本文格式為Word版,下載可任意編輯——GIS安裝作業(yè)指導(dǎo)書
110kVGIS設(shè)備安裝作業(yè)指導(dǎo)書
批準(zhǔn):日期:年月日
審核:日期:年月日
日期:年月日
編寫:日期:年月日
中國能源建設(shè)集團(tuán)XX省電力建設(shè)第三工程公司
霞浦延亭風(fēng)電場工程土建施工及設(shè)備安裝調(diào)試工程項(xiàng)目部
年月日
1
目錄
一、二、三、四、五、六、七、八、
適用范圍······················································································1編制依據(jù)······················································································2作業(yè)流程:····················································································2工藝流程說明及主要質(zhì)量控制要點(diǎn)·····················································3危險點(diǎn)辨識及預(yù)控措施:·································································9工藝質(zhì)量要求:············································································10質(zhì)量通病防治措施:······································································12強(qiáng)制性條文:···············································································12
一、適用范圍
本作業(yè)指導(dǎo)書適用于霞浦延亭風(fēng)電場工程土建施工及設(shè)備安裝調(diào)試工程。
1
二、編制依據(jù)
序號12345678引用標(biāo)準(zhǔn)《電氣裝置安裝工程高壓電器施工及驗(yàn)收規(guī)范》GBJ147-90《電力建設(shè)施工質(zhì)量檢驗(yàn)及評定標(biāo)準(zhǔn)》DL/T5161.1-2023《國家電網(wǎng)公司輸變電工程標(biāo)準(zhǔn)工藝(三):工藝標(biāo)準(zhǔn)庫》《電力建設(shè)安全工作規(guī)程》(變電站部分)電氣裝置篇《電氣裝置安裝工程母線裝置施工及驗(yàn)收規(guī)范》GBJ149-90國家電網(wǎng)公司輸變電工程《施工工藝示范手冊》(變電工程分冊電氣部分)廠家說明書及出廠技術(shù)文件設(shè)計(jì)施工圖及工程施工質(zhì)量驗(yàn)收規(guī)范等,本工程項(xiàng)目部編制的《施工組織設(shè)計(jì)》、《創(chuàng)優(yōu)實(shí)施細(xì)則》、《質(zhì)量通病防治方案》及《強(qiáng)制性條文實(shí)施計(jì)劃》等有關(guān)施工指導(dǎo)文件。三、作業(yè)流程:
2
施工準(zhǔn)備土建驗(yàn)收、基礎(chǔ)復(fù)測設(shè)備組裝設(shè)備固定管道連接及其它附件安裝電纜敷設(shè)及二次接線真空處理、充SF6氣體設(shè)備調(diào)整現(xiàn)場檢查和試驗(yàn)質(zhì)量驗(yàn)收
圖3-1GIS安裝作業(yè)流程圖
四、工藝流程說明及主要質(zhì)量控制要點(diǎn)4.1作業(yè)準(zhǔn)備
4.1.1、人員配備
3
工序名稱設(shè)備吊裝及對接設(shè)備附件安裝抽真空、充SF6氣體工作人數(shù)5人4人2人負(fù)責(zé)人黃平華黃平華黃平華監(jiān)護(hù)人黃斌黃斌黃斌4.1.2、材料準(zhǔn)備
序號1材料及要求各類密封膠、涂于導(dǎo)體接觸面的電力復(fù)合脂、洗滌劑(乙醇、丙酮)、白棉布、擦拭紙、透明塑料薄膜4.1.3、主要工器具及儀器準(zhǔn)備
名稱汽車吊水平儀柔性吊帶撬棍扭力扳手開口、梅花扳手等各種形式緊固工具榔頭SF6氣體回收充氣裝置鋼卷尺抽真空泵干濕度計(jì)SF6密度表微量水份儀氣體檢漏儀卸扣鏈條葫蘆規(guī)格/型號25T大的5m3T3T單位輛把條把套套把臺個臺個個臺臺個個數(shù)量1223222121111144備注4.2、作業(yè)質(zhì)量要求
4.2.1GIS設(shè)備在運(yùn)輸和裝卸過程中不得倒置、傾翻、碰撞和受到猛烈的振動。
4.2.2充有六氟化硫等氣體的運(yùn)輸單元,應(yīng)按產(chǎn)品技術(shù)規(guī)定檢查壓力值,并做好記錄,有異常狀況時應(yīng)及時采取措施。
4.2.3設(shè)備基礎(chǔ)及預(yù)埋槽鋼的水平誤差,不應(yīng)超過產(chǎn)品的技術(shù)規(guī)定。
4.2.4設(shè)備安裝時,其相對濕度不允許超過80%;必需選擇晴好天氣,且風(fēng)速要小于3級。若遇下雨天或相對濕度超標(biāo)時阻止進(jìn)行開啟氣室的安裝工作,安裝現(xiàn)場與外界之間要設(shè)置圍欄,且應(yīng)控
4
作業(yè)活動危險點(diǎn)(危險源)操作、指揮人員的失誤,吊具、捆綁防范類型預(yù)控措施吊裝方式不符合要求,繩索、吊具缺陷或選擇錯誤。起重傷害1.作業(yè)由專人指揮,起重人員取證上崗。2、吊裝前檢查起重機(jī)具,不符合要求的全部更換。穩(wěn)盤必需配備足夠施工人員,以防傾倒傷人。電鉆、電設(shè)備安裝設(shè)備傾倒,與帶電體隔離不當(dāng)物體打擊觸電源線絕緣良好,開關(guān)靈活,配置漏電保護(hù)插臺,安裝后及時清理雜物,關(guān)閉電源開關(guān)。在運(yùn)行變電所安裝盤屏,嚴(yán)格執(zhí)行運(yùn)行單位規(guī)定,聽從運(yùn)行單位安全監(jiān)護(hù)人員指揮,帶電系統(tǒng)要設(shè)置明顯標(biāo)志,并采用可靠的隔離措施,設(shè)置警示標(biāo)志。充SF6氣體GIS就位對口六氟化硫氣體和其他氣體混放爆炸中毒防沙防潮六氟化硫氣體必需單獨(dú)存放,房間須有通風(fēng)口。風(fēng)沙潮氣選擇天氣晴朗天氣,施工前必需對場地進(jìn)行清潔。必要時設(shè)置防塵帳篷(對接前要保證各對接口無塵跡、水跡)六、工藝質(zhì)量要求:
工藝名稱組合電器安裝(1)組合電器地腳應(yīng)可靠固定。(2)電氣連接可靠,且接觸良好(3)組合電器及其傳動機(jī)構(gòu)的聯(lián)動(1)要求設(shè)備基礎(chǔ):相間標(biāo)高誤差,220kV以下≦2mm,220kV及以上≦5mm;同相標(biāo)高誤差≦2mm;同組間x,y軸線誤差≦1mm;地基表面,相鄰基礎(chǔ)埋件誤差≦2mm,全部基礎(chǔ)埋件誤差≦5mm.工藝標(biāo)準(zhǔn)施工要點(diǎn)例如圖片正常,無卡阻現(xiàn)象,(2)設(shè)備本體、母線組裝:分、合閘指示正確,1)部件裝配應(yīng)在無風(fēng)沙、無雨輔助開關(guān)及電氣閉鎖動作正確可靠。(4)支架及接地雪、空氣相對濕度小于80%的條件下進(jìn)行,并根據(jù)產(chǎn)品要求嚴(yán)格采取防塵、防潮措施。10
引線應(yīng)無銹蝕和損傷,接地良好。(5)電纜及二次接線排列整齊、美觀,固定與防護(hù)措施可靠,有條件時采用封閉橋架形式。(6)油漆應(yīng)完整,相色標(biāo)志正確。(7)組合電器的外套筒法蘭連接處應(yīng)做地線跨接。2)應(yīng)按制造廠的編號和規(guī)定的程序進(jìn)行裝配,不得混裝。3)各個氣室預(yù)充壓力檢查必需符合產(chǎn)品技術(shù)要求。4)應(yīng)對可見的觸頭連接、支撐絕緣件和盤式絕緣子進(jìn)行檢查,應(yīng)清潔無損傷。5)法蘭對接前應(yīng)先對法蘭面、密封槽及密封圈進(jìn)行檢查,法蘭對微弱傷痕可平整。密封面、密封圈用清潔無纖維袒露白布或不起毛的擦拭紙蘸無水酒精擦拭清白。密封圈應(yīng)確認(rèn)規(guī)格正確,然后在空氣一側(cè)均勻地涂密封劑,涂完密封劑應(yīng)馬上接口或蓋封板,并注意不得使密封劑流入密封圈內(nèi)側(cè)。面及密封槽應(yīng)光亮、無損傷,接地引線安裝(1)接地引線采用扁鋼時,應(yīng)經(jīng)熱鍍鋅防腐。(2)按產(chǎn)品要求接地引線與設(shè)備本體采用螺栓搭接,搭接面緊湊。(3)接地體橫平豎直,簡捷美觀。(4)接地引線地面以上部分應(yīng)采用黃綠接地漆標(biāo)識,接地漆的間隔寬度、順序一致。(5)按運(yùn)行要求設(shè)置試驗(yàn)接地端子(1)用于地面以上的鍍鋅扁鋼應(yīng)進(jìn)行必要的校直。(2)扁鋼彎曲時,應(yīng)采用機(jī)械冷彎,避免熱彎損壞鋅層。應(yīng)防腐。(4)接地引線顏色標(biāo)識應(yīng)符合規(guī)范。的接地點(diǎn)進(jìn)行接地,(3)焊接位置及鋅層破損處11
七、質(zhì)量通病防治措施:
表7-1質(zhì)量通病防治措施執(zhí)行狀況檢查表
工程名稱單位工程施工單位序號1234充油(氣)設(shè)備滲漏主要發(fā)生在法蘭連接處。安裝前應(yīng)詳細(xì)檢查密封圈材質(zhì)及法蘭面平整度是否滿足標(biāo)準(zhǔn)要求;螺栓緊固力矩應(yīng)滿足廠家說明書要求。在設(shè)備支柱上配置隔離開關(guān)機(jī)構(gòu)箱支架時,電(氣)焊不得造成設(shè)備支柱及機(jī)構(gòu)箱污染。為防止垂直拉桿脫扣,隔離開關(guān)垂直及水平拉桿連接處夾緊部位應(yīng)可靠緊固。在槽鋼或角鋼上采用螺栓固定設(shè)備時,槽鋼及角鋼內(nèi)側(cè)應(yīng)穿入與螺栓規(guī)格一致的楔形方平墊,不得使用圓平墊。充油設(shè)備套管使用硬導(dǎo)線連接時,套管端子不得受力。對設(shè)備安裝中的穿芯螺栓,要保證兩側(cè)螺栓露出長度一致。防治措施霞浦延亭風(fēng)電場工程土建施工及設(shè)備安裝調(diào)試工程。110kV屋內(nèi)配電裝置項(xiàng)目經(jīng)理執(zhí)行狀況56電氣設(shè)備聯(lián)接部件間銷針的開口角度不得小于60°。項(xiàng)目部質(zhì)檢員:年月日專業(yè)監(jiān)理工程師:年月日八、強(qiáng)制性條文:
12
表8-1強(qiáng)制性條文執(zhí)行狀況檢查表(總表)
工程名稱分部(子分部)工程名稱施工單位強(qiáng)制性條文內(nèi)容強(qiáng)制性條文內(nèi)容執(zhí)行要素執(zhí)行要素霞浦延亭風(fēng)電場工程土建施工及設(shè)備安裝調(diào)試工程。設(shè)備安裝單位(子單位)工程名稱分項(xiàng)工程名稱項(xiàng)目經(jīng)理執(zhí)行狀況執(zhí)行狀況110kV屋內(nèi)配電裝置相關(guān)資料相關(guān)資料《電氣裝置安裝工程電氣設(shè)備交接試驗(yàn)標(biāo)準(zhǔn)》(GB50150—2023)4.4.1在驗(yàn)收時,應(yīng)進(jìn)行以下檢查:聯(lián)動檢查報警值:閉鎖值:氣體壓力:斷路器試驗(yàn)報告編氣體含水量:號:斷路器安裝記錄編號:安裝記錄編號:密度繼電器試驗(yàn)報告編號:傳動記錄編號:三、斷路器及其操動機(jī)構(gòu)的聯(lián)動應(yīng)正常,分合閘動作檢查無卡阻現(xiàn)象;分、合閘指示正確;輔助開關(guān)動作正確可靠。四、密度繼電器的報警,閉鎖定值應(yīng)符合規(guī)定,電氣回路傳動正確。輔助開關(guān)動作報警值、閉鎖值電氣傳動氣體壓力五、六氟化硫氣體壓力、泄漏率和含水量應(yīng)符合規(guī)定斷路器氣體檢漏六、接地良好。3屋內(nèi)外配電裝置的金屬或鋼筋混凝土構(gòu)架以及靠近帶電部分的金屬遮欄和金屬門;12氣體絕緣全封閉組合電器(GIS)的外殼接地端子和箱式變電站的金屬箱體;3.3.5每個電氣裝置的接地應(yīng)以單獨(dú)的接地線與接地匯流排或接地干線相連接。嚴(yán)禁在一個接地線中串接幾個需要接地的電氣裝置。重要設(shè)備和設(shè)備構(gòu)架連接方式連接點(diǎn)材質(zhì)性能接地檢查接地檢查接地檢查氣體含水量接地檢查記錄編號:接地檢查記錄編號:接地檢查記錄編號:13
應(yīng)有兩根與主地網(wǎng)不同地點(diǎn)連接的接地引下線,且每根接地引下線均應(yīng)符合熱穩(wěn)定及機(jī)械強(qiáng)度的要求,連接引線應(yīng)便于定期進(jìn)行檢查測試。3.3.12發(fā)電廠、變電所電氣裝置以下部位應(yīng)專門敷設(shè)接地線直接與接地體或接地母線連接:2高壓配電裝置的金屬外殼;3110kV及以上鋼筋混凝土構(gòu)件支座上電氣設(shè)備金屬外殼;1測量主回
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 沈陽理工大學(xué)《面向?qū)ο蟪绦蛟O(shè)計(jì)》2022-2023學(xué)年期末試卷
- 沈陽理工大學(xué)《機(jī)械工程控制基礎(chǔ)》2022-2023學(xué)年期末試卷
- 沈陽理工大學(xué)《粉體材料科學(xué)基礎(chǔ)》2022-2023學(xué)年第一學(xué)期期末試卷
- 關(guān)于空氣維保合同的情況說明
- 國企購車合同范本
- 合同 能源管理方式
- 合同法937條原文內(nèi)容
- 2024不銹鋼制作合同范本產(chǎn)品制作合同范本
- 2024小區(qū)簡易房屋裝修合同范本
- 2024家庭裝修合同補(bǔ)充協(xié)議書范本
- 第三單元(知識清單)- 高二語文選擇性必修下冊同步備課系列(統(tǒng)編版)
- 機(jī)加工安全事故案例演示文稿
- 凱文杜蘭特-英語介紹
- 剖宮產(chǎn)術(shù)后再次妊娠陰道分娩管理的專家共識
- 最全的俄語教學(xué)課件
- 非招標(biāo)方式采購文件示范文本
- 改進(jìn)維持性血液透析患者貧血狀況PDCA
- 循證護(hù)理學(xué)(理論部分)智慧樹知到答案章節(jié)測試2023年復(fù)旦大學(xué)
- 醫(yī)院開展老年友善醫(yī)療機(jī)構(gòu)建設(shè)工作總結(jié)
- 餐飲檔口和門店消防安全培訓(xùn)
- D500-D505 2016年合訂本防雷與接地圖集
評論
0/150
提交評論