項(xiàng)目專項(xiàng)施工方案
青島中綠園項(xiàng)目
落地式腳手架專項(xiàng)施工方案(C類)
編制單位:中建八局第一建設(shè)有限公司
編制人:.
日期:2023年9月.
1
項(xiàng)目專項(xiàng)施工方案
目錄
1編制依據(jù)......................................................................................................................................................5
2工程概況......................................................................................................................................................5
2.1工程建設(shè)概況一覽表........................................................................................................................5
2.2設(shè)計(jì)概況..........................................................................................................................................6
2.2.1建筑設(shè)計(jì)概況..................................................................................................................................6
腳手架設(shè)計(jì)情況........................................................................................................................................8
2.3工程施工條件....................................................................................................................................9
3施工安排......................................................................................................................................................9
3.1項(xiàng)目管理組織....................................................................................................................................9
3.2項(xiàng)目管理目標(biāo)..................................................................................................................................11
3.3各項(xiàng)資源供應(yīng)方式..........................................................................................................................11
3.4施工流水段的劃分及施工工藝流程..............................................................................................11
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對措施..........................................................................................12
4施工進(jìn)度計(jì)劃............................................................................................................................................12
5施工準(zhǔn)備與資源配置計(jì)劃........................................................................................................................12
5.1施工準(zhǔn)備計(jì)劃..................................................................................................................................12
5.2資源配置計(jì)劃..................................................................................................................................13
6施工方法及工藝要求................................................................................................................................14
6.1方案及技術(shù)參數(shù).............................................................................................................................14
6.2施工工藝流程.................................................................................................................................16
6.3施工要點(diǎn).........................................................................................................................................16
6.3.1定距定位............................................................................................................................16
6.3.2場地平整............................................................................................................................16
6.3.3水平桿................................................................................................................................17
6.3.4腳手板................................................................................................................................17
6.3.5立桿....................................................................................................................................18
6.3.6連墻件................................................................................................................................18
6.3.7剪刀撐................................................................................................................................19
6.3.8欄桿、擋腳板及安全網(wǎng)設(shè)置............................................................................................20
6.3.9水平兜網(wǎng)............................................................................................................................20
6.3.10架體高差處做法................................................................................................................20
6.3.11施工安全通道....................................................................................................................21
6.3.12門洞通道............................................................................................................................21
6.3.13細(xì)部節(jié)點(diǎn)大樣....................................................................................................................22
6.3.14腳手架的拆除....................................................................................................................23
6.4驗(yàn)收標(biāo)準(zhǔn).........................................................................................................................................24
6.5驗(yàn)收程序.........................................................................................................................................24
6.6驗(yàn)收內(nèi)容.........................................................................................................................................25
6.7驗(yàn)收人員.........................................................................................................................................26
第七章各項(xiàng)管理計(jì)劃..................................................................................................................................26
7.1綠色施工管理計(jì)劃.........................................................................................................................26
7.1.1綠色施工組織機(jī)構(gòu)和職責(zé)分工..........................................................................................26
7.1.2資源利用管理制度..............................................................................................................27
7.1.3資源節(jié)約及利用計(jì)劃及保證措施......................................................................................27
2
項(xiàng)目專項(xiàng)施工方案
7.1.4環(huán)境管理目標(biāo)......................................................................................................................28
7.1.5環(huán)境管理組織機(jī)構(gòu)和職責(zé)分工..........................................................................................29
7.1.6重大環(huán)境因素清單..............................................................................................................29
7.1.7環(huán)境保護(hù)資源配置計(jì)劃......................................................................................................29
7.1.8環(huán)境保護(hù)措施......................................................................................................................29
7.1.9施工環(huán)境保證措施..............................................................................................................29
7.2進(jìn)度管理計(jì)劃.................................................................................................................................30
7.2.1確定施工進(jìn)度控制點(diǎn)..........................................................................................................30
7.2.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工..................................................................................30
7.2.3進(jìn)度管理措施......................................................................................................................30
7.3質(zhì)量管理計(jì)劃.................................................................................................................................31
7.3.1質(zhì)量控制目標(biāo)分解..............................................................................................................31
7.3.2質(zhì)量管理組織機(jī)構(gòu)及職責(zé)分工..........................................................................................31
7.3.3確定質(zhì)量控制點(diǎn)..................................................................................................................31
7.3.4現(xiàn)場質(zhì)量管理制度..............................................................................................................32
7.3.5質(zhì)量保證措施......................................................................................................................32
7.3.6腳手架檢查與驗(yàn)收..............................................................................................................33
7.4安全管理計(jì)劃.................................................................................................................................34
7.4.1職業(yè)健康安全管理分解目標(biāo)..............................................................................................34
7.4.2安全管理組織機(jī)構(gòu)和職責(zé)分工..........................................................................................34
7.4.3職業(yè)健康安全危險(xiǎn)源..........................................................................................................35
7.4.4職業(yè)健康安全資源配置計(jì)劃..............................................................................................36
7.4.5安全生產(chǎn)管理制度..............................................................................................................36
7.4.6安全生產(chǎn)保證措施..............................................................................................................37
7.5成品保護(hù)管理計(jì)劃.........................................................................................................................39
8應(yīng)急預(yù)案....................................................................................................................................................39
8.1事故類型和危害程度分析...............................................................................................................39
8.2組織機(jī)構(gòu)及職責(zé)...............................................................................................................................39
8.2.1應(yīng)急組織機(jī)構(gòu)......................................................................................................................39
8.2.2應(yīng)急小組職責(zé)........................................................................................................................40
8.3預(yù)防與預(yù)警.......................................................................................................................................40
8.3.1危險(xiǎn)源監(jiān)控............................................................................................................................40
8.3.2預(yù)警行動(dòng)..............................................................................................................................41
8.4信息報(bào)告程序...................................................................................................................................41
8.5應(yīng)急處置...........................................................................................................................................41
8.6防疫措施...........................................................................................................................................41
防疫指揮機(jī)構(gòu)及職責(zé)..................................................................................................................41
應(yīng)急響應(yīng)流程..............................................................................................................................43
入場人員管理措施......................................................................................................................43
日常工作防疫措施......................................................................................................................44
9計(jì)算書和相關(guān)圖紙....................................................................................................................................45
雙排扣件鋼管腳手架計(jì)算書..........................................................................................................................45
依據(jù)規(guī)范:........................................................................................................................................................45
計(jì)算參數(shù):........................................................................................................................................................45
一、小橫桿的計(jì)算:........................................................................................................................................45
3
項(xiàng)目專項(xiàng)施工方案
1.均布荷載值計(jì)算..................................................................................................................................46
2.抗彎強(qiáng)度計(jì)算......................................................................................................................................46
3.撓度計(jì)算..............................................................................................................................................46
二、大橫桿的計(jì)算:........................................................................................................................................47
1.荷載值計(jì)算..........................................................................................................................................47
2.抗彎強(qiáng)度計(jì)算......................................................................................................................................47
3.撓度計(jì)算..............................................................................................................................................47
三、扣件抗滑力的計(jì)算:................................................................................................................................48
四、腳手架荷載標(biāo)準(zhǔn)值:................................................................................................................................49
五、立桿的穩(wěn)定性計(jì)算:................................................................................................................................50
1.不考慮風(fēng)荷載時(shí),立桿的穩(wěn)定性計(jì)算................................................................................................50
2.考慮風(fēng)荷載時(shí),立桿的穩(wěn)定性計(jì)算....................................................................................................51
六、最大搭設(shè)高度的計(jì)算:............................................................................................................................52
七、連墻件的計(jì)算:........................................................................................................................................53
八、立桿的地基承載力計(jì)算:........................................................................................................................54
4
項(xiàng)目專項(xiàng)施工方案
1編制依據(jù)
序號類別文件名稱編號
1國家行中華人民共和國安全生產(chǎn)法國家主席令第88號
2政文件建設(shè)工程安全生產(chǎn)管理?xiàng)l例國務(wù)院令第393號
山東省人民政府令第
3山東省建筑安全生產(chǎn)管理規(guī)定(2018年)
地方行311號
政文件青島市人民政府令第
4青島市建筑工程文明施工管理若干規(guī)定
173號
5《建設(shè)工程項(xiàng)目管理規(guī)范》GB/T50326-2017
6《建筑工程綠色施工規(guī)范》GB/T50905-2014
7《建筑工程綠色施工評價(jià)標(biāo)準(zhǔn)》GB/T50640-2010
8《施工企業(yè)安全生產(chǎn)管理規(guī)范》GB50656-2011
9《建設(shè)工程施工現(xiàn)場消防安全技術(shù)規(guī)范》GB50720-2011
10《建筑施工安全技術(shù)統(tǒng)一規(guī)范》GB50870-2013
11《建筑變形測量規(guī)范》JGJ8-2016
12《施工現(xiàn)場臨時(shí)用電安全技術(shù)規(guī)范》JGJ46-2005
13《建筑施工腳手架安全技術(shù)統(tǒng)一標(biāo)準(zhǔn)》GB51210-2016
14國家行業(yè)《鋼管腳手架扣件》GB15831-2006
規(guī)范
15《木結(jié)構(gòu)設(shè)計(jì)標(biāo)準(zhǔn)》GB50005-2017
16《建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范》JGJ130-2011
17《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
18《施工企業(yè)安全生產(chǎn)評價(jià)標(biāo)準(zhǔn)》JGJ/T77-2010
19《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
20《建筑施工臨時(shí)支撐結(jié)構(gòu)技術(shù)規(guī)范》JGJ300-2013
住建部令【2018】37號
21《危險(xiǎn)性較大分部分項(xiàng)工程安全管理規(guī)定》
令
關(guān)于實(shí)施《危險(xiǎn)性較大分部分項(xiàng)工程安全管理
22建辦質(zhì)【2018】31號文
規(guī)定》有關(guān)問題的通知
地方規(guī)《山東省房屋市政施工危險(xiǎn)性較大分部分項(xiàng)魯建質(zhì)安字〔2018〕15
23
范標(biāo)準(zhǔn)工程安全管理實(shí)施細(xì)則》號
24合同青島中綠園項(xiàng)目總承包合同/
25青島中綠園項(xiàng)目施工藍(lán)圖/
其他
26PKPM安全技術(shù)軟件/
2工程概況
2.1工程建設(shè)概況一覽表
工程名稱青島中綠園項(xiàng)目工程性質(zhì)住宅
建設(shè)規(guī)模(造價(jià))40300萬元工程地址
5
項(xiàng)目專項(xiàng)施工方案
總占地面積47457m2總建筑面積164708.86㎡
主體結(jié)構(gòu)、裝飾裝修、
建設(shè)單位項(xiàng)目承包范圍屋面、外墻裝飾、機(jī)
電及水暖安裝等
設(shè)計(jì)單位主要分包工程幕墻、精裝修
勘察單位質(zhì)量青島市優(yōu)質(zhì)結(jié)構(gòu)
監(jiān)理單位工期757天
合同要求
山東省安全文明示
總承包單位安全
范工地
質(zhì)量監(jiān)督單位綠色施工/
工程主要功能或用途住宅樓、地下車庫及配套用房
2.2設(shè)計(jì)概況
2.2.1建筑設(shè)計(jì)概況
地下建筑面積46066.36㎡主樓建筑面積118642.5㎡裙房建筑面積/
地上2/23/24/26首層3.00m最大層高3.00m
層數(shù)地下1/2層層高標(biāo)準(zhǔn)層3.00m
防火等級一級/二級
裙樓/地下2.88m
圖2.2-1青島中綠園項(xiàng)目建筑平面總圖
6
項(xiàng)目專項(xiàng)施工方案
圖2.2-2標(biāo)準(zhǔn)層平面圖
7
項(xiàng)目專項(xiàng)施工方案
圖2.2-3建筑立面圖
腳手架設(shè)計(jì)情況
本工程落地外腳手架采用雙排扣件式鋼管腳手架,腳手架全部采用φ48.3×3.6mm
8
項(xiàng)目專項(xiàng)施工方案
的鋼管搭設(shè),操作層滿鋪木腳手板,外側(cè)懸掛綠色密目安全網(wǎng)。腳手架搭設(shè)尺寸:立桿
縱距1.5m,橫距0.9m,內(nèi)立桿距建筑物墻邊或懸挑板邊為0.30m,水平桿步距1.8m,立
桿縱距需結(jié)合立桿所在平面的縱向尺寸,進(jìn)行調(diào)整確定。
1、主樓外腳手架基礎(chǔ)位于地下車庫頂板處,
2、地下車庫頂板與框架梁施工時(shí)外腳手架基礎(chǔ)位于基礎(chǔ)筏板上
3、地下室外墻區(qū)域施工時(shí),外腳手架基礎(chǔ)位于基底土層上,基底土為中砂,地基承
載力大于180kpa。
2.3工程施工條件
1、現(xiàn)場臨時(shí)道路暢通,主干道已進(jìn)行硬化處理,可以保證運(yùn)輸車輛同行。
2、搭設(shè)腳手架所需的鋼管、扣件、安全網(wǎng)等材料進(jìn)場并經(jīng)檢驗(yàn)后確定合格后方可使
用。
3、腳手架搭設(shè)區(qū)域基礎(chǔ)硬化/整平完成,能夠滿足荷載要求。
3施工安排
3.1項(xiàng)目管理組織
序號崗位名稱姓名職責(zé)
1)認(rèn)真貫徹執(zhí)行相關(guān)環(huán)境法律、法規(guī)和各項(xiàng)規(guī)章制度,對本工程
安全施工及環(huán)境管理負(fù)責(zé);
2)組織項(xiàng)目總工、技術(shù)部、工程部、安全部、質(zhì)量部和物資部制
1項(xiàng)目經(jīng)理
定現(xiàn)場施工管理制度;
3)每周定期組織施工現(xiàn)場的施工管理情況進(jìn)行檢查;
4)組織項(xiàng)目部各部門迎接外部對項(xiàng)目現(xiàn)場施工的檢查。
1)全面負(fù)責(zé)項(xiàng)目安全施工及環(huán)境管理;
執(zhí)行項(xiàng)目經(jīng)
22)具體落實(shí)項(xiàng)目現(xiàn)場施工管理制度;
理
3)全面負(fù)責(zé)項(xiàng)目的外部迎檢工作。
1)負(fù)責(zé)施工組織、計(jì)劃落實(shí)、方案實(shí)施、工序控制和施工協(xié)調(diào)等。
2)進(jìn)行質(zhì)量、安全、環(huán)保等方面管理和配合協(xié)調(diào);完成施工前期
準(zhǔn)備工作。
3)負(fù)責(zé)項(xiàng)目施工技術(shù)管理、施工技術(shù)方案編制、圖紙會(huì)審和技術(shù)
核定。
3項(xiàng)目總工4)負(fù)責(zé)對分包施工方案的審定,材料設(shè)備的選型和審核,統(tǒng)籌分
包工程的設(shè)計(jì)變更和技術(shù)核定工作,參與相關(guān)分包商和供應(yīng)商的選
擇。
5)參與編制項(xiàng)目質(zhì)量計(jì)劃、項(xiàng)目職業(yè)健康安全管理計(jì)劃、環(huán)境管
理計(jì)劃,負(fù)責(zé)技術(shù)資料及影像資料的收集整理工作,與質(zhì)量管理部
門配合,參與項(xiàng)目階段交驗(yàn)和竣工交驗(yàn),共同負(fù)責(zé)工程創(chuàng)優(yōu)活動(dòng)。
1)負(fù)責(zé)項(xiàng)目預(yù)算成本的編制和成本控制工作。
2)負(fù)責(zé)本項(xiàng)目分包招標(biāo)文件的編制;負(fù)責(zé)分包商選擇工作;參與
4商務(wù)經(jīng)理
供應(yīng)商的選擇工作。
3)配合財(cái)務(wù)編制開支預(yù)算和資金計(jì)劃。
9
項(xiàng)目專項(xiàng)施工方案
4)負(fù)責(zé)與招標(biāo)人和分包人的結(jié)算工作,編制項(xiàng)目請款、分包付款
文件。
5)負(fù)責(zé)項(xiàng)目合同管理、造價(jià)確定以及二次經(jīng)營等事務(wù)的日常工作。
6)負(fù)責(zé)準(zhǔn)備竣工決算報(bào)告。
負(fù)責(zé)施工現(xiàn)場安全文明施工與進(jìn)度總管理,協(xié)調(diào)現(xiàn)場施工組織策劃,
5生產(chǎn)經(jīng)理
以及施工進(jìn)度、成本、質(zhì)量和安全控制等。
1)負(fù)責(zé)項(xiàng)目安全生產(chǎn)、文明施工和環(huán)境保護(hù)工作,對模板工程施
工進(jìn)行安全監(jiān)督和安全旁站。
2)負(fù)責(zé)編制項(xiàng)目職業(yè)健康安全管理計(jì)劃、環(huán)境管理計(jì)劃和管理制
度并監(jiān)督實(shí)施,制定員工安全培訓(xùn)計(jì)劃,并負(fù)責(zé)組織實(shí)施。
3)負(fù)責(zé)每周的安全生產(chǎn)例會(huì),定期和不定期組織安全生產(chǎn)和文明
施工檢查,加強(qiáng)安全監(jiān)督管理、消除施工現(xiàn)場安全隱患。
6安全總監(jiān)4)負(fù)責(zé)安全目標(biāo)的分解落實(shí)和安全生產(chǎn)責(zé)任制的考核評比。
5)負(fù)責(zé)項(xiàng)目安全應(yīng)急預(yù)案編制,進(jìn)行安全應(yīng)急演練,保證施工生
產(chǎn)的正常進(jìn)行。
6)負(fù)責(zé)對各專業(yè)項(xiàng)目部的安全監(jiān)督和管理工作,督促各專業(yè)項(xiàng)目
部作好安全防護(hù)工作,消除施工過程中的安全隱患,確保安全生產(chǎn)。
7)負(fù)責(zé)大型施工機(jī)械的維修保養(yǎng),確保施工機(jī)械使用正常。
8)負(fù)責(zé)施工現(xiàn)場及生活區(qū)消防隱患排查、消防器具維護(hù)工作。
1)負(fù)責(zé)工程質(zhì)量的現(xiàn)場監(jiān)督檢查和懸挑腳手架施工的質(zhì)量驗(yàn)收。
2)負(fù)責(zé)一般不合格品的處置,發(fā)現(xiàn)嚴(yán)重不合格品及時(shí)報(bào)告3)技術(shù)
7質(zhì)量總監(jiān)負(fù)責(zé)人,并負(fù)責(zé)處置后的質(zhì)量驗(yàn)收與評定。
4)對勞務(wù)分包和腳手架施工班組提出質(zhì)量獎(jiǎng)罰。
5)質(zhì)量驗(yàn)收文件的記錄與整理。
1)負(fù)責(zé)編制項(xiàng)目物資領(lǐng)用管理制度和日常管理工作。
2)負(fù)責(zé)物資進(jìn)出庫管理和倉儲管理。
3)負(fù)責(zé)對材料的標(biāo)識作統(tǒng)一策劃。
8物資工程師
4)負(fù)責(zé)監(jiān)督檢查所有進(jìn)場物資的質(zhì)量,協(xié)助做好技術(shù)資料的收集
整理工作。
5)具體負(fù)責(zé)竣工時(shí)庫存物資的善后處理。
1)負(fù)責(zé)現(xiàn)場施工組織、計(jì)劃落實(shí)、方案實(shí)施、工序控制和施工協(xié)
調(diào)等。
2)進(jìn)行質(zhì)量、安全、環(huán)保方面管理和配合協(xié)調(diào);完成施工前期準(zhǔn)
備工作。
3)負(fù)責(zé)項(xiàng)目施工技術(shù)管理、施工技術(shù)方案編制、圖紙會(huì)審和技術(shù)
核定。
9技術(shù)工程師4)負(fù)責(zé)對分包施工方案的審定,材料設(shè)備的選型和審核,統(tǒng)籌分
包工程的設(shè)計(jì)變更和技術(shù)核定工作,參與相關(guān)分包商和供應(yīng)商的選
擇。
5)參與編制項(xiàng)目質(zhì)量計(jì)劃、項(xiàng)目職業(yè)健康安全管理計(jì)劃、環(huán)境管
理計(jì)劃,負(fù)責(zé)技術(shù)資料及影像資料的收集整理工作,與質(zhì)量管理部
門配合,參與項(xiàng)目階段交驗(yàn)和竣工交驗(yàn),共同負(fù)責(zé)工程創(chuàng)優(yōu)活動(dòng)。
6)負(fù)責(zé)定位,測量,技術(shù)復(fù)核等工作。
1)對現(xiàn)場施工生產(chǎn)、進(jìn)度計(jì)劃全面負(fù)責(zé),確保工程施工順利進(jìn)行。
2)對工程各專業(yè)項(xiàng)目部之間的施工生產(chǎn)進(jìn)行協(xié)調(diào)。
3)負(fù)責(zé)各專業(yè)工種之間的協(xié)調(diào)及配合,制定各專業(yè)項(xiàng)目工期、質(zhì)
10專業(yè)工程師量、成本、安全文明施工等各項(xiàng)管理目標(biāo)、措施,并組織各專業(yè)日
常工作的落實(shí),組織各分項(xiàng)工程的施工、驗(yàn)收工作等,及時(shí)解決施
工中出現(xiàn)的各種問題。
4)現(xiàn)場勞務(wù)管理。
11試驗(yàn)工程師負(fù)責(zé)進(jìn)場材料的試驗(yàn)、檢驗(yàn)工作。
10
項(xiàng)目專項(xiàng)施工方案
1)收集整理施工技術(shù)資料。
12資料員2)實(shí)施腳手架施工的文件控制,負(fù)責(zé)腳手架施工過程的所有文件
的報(bào)批、收發(fā)、標(biāo)識、記錄、更改等。
3.2項(xiàng)目管理目標(biāo)
項(xiàng)目管理目標(biāo)名稱目標(biāo)值
工期
質(zhì)量目標(biāo)主控項(xiàng)目全部合格,一般項(xiàng)目符合要求
安全文明目標(biāo)不發(fā)生安全事故,符合安全文明施工要求
綠色施工目標(biāo)符合綠色施工要求
科技目標(biāo)/
3.3各項(xiàng)資源供應(yīng)方式
1)勞務(wù)資源安排一覽表
施工項(xiàng)目專業(yè)施工隊(duì)資質(zhì)開始施工分包分包商
建設(shè)工期責(zé)任人
名稱名稱要求時(shí)間方式選擇方式
落地腳手架林海勞務(wù)有限勞務(wù)分
一級100天公司選定
搭拆公司包
落地腳手架圣世元茂勞務(wù)勞務(wù)分
一級100天公司選定
搭拆有限公司包
2)施工周轉(zhuǎn)工具采購供應(yīng)安排一覽表
周轉(zhuǎn)工具名稱估計(jì)數(shù)量提供方式要求進(jìn)場時(shí)間計(jì)劃出場時(shí)間責(zé)任人
鋼管30dun租賃
扣件20000個(gè)租賃
安全網(wǎng)50000㎡采購
3.4施工流水段的劃分及施工工藝流程
1施工流水段的劃分
4#樓、12#樓、6#樓、5#樓、8#樓→1#樓、5#樓、9#樓、10#樓→2#樓、3#樓、7#樓、
13#樓、14#樓
11
項(xiàng)目專項(xiàng)施工方案
圖3.4施工分區(qū)示意圖
2施工工藝流程
場地平整、夯實(shí)→定位設(shè)置通長腳手板、底座→縱向掃地桿→立桿→橫向掃地桿→
小橫桿→大橫桿→剪刀撐→連墻件→鋪腳手板→扎防護(hù)欄桿→扎安全網(wǎng)。
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對措施
序重點(diǎn)和難
具體分析應(yīng)對措施責(zé)任人
號點(diǎn)
腳手架基必須保證腳手架基礎(chǔ)夯實(shí)的密
1保證基底土層夯實(shí)度,排水通暢
礎(chǔ)實(shí)度及平整度
外腳手架搭設(shè)屬于危險(xiǎn)性較大編制與實(shí)際工程密切相符的施工技
易發(fā)生的分項(xiàng)工程,在搭設(shè)過程中存術(shù)方案,腳手架搭設(shè)前對作業(yè)人員
2
安全事故在高空墜物、高處墜落、架進(jìn)行詳細(xì)的安全技術(shù)交底。
體坍塌等危險(xiǎn)源
1、明確連墻件布置形式及構(gòu)造要求,
連墻件設(shè)
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 文化場館防水修繕合同
- 郊區(qū)倉庫租賃協(xié)議
- 橋梁施工平地機(jī)租賃合同
- 高速公路修建施工合同
- 電影院彩繪施工合同
- 證券交易所安保人員聘用協(xié)議
- 建筑施工合同:城市地下管網(wǎng)改造
- 城市公寓交易合同模板
- 紀(jì)念館真石漆修復(fù)合同
- 北師版七年級數(shù)學(xué)上冊期末復(fù)習(xí)考點(diǎn) 清單04 基本平面圖形(12個(gè)考點(diǎn)梳理+題型解讀+提升訓(xùn)練)
- 儀式外包合同范例
- 物流運(yùn)輸雙氧水安全應(yīng)急預(yù)案
- 2025年上半年中科院大連化學(xué)物理研究所金催化研究中心(2302組)招聘1人易考易錯(cuò)模擬試題(共500題)試卷后附參考答案
- 【項(xiàng)目方案】合同能源托管模式下開展校園綜合能源建設(shè)方案-中教能研院
- 2024-2030年中國抗菌肽行業(yè)發(fā)展現(xiàn)狀及前景趨勢分析報(bào)告
- 功能科提高動(dòng)態(tài)心電圖檢查人次PDCA
- 氣球活動(dòng)布置合同范例
- 醫(yī)學(xué)綜合英語學(xué)習(xí)通超星期末考試答案章節(jié)答案2024年
- DB14-T2551-2022公路隧道缺陷與病害處治及驗(yàn)收技術(shù)規(guī)范
- 工業(yè)自動(dòng)化設(shè)備驗(yàn)收及實(shí)施方案
評論
0/150
提交評論