南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
目錄
第一章編制依據(jù)............................................................................................................................................1
1.1相關(guān)文件、資料................................................................................................................................................1
1.2相關(guān)規(guī)范、標(biāo)準(zhǔn)................................................................................................................................................1
第二章工程概況............................................................................................................................................3
2.1工程簡介...........................................................................................................................................................3
2.2連續(xù)梁設(shè)計概況................................................................................................................................................3
2.2.1寶楊區(qū)間(33+55+33)m連續(xù)箱梁.......................................................................................................3
2.2.2楊東區(qū)間(36+64+36)m連續(xù)箱梁.......................................................................................................5
2.3周邊環(huán)境...........................................................................................................................................................6
2.4工程數(shù)量表.......................................................................................................................................................7
第三章施工部署............................................................................................................................................9
3.1施工管理組織機構(gòu)............................................................................................................................................9
3.1.1施工管理組織機構(gòu)設(shè)置...........................................................................................................................9
3.1.2各崗位及部門管理職責(zé)及權(quán)限................................................................................................................9
3.2工期安排.........................................................................................................................................................10
3.3資源配置計劃.................................................................................................................................................10
3.3.1勞動力配置計劃.....................................................................................................................................10
3.3.2施工機械配置計劃.................................................................................................................................11
第四章施工工藝與方法..............................................................................................................................12
4.1總體施工方案.................................................................................................................................................12
4.1.1掛籃懸臂施工工藝流程.........................................................................................................................12
4.1.2連續(xù)梁臨時固結(jié)設(shè)置.............................................................................................................................13
4.1.3各梁段體積及重量.................................................................................................................................13
4.1.4施工順序.................................................................................................................................................14
4.2掛籃設(shè)計、安裝及壓載..................................................................................................................................14
4.2.1掛籃結(jié)構(gòu)設(shè)計.........................................................................................................................................14
4.2.2掛籃制作質(zhì)量控制要求.........................................................................................................................21
4.2.3掛籃拼裝.................................................................................................................................................21
4.2.4掛籃安裝注意事項.................................................................................................................................22
4.2.5掛籃行走.................................................................................................................................................23
4.2.6掛籃預(yù)壓.................................................................................................................................................25
4.2.7掛籃拆除.................................................................................................................................................26
4.3懸臂澆筑段施工.............................................................................................................................................27
4.3.1懸臂施工流程.........................................................................................................................................28
4.3.2鋼筋綁扎.................................................................................................................................................28
4.3.3預(yù)應(yīng)力筋加工及安裝.............................................................................................................................29
4.3.4混凝土澆筑養(yǎng)護.....................................................................................................................................31
4.3.5預(yù)應(yīng)力張拉、壓漿及封錨.....................................................................................................................32
4.3.6施工監(jiān)控.................................................................................................................................................35
1
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
4.4合龍段施工.....................................................................................................................................................36
4.4.2合攏施工準(zhǔn)備.........................................................................................................................................37
4.4.3邊跨合龍段施工.....................................................................................................................................37
4.4.4中跨合龍段施工.....................................................................................................................................40
4.5體系轉(zhuǎn)換.........................................................................................................................................................42
第五章質(zhì)量保證措施..................................................................................................................................43
5.1施工管理組織機構(gòu)..........................................................................................................................................43
5.2施工質(zhì)量管理制度..........................................................................................................................................43
5.3施工質(zhì)量技術(shù)保障措施..................................................................................................................................44
5.3.1混凝土質(zhì)量保證措施.............................................................................................................................44
5.3.2鋼筋工程質(zhì)量保證措施.........................................................................................................................45
5.3.3模板工程質(zhì)量保證措施.........................................................................................................................45
5.3.4預(yù)應(yīng)力工程質(zhì)量保證措施.....................................................................................................................45
5.3.5預(yù)應(yīng)力混凝土防崩裂措施.....................................................................................................................45
5.3.6成品保護措施.........................................................................................................................................46
第六章安全保證措施..................................................................................................................................47
6.1施工管理組織機構(gòu)..........................................................................................................................................47
6.2施工安全管理制度..........................................................................................................................................47
6.3安全技術(shù)保障措施..........................................................................................................................................48
6.3.1掛籃施工安全技術(shù)措施.........................................................................................................................48
6.3.2模板施工安全技術(shù)措施.........................................................................................................................49
6.3.3混凝土澆筑安全技術(shù)措施.....................................................................................................................50
6.3.4吊裝施工安全技術(shù)措施.........................................................................................................................51
6.3.5防高處墜落安全技術(shù)措施.....................................................................................................................51
6.3.6臨時用電安全技術(shù)措施.........................................................................................................................52
6.3.7臨近既有道路及構(gòu)筑物施工安全措施..................................................................................................52
6.3.8交通安全措施.........................................................................................................................................53
6.3.9文明施工技術(shù)措施.................................................................................................................................53
6.3.10雨季施工安全技術(shù)措施.......................................................................................................................54
6.3.11夏季施工安全技術(shù)措施.......................................................................................................................54
6.3.12夜間施工安全技術(shù)措施.......................................................................................................................55
6.3.13受限空間安全技術(shù)措施.......................................................................................................................55
6.4危險源及管控措施..........................................................................................................................................55
第七章施工人員配置和分工.......................................................................................................................57
7.1.1施工管理人員及分工.............................................................................................................................57
7.1.2專職安全生產(chǎn)管理人員.........................................................................................................................58
7.1.3特種作業(yè)人員.........................................................................................................................................58
第八章驗收要求..........................................................................................................................................59
8.1材料驗收.........................................................................................................................................................59
8.1.1驗收人員.................................................................................................................................................59
8.1.2材料驗收.................................................................................................................................................59
2
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
8.2掛籃檢查.........................................................................................................................................................59
8.2.1參與人員.................................................................................................................................................59
8.2.2掛籃檢查及驗收時間.............................................................................................................................60
8.2.3檢查標(biāo)準(zhǔn)與方法.....................................................................................................................................60
8.3模板及支撐系統(tǒng)安全驗收..............................................................................................................................60
8.3.1參與人員.................................................................................................................................................60
8.3.2驗收時間.................................................................................................................................................60
8.3.3驗收內(nèi)容.................................................................................................................................................60
8.4掛籃拼裝檢查安全驗收..................................................................................................................................61
8.4.1參與人員.................................................................................................................................................61
8.4.2驗收時間.................................................................................................................................................61
8.4.3驗收內(nèi)容.................................................................................................................................................61
8.5關(guān)鍵節(jié)點前施工條件驗收..............................................................................................................................63
第九章應(yīng)急預(yù)案..........................................................................................................................................64
9.1應(yīng)急救援組織機構(gòu)..........................................................................................................................................64
9.2職責(zé)分工.........................................................................................................................................................65
9.2.1應(yīng)急救援領(lǐng)導(dǎo)小組職責(zé).........................................................................................................................65
9.2.2應(yīng)急救援小組職責(zé).................................................................................................................................66
9.3應(yīng)急救援小組成員聯(lián)系電話..........................................................................................................................68
9.4施工應(yīng)急措施.................................................................................................................................................69
9.4.1起重機安全預(yù)案.....................................................................................................................................69
9.4.2防高空墜落預(yù)案.....................................................................................................................................69
9.4.3觸電事故應(yīng)急預(yù)案.................................................................................................................................70
9.4.4防臺風(fēng)、暴雨應(yīng)急預(yù)案.........................................................................................................................71
9.5應(yīng)急救援物資.................................................................................................................................................71
9.6應(yīng)急救援路線.................................................................................................................................................72
第十章附件.................................................................................................................................................74
附件一:三角掛籃結(jié)構(gòu)設(shè)計圖及施工工況圖................................................................................................74
附件二:懸臂連續(xù)梁施工步驟圖....................................................................................................................74
附件三:0號塊支架設(shè)計圖............................................................................................................................74
附件四:三角掛籃計算書...............................................................................................................................74
附件五:掛籃廠家資質(zhì)文件............................................................................................................................74
3
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
4
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
第一章編制依據(jù)
1.1相關(guān)文件、資料
(1)《中華人民共和國建筑法》(主席令第19號)
(2)《建筑工程質(zhì)量管理條例》(國務(wù)院令第279號)
(3)《建設(shè)工程安全生產(chǎn)管理條例》(國務(wù)院令第393號)
(4)中華人民共和國住房和城鄉(xiāng)建設(shè)部令第37號《危險性較大的分部分項工程安
全管理規(guī)定》
(5)住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實施《危險性較大的分部分項工程安全管理規(guī)定》
有關(guān)問題的通知建辦質(zhì)(2018)31號文
(6)《江蘇省房屋建筑和市政基礎(chǔ)設(shè)施工程危險性較大的分部分項工程安全管理實
施細則(2019版)》(蘇建質(zhì)安〔2019〕378號)
(7)《南京地鐵工程建設(shè)安全生產(chǎn)管理辦法》
(8)南京至句容城際軌道交通工程DS6-TA02標(biāo)三工區(qū)《實施性施工組織設(shè)計》
(9)《南京至句容城際軌道交通工程施工總承包DS6-TA02標(biāo)合同文件》
(10)《南京至句容城際軌道交通工程施工總承包DS6-TA02標(biāo)施工圖紙》
1.2相關(guān)規(guī)范、標(biāo)準(zhǔn)
(1)《地下鐵道工程施工質(zhì)量驗收標(biāo)準(zhǔn)》(GB/T50299—2018)
(2)《城市軌道交通工程監(jiān)測技術(shù)規(guī)范》(GB50911-2013)
(3)《混凝土結(jié)構(gòu)工程施工質(zhì)量驗收規(guī)范》(GB50204-2015)
(4)《鋼結(jié)構(gòu)設(shè)計規(guī)范》(GB50017-2017)
(5)《組合鋼模板技術(shù)規(guī)范》(GBT50214-2013)
(6)《鐵路預(yù)應(yīng)力混凝土連續(xù)梁(鋼構(gòu))懸臂澆筑施工技術(shù)指南》(TZ324-2010)
(7)《客貨共線鐵路橋涵工程施工技術(shù)規(guī)程》(Q/CR9652—2017)
(8)《鐵路橋涵工程施工質(zhì)量驗收標(biāo)準(zhǔn)》(TB10415—2018)
(9)《鐵路混凝土工程施工質(zhì)量驗收標(biāo)準(zhǔn)》(TB10424—2018)
(10)《高速鐵路橋涵工程施工質(zhì)量驗收標(biāo)準(zhǔn)》(TB10752—2018)
(11)《鐵路橋涵工程施工安全技術(shù)規(guī)程》(TB10303—2009)
(12)《鋼筋焊接及驗收規(guī)程》(JGJ18-2012)
(13)《鋼筋機械連接技術(shù)規(guī)程》(JGJ107-2016)
(14)《建筑施工模板安全技術(shù)規(guī)范》(JGJ162—2008)
1
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
(15)《建筑施工高處作業(yè)安全技術(shù)規(guī)范》(JGJ80-2016)
(16)《建筑工程大模板技術(shù)規(guī)范》(JGJ/T74-2017)
(17)《橋梁懸臂澆筑施工技術(shù)標(biāo)準(zhǔn)》(CJJ/T281-2018)
(18)《城市軌道交通橋梁工程及驗收標(biāo)準(zhǔn)》(CJJ/T281-2018)
(19)《南京地鐵工程建設(shè)安全生產(chǎn)文明施工標(biāo)準(zhǔn)化圖集》
(20)《南京地鐵工程建設(shè)安全生產(chǎn)管理辦法》
2
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
第二章工程概況
2.1工程簡介
南京至句容城際軌道交通工程施工總承包DS6-TA02標(biāo)三工區(qū)線路出寶華山站后沿寶
華山路中央分隔帶向東敷設(shè),在肖桿河橋前向南穿過空地轉(zhuǎn)入長江路(容城大道),沿長
江路(容城大道)中央分隔帶向南敷設(shè),經(jīng)楊塘路站(高架站),過肖桿河并跨越福地路
和行香路后繼續(xù)沿現(xiàn)狀東昌北路路中敷設(shè)至入洞口,里程K33+915.117~K38+468.996,
全長4.554km。施工范圍內(nèi)存在2座懸臂連續(xù)箱梁,詳見下圖。
圖2.1-1寧句城際DS6-TA02標(biāo)三工區(qū)線路走向圖
2.2連續(xù)梁設(shè)計概況
2.2.1寶楊區(qū)間(33+55+33)m連續(xù)箱梁
寶華山站~楊塘路站(33+55+33)m預(yù)應(yīng)力混凝土連續(xù)箱梁,位于線路與句容河交叉
處,里程樁號起訖為K34+979.117~K35+100.117,橋梁全長120.8m,對稱懸臂現(xiàn)澆施
3
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
工。
圖2.2-1寶楊區(qū)間(33+55+33)m連續(xù)懸澆箱梁橋型布置圖
(1)梁體為單箱雙室、斜腹板、變高度、變截面結(jié)構(gòu)。箱梁頂寬10.16m,箱梁底寬
5.06~5.81m。頂板厚度均為28cm;底板厚度28至60cm,按二次拋物線線性變化;腹板
厚35~60cm,厚度按折線變化,箱梁兩側(cè)腹板與頂?shù)装逑嘟惶幘捎脠A弧倒角過渡。全聯(lián)
在端支點中支點處共設(shè)4道橫隔板,中支點橫隔板設(shè)有孔洞,供檢查人員通過。
(2)梁全長為120.8m,跨度為(33+55+33)m,中支點截面中心處梁高3.5m,跨中
2m直線段,邊跨6.4m直線段,截面中心處梁高為2.0m。梁底下緣按二次拋物線變化,
邊支座中心線至梁端0.55m。
橋梁斷面結(jié)構(gòu)形式如下圖。
圖2.2-2寶楊區(qū)間(33+55+33)m連續(xù)懸澆箱梁斷面圖
(3)連續(xù)梁節(jié)段按澆筑類型劃分為三類:支架現(xiàn)澆段、懸臂端、合龍段。
懸臂段:1-6#塊兩組、1′-6′#塊兩組,共24塊,最大懸臂塊長度4m;
4
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
合龍段:兩個邊跨合龍段7#段,一個中跨合龍段7′#,合龍段長度均為2m。
2.2.2楊東區(qū)間(36+64+36)m連續(xù)箱梁
楊塘路站~東大街站(36+64+36)m預(yù)應(yīng)力混凝土連續(xù)箱梁,位于線路與句容河交叉
處,里程樁號起訖為K37+723.946~K37+859.946,橋梁全長135.8m,對稱懸臂現(xiàn)澆施
工。
圖2.2-3楊東區(qū)間(36+64+36)m連續(xù)懸澆箱梁橋型布置圖
(1)梁體為單箱雙室、斜腹板、變高度、變截面結(jié)構(gòu)。箱梁頂寬10.16m,箱梁底寬
4.81~5.81m。頂板厚度均為28cm;底板厚度28至100cm,按二次拋物線線性變化;腹板
厚40~80cm,厚度按折線變化,箱梁兩側(cè)腹板與頂?shù)装逑嘟惶幘捎脠A弧倒角過渡。全聯(lián)
在端支點中支點處共設(shè)4道橫隔板,中支點橫隔板設(shè)有孔洞,供檢查人員通過。
(2)梁全長為135.8m,跨度為(36+64+36)m,中支點截面中心處梁高4m,跨中2m
直線段,邊跨4.9m直線段,截面中心處梁高為2.0m。梁底下緣按二次拋物線變化,邊支
座中心線至梁端0.55m。
橋梁斷面結(jié)構(gòu)形式如下圖。
5
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
圖2.2-4楊東區(qū)間(36+64+36)m連續(xù)懸澆箱梁斷面圖
(3)連續(xù)梁節(jié)段按澆筑類型劃分為三類:支架現(xiàn)澆段、懸臂端、合龍段。
懸臂段:1-7#塊四組,共28塊,最大懸臂塊長度4m;
合龍段:兩個邊跨合龍段8#段,一個中跨合龍段8′#節(jié)段,合龍段長度均為2m。
2.3周邊環(huán)境
第一次跨越肖桿河:KY37墩至KY41墩間線路斜跨S266省道及肖桿河,高程
25.57m~15.69m,現(xiàn)狀地形呈下窄上寬的倒梯形,線路斜跨S266省道緊鄰肖桿橋西側(cè)橋
墩跨越肖桿河,該區(qū)間河道在勘察期間正在進行河道整治,原河道兩岸經(jīng)開挖,坡度較
陡,河道坡頂受堆填影響,地勢起伏較大,地形較復(fù)雜。
圖2.3-1寶楊區(qū)間(33+55+33)m連續(xù)梁現(xiàn)狀環(huán)境
第二次跨越肖桿河:LY9-LY11上跨肖桿河,河道過水?dāng)嗝鎸挾燃s29m,河道水深
0.3m~0.5m,水流較緩,水面標(biāo)高15.51m(隨著下雨會有微幅變化)。兩側(cè)為岸邊,施工
環(huán)境較好。
6
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
圖2.3-2楊東區(qū)間(36+64+36)m連續(xù)梁現(xiàn)狀環(huán)境
2.4工程數(shù)量表
表2.4-1寶華山站~楊塘路站(33+55+33)m連續(xù)懸澆箱梁工程數(shù)量表
數(shù)量
序號部位項目材料規(guī)格單位備注
分項合計
1主梁C501149.24\
2混凝土其他C50m325.921179.06齒塊混凝土
3封錨C503.9封錨補償收縮混凝土
49Φs15.2350.6
5鋼絞線12Φs15.2kg3860952024.3不含備用束
615Φs15.213064.7
7錨具張拉端錨套232232\
梁部
8內(nèi)徑90mmm3551.1
波紋管3583.3金屬波紋管
9內(nèi)徑80mmm32.2
10286488.8
112262307.8
12普通鋼筋18kg6634.8313468.5HRB400
1316164815
141273222.1
153000KN-ZX44縱向活動支座
16支座12500KN-ZX個22縱向活動支座
1712500KN-GD22固定支座
18鋁制人洞蓋鋁材30.830.8\
其他kg
19板HRB400鋼料456456\
7
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
表2.4-2楊塘路站~東大街站(36+64+36)m連續(xù)懸澆箱梁工程數(shù)量表
數(shù)量
序號部位項目材料規(guī)格單位備注
分項合計
1主梁C501399.8\
2混凝土齒塊C50m330.21432.2齒塊混凝土
3封錨C502.2封錨補償收縮混凝土
412Φs15.239141.8
鋼絞線kg67814.6不含備用束
515Φs15.228672.7
612Φs15.2140
梁部252張拉端錨
715Φs15.2112
錨具套
812Φs15.228
28固定端錨
915Φs15.20
10定位鋼筋8kg3267.73267.7HPB300
11波紋管內(nèi)徑90mmm4490.94490.9金屬波紋管
12普通鋼筋kg342549.6342549.6HRB400
133000KN-ZX44縱向活動支座
14支座15000KN-ZX個22縱向活動支座
1515000KN-GD22固定支座
16鋼材76.476.4Q235
人洞蓋板kg
17普通鋼筋265.2265.2HRB400
18混凝土m30.550.55C50
擋水臺
19其他普通鋼筋kg144.2144.2HRB400
20型鋼kg3211.23211.2Q235
合龍段骨
21鋼板kg2261.42261.4Q235
架
22普通鋼筋kg424.2424.2HRB400
8
南京軌道交通工程施工總承包2023年懸臂連續(xù)梁掛籃專項施工方案
第三章施工部署
3.1施工管理組織機構(gòu)
3.1.1施工管理組織機構(gòu)設(shè)置
項目部建立以項目經(jīng)理為首的施工管理組織機構(gòu),各領(lǐng)導(dǎo)班子及項目部全體人員齊
抓共管安全,并設(shè)專門的安全管理機構(gòu)-安全部,設(shè)安全總監(jiān),專職安全管理人員。
項目經(jīng)理鄧向振
項目副經(jīng)理陳兵安全總監(jiān)徐帥項目總工程師陶治法
安全環(huán)境
技術(shù)管理質(zhì)量管理工程管理物資設(shè)備合約商務(wù)
管理部潘
部吳少波部邢文康部吳寶夏部張峰部信非非
寧
各專業(yè)作業(yè)隊專業(yè)工程分包單位
作業(yè)班組
圖3.1-1施工管理組織機構(gòu)
3.1.2各崗位及部門管理職責(zé)及權(quán)限
表3.1-1各崗位及部門人員管理職責(zé)與權(quán)限
崗位名稱崗位職責(zé)與權(quán)限
1、項目經(jīng)理是連續(xù)懸澆箱梁施工的安全、質(zhì)量第一責(zé)任人;
項目經(jīng)理2、統(tǒng)籌安排連續(xù)懸澆箱梁施工與其他專業(yè)工程之前的關(guān)系;
3、保證施工隊農(nóng)民工工資支付,確保項目生產(chǎn)工作穩(wěn)步進行。
1、連續(xù)懸澆箱梁施工的技術(shù)負責(zé)人,對連續(xù)梁質(zhì)量負技術(shù)責(zé)任;
2、組織編制施工方案;
項目總工
3、檢查方案中安全措施落實情況;
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 清潔工程智能化施工合同
- 醫(yī)療機構(gòu)質(zhì)量管理與合規(guī)
- 工業(yè)園區(qū)道路級配碎石鋪設(shè)協(xié)議
- 居民燃氣使用指導(dǎo)手冊
- 苗木花卉買賣合同范本
- 電力公司解除聘用合同說明
- 寫字樓交易合同范本
- 水果市場裝卸人員聘用合同
- 航空垃圾特種管理辦法
- 藥品行業(yè)自律規(guī)范要求
- 2024版影視制作公司與演員經(jīng)紀(jì)公司合作協(xié)議3篇
- 新疆大學(xué)答辯模板課件模板
- 數(shù)值分析智慧樹知到期末考試答案2024年
- (正式版)HGT 22820-2024 化工安全儀表系統(tǒng)工程設(shè)計規(guī)范
- 2024年浙江省新華書店集團招聘筆試參考題庫附帶答案詳解
- 跨文化溝通心理學(xué)智慧樹知到期末考試答案2024年
- 《中華民族共同體概論》考試復(fù)習(xí)題庫(含答案)
- 【綠色評價】發(fā)展綠色指標(biāo)評價測試五年級《英語》第一學(xué)期上冊期末試卷及答案解析
- 預(yù)制梁場建設(shè)驗收標(biāo)準(zhǔn)
- 物理電學(xué)暗箱專題30道
- 三國志11武將出場時間地點整理
評論
0/150
提交評論