濟(jì)寧xx路北延高鐵連接線項(xiàng)目
預(yù)制箱梁吊裝專項(xiàng)施工方案
(格式最終版)
中建x局第二建設(shè)有限公司
濟(jì)寧路北延高鐵連接線項(xiàng)目部
目錄
1編制依據(jù)......................................................................................................................................................6
1.1標(biāo)準(zhǔn)規(guī)范.............................................................................................................................................6
1.2其他參考資料.....................................................................................................................................7
1.3編制目的.............................................................................................................................................7
2工程概況......................................................................................................................................................7
2.1工程建設(shè)概況一覽表.........................................................................................................................7
2.2設(shè)計(jì)概況.............................................................................................................................................7
2.3工程施工條件.....................................................................................................................................9
3施工安排......................................................................................................................................................9
3.1項(xiàng)目管理組織.....................................................................................................................................9
3.2各項(xiàng)資源供應(yīng)方式...........................................................................................................................11
3.3施工流水段的劃分及施工工藝流程...............................................................................................12
3.4工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施...........................................................................................13
4施工進(jìn)度計(jì)劃............................................................................................................................................14
5施工準(zhǔn)備與資源配置計(jì)劃........................................................................................................................17
5.1施工準(zhǔn)備計(jì)劃...................................................................................................................................17
5.2資源配置計(jì)劃...................................................................................................................................20
6施工方法及工藝要求................................................................................................................................21
6.1施工準(zhǔn)備...........................................................................................................................................21
6.2梁場(chǎng)起梁、裝梁...............................................................................................................................29
6.3運(yùn)梁...................................................................................................................................................30
6.4測(cè)量放樣...........................................................................................................................................31
6.5支座安裝...........................................................................................................................................31
6.6箱梁架設(shè)順序...................................................................................................................................32
6.7履帶吊(汽車吊)架設(shè)箱梁安裝...................................................................................................34
7季節(jié)性保證措施........................................................................................................................................38
7.1雨季施工保證措施.........................................................................................................................38
7.1.1雨季施工的技術(shù)措施..........................................................................................................38
7.1.2雨季施工的安全措施..........................................................................................................38
7.2高溫施工保證措施.........................................................................................................................39
7.3大風(fēng)天氣下安全措施.....................................................................................................................40
8工期保證措施............................................................................................................................................40
8.1工期保證體系.................................................................................................................................40
8.1.1進(jìn)度保障體系......................................................................................................................40
8.1.2進(jìn)度管理體系......................................................................................................................41
8.2工期保證措施.................................................................................................................................42
8.2.1保證工期的組織措施..........................................................................................................42
8.2.2保證工期的技術(shù)措施..........................................................................................................42
9質(zhì)量保證措施............................................................................................................................................43
9.1質(zhì)量保證體系.................................................................................................................................43
9.1.1思想保證..............................................................................................................................44
9.1.2組織保證..............................................................................................................................44
9.1.3技術(shù)保證..............................................................................................................................47
9.1.4施工保證..............................................................................................................................47
9.1.5經(jīng)濟(jì)保證..............................................................................................................................49
9.2檢測(cè)、試驗(yàn)保證措施.....................................................................................................................49
10安全保證措施..........................................................................................................................................50
10.1風(fēng)險(xiǎn)源識(shí)別...................................................................................................................................50
10.2危險(xiǎn)目標(biāo)的確定...........................................................................................................................51
10.3組織保證措施...............................................................................................................................51
10.4技術(shù)保證措施...............................................................................................................................54
10.5施工保證措施...............................................................................................................................56
10.6特種設(shè)備的安全管理...................................................................................................................62
10.6.1特種設(shè)備驗(yàn)收小組及其職責(zé)............................................................................................62
10.6.2特種設(shè)備的進(jìn)場(chǎng)條件........................................................................................................62
10.6.3特種設(shè)備的檢查與驗(yàn)收....................................................................................................63
10.6.4特種設(shè)備的操作人員........................................................................................................63
10.6.5特種設(shè)備日常檢查............................................................................................................63
10.7起重鋼絲繩的檢查驗(yàn)收管理.......................................................................................................63
10.7.1鋼絲繩使用前的檢查........................................................................................................63
10.7.2鋼絲繩的日常檢查............................................................................................................64
10.7.3鋼絲繩的報(bào)廢標(biāo)準(zhǔn)............................................................................................................64
11應(yīng)急預(yù)案..................................................................................................................................................64
11.1應(yīng)急預(yù)案的方針與原則.................................................................................................................65
11.2應(yīng)急救援小組機(jī)構(gòu)與職責(zé)...........................................................................................................65
11.3吊裝時(shí)的應(yīng)急準(zhǔn)備.......................................................................................................................67
11.4施工現(xiàn)場(chǎng)的急救步驟...................................................................................................................67
11.5應(yīng)急處理措施...............................................................................................................................69
11.6事故的處理與報(bào)告.......................................................................................................................70
12驗(yàn)收要求..................................................................................................................................................71
12.1驗(yàn)收標(biāo)準(zhǔn).......................................................................................................................................71
12.2驗(yàn)收程序.......................................................................................................................................71
12.3驗(yàn)收人員.......................................................................................................................................71
12.4驗(yàn)收內(nèi)容.......................................................................................................................................71
12.4.1機(jī)械驗(yàn)收............................................................................................................................71
12.4.2起重鋼絲繩驗(yàn)收................................................................................................................74
13施工管理及作業(yè)人員配備和分工..........................................................................................................76
13.1人員配置情況...............................................................................................................................76
13.2特種設(shè)備驗(yàn)收小組及其職責(zé).......................................................................................................77
13.3特種設(shè)備的操作人員...................................................................................................................77
14計(jì)算書和相關(guān)圖紙..................................................................................................................................78
14.1履帶吊雙機(jī)抬吊驗(yàn)算.....................................................................................................................78
14.2履帶吊平面占位.............................................................................................................................78
14.3履帶吊抗傾覆驗(yàn)算.........................................................................................................................80
14.4汽車吊起重驗(yàn)算.............................................................................................................................81
14.5汽車吊平面占位.............................................................................................................................81
14.6汽車吊抗傾覆驗(yàn)算.........................................................................................................................83
1編制依據(jù)
1.1標(biāo)準(zhǔn)規(guī)范
表1.1-1標(biāo)準(zhǔn)規(guī)范
序
類別文件名稱編號(hào)
號(hào)
中華人民共和國(guó)住
《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)
1房和城鄉(xiāng)建設(shè)部令
定》
國(guó)家行政文第37號(hào)
件住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實(shí)施《危險(xiǎn)性
2較大的分部分項(xiàng)工程安全管理規(guī)定》有關(guān)建辦質(zhì)[2018]31號(hào)
問題的通知
《山東省房屋市政施工危險(xiǎn)性較大分部分魯建質(zhì)安字
3
地方行政文項(xiàng)工程安全管理實(shí)施細(xì)則》[2018]15號(hào)
件
4《特種設(shè)備安全監(jiān)察條例》國(guó)務(wù)院令第549號(hào)
5《建筑施工起重吊裝工程安全技術(shù)規(guī)范》JGJ276-2012
6《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
7《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
8《起重機(jī)手勢(shì)信號(hào)》GB/T5082-2019
9《建設(shè)工程施工現(xiàn)場(chǎng)環(huán)境與衛(wèi)生標(biāo)準(zhǔn)》JGJ146-2013
《起重機(jī)鋼絲繩保養(yǎng)、維護(hù)、檢驗(yàn)和報(bào)
10GB/T5972-2016
廢》
國(guó)家行業(yè)規(guī)
11范《城市橋梁工程施工與質(zhì)量驗(yàn)收規(guī)范》CJJ2-2008
12《公路工程施工安全技術(shù)規(guī)范》JTGF90-2015
《公路鋼筋混凝土及預(yù)應(yīng)力混凝土橋涵設(shè)
13JTG3362-2018
計(jì)規(guī)范》
14《公路橋涵施工技術(shù)規(guī)范》JTG∕T3650-2020
《公路工程質(zhì)量檢驗(yàn)評(píng)定標(biāo)準(zhǔn)第一冊(cè)土
15JTGF80/1-2017
建工程》
16《城市道路工程設(shè)計(jì)規(guī)范》CJJ37-2012
序
類別文件名稱編號(hào)
號(hào)
《起重機(jī)及起重機(jī)械鋼絲繩選擇第2部GB/T24811.2-
17
分流動(dòng)式起重機(jī)利用系數(shù)》2009
《公路工程裝配式施工質(zhì)量驗(yàn)收評(píng)定標(biāo)DG/TJ08-2250-
18
準(zhǔn)》2017
19《安全生產(chǎn)風(fēng)險(xiǎn)分級(jí)管控體系通則》DB37/T2882-2016
20地方規(guī)標(biāo)準(zhǔn)《生產(chǎn)安全事故隱患排查治理體系通則》DB37/T2883-2016
21《特種設(shè)備使用安全管理規(guī)范》DB13/T2092-2014
1.2其他參考資料
(1)《濟(jì)寧市任城區(qū)xx路北延高鐵連接線項(xiàng)目施工組織設(shè)計(jì)》;
(2)《濟(jì)寧市任城區(qū)xx路北延高鐵連接線項(xiàng)目施工管理策劃》;
(3)《濟(jì)寧市任城區(qū)xx路北延高鐵連接線項(xiàng)目質(zhì)量管理策劃》;
(4)本公司施工技術(shù)標(biāo)準(zhǔn)、機(jī)械裝備及施工經(jīng)驗(yàn)。
(5)濟(jì)寧市任城區(qū)xx路北延高鐵連接線項(xiàng)目施工圖。
1.3編制目的
(1)合理、科學(xué)、可靠組織施工和部署,明確施工方法和施工工藝。
(2)明確質(zhì)量目標(biāo),健全保證體系,完善保證措施,確保質(zhì)量滿足設(shè)計(jì)及規(guī)范要求。
(3)明確安全目標(biāo),采取安全可靠措施,確保施工安全、人員和設(shè)備安全。
(4)明確工期目標(biāo),合理安排生產(chǎn)計(jì)劃,保證工期措施得力,確保工程工期滿足業(yè)
主要求。
2工程概況
2.1工程建設(shè)概況一覽表
表2.1-1工程建設(shè)概況一覽表
跨徑數(shù)量(片)梁重范圍(t)
25m11085-91
30m443100-107
2.2設(shè)計(jì)概況
本標(biāo)段橋梁?jiǎn)慰卓鐝?5m和30m的上部結(jié)構(gòu)為預(yù)應(yīng)力混凝土簡(jiǎn)支小箱梁,橋梁橫向
為雙向1.5%橫坡。每孔在跨架設(shè)預(yù)制箱梁標(biāo)準(zhǔn)段為8片,變截面最多架設(shè)箱梁數(shù)量為14
片,平行匝道架設(shè)箱梁數(shù)量為3片。下部結(jié)構(gòu)分幅時(shí),中間小箱梁設(shè)置為內(nèi)邊梁。
預(yù)應(yīng)力混凝土小箱梁底寬1m,腹板側(cè)面1:4斜度,頂板橫坡為1.5%。小箱梁跨中設(shè)
中橫隔板一道,厚0.2m,支承處設(shè)支點(diǎn)橫隔板一道,厚0.3m。預(yù)應(yīng)力鋼束采用10束鋼
絞線斷面布置。預(yù)應(yīng)力混凝土小箱梁中梁最大吊重約為100t,邊梁最大吊重約107t。簡(jiǎn)
支小箱梁采用板式支座GJZ350×550×99。
圖2.2-1中梁橫斷圖
圖2.2-2外邊梁橫斷面
圖2.2-3內(nèi)邊梁橫斷面
2.3工程施工條件
所有預(yù)制箱梁均由中鐵四局預(yù)制場(chǎng)統(tǒng)一制作加工,材料均由中鐵四局提供。
本工程橋梁施工上跨濟(jì)北礦區(qū)鐵路,鐵路橫穿位置位于42#軸和43#軸之間,以鐵路
為分?jǐn)喾譃閮商幨┕ざ温洹?/p>
施工現(xiàn)場(chǎng)影響吊裝施工的管線基本遷改完成,剩余一處K1+950(農(nóng)科院試驗(yàn)田南端)
220KV高壓線尚未遷改,影響36#軸吊裝施工,計(jì)劃對(duì)該處高壓線進(jìn)行提升再進(jìn)行施工,
確保36#軸吊裝施工不受影響,35#軸、37#軸距高壓線水平距離均超過35m,施工不受影
響。
施工現(xiàn)場(chǎng)無既有道路,在建設(shè)道路兩側(cè)非機(jī)動(dòng)車道設(shè)置便道,便道寬4.5m,使用磚
渣鋪設(shè),磚渣厚度50cm,只行走運(yùn)輸車輛,便道設(shè)置橫坡,施工前使用重型釬探進(jìn)行地
基承載力檢測(cè),實(shí)測(cè)處理后的地基承載力大于300Kpa,確保吊裝安全。
3施工安排
3.1項(xiàng)目管理組織
1管理組織
圖3.1-1項(xiàng)目管理組織
2管理職責(zé)
表3.1-1項(xiàng)目管理職責(zé)
序
部門姓名崗位名稱崗位職責(zé)
號(hào)
1項(xiàng)目經(jīng)理全面負(fù)責(zé)箱梁吊裝過程管理工作
協(xié)助項(xiàng)目經(jīng)理對(duì)箱梁吊裝過程進(jìn)行管
2執(zhí)行經(jīng)理
理工作
3商務(wù)經(jīng)理全面負(fù)責(zé)商務(wù)管理工作
箱梁吊裝技術(shù)指導(dǎo)、現(xiàn)場(chǎng)計(jì)劃、平面
4項(xiàng)目總工
項(xiàng)目班子布置、施工管理等
5項(xiàng)目副經(jīng)理全面負(fù)責(zé)鐵路以北箱梁吊裝管理工作
6項(xiàng)目副經(jīng)理全面負(fù)責(zé)鐵路以南箱梁吊裝管理工作
7外協(xié)副經(jīng)理負(fù)責(zé)征地拆遷、外協(xié)
8安全總監(jiān)全面負(fù)責(zé)箱梁吊裝現(xiàn)場(chǎng)安全生產(chǎn)管理
9造價(jià)工程師
商務(wù)部商務(wù)管理工作
10造價(jià)工程師
11物資主管箱梁吊裝物資總采購(gòu)、現(xiàn)場(chǎng)材料管理
12物資部材料工程師
箱梁吊裝物資采購(gòu)、驗(yàn)收、計(jì)量
13材料工程師
序
部門姓名崗位名稱崗位職責(zé)
號(hào)
14責(zé)任工程師負(fù)責(zé)鐵路以南現(xiàn)場(chǎng)施工管理
15責(zé)任工程師負(fù)責(zé)鐵路以北現(xiàn)場(chǎng)施工管理
負(fù)責(zé)鐵路以南箱梁吊裝施工的現(xiàn)場(chǎng)管
16專業(yè)工程師
工程部理
負(fù)責(zé)鐵路以北箱梁吊裝施工的現(xiàn)場(chǎng)管
17專業(yè)工程師
理
18勞務(wù)工程師負(fù)責(zé)隊(duì)伍勞務(wù)管理對(duì)接工作
19專業(yè)工程師負(fù)責(zé)BIM模型建立及預(yù)制箱梁管理
20專業(yè)工程師
完成箱梁吊裝技術(shù)質(zhì)量方面工作
21專業(yè)工程師
22資料工程師負(fù)責(zé)箱梁吊裝資料編寫整理收集
23試驗(yàn)主管負(fù)責(zé)指導(dǎo)現(xiàn)場(chǎng)試驗(yàn)檢測(cè)
24技術(shù)部試驗(yàn)工程師
現(xiàn)場(chǎng)質(zhì)量檢驗(yàn),制定檢驗(yàn)臺(tái)賬
25試驗(yàn)工程師
26測(cè)量主管負(fù)責(zé)箱梁吊裝現(xiàn)場(chǎng)施工測(cè)量及復(fù)核
負(fù)責(zé)鐵路以南箱梁箱梁吊裝現(xiàn)場(chǎng)施工
27測(cè)量工程師
測(cè)量及復(fù)核
負(fù)責(zé)鐵路以北箱梁箱梁吊裝現(xiàn)場(chǎng)施工
28測(cè)量工程師
測(cè)量及復(fù)核
29質(zhì)量部質(zhì)量總監(jiān)負(fù)責(zé)箱梁吊裝過程總體質(zhì)量管理
30安全工程師鐵路以北箱梁吊裝現(xiàn)場(chǎng)安全生產(chǎn)管理
安全部
31安全工程師鐵路以南箱梁吊裝現(xiàn)場(chǎng)安全生產(chǎn)管理
綜合辦公
32辦公室主任行政辦公、后勤保障
室
3.2各項(xiàng)資源供應(yīng)方式
項(xiàng)目為施工總承包,箱梁吊裝隊(duì)伍為專業(yè)分包隊(duì)伍,人員、機(jī)械均由隊(duì)伍提供。
表3.2-1分包商進(jìn)出場(chǎng)安排
序號(hào)事項(xiàng)計(jì)劃時(shí)間責(zé)任人
1分包商進(jìn)場(chǎng)2021年7月10日
2南區(qū)兩臺(tái)履帶吊及汽車吊進(jìn)場(chǎng)2021年7月15日
3北區(qū)兩臺(tái)履帶吊及汽車吊進(jìn)場(chǎng)2021年8月25日
4材料進(jìn)場(chǎng)2021年7月18日
5機(jī)械設(shè)備出場(chǎng)2021年10月20日
6分包商出場(chǎng)2021年10月25日
3.3施工流水段的劃分及施工工藝流程
1施工流水段的劃分
箱梁吊裝施工以濟(jì)北鐵路為中斷處,分為南北兩側(cè),施工時(shí)從南北兩端同時(shí)向鐵路
推進(jìn)。
圖3.3-1箱梁吊裝施工順序
2施工工藝流程
施工準(zhǔn)備
履帶吊檢修吊梁于平板拖車上運(yùn)梁設(shè)備檢修
作業(yè)場(chǎng)地修整處理運(yùn)梁至待架橋跨
履帶吊起吊梁體、
履帶吊就位
帶載調(diào)整位置
箱梁落梁就位
梁片間鋼筋橫向連接
平板拖車返回梁場(chǎng)
進(jìn)行第二片梁運(yùn)輸、吊裝
圖3.3-2履帶吊吊裝施工順序
施工準(zhǔn)備
汽車吊檢修吊梁于平板拖車上運(yùn)梁設(shè)備檢修
作業(yè)場(chǎng)地修整處理運(yùn)梁至待架橋跨
汽車吊就位起吊梁體就位
梁片間鋼筋橫向連接
平板拖車返回梁場(chǎng)
進(jìn)行第二片梁運(yùn)輸、吊裝
圖3.3-3汽車吊吊裝施工順序
3.4工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施
表3.4-1重難點(diǎn)分析及對(duì)應(yīng)措施
序重點(diǎn)和難
具體分析應(yīng)對(duì)措施責(zé)任人
號(hào)點(diǎn)
運(yùn)輸過程中安排車輛跟隨,在
箱梁運(yùn)輸時(shí)安全保障十分連荷路-同濟(jì)路路口、同濟(jì)路-
關(guān)鍵,尤其是運(yùn)輸車輛需北外環(huán)路口、北外環(huán)-北二環(huán)
1箱梁運(yùn)輸張喜榮
要轉(zhuǎn)彎時(shí),現(xiàn)場(chǎng)協(xié)調(diào)指揮路口、北二環(huán)-建設(shè)北路路
以及臨時(shí)布置至關(guān)重要???、建設(shè)北路-張拾路路口、
建設(shè)北路、任興路路口做好臨
序重點(diǎn)和難
具體分析應(yīng)對(duì)措施責(zé)任人
號(hào)點(diǎn)
時(shí)交通指揮工作,提前報(bào)備交
通主管部門,必要時(shí)與交警進(jìn)
行協(xié)作,布置反光錐、交通指
示標(biāo)牌和臨時(shí)交通信號(hào)燈,保
證運(yùn)輸車輛轉(zhuǎn)彎安全。
雙機(jī)抬吊是選擇兩臺(tái)規(guī)格相同
箱梁安裝時(shí)采用雙機(jī)抬
的機(jī)械,選擇技術(shù)精湛、經(jīng)驗(yàn)
2箱梁安裝吊,對(duì)吊車司機(jī)的操作能劉洪印
豐富的吊車司機(jī),吊裝過程中
力及配合要求很高。
配備專職指揮人員。
4施工進(jìn)度計(jì)劃
計(jì)劃2021年7月20日開工,2021年10月19日全部竣工,總工期104日歷天。鐵
路南北兩側(cè)在具有施工條件時(shí)可同時(shí)推進(jìn),共有兩個(gè)工作面同時(shí)進(jìn)行,每天每個(gè)工作面
可以完成1跨箱梁的架設(shè)。
表4-1鐵路以南施工計(jì)劃
序號(hào)鐵路以南施工部位架設(shè)時(shí)間
1PM10-PM112021年7月20日
2PM11-PM122021年7月21日
3PM12-PM132021年7月22日
4PM13-PM142021年7月23日
5PM14-PM152021年7月24日
6PM15-PM162021年7月25日
7PM16-PM172021年7月26日
8PM17-PM182021年7月27日
9PM18-PM192021年7月28日
10PM19-PM202021年7月29日
11PM20-PM212021年7月30日
12PM21-PM222021年8月15日
13PM22-PM232021年8月16日
序號(hào)鐵路以南施工部位架設(shè)時(shí)間
14PM23-PM242021年8月17日
15PM24-PM252021年8月18日
16PM25-PM262021年8月19日
17PM26-PM272021年8月20日
18PM28-PM292021年8月21日
19PM29-PM302021年8月28日
20PM08-PM092021年8月29日
21PM09-PM102021年8月30日
22PM07-PM082021年8月31日
23PM30-PM312021年9月1日
24PM31-PM322021年9月2日
25PM32-PM332021年9月3日
26PM33-PM342021年9月10日
27PM38-PM392021年9月11日
28PM39-PM402021年9月13日
29PM0-PM012021年9月13日
30PM01-PM022021年9月14日
31PM02-PM032021年9月15日
32PM03-PM042021年9月16日
33PM04-PM052021年9月17日
34PM36-PM372021年10月1日
35PM37-PM382021年10月2日
36PM40-PM412021年10月3日
37PM41-PM422021年10月5日
表4-2鐵路以北施工計(jì)劃
序號(hào)施工部位架設(shè)時(shí)間
1PM68-PM692021年9月1日
序號(hào)施工部位架設(shè)時(shí)間
2PM67-PM682021年9月2日
3PM66-PM672021年9月3日
4PM65-PM662021年9月10日
5PM64-PM652021年9月11日
6PM63-PM642021年9月12日
7PM62-PM632021年9月13日
8PM61-PM622021年9月14日
9PM60-PM612021年9月15日
10PM44-PM452021年9月17日
11PM43-PM442021年9月19日
12PM51-PM522021年9月25日
13PM52-PM532021年9月26日
14PM53-PM542021年9月27日
15PM54-PM552021年9月28日
16PM55-PM562021年9月29日
17PM56-PM572021年9月30日
18PM57-PM582021年10月1日
19PM58-PM592021年10月2日
20PM45-PM46主線2021年10月9日
21PM46-PM47主線2021年10月10日
22PM47-PM48主線2021年10月11日
23PM48-PM49主線2021年10
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025-2030年中國(guó)硬度計(jì)市場(chǎng)競(jìng)爭(zhēng)格局及投資戰(zhàn)略研究報(bào)告
- 2025-2030年中國(guó)男士護(hù)膚品行業(yè)競(jìng)爭(zhēng)狀況及發(fā)展趨勢(shì)分析報(bào)告
- 2025-2030年中國(guó)電熱線市場(chǎng)運(yùn)行狀況及前景趨勢(shì)分析報(bào)告
- 上海工程技術(shù)大學(xué)《預(yù)防口腔醫(yī)學(xué)》2023-2024學(xué)年第二學(xué)期期末試卷
- 沈陽(yáng)藥科大學(xué)《工業(yè)網(wǎng)絡(luò)與組態(tài)技術(shù)》2023-2024學(xué)年第二學(xué)期期末試卷
- 中南大學(xué)《電動(dòng)汽車原理與設(shè)計(jì)》2023-2024學(xué)年第二學(xué)期期末試卷
- 沈陽(yáng)航空航天大學(xué)北方科技學(xué)院《初中道德與法治課程標(biāo)準(zhǔn)與教材》2023-2024學(xué)年第二學(xué)期期末試卷
- 遼寧中醫(yī)藥大學(xué)杏林學(xué)院《電工儀表與測(cè)量》2023-2024學(xué)年第二學(xué)期期末試卷
- 廣西金融職業(yè)技術(shù)學(xué)院《化工熱力學(xué)》2023-2024學(xué)年第二學(xué)期期末試卷
- 2025年安全員《A證》考試題庫(kù)
- 《政府管制基本理論》課件
- 環(huán)境巖土工程學(xué)課件-東南大學(xué)-潘華良境巖土工程學(xué)概論-9大環(huán)境巖土工程問題
- 《紅樓夢(mèng)》中寶黛之間的愛情與悲劇分析
- 養(yǎng)老產(chǎn)業(yè)并購(gòu)重組
- 2024年1月浙江高考英語聽力考試試題真題完整版答案詳解+MP3文本
- 《SolidWorks建模實(shí)例教程》第5章 裝配建模及實(shí)例
- 口腔科護(hù)理教學(xué)查房
- 《趙匡胤:北宋的開國(guó)皇帝》
- 二年級(jí) 書法 開學(xué)第一課課
- 精神科病人跌倒的預(yù)防與處理
- 蒸壓加氣混凝土砌塊干燥收縮檢測(cè)記錄11969-2020
評(píng)論
0/150
提交評(píng)論