項目專項施工方案
高新數(shù)碼港四期(南區(qū))項目總承包工程
塔吊安拆施工方案
編制單位:中建八局第一建設(shè)有限公司
編制人:
編制時間:2023年6月20日
項目專項施工方案
目錄
第一章編制依據(jù).........................................................................................................................1
第二章工程概況.........................................................................................................................2
2.1工程建設(shè)概況表.......................................................................................................................2
2.2設(shè)計概況...................................................................................................................................2
2.3工程施工條件...........................................................................................................................5
2.4塔機附著概況...........................................................................................................................5
2.4.1塔機高度概況.....................................................................................................................5
2.4.2塔機附著立面圖.................................................................................................................6
2.4.3塔機附著形式概況...........................................................................................................11
第三章施工安排.......................................................................................................................14
3.1項目管理組織.........................................................................................................................14
3.1.1項目組織架構(gòu)圖.............................................................................................................14
3.1.2人員職責(zé).........................................................................................................................14
3.2項目管理目標(biāo).........................................................................................................................15
3.3各項資源供應(yīng)方式.................................................................................................................15
3.3.1勞務(wù)資源安排一覽表.....................................................................................................15
3.3.2大型機械設(shè)備采購供應(yīng)安排一覽表.............................................................................16
3.4施工流水段的劃分及施工工藝流程......................................................................................16
3.4.1施工流水段的劃分.........................................................................................................16
3.4.2施工工藝流程.................................................................................................................16
3.5工程施工重點和難點分析及應(yīng)對措施..................................................................................16
第四章施工進度計劃................................................................................................................16
第五章施工準(zhǔn)備及資源配置計劃.............................................................................................17
5.1施工準(zhǔn)備計劃.........................................................................................................................17
5.1.1技術(shù)準(zhǔn)備.........................................................................................................................17
5.1.2現(xiàn)場準(zhǔn)備.........................................................................................................................17
5.2資源配置計劃.........................................................................................................................18
5.2.1勞動力配置計劃.............................................................................................................18
5.2.2工程施工主要周轉(zhuǎn)材料配置計劃...................................................................................18
5.2.3施工機具配置計劃.........................................................................................................18
第六章施工方法及工藝要求.....................................................................................................19
項目專項施工方案
6.1方案及技術(shù)參數(shù).....................................................................................................................19
6.2塔吊安裝施工工藝流程..........................................................................................................23
6.3施工要點.................................................................................................................................23
6.3.1安裝前檢查.....................................................................................................................23
6.3.2塔吊安裝.........................................................................................................................25
6.3.3安裝后的自檢.................................................................................................................36
6.3.4電氣安裝與調(diào)試.............................................................................................................37
6.3.5安裝后的試車...................................................................................................................38
6.4安裝施工過程監(jiān)測.................................................................................................................40
6.5塔吊拆除.................................................................................................................................40
6.5.1塔吊拆除施工工藝流程.................................................................................................40
6.5.2塔吊拆除施工要點.........................................................................................................41
6.5.3拆除施工過程監(jiān)測.........................................................................................................45
6.6塔吊注意事項.........................................................................................................................45
6.6.1塔吊安裝注意事項.........................................................................................................45
6.6.2塔吊頂升注意事項.........................................................................................................47
6.6.3塔吊拆除注意事項.........................................................................................................48
6.6.4設(shè)備進出場安拆作業(yè)對場地和環(huán)境的要求.................................................................50
6.7驗收標(biāo)準(zhǔn).................................................................................................................................50
6.8驗收程序.................................................................................................................................52
6.9驗收內(nèi)容.................................................................................................................................53
6.10驗收人員...............................................................................................................................55
第七章進度管理計劃................................................................................................................56
7.1確定施工進度控制點.............................................................................................................56
7.2進度管理措施.........................................................................................................................56
7.3趕工措施.................................................................................................................................57
第八章質(zhì)量管理計劃................................................................................................................57
8.1項目質(zhì)量管理的組織機構(gòu)并明確職責(zé)..................................................................................57
8.2質(zhì)量要求.................................................................................................................................58
8.3現(xiàn)場質(zhì)量管理制度.................................................................................................................58
8.4質(zhì)量保證措施.........................................................................................................................59
第九章安全管理計劃................................................................................................................61
9.1職業(yè)健康安全管理分解目標(biāo)..................................................................................................61
9.2建立安全組織機構(gòu),明確安全職責(zé)和權(quán)限..........................................................................61
項目專項施工方案
9.3職業(yè)健康安全重大危險源......................................................................................................62
9.4職業(yè)健康安全資源配置計劃..................................................................................................63
9.5施工現(xiàn)場安全生產(chǎn)管理制度..................................................................................................63
9.6安全保證措施.........................................................................................................................64
第十章環(huán)境管理計劃................................................................................................................65
10.1環(huán)境管理目標(biāo).......................................................................................................................65
10.2環(huán)境管理職責(zé)分工...............................................................................................................65
10.3辨識重大環(huán)境因素...............................................................................................................65
10.4環(huán)境保護資源配置計劃........................................................................................................66
10.5施工環(huán)境保證措施...............................................................................................................66
第十一章綠色施工管理計劃.....................................................................................................66
11.1綠色施工職責(zé)分工...............................................................................................................66
11.2資源節(jié)約及利用計劃及保證措施........................................................................................67
11.3資源節(jié)約管理規(guī)章制度........................................................................................................67
第十二章成品保護管理計劃.....................................................................................................68
12.1成品保護職責(zé)分工...............................................................................................................68
12.2成品保護計劃及保證措施....................................................................................................68
第十三章?lián)P塵治理管理............................................................................................................68
13.1揚塵治理...............................................................................................................................68
13.1.1揚塵控制要點...............................................................................................................68
13.1.2具體控制措施...............................................................................................................69
13.2環(huán)境管控...............................................................................................................................70
13.2.1環(huán)境管理.......................................................................................................................70
13.2.2職業(yè)健康管理...............................................................................................................72
第十四章應(yīng)急預(yù)案....................................................................................................................73
14.1事故類型和危害程度分析....................................................................................................73
14.2組織機構(gòu)及職責(zé)分工...........................................................................................................73
14.3預(yù)防與預(yù)警...........................................................................................................................74
14.3.1危險源監(jiān)控和預(yù)防.......................................................................................................74
14.3.2預(yù)警行動.......................................................................................................................74
14.4信息報告程序.......................................................................................................................75
14.4.1電話報警.......................................................................................................................75
14.4.2現(xiàn)場疏導(dǎo)、自救...........................................................................................................75
項目專項施工方案
14.5應(yīng)急處置...............................................................................................................................75
14.5.1高空墜落事故...............................................................................................................75
14.5.2觸電事故.......................................................................................................................76
14.5.3物體打擊事故...............................................................................................................77
14.6傷亡事故的報告...................................................................................................................77
14.6.1搶救人員.......................................................................................................................77
14.6.2保護現(xiàn)場.......................................................................................................................77
14.6.3現(xiàn)場清理.......................................................................................................................78
14.7應(yīng)急物資準(zhǔn)備.......................................................................................................................78
14.8傷亡事故的處理...................................................................................................................78
14.9應(yīng)急聯(lián)絡(luò)...............................................................................................................................78
第十五章新冠肺炎疫情防控措施.............................................................................................79
15.1總體目標(biāo)...............................................................................................................................79
15.2組織管理...............................................................................................................................80
15.3工作要求...............................................................................................................................82
15.4施工中具體措施...................................................................................................................84
15.5上報制度與責(zé)任追究...........................................................................................................84
15.6新型冠狀病毒感染肺炎定點上報聯(lián)系醫(yī)院........................................................................85
項目專項施工方案
第一章編制依據(jù)
序號類別文件名稱編號
1《建設(shè)工程安全生產(chǎn)管理條例》國務(wù)院令第393號
中華人民共和國建設(shè)部
2《建筑起重機安全監(jiān)督管理規(guī)定》
令第166號
國家行政文件
中華人民共和國國務(wù)院
3《氣象災(zāi)害防御條例》
令第570號
4《危險性較大的分部分項工程安全管理規(guī)定》住建部令第37號
《建筑施工塔式起重機安裝、使用、拆卸安全
5JGJ196-2010
技術(shù)規(guī)程》
6《塔式起重機混凝土基礎(chǔ)工程技術(shù)標(biāo)準(zhǔn)》JGJ/T187-2023
7《塔式起重機安全規(guī)程》GB5144-2006
8《塔式起重機》GB/T5031-2023
9《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
10《建筑機械使用安全技術(shù)規(guī)程》JGJ33-2012
11國家行業(yè)規(guī)范T7020塔式起重機使用說明書/
12T7530塔式起重機使用說明書/
13TC6013塔式起重機使用說明書
50t汽車吊起重性能參數(shù)
1470t汽車吊起重性能參數(shù)/
220t汽車吊起重性能參數(shù)
鄭州高新數(shù)碼港(四期)U44-01地塊項目施工
15/
圖紙
16本項目巖土工程詳細(xì)勘察報告/
17技術(shù)質(zhì)量管理手冊2023版
企業(yè)文件
18安全施工管理手冊2023版
1/86
項目專項施工方案
第二章工程概況
2.1工程建設(shè)概況表
表2.1-1工程建設(shè)概況一覽表
工程名稱鄭州高新數(shù)碼港四期(南區(qū))
項目地點河南省鄭州市高新區(qū)瑞達路以西國槐街以南金梭路以東科學(xué)大道以北
建設(shè)單位河南正弘高新實業(yè)有限公司
設(shè)計單位中國電子工程設(shè)計院有限公司
監(jiān)理單位上海建科工程咨詢有限公司
施工單位中建八局第一建設(shè)有限公司
地下建筑面積約10.49萬平方米,地上建筑面積約15.52萬m2;包括6#商
建設(shè)規(guī)模
業(yè)裙樓、8#寫字樓、二期地下商業(yè)及地下車庫。
項目性質(zhì)商業(yè)辦公
施工范圍施工圖紙范圍內(nèi)建筑安裝施工
質(zhì)量目標(biāo)合格
安全文明目標(biāo)省級安全文明工地
2.2設(shè)計概況
塔吊起重性能表見表2.2-1。
表2.2-1塔吊性能表
塔機初始安裝
塔吊塔吊最終塔吊臂長起重臂
編號功率使用標(biāo)準(zhǔn)附著樓號
型號高度H0(m)(m)方向
(KW)節(jié)(個)
1#T70207850北67.91+136#商業(yè)
2#T70208455北67.91+156#商業(yè)
3#T753021165南82.51+178#塔樓
4#T70209170西67.91+156#商業(yè)
5#T70207860西67.91+136#商業(yè)
6#TC60134055東北391+106#商業(yè)
2/86
項目專項施工方案
圖2.2-1T7530起重特性表
3/86
項目專項施工方案
圖2.2-2T7020起重特性表
圖2.2-3TC6013起重特性表
4/86
項目專項施工方案
鄭州高新數(shù)碼港(四期)U44-01地塊項目塔吊覆蓋區(qū)域內(nèi)單體具體概況如表
2.2-2,塔吊平面布置圖見圖2.2-4。
表2.2-2各棟樓概況表
序號樓號概況備注
1#塔吊
2#塔吊
建筑層數(shù):地下3層,地上7層;地下室基礎(chǔ)頂至屋面最高構(gòu)
16#商業(yè)4#塔吊
筑物的高度為63.9m。
5#塔吊
6#塔吊
建筑層數(shù):地下3層,地上34層;地下室基礎(chǔ)頂至屋面最高
28#塔樓3#塔吊
構(gòu)筑物的高度為196.3m。
圖2.2-4塔吊平面布置圖
2.3工程施工條件
本工程運輸塔吊設(shè)備道路和下基坑道路已貫通,已配置塔吊運行的獨立二級配
電箱。塔吊安裝前基礎(chǔ)強度需達到設(shè)計強度的80%,使用時基礎(chǔ)強度需要達到設(shè)計
強度的100%。預(yù)埋件位置需預(yù)留正確,塔機預(yù)埋支腿水平度誤差不得超過2mm。
2.4塔機附著概況
2.4.1塔機高度概況
現(xiàn)場安裝塔機獨立高度無法滿足施工需要的,需要對塔機進行附著處理,具體
附著概況如表2.4-1所示:
5/86
項目專項施工方案
表2.4-1塔吊附著表
是否需要附
塔機編號塔機型號最終高度(m)獨立高度(m)附著形式
著
1#T70207860是耳板預(yù)埋
2#T70208460是耳板預(yù)埋
3#T753021160是耳板預(yù)埋
4#T70209160是耳板預(yù)埋
5#T70207860是耳板預(yù)埋
6#TC60134045否無
2.4.2塔機附著立面圖
11#T7020塔機附著立面圖
第一道附著
第13節(jié)標(biāo)準(zhǔn)節(jié)中心
60F以上827mm
0
0
8
7
附著道數(shù)標(biāo)準(zhǔn)節(jié)高度相對樓層高度
第一道附著第13節(jié)標(biāo)準(zhǔn)節(jié)中心6F以上827mm
21#T7020塔機附著平面圖(1#T7020附著梁柱為軸5交軸M的柱、軸5交軸
L的柱)
32#T7020塔機附著立面圖
6/86
項目專項施工方案
第一道附著
0第13節(jié)標(biāo)準(zhǔn)節(jié)中心
06F以上827mm
2
8
附著道數(shù)標(biāo)準(zhǔn)節(jié)高度相對樓層高度
第一道附著第13節(jié)標(biāo)準(zhǔn)節(jié)中心6F以上827mm
42#T7020塔機附著平面圖(2#T7020附著梁柱為軸13交軸L以北的柱,軸15
交軸L以北的柱)
54#T7020塔機附著立面圖
7/86
項目專項施工方案
0
0
0
1
9
附著道數(shù)標(biāo)準(zhǔn)節(jié)高度相對樓層高度
第一道附著第13節(jié)標(biāo)準(zhǔn)節(jié)中心6F以上827mm
64#T7020塔機附著平面圖(4#T7020附著梁柱為軸6交軸B的柱,軸7交軸
B東北的柱)
75#T7020塔機附著立面圖
8/86
項目專項施工方案
0
0
0
8
7
附著道數(shù)標(biāo)準(zhǔn)節(jié)高度相對樓層高度
第一道附著第13節(jié)標(biāo)準(zhǔn)節(jié)中心6F以上827mm
85#T7020塔機附著平面圖(5#T7020附著梁柱為軸17交軸A的柱,軸18交
軸A的柱)
93#T7530塔機附著立面圖
9/86
項目專項施工方案
附著道數(shù)標(biāo)準(zhǔn)節(jié)高度相對樓層高度
第一道附著第13節(jié)標(biāo)準(zhǔn)節(jié)中心6F以上300mm
第二道附著第23節(jié)標(biāo)準(zhǔn)節(jié)中心12F以上1600mm
第三道附著第33節(jié)標(biāo)準(zhǔn)節(jié)中心19F以上1830mm
第四道附著第43節(jié)標(biāo)準(zhǔn)節(jié)中心26F以上2431mm
第五道附著第53節(jié)標(biāo)準(zhǔn)節(jié)中心33F以上1928mm
第六道附著第58節(jié)標(biāo)準(zhǔn)節(jié)中心38F以上2641mm
10/86
項目專項施工方案
103#T7530塔機附著平面圖(3#T7530附著梁柱為軸28交軸M的柱,軸28
交軸L的柱)
116#TC6013的附著詳情
TC6013的最終安裝高度為40米,獨立高度滿足要求,無需附著。
2.4.3塔機附著形式概況
5臺塔機附著位置均在現(xiàn)澆柱上,附著形式為耳板預(yù)埋,塔身附著框采用桁架
結(jié)構(gòu),其材質(zhì)為Q345B,安裝尺寸為2*2m,具體結(jié)構(gòu)形式如圖2.4.3-1所示;拉桿
材質(zhì)為Q345B,截面尺寸為Ф194-8,焊接調(diào)節(jié)絲杠頭作為預(yù)埋件與塔身附著框的連
接,每道附著需三根拉桿,具體長度和拉桿張開角以實際為準(zhǔn),其結(jié)構(gòu)形式如圖
2.4.3-2所示。
此附著件安裝方式為預(yù)埋安裝,預(yù)埋件預(yù)埋三級螺紋鋼直徑要求為25mm,長度
不低于625mm。具體結(jié)構(gòu)形式見圖2.4.3-3,當(dāng)墻柱鋼筋綁扎完成后,應(yīng)將附著預(yù)
埋件安裝至合適位置并固定牢靠,安裝位置的墻柱鋼筋應(yīng)使用長500mm、直徑為25mm
的HRB400三級螺紋鋼進行橫豎向加密,橫向24根,上下四排,每排6根,間距
25mm,豎向16根,間距為125mm。待混凝土澆灌完成且強度達到要求時,可進行頂
升附著程序。其施工節(jié)點及配筋圖見圖2.4.3-4,2.4.3-5所示:
11/86
項目專項施工方案
圖2.4.3-1塔身附著框結(jié)構(gòu)形式
圖2.4.3-2拉桿結(jié)構(gòu)形式
圖2.4.3-3附著耳板示意圖
12/86
項目專項施工方案
加密鋼筋
圖2.4.3-4施工節(jié)點圖紙
圖2.4.3-5加密鋼筋配筋圖
13/86
項目專項施工方案
第三章施工安排
3.1項目管理組織
3.1.1項目組織架構(gòu)圖
塔吊安拆專業(yè)施工單位為山東中誠機械租賃有限公司,根據(jù)施工合同或協(xié)議的
要求,我單位對塔機安裝、運輸、拆卸全過程進行管理和監(jiān)控,確保質(zhì)量目標(biāo)、工
期目標(biāo)的實現(xiàn),確定如下組織機構(gòu)。
項目經(jīng)理
技術(shù)員安全員施工工長
塔機安拆班組
起重指揮塔機安拆工隊安裝電工汽車吊司機現(xiàn)場配合人員
圖3.1-1塔吊安拆施工項目部組織機構(gòu)圖
3.1.2人員職責(zé)
1)根據(jù)施工合同或協(xié)議的要求、對塔機安裝、運輸、拆卸全過程進行管理和
監(jiān)控,確保質(zhì)量目標(biāo)、工期目標(biāo)的實現(xiàn),確定如下組織機構(gòu),并明確分工職責(zé):
2)管理人員及班組分工職責(zé)
序號職務(wù)姓名工作職責(zé)
1項目經(jīng)理李煥全面負(fù)責(zé)項目管理工作。
1)施工方案的審核
2項目總工任景濤
2)組織現(xiàn)場的技術(shù)復(fù)核、驗收工作;
索亞楠1)施工方案編制;
3技術(shù)工程師
劉壯2)參加現(xiàn)場的技術(shù)復(fù)核、驗收工作。
1)總體施工進度計劃的安排;
2)施工現(xiàn)場平面管理;
陳長征
3)組織協(xié)調(diào)各專業(yè)隊伍和專業(yè)分包的現(xiàn)場管理;
4專業(yè)工程師王浩洋
3)負(fù)責(zé)施工過程控制,對施工過程中的質(zhì)量、安全、文明
梁光陰
施工、成品保護等負(fù)責(zé);
4)負(fù)責(zé)主要機械設(shè)備、周轉(zhuǎn)工具、勞務(wù)人員的計劃與調(diào)配。
1)參與危險源辨識、風(fēng)險評價與控制策劃,參與環(huán)境因素
的識別與評價;
5安全總監(jiān)賀嘉
2)定期進行監(jiān)測,發(fā)現(xiàn)問題下達整改通知單,并對整改情
況進行驗證。
14/86
項目專項施工方案
序號職務(wù)姓名工作職責(zé)
1)負(fù)責(zé)工程質(zhì)量的現(xiàn)場監(jiān)督檢查、質(zhì)量驗收;
2)發(fā)現(xiàn)嚴(yán)重不合格品及時報告項目總工,并負(fù)責(zé)處置后的
6質(zhì)量工程師谷天水
質(zhì)量驗收與評定;
3)質(zhì)量驗收文件的記錄與整理。
7班組負(fù)責(zé)人張亞男負(fù)責(zé)整個項目實施,保證工期、質(zhì)量安全處于受控狀態(tài)。
班組技術(shù)負(fù)
8張輝負(fù)責(zé)技術(shù)方案制定,確保方案的正確性,科學(xué)性和可行性。
責(zé)人
班組安全負(fù)落實安全責(zé)任制度,負(fù)責(zé)檢查,監(jiān)督現(xiàn)場人、機、物安全性、
9楊慶華
責(zé)人可靠性,制止違章作業(yè),消除可能存在的安全隱患。
負(fù)責(zé)現(xiàn)場的吊裝指揮;負(fù)責(zé)每日的工作安排,安全交底、工
10安裝負(fù)責(zé)人張步濤
作記錄,嚴(yán)格執(zhí)行施工方案,制止任何違章作業(yè)。
嚴(yán)守工作紀(jì)律,服從正確安排,正確使用勞保用品,防護齊
11起重工5人
全,
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 借款人與出質(zhì)人之間的合同
- 簡易個人分包合同
- 廢止采購合同
- 專業(yè)分包工程合同樣本
- 專業(yè)工程勘察招標(biāo)啟示
- 互聯(lián)網(wǎng)金融交易擔(dān)保協(xié)議
- 土工網(wǎng)帶采購合同
- 技術(shù)服務(wù)合同稅率動態(tài)
- 技術(shù)服務(wù)合同的技術(shù)改進費用標(biāo)準(zhǔn)
- 招標(biāo)文件價格詢價步驟
- 現(xiàn)代學(xué)徒制課題:數(shù)字化時代中國特色學(xué)徒制創(chuàng)新發(fā)展路徑研究(附:研究思路模板、可修改技術(shù)路線圖)
- GB 45067-2024特種設(shè)備重大事故隱患判定準(zhǔn)則
- 職業(yè)本科《大學(xué)英語》課程標(biāo)準(zhǔn)
- 東亞研究智慧樹知到期末考試答案章節(jié)答案2024年廣東外語外貿(mào)大學(xué)
- DB11T 489-2024 建筑基坑支護技術(shù)規(guī)程
- JTGT F20-2015 公路路面基層施工技術(shù)細(xì)則
- 三戰(zhàn)課件(輿論戰(zhàn)、法律戰(zhàn)、心理戰(zhàn))
- 小學(xué)二年級上冊美術(shù)期末試卷
- “一步法”煤基直接還原技術(shù)探討
- 道路運輸從業(yè)人員從業(yè)資格管理檔案轉(zhuǎn)籍申請表
- 加強員工隊伍建設(shè) 推動企業(yè)和諧發(fā)展
評論
0/150
提交評論