房建(F地塊)工程
地下室高大模板安全專項(xiàng)施工方案
(格式最終版)
編制單位:
編制人:
日期:
目錄
1編制依據(jù)........................................................................................................................1
2工程概況........................................................................................................................2
2.1工程建設(shè)概況一覽表.........................................................................................2
2.2設(shè)計(jì)概況.............................................................................................................2
2.3工程施工條件.....................................................................................................7
3施工安排........................................................................................................................8
3.1項(xiàng)目管理組織.....................................................................................................8
3.2項(xiàng)目管理目標(biāo)...................................................................................................10
3.3各項(xiàng)資源供應(yīng)方式...........................................................................................10
3.4施工流水段的劃分及施工工藝流程...............................................................11
3.4.1施工流水段的劃分................................................................................11
3.4.2施工工藝流程........................................................................................12
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施...........................................................13
3.6新技術(shù)應(yīng)用要求...............................................................................................14
3.7關(guān)鍵及特殊過程控制.......................................................................................14
4施工進(jìn)度計(jì)劃..............................................................................................................14
5施工準(zhǔn)備與資源配置計(jì)劃..........................................................................................15
5.1施工準(zhǔn)備計(jì)劃...................................................................................................15
5.1.1技術(shù)準(zhǔn)備................................................................................................15
5.1.2現(xiàn)場準(zhǔn)備................................................................................................16
5.2資源配置計(jì)劃...................................................................................................17
5.2.1勞動(dòng)力配置計(jì)劃....................................................................................17
5.2.2工程施工主要周轉(zhuǎn)材料配置計(jì)劃........................................................17
5.2.3施工機(jī)具配置計(jì)劃................................................................................17
5.2.4測量設(shè)備配置計(jì)劃................................................................................18
6施工方法及工藝要求..................................................................................................19
6.1方案及技術(shù)參數(shù)...............................................................................................19
6.1.1高大模板技術(shù)參數(shù)表............................................................................19
6.1.2墻、柱、梁工藝參數(shù)............................................................................25
6.1.3施工參數(shù)概述........................................................................................26
6.1.4架體工藝參數(shù)........................................................................................27
6.2施工工藝流程...................................................................................................28
6.2.1模板施工流程........................................................................................28
6.2.2安裝前的準(zhǔn)備工作................................................................................28
6.2.3墻模板安裝............................................................................................29
6.24柱模板安裝............................................................................................30
6.2.5梁、板模板安裝....................................................................................30
6.3施工要點(diǎn)...........................................................................................................32
6.3.1地下室外墻后澆帶模板設(shè)計(jì)................................................................32
6.3.2樓板、梁后澆帶模板設(shè)計(jì)....................................................................32
6.3.3梁柱接頭模板設(shè)計(jì)................................................................................33
6.3.4地下室外墻穿墻螺栓模板設(shè)計(jì)............................................................34
6.3.5混凝土澆筑............................................................................................34
6.3.6剪刀撐設(shè)置............................................................................................36
6.3.7架體監(jiān)測................................................................................................37
6.3.8模板拆除................................................................................................40
6.3.9安全管理與維護(hù)....................................................................................41
6.3.10冬季施工措施......................................................................................43
6.4驗(yàn)收標(biāo)準(zhǔn)...........................................................................................................45
6.5驗(yàn)收程序...........................................................................................................46
6.6驗(yàn)收內(nèi)容...........................................................................................................46
6.7驗(yàn)收人員...........................................................................................................47
7各項(xiàng)管理計(jì)劃..............................................................................................................47
7.1綠色施工管理計(jì)劃...........................................................................................47
7.1.1資源利用管理計(jì)劃................................................................................47
7.1.2環(huán)境管理計(jì)劃........................................................................................50
7.2進(jìn)度管理計(jì)劃...................................................................................................52
7.2.1確定施工進(jìn)度控制點(diǎn)............................................................................52
7.2.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工....................................................52
7.2.3進(jìn)度管理措施........................................................................................53
7.3質(zhì)量管理計(jì)劃...................................................................................................54
7.3.1質(zhì)量控制目標(biāo)分解................................................................................54
7.3.2質(zhì)量管理組織機(jī)構(gòu)及職責(zé)分工............................................................54
7.3.3確定質(zhì)量控制點(diǎn)....................................................................................55
7.3.4現(xiàn)場質(zhì)量管理制度................................................................................55
7.3.5質(zhì)量保證措施........................................................................................56
7.4安全管理計(jì)劃...................................................................................................61
7.4.1職業(yè)健康安全管理分解目標(biāo)................................................................61
7.4.2現(xiàn)場職業(yè)健康安全管理組織機(jī)構(gòu)和職責(zé)分工....................................61
7.4.3職業(yè)健康安全重大危險(xiǎn)源....................................................................62
7.4.4職業(yè)健康安全資源配置計(jì)劃................................................................63
7.4.5施工現(xiàn)場安全生產(chǎn)管理制度................................................................63
7.4.6安全生產(chǎn)保證措施................................................................................64
7.5成品保護(hù)管理計(jì)劃...........................................................................................68
7.5.1成品保護(hù)管理目標(biāo)................................................................................68
7.5.2成品保護(hù)管理組織和職責(zé)分工............................................................68
7.5.3成品和設(shè)備保護(hù)的管理制度................................................................69
7.5.4成品保證措施........................................................................................69
8應(yīng)急預(yù)案......................................................................................................................70
8.1事故類型和危害程度分析...............................................................................70
8.2組織機(jī)構(gòu)及職責(zé)分工.......................................................................................70
8.2.1應(yīng)急組織機(jī)構(gòu)........................................................................................70
8.2.2應(yīng)急小組職責(zé)分工................................................................................70
8.3預(yù)防與預(yù)警.......................................................................................................71
8.3.1危險(xiǎn)源監(jiān)控............................................................................................71
8.3.2預(yù)警行動(dòng)................................................................................................71
8.4信息報(bào)告程序...................................................................................................72
8.4.1事故報(bào)告原則........................................................................................72
8.4.2緊急通訊聯(lián)絡(luò)........................................................................................73
8.4.3事故報(bào)告程序........................................................................................73
8.4.4報(bào)告內(nèi)容................................................................................................73
8.5應(yīng)急處置...........................................................................................................73
8.5.1高處墜落現(xiàn)場處置措施........................................................................74
8.5.2物體打擊現(xiàn)場處置措施........................................................................74
8.5.3機(jī)械傷害事故的應(yīng)急預(yù)案....................................................................75
8.5.4發(fā)生的觸電事故的應(yīng)急預(yù)案................................................................75
8.5.5火災(zāi)、爆炸與爆燃事故發(fā)生的應(yīng)急預(yù)案............................................76
8.6應(yīng)急救援...........................................................................................................77
8.7應(yīng)急結(jié)束...........................................................................................................77
8.8后期處置...........................................................................................................78
8.9常態(tài)化疫情防控措施.......................................................................................78
9計(jì)算書和相關(guān)圖紙......................................................................................................78
9.1樓板模板支撐架體計(jì)算書...............................................................................79
9.2250x800梁底模板架體計(jì)算書........................................................................90
9.3250x1900梁底模板架體計(jì)算書....................................................................103
9.4250x800梁側(cè)模計(jì)算書..................................................................................117
9.5250x1900梁側(cè)模板計(jì)算書............................................................................123
9.6600x600柱模板計(jì)算書..................................................................................130
9.7800x800柱模板計(jì)算書..................................................................................138
9.8300厚墻體計(jì)算書..........................................................................................145
9.9深化設(shè)計(jì)圖紙.................................................................................................154
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
1編制依據(jù)
序號(hào)類別文件名稱編號(hào)
關(guān)于實(shí)施《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定》建辦質(zhì)〔2018〕
1
有關(guān)問題的通知31號(hào)
國家行政文住房和城鄉(xiāng)建設(shè)部令第
2《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定》
件37號(hào)
住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于印發(fā)《危險(xiǎn)性較大的分部分
3建辦質(zhì)〔2021〕48號(hào)
項(xiàng)工程專項(xiàng)施工方案編制指南》的通知
河南省第十三屆人民代表
4地方行政文《河南省安全生產(chǎn)條例》大會(huì)常務(wù)委員會(huì)第十次會(huì)
件議通過
5《河南省建筑工程施工質(zhì)量標(biāo)準(zhǔn)化管理實(shí)施辦法》豫建建[2014]114號(hào)
6《鋼管腳手架扣件》GB15831-2006
7《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2012
8《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范》(2015年版)GB50010-2010
9《工程測量標(biāo)準(zhǔn)》GB50026-2020
10《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50204-2015
11《建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)》GB50300-2013
12《混凝土結(jié)構(gòu)工程施工規(guī)范》GB50666-2011
13《建筑施工腳手架安全技術(shù)統(tǒng)一標(biāo)準(zhǔn)》GB51210-2016
14國家行業(yè)規(guī)《混凝土模板用膠合板》GB/T17656-2018
范
15《建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范》JGJ130-2011
16《建筑施工模板安全技術(shù)規(guī)范》JGJ162-2008
17《建筑施工臨時(shí)支撐結(jié)構(gòu)技術(shù)規(guī)范》JGJ300-2013
18《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
19《施工現(xiàn)場臨時(shí)用電安全技術(shù)規(guī)范》(附條文說明)JGJ46-2005
20《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
21《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
22《建筑工程冬期施工規(guī)程》JGJ/T104-2011
23團(tuán)體標(biāo)準(zhǔn)《建筑施工承插型輪扣式模板支架安全技術(shù)規(guī)程》T/CCIAT0003-2019
24招投標(biāo)文件湛河春天(F地塊)招投標(biāo)文件/
25合同湛河春天(F地塊)施工合同/
26設(shè)計(jì)文件湛河春天(F地塊)相關(guān)圖紙/
27企業(yè)技術(shù)標(biāo)建筑施工腳手架安全技術(shù)標(biāo)準(zhǔn)ZJQ08-SGJB003-2017
28準(zhǔn)模板及支架工程施工技術(shù)標(biāo)準(zhǔn)ZJQ08-SGJB011-2017
29企業(yè)文件《技術(shù)質(zhì)量管理手冊(cè)》2022版
1
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
30《安全施工管理手冊(cè)》2022版
31其他PKPM計(jì)算軟件V5.2版
2工程概況
2.1工程建設(shè)概況一覽表
工程名稱湛河春天(F地塊)工程性質(zhì)住宅
地下1層,地上2/10/11市湛河區(qū)長江路與嵩山路東南
建設(shè)規(guī)模工程地址
層角
總建筑面
總占地面積4.5萬㎡12.2萬㎡
積
項(xiàng)目承包土建、水暖、電氣、消防、電
建設(shè)單位
范圍梯、弱電、通風(fēng)工程
主要分包
設(shè)計(jì)單位無
工程
質(zhì)合格,確?!昂幽鲜≠|(zhì)量標(biāo)準(zhǔn)
勘察單位
合量化示范工地”
同工
監(jiān)理單位525日歷天
要期
中建x局第一建設(shè)有限公求安
總承包單位省級(jí)文明工地
司全
地下一層為車庫,地上為住宅(21#樓為物管用房和黨建活動(dòng)中心,35#
工程主要功能或用途
樓為辦公樓)
2.2設(shè)計(jì)概況
本工程共16棟單體,車庫層高4m,其中僅主樓地下一層層高超過5m,層高為
5.65m、5.45m,其中21#地下一層層高4.95m,架體采用輪扣式架體,根據(jù)規(guī)范要求超過
5m屬于超過一定規(guī)模的危險(xiǎn)性較大的分部分項(xiàng)工程,本工程僅18#、19#、20#、22#、
23#、25#、26#、27#、28#、29#、30#、31#、32#、33#、34#、35#樓地下一層屬于超過
一定規(guī)模的危險(xiǎn)性較大的分部分項(xiàng)工程,地下室及車庫梁板不存在高支模。
本工程主要采用φ48.3x3.6mm輪扣式立桿,橫桿采用φ48.3x3.0mm橫桿,主龍骨采
永直徑48.3x3.6mm厚鋼管,背楞及次龍骨采用40x40x1.5mm方鋼管和40x60mm方木。
2
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
圖2.2-1高支模區(qū)域分布圖
表2.2-1高大模板結(jié)構(gòu)概況情況一覽表
板厚支撐地基/基
部位/區(qū)域?qū)痈適長度×寬度m梁截面長×寬mm
mm礎(chǔ)
200×450、200×400、
18#、22#樓5.4543.6×16.9180筏板
200×550、250×1700
250×800、250×1700、
19#樓5.4560×15.8200×450、200×500、180筏板
200×800
200×400、200×450、
20#、26#、
5.4557.6×15200×500、200×550、180筏板
27#、30#
250×1700
200×600、200×450、
23#、25#、
5.6530×15.8200×400、200×500、180筏板
28#、29#
250×1900
200×400、200×500、
31#樓5.6543.6×12.8180筏板
200×450、250×1900
200×600、200×400、
32#、33#樓5.6550.5×15180筏板
200×450、250×1900
200×450、200×400、
35#樓5.6543.6×22.2200×500、200×600、180筏板
250×1900
3
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
圖2.2-218#、22#樓平、剖面圖
圖2.2-319#樓平、剖圖
4
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
圖2.2-420#、26#、27#、30#樓平、剖面布置圖
圖2.2-523#、25#、28#、29#樓平、剖面布置圖
5
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
圖2.2-631#樓平、剖面布置圖
圖2.2-732#、33#樓平、剖面布置圖
6
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
圖2.2-835#樓平、剖面布置圖
2.3工程施工條件
本工程位于xx湛河區(qū)長江路與嵩山路東南角,基坑已采用土釘墻支護(hù),坡頂為場區(qū)
環(huán)形硬化道路,周圍空曠,無建筑物構(gòu)造物,地下無管線,場區(qū)道路通暢,高支模區(qū)域
內(nèi)筏板具備澆筑條件,澆筑后達(dá)到一定強(qiáng)度后即可進(jìn)行高支模施工,現(xiàn)場設(shè)置4個(gè)材料
堆場,足夠周轉(zhuǎn)材料堆放轉(zhuǎn)運(yùn),共設(shè)置7臺(tái)塔吊,材料轉(zhuǎn)運(yùn)快捷方便,高支模區(qū)域場內(nèi)
道路通暢,混凝土采用汽車泵澆筑,無需布置布料機(jī)。
周轉(zhuǎn)料具由勞務(wù)自行提供,項(xiàng)目部在進(jìn)場時(shí)監(jiān)督周轉(zhuǎn)料具規(guī)格、尺寸,是否滿足規(guī)
范要求。進(jìn)場前先由勞務(wù)對(duì)材料樣品并報(bào)送項(xiàng)目部進(jìn)行驗(yàn)收,驗(yàn)收通過后方可大批量進(jìn)
場施工。
7
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
圖2.3-1現(xiàn)場平面布置圖
3施工安排
3.1項(xiàng)目管理組織
項(xiàng)目經(jīng)理
項(xiàng)目總工商務(wù)經(jīng)理安全總監(jiān)生產(chǎn)經(jīng)理質(zhì)量總監(jiān)
技商安工質(zhì)
術(shù)務(wù)全程量
部部部部部
圖3.1-1組織架構(gòu)圖
表3.1-1項(xiàng)目組織機(jī)構(gòu)職責(zé)分工
8
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
序號(hào)部門管理職務(wù)姓名職責(zé)和權(quán)限
1)現(xiàn)場總指揮,負(fù)責(zé)施工過程中對(duì)整個(gè)工程實(shí)施綜合協(xié)調(diào)
和管理,明確小組分工和職責(zé),責(zé)任到人。
2)對(duì)現(xiàn)場施工進(jìn)行總體策劃,明確施工任務(wù)。
1項(xiàng)目經(jīng)理欒華鋒3)組織進(jìn)行機(jī)械設(shè)備、材料、周轉(zhuǎn)工具、勞務(wù)人員等資源
的配置。
4)對(duì)施工安全、質(zhì)量、進(jìn)度、文明施工等各個(gè)方面工作進(jìn)
行管控和督促。
1)協(xié)助項(xiàng)目經(jīng)理,具體負(fù)責(zé)模板工程施工中各項(xiàng)項(xiàng)目管理
工作和準(zhǔn)備工作的落實(shí)。
2)組織編制施工進(jìn)度計(jì)劃、材料進(jìn)場計(jì)劃、安全檢查計(jì)劃
項(xiàng)等各類計(jì)劃,并下達(dá)執(zhí)行指令,對(duì)工程施工生產(chǎn)、安全、質(zhì)
2目項(xiàng)目總工王敉鵬量、現(xiàn)場總協(xié)調(diào)管理全面負(fù)責(zé),確保工程施工順利進(jìn)行。
領(lǐng)3)負(fù)責(zé)現(xiàn)場高支模工程施工期間施工技術(shù)指導(dǎo),高支模施
導(dǎo)工方案的編寫,組織對(duì)高支模施工區(qū)域的技術(shù)復(fù)核,對(duì)高支
層模的施工進(jìn)行旁站監(jiān)督,對(duì)現(xiàn)場的施工架體進(jìn)行組織安全驗(yàn)
收。
1)負(fù)責(zé)對(duì)總包方的工程結(jié)算管理和現(xiàn)場簽證管理;
3商務(wù)經(jīng)理蔣振西2)負(fù)責(zé)現(xiàn)場的主體勞務(wù)的分包合同,對(duì)現(xiàn)場施工進(jìn)行合約
支持;
1)參與項(xiàng)目危險(xiǎn)源辨識(shí)、風(fēng)險(xiǎn)評(píng)價(jià)與控制策劃,參與環(huán)境
因素的識(shí)別與評(píng)價(jià)。
2)參與項(xiàng)目職業(yè)健康安全與環(huán)境管理規(guī)劃、管理方案及技
4安全總監(jiān)朱明陽
術(shù)措施方案的制定,落實(shí)相關(guān)責(zé)任。
3)參與高大模板架體的驗(yàn)收工作,對(duì)不合格之處提出整
改,并進(jìn)行復(fù)驗(yàn)。
1)協(xié)助項(xiàng)目總工完成施工方案的編制,材料、設(shè)備的選定
和審核。
2)對(duì)施工作業(yè)人員進(jìn)行高大模板的專項(xiàng)技術(shù)交底、安全交
5技術(shù)工程師高虎
底,協(xié)調(diào)各專業(yè)之間的技術(shù)問題。
技
3)負(fù)責(zé)高支模架體的搭設(shè)過程的旁站監(jiān)督、技術(shù)指導(dǎo)、技
術(shù)
術(shù)復(fù)核工作。
部
1)負(fù)責(zé)施工現(xiàn)場的定位放線,及時(shí)進(jìn)行復(fù)核。
測量工程師2)負(fù)責(zé)高支模架體變形監(jiān)測的布置、測量、記錄工作,及
6欒天航
兼職試驗(yàn)時(shí)向項(xiàng)目總工匯報(bào)架體變形監(jiān)測情況。
3)負(fù)責(zé)混凝土試塊的留置、取送樣工作。
1)負(fù)責(zé)監(jiān)督現(xiàn)場質(zhì)量,對(duì)現(xiàn)場進(jìn)行驗(yàn)收,協(xié)助總工對(duì)現(xiàn)場
質(zhì)進(jìn)行質(zhì)量管理。
7量質(zhì)量總監(jiān)杜康樂2)負(fù)責(zé)一般不合格品的處置,發(fā)現(xiàn)嚴(yán)重不合格品及時(shí)報(bào)告
部項(xiàng)目總工,并負(fù)責(zé)處置后的質(zhì)量驗(yàn)收與評(píng)定。
4)質(zhì)量驗(yàn)收文件的記錄與整理。
1)總體施工進(jìn)度計(jì)劃的安排;
2)施工現(xiàn)場平面管理;
3)負(fù)責(zé)施工期間各專業(yè)之間的協(xié)調(diào)及配合工作,組織各分
工項(xiàng)工程的施工穿插工作等,及時(shí)解決施工中出現(xiàn)的各種問
8程生產(chǎn)經(jīng)理任景濤題。
部4)負(fù)責(zé)施工過程控制,對(duì)施工過程中的質(zhì)量、安全、文明
施工、成品保護(hù)等負(fù)責(zé);
5)負(fù)責(zé)機(jī)械設(shè)備、周轉(zhuǎn)工具、勞務(wù)人員的計(jì)劃與調(diào)配。
6)對(duì)現(xiàn)場的重大危險(xiǎn)源進(jìn)行旁站監(jiān)督,組織現(xiàn)場的施工模
9
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
序號(hào)部門管理職務(wù)姓名職責(zé)和權(quán)限
板架體驗(yàn)收。
1)負(fù)責(zé)施工期間項(xiàng)目各區(qū)域范圍內(nèi)的日常生產(chǎn)、安全、質(zhì)
量、工期等各項(xiàng)管理目標(biāo)、措施的全面落實(shí)。
禹金濤2)做好施工記錄,協(xié)調(diào)各專業(yè)之間的相互配合,及時(shí)解決
9專業(yè)工程師
張創(chuàng)創(chuàng)施工中出現(xiàn)的問題。
3)執(zhí)行施工方案,督促勞務(wù)隊(duì)伍遵守安全操作規(guī)程,按規(guī)
范、規(guī)程、圖紙要求施工。
1)巡回進(jìn)行職業(yè)健康安全/環(huán)境管理檢查,對(duì)關(guān)鍵特性參數(shù)
定期進(jìn)行監(jiān)測,發(fā)現(xiàn)問題下達(dá)整改通知單,并對(duì)整改情況進(jìn)
安行驗(yàn)證。
11全安全工程師江亞西2)負(fù)責(zé)職業(yè)健康安全/環(huán)境應(yīng)急準(zhǔn)備檢查,按應(yīng)急預(yù)案進(jìn)行
部響應(yīng)。
3)參與模板架體的驗(yàn)收工作,對(duì)不合格之處提出整改,下
發(fā)安全整改通知單,并進(jìn)行復(fù)驗(yàn)。
1)負(fù)責(zé)對(duì)總包方的工程結(jié)算管理和現(xiàn)場簽證管理。
2)及時(shí)收集整理現(xiàn)場簽證資料,辦理與發(fā)包方簽證。
商3)審核分包簽證,辦理分包結(jié)算。
12務(wù)商務(wù)工程師黃文鑫4)對(duì)現(xiàn)場的商務(wù)合同進(jìn)行管理與交底,對(duì)現(xiàn)場的合約進(jìn)行
部管理
5)建立完善的各類管理臺(tái)帳及目錄、收集整理歸檔商務(wù)資
料。
3.2項(xiàng)目管理目標(biāo)
表3.2-1項(xiàng)目管理目標(biāo)表
項(xiàng)目管理目標(biāo)名稱目標(biāo)值
工期94日歷天。
質(zhì)量目標(biāo)合格
安全目標(biāo)無安全事故發(fā)生
綠色施工目標(biāo)五節(jié)一環(huán)保
3.3各項(xiàng)資源供應(yīng)方式
表3.3-1勞務(wù)資源供應(yīng)表
施工項(xiàng)目名專業(yè)施工隊(duì)
開始施工時(shí)間建設(shè)工期分包方式分包商選擇方式責(zé)任人
稱名稱
巴中民生建
1區(qū)高支模筑勞務(wù)有限2022-2-1494天勞務(wù)分包項(xiàng)目選擇公司批準(zhǔn)蔣振西
公司
河南志國建
2區(qū)高支模筑勞務(wù)有限2022-2-1494天勞務(wù)分包項(xiàng)目選擇公司批準(zhǔn)蔣振西
公司
表3.3-2工程用大宗物資供應(yīng)安排一覽表
10
湛河春天(F地塊)地下室高大模板安全專項(xiàng)施工方案
采購/租賃
物資名稱采購/租賃單位擬選供應(yīng)商要求進(jìn)場時(shí)間責(zé)任人
地點(diǎn)
混凝土項(xiàng)目部xx市祥泰建材有限公司xx隨現(xiàn)場進(jìn)度申鵬
鋼筋項(xiàng)目部鄭州錦合順貿(mào)易有限公司
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 林地承包合同范本
- 2025年外研版八年級(jí)地理下冊(cè)月考試卷含答案
- 2025年中圖版七年級(jí)生物上冊(cè)階段測試試卷含答案
- 2025年牛津上海版七年級(jí)生物上冊(cè)月考試卷含答案
- 2025年統(tǒng)編版選擇性必修3化學(xué)上冊(cè)月考試卷含答案
- 2025年湘教版九年級(jí)歷史上冊(cè)階段測試試卷含答案
- 2025年華東師大版拓展型課程化學(xué)下冊(cè)階段測試試卷含答案
- 2025年木材加工企業(yè)安全生產(chǎn)責(zé)任保險(xiǎn)合同范本4篇
- 二零二五版明星代言合同違約責(zé)任及處理協(xié)議3篇
- 二零二五年度店面升級(jí)改造與智能安防系統(tǒng)集成合同4篇
- 霧化吸入療法合理用藥專家共識(shí)(2024版)解讀
- 2021年全國高考物理真題試卷及解析(全國已卷)
- 拆遷評(píng)估機(jī)構(gòu)選定方案
- 趣味知識(shí)問答100道
- 鋼管豎向承載力表
- 2024年新北師大版八年級(jí)上冊(cè)物理全冊(cè)教學(xué)課件(新版教材)
- 人教版數(shù)學(xué)四年級(jí)下冊(cè)核心素養(yǎng)目標(biāo)全冊(cè)教學(xué)設(shè)計(jì)
- JJG 692-2010無創(chuàng)自動(dòng)測量血壓計(jì)
- 三年級(jí)下冊(cè)口算天天100題(A4打印版)
- 徐州市2023-2024學(xué)年八年級(jí)上學(xué)期期末地理試卷(含答案解析)
- CSSD職業(yè)暴露與防護(hù)
評(píng)論
0/150
提交評(píng)論