9)、工地材料須分類堆放整齊,并有相應(yīng)標(biāo)識(shí),產(chǎn)品不許直接接觸地面,底部應(yīng)墊高100mm,施工人員施工完后須清理施工現(xiàn)場(chǎng),避免材料損壞丟失;(10)、為減低施工對(duì)周圍環(huán)境的影響,物料在夜間進(jìn)場(chǎng),進(jìn)場(chǎng)施工盡量安排在白天進(jìn)行。定期進(jìn)行安全檢查,制定每天安全檢查范圍及如何防止使用工具落下方法:工具防止落下方法扳手小工具有繩栓在安全帶上重工具用繩子栓在結(jié)構(gòu)件上或腳手架上水平尺水平尺用繩子栓在結(jié)構(gòu)件上或腳手架上鐵筆用繩子栓在結(jié)構(gòu)件上或腳手架上槌子量度尺螺絲刀小工具有繩栓在安全帶上重工具用繩子栓在結(jié)構(gòu)件上或腳手架上延長(zhǎng)電線用繩子栓在結(jié)構(gòu)件上或腳手架上焊條將新焊條放在皮袋內(nèi),用完焊放入鐵罐內(nèi),以保持工地清潔。經(jīng)緯儀用繩子栓在結(jié)構(gòu)件上或腳手架上(11)、施工吊蘭安全使用措施詳見(jiàn)吊蘭施工方案(12)、高空作業(yè)安全及注意事項(xiàng)1)、安裝人員在進(jìn)入施工現(xiàn)場(chǎng)必須帶安全帽。要選擇合格產(chǎn)品,有檢驗(yàn)部門批量驗(yàn)證和工廠檢驗(yàn)合格證;施工人員進(jìn)入現(xiàn)場(chǎng)前必須檢查安全帽是否損壞,是否符合安全要求,施工人員帶安全帽時(shí)必須系好下額帶,以防發(fā)生高處墜落,帽飛人落的現(xiàn)象。2)、高空施工操作時(shí)必須系好安全帶。安全帶要選用合格產(chǎn)品,有廠家永久字樣的商標(biāo)及合格證。進(jìn)入現(xiàn)場(chǎng)必須檢查安全帶是否完好,安全帶必須掛在牢固結(jié)實(shí)的地方。3)、施工人員應(yīng)配置袋、工具箱、以防工具的掉落。工具用后放入工具袋、工具箱內(nèi)。施工中待用物料放置時(shí)距洞口及樓板沿水平距離1米以上。收工后,做到工完場(chǎng)清。4)、在高層建筑幕墻與上部結(jié)構(gòu)施工交叉作業(yè)時(shí),結(jié)構(gòu)施工層下方須總包單位挑出3米以上的防護(hù)裝置,如果架設(shè)安全網(wǎng)有困難,可采用其它有效方法,保證安全施工。第四節(jié)文明施工措施1、文明施工組織管理機(jī)構(gòu)文明施工組織管理,根據(jù)項(xiàng)目實(shí)際情況成立文明施工管理領(lǐng)導(dǎo)小組,由項(xiàng)目經(jīng)理任組長(zhǎng),項(xiàng)目副經(jīng)理任副組長(zhǎng),現(xiàn)場(chǎng)各部門部長(zhǎng)及后勤、保衛(wèi)責(zé)任人均為成員,文明施工的日常管理領(lǐng)導(dǎo)工作由組長(zhǎng)主持。2、現(xiàn)場(chǎng)文明施工措施要認(rèn)真貫徹執(zhí)行建設(shè)部的《建筑工地施工現(xiàn)場(chǎng)管理規(guī)定》及公司制定的有關(guān)文明工地標(biāo)準(zhǔn)。施工組織規(guī)劃中的文明施工要求是搞好文明施工管理的基本條件,以平面布置為基礎(chǔ),管理制度為依據(jù),責(zé)任到人,執(zhí)行到崗為保證,檢查考核為手段,管理好文明施工。(1)、循序作業(yè)按程序施工,作業(yè)順序合理,不因工序顛倒造成返工,浪費(fèi)和阻礙其它項(xiàng)目施工作業(yè),作業(yè)計(jì)劃明確,人員和機(jī)構(gòu)安排有條理,不混亂,不窩工。(2)、按圖用地大宗材料、設(shè)備、構(gòu)件、器具、臨時(shí)建筑設(shè)施,加工用地嚴(yán)格遵守施工平面布置圖的規(guī)定,道路及排水暢通,場(chǎng)地平整。(3)、現(xiàn)場(chǎng)容貌門面要莊重大方整齊,廣告宣傳標(biāo)語(yǔ)要寫醒目美觀。(4)、“一圖七牌”圖牌要齊全、規(guī)矩、醒目、懸掛在場(chǎng)內(nèi)明顯的位置。(5)、分區(qū)管理劃區(qū)管理,做到“落手清”現(xiàn)場(chǎng)著重管好“清理、回收、利用、歸庫(kù)”四個(gè)環(huán)世;工完、料凈、場(chǎng)清、各工序成品保護(hù)等工作要定期檢查及時(shí)評(píng)比。(6)、清潔衛(wèi)生工程作業(yè)場(chǎng)所、生產(chǎn)臨時(shí)設(shè)施(車間、庫(kù)房、機(jī)柵、辦公室、宿舍、浴室、廁

溫馨提示

  • 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
  • 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。

評(píng)論

0/150

提交評(píng)論