第一章技術(shù)標(biāo)書編制說明............................................................1
第一節(jié)工程概況...............................................................6
1.2周邊環(huán)境.................................................................9
1.3地質(zhì)概況................................................................10
1.4工程特點(diǎn)和難點(diǎn)分析.....................................................10
第二節(jié)標(biāo)書編制的范圍及依據(jù)..................................................11
2.1技術(shù)標(biāo)標(biāo)書編制范圍......................................................11
2.2技術(shù)標(biāo)標(biāo)書編制依據(jù).....................................................11
第三節(jié)投標(biāo)承諾..............................................................11
3.1工程質(zhì)量................................................................11
3.2工程進(jìn)度................................................................12
3.3安全施工................................................................12
3.4文明施工管理目標(biāo)........................................................12
3.5竣工資料................................................................13
第四節(jié)技術(shù)標(biāo)編制原則.........................................................13
第二章施工部署....................................................................75
第一節(jié)施工部署總體安排......................................................15
第二節(jié)施工段的劃分及施工總體流向...........................................15
2.1施工區(qū)段的劃分..........................................................15
2.2施工總體流向............................................................15
第三節(jié)施工準(zhǔn)備..............................................................16
3.1施工現(xiàn)場平面布置說明....................................................16
3.2施工大臨設(shè)施布置.......................................................17
第四節(jié)施工進(jìn)度計(jì)劃..........................................................17
4.1施工進(jìn)度計(jì)劃表..........................................................17
4.2施工進(jìn)度保證措施.......................................................18
第五節(jié)機(jī)械設(shè)備勞動力計(jì)劃....................................................23
5.1主要機(jī)械設(shè)備計(jì)劃表.....................................................23
5.2勞動力計(jì)劃..............................................................24
第三章針對本工程特點(diǎn)的技術(shù)措施...................................................25
第一節(jié)穿越橋洞的方案.........................................................25
1.1工程概述.................................................................25
1.2施工準(zhǔn)備................................................................25
1.3主要技術(shù)措施............................................................25
第二節(jié)高壓線段下管道鋪設(shè)措施................................................26
2.1工程概述................................................................26
2.2施工準(zhǔn)備................................................................26
2.3主要技術(shù)措施............................................................27
第三節(jié)地下管線及構(gòu)筑物保護(hù)措施..............................................27
3.1工程概述................................................................27
3.2監(jiān)測方案................................................................27
3.3地下管線及臨近構(gòu)筑物保護(hù)措施...........................................31
3.4預(yù)計(jì)可能發(fā)生情況的對黃..................................................33
第四節(jié)確保周邊道路及河道暢通措施............................................34
4.1工程概述................................................................34
4.2確保市政道路暢通的措施..................................................34
4.3確保鄉(xiāng)間道路的暢通.....................................................35
4.4確保河道暢通措施.......................................................35
第五節(jié)針對可能出現(xiàn)流沙的防治措施............................................36
5.1工程概述................................................................36
5.2流沙防治措施............................................................36
5.3應(yīng)急措施................................................................36
第四章主要分項(xiàng)工程施工技術(shù)方案...............................................................................................37
第一節(jié)施工測量..........37
1.1工程概述................................................................37
1.2測量依據(jù)................................................................37
1.3軸線及高程測量控制網(wǎng)的平面布置.........................................37
1.4平面控制方法............................................................38
1.5高程控制................................................................39
1.6測量器具一覽表.........................................................40
第二節(jié)溝槽圍護(hù)工程..........................................................40
2.1工程概述................................................................40
2.2溝槽圍護(hù)................................................................41
2.3鋼板樁支護(hù)..............................................................41
第三節(jié)輕型井點(diǎn)降水..........................................................43
3.1工程概述................................................................43
3.2輕型井點(diǎn)工藝流程.......................................................44
3.3輕井施工要點(diǎn)...........................................................44
第四節(jié)溝槽開挖...............................................................45
4.1機(jī)械布置................................................................45
4.2施工要點(diǎn)................................................................46
4.3鋼板樁支護(hù)段開挖.......................................................46
第五節(jié)排管工程...............................................................47
5.1工程概述................................................................47
5.2管道基礎(chǔ)................................................................47
5.3下管....................................................................48
5.4管道接口................................................................48
5.5管道試壓................................................................51
5.6溝槽回填................................................................52
第六節(jié)倒虹管施工.............................................................52
6.1工程概述................................................................52
6.2施工總則................................................................52
6.3施工要點(diǎn)................................................................53
第七節(jié)頂管工程...............................................................54
7.1工程概述................................................................54
7.2沉井工程概況............................................................54
7.3沉井施工................................................................54
7.4頂管施工................................................................62
第八節(jié)管橋施工...............................................................70
8.1工程概述................................................................70
8.2施工流程................................................................70
8.3灌注樁施工..............................................................70
8.4鋼筋艙支架..............................................................75
第九節(jié)沉管工程...............................................................77
9.1工程概述................................................................77
9.2施工工藝................................................................78
第十節(jié)特殊季節(jié)施工技術(shù)措施..................................................82
10.1雨季施工技術(shù)措施.......................................................82
10.2高溫季節(jié)施工技術(shù)措施...................................................83
10.3冬季施工技術(shù)措施......................................................83
第四章質(zhì)量保證措施..........................................................................................................................84
第一節(jié)質(zhì)量承諾及保證體系....................................................84
1.1施工質(zhì)量自報(bào)等級........................................................84
1.2質(zhì)量保證體系............................................................84
1.3質(zhì)量管理責(zé)任制.........................................................85
1.4質(zhì)量管理依據(jù)............................................................90
1.5工程質(zhì)量檢查制度.......................................................90
1.6質(zhì)量管理措施...........................................................92
第二節(jié)分項(xiàng)工程質(zhì)量保證措施..................................................93
2.1工程測量保證措施.......................................................93
2.2工地材料的試驗(yàn)與檢驗(yàn)....................................................93
2.3管道質(zhì)量控制內(nèi)容.......................................................94
2.4鉆孔灌注樁質(zhì)量保證措施..................................................95
2.5模板工程質(zhì)量保證措施....................................................96
2.6鋼筋工程質(zhì)量保證措施...................................................97
2.7混凝土工程質(zhì)量保證措施..................................................98
2.8頂管工程質(zhì)量保證措施....................................................99
2.9沉管工程質(zhì)量保證措施...................................................101
第三節(jié)質(zhì)量通病預(yù)防措施......................................................102
3.1排管工程...............................................................102
3.2頂管工程質(zhì)量痛病防治措施...............................................105
第五章工程安全保證措施..............................................................................................................107
第一節(jié)安全管理方針與目標(biāo)..................................................107
1.1安全管理方針...........................................................107
1.2安全管理目標(biāo)...........................................................107
1.3管理目標(biāo)分解...........................................................107
第二節(jié)安全組織保證體系.....................................................107
第三節(jié)安全教育程序、活動及檢查............................................109
3.1安全教育程序...........................................................109
3.2安全活動...............................................................109
3.3安全檢查...............................................................110
第四節(jié)現(xiàn)場安全管理制度.....................................................110
4.1施工組織設(shè)計(jì)...........................................................110
4.2安全責(zé)任制度...........................................................111
4.3安全教育和交底.........................................................111
4.4強(qiáng)化安全檢查制度.......................................................111
4.5安全設(shè)施...............................................................Ill
4.6安全例會制度...........................................................112
4.7值班制度...............................................................112
4.8七牌二圖”..............................................................112
4.9大型設(shè)備管理制度:.....................................................112
4.10特種作業(yè)人員..........................................................112
4.11防火制度...............................................................113
第五節(jié)現(xiàn)場施工安全(技術(shù))措施............................................113
5.1土方工程安全保證措施...................................................113
5.2模板工程安全保證措施..................................................114
5.3鋼筋工程安全保證措施..................................................115
5.4混凝土工程安全保證措施.................................................116
5.5施工用電安全保證措施...................................................116
5.6機(jī)械施工安全保證措施..................................................118
5.7消防措施...............................................................120
第六章確保文明工地的措施............................................................................................................121
第一節(jié)文明施工措施.........................................................121
1.1文明施工目標(biāo)...........................................................121
1.2文明施工保證體系.......................................................121
13文明施工管理具體措施....................................................122
1.4現(xiàn)場標(biāo)準(zhǔn)化管理保證措施.................................................125
第二節(jié)施工協(xié)調(diào)與環(huán)境保護(hù)...................................................127
2.1施工協(xié)調(diào)措施...........................................................127
2.2環(huán)境保護(hù)措施...........................................................128
第七章工程承包管理、施工配合措施...........................................................................................130
第一節(jié)施工管理的責(zé)任.......................................................130
第二節(jié)組織機(jī)構(gòu)與職責(zé).......................................................130
第三節(jié)施工管理措施.........................................................131
3.1施工準(zhǔn)備...............................................................131
3.2綜合平衡...............................................................131
3.3質(zhì)量監(jiān)控...............................................................132
3.4對工程進(jìn)度的控制......................................................136
3.5對施工技術(shù)的管理.......................................................138
3.6對安全、文明施工的管理.................................................140
第四節(jié)與設(shè)計(jì)、監(jiān)理的配合辦調(diào)..............................................141
4.1與監(jiān)理單位的配合協(xié)調(diào)...................................................141
4.2與設(shè)計(jì)單位的配合協(xié)調(diào)...................................................142
附件一、施工進(jìn)度計(jì)劃表..................................................................................................................144
附件二、施工方案附圖......................................................................................................................145
第一章技術(shù)標(biāo)書編制說明
第一節(jié)工程概況
?工程名稱:*******原水管道擴(kuò)建工程
?工程地點(diǎn):青浦區(qū)朱家角鎮(zhèn)
?工程概況:本工程是由上海市政工程設(shè)計(jì)研究院設(shè)計(jì)的*******
原水管道擴(kuò)建工程O*******是青浦中部地區(qū)的一座現(xiàn)
代化集中水廠,隨著*******的服務(wù)范圍的擴(kuò)大,以及
青浦區(qū)經(jīng)濟(jì)的快速發(fā)展,最高日供水量達(dá)到10.05萬
M3/d,已滿負(fù)荷運(yùn)行,迫切需要進(jìn)行第二水廠原水管
道擴(kuò)建。該擴(kuò)建工程建設(shè)規(guī)模為從太浦河原水廠至第
二水廠鋪設(shè)一根DN1600的鋼管原水輸水管,長度為
15.5KM(其中練塘段長度約7.2KM,朱家角段長度約
8.3KM)O原水管道埋設(shè)深度按抗浮要求和不影響耕作
及農(nóng)作物生長為原則考慮,覆土大于1.2M。
?主要工程施工內(nèi)容:鋪設(shè)方式分暗埋段、管橋、倒虹管、頂管、沉
管筆,管道埋設(shè)深度、劃分等見表1T:
表IT
區(qū)間管道直徑鋪設(shè)形式埋深(米)距離(米)
練塘段
取水泵站?太浦河大橋DN1200暗埋2.484
穿越太浦河大橋DN1600暗埋3.2?4.980
太浦河向北?清水港DN1600暗埋2.8?3.21243
過清水港DN1600管橋/86
清水港~溯甸河DN1600暗埋2.8?4.2611
過海甸河DN1600管橋/45
海甸河?攔路港DN1600暗埋2.8?3.4712
過攔路港DN1600頂管/374
攔路港?石河南側(cè)DN1G00喑埋2.8-5.51296
過石河DN1600管橋/48
石河?2號無名河DN1600暗埋2.9?3.0750
過2號無名河DN1600管橋/59
2號無名河?朱海河DN1600暗埋2.8?3.4649
過朱海河DN1600頂管/218
朱海河?沈太河DN1600暗埋2.9?4.4873
過沈太河DN1600管橋/52
沈太河?沈磚路DN1600暗埋2.8?3.3458
朱家角段
沈太路?沈磚路N號河DN1600暗埋2.9?4.41034
過沈磚路N號河DN1600管橋/66
沈磚路N號河?P號河DN1600暗埋2.8?3.3160
過P號河DN1600倒虹管7.448
P號河?東莊灣橋DN1600暗埋2.9?3.4220
過東莊灣橋DN1600管橋/46
東莊灣橋?過沈磚路DN1600暗埋2.864
過沈彼路DN1600頂管/41
過沈磚路?新1號橋DN1600暗埋2.8?3.4621
過新1號河DN1600管橋/44
新1號河?新2號河DN1600暗埋2.8-4.1704
過新2號河DN1600倒虹管7.653
新2號河?新3號河DN1600暗埋2.8?3.0270
過新3號河DN1600管橋/45
新3號河?新4號河DN1600暗埋2.8?2.9120
過新4號河DN1600管橋/45
新4號河?新5號河DN1600暗埋2.9380
過新5號河DN1600管橋/56
新5號河?新6號河DN1600暗埋2.8—3.1556
過新6號河DN1600管橋/45
新6號河?新7號河DN1600暗埋2.8?2.9482
過新7號河DN1600管橋/59
新7號河?新8號河DN1600暗埋2.8?3.0432
過新8號河DN1600管橋/47
新8號河?滬青平高速DN1600暗埋2.8?4.9798
穿越滬青平高速DN1600暗埋2.965
滬青平高速?無名河DN1600暗埋2.9-3.0264
過無名河DN1600管橋/47
無名河?新開河DN1600暗埋2.8?3.2750
過新開河DN1600管橋/51
新開河?西大盈港DN1600暗埋2.8-3.0346
西大盈港?二水廠DN1600沉管/79
1.2周邊環(huán)境
本工程練塘段從原水廠引出穿越太浦河橋墩后,向北沿朱楓路東
側(cè)紅線至石河以北186m后向東轉(zhuǎn),沿途主要經(jīng)過農(nóng)田至沈太路,穿越
沈太路后,沿沈太路東側(cè)往北走向,到達(dá)沈磚路進(jìn)入朱家角段,然后
右轉(zhuǎn)向東沿沈磚路南側(cè)走向,過了東莊灣橋后穿過沈磚路沿沈磚路北
側(cè)走過一段后,轉(zhuǎn)向往北沿外塘河,此段為農(nóng)田,在滬青平高速橋墩
下穿過后沿西大盈港一直向北穿越農(nóng)田后,轉(zhuǎn)向東過西大盈港到二水
r,見附圖1。
1.3地質(zhì)概況
本工程由于業(yè)主未提供詳細(xì)的地質(zhì)勘察資料,從現(xiàn)有的資料分析,
本工程管道埋深在3m?4m左右,基本處于淤泥質(zhì)粉質(zhì)粘土,極易發(fā)生
流沙現(xiàn)象,施工時必須準(zhǔn)備好防流沙措施及應(yīng)急措施。
1.4工程特點(diǎn)和難點(diǎn)分析
?線路長涉及到場地范圍相當(dāng)大。
?本工程管道鋪設(shè)方案多,涉及到頂管、沉管、管橋、暗埋等。
?周邊環(huán)境復(fù)雜,施工中會碰到綠化、道路、河道、橋梁、農(nóng)田、
高壓線等。
?本工程土質(zhì)差。
?工期較緊。施工組織要求高。
?由于業(yè)主未提供詳細(xì)的地下管線圖,估計(jì)在穿越市政道路及鄉(xiāng)
間道路時將碰到地下管線
第二節(jié)標(biāo)書編制的范圍及依據(jù)
2.1技術(shù)標(biāo)標(biāo)書編制范圍
*******原水管道擴(kuò)建工程施工圖所示的全部內(nèi)容,本標(biāo)書主要對
管道暗埋、頂管、沉管、管橋施工及本工程特點(diǎn)作了詳述。
2.2技術(shù)標(biāo)標(biāo)書編制依據(jù)
?本工程招標(biāo)文件及有關(guān)設(shè)計(jì)圖紙。
?招標(biāo)補(bǔ)遺文件。
?現(xiàn)場踏勘情況。
?有關(guān)的技術(shù)標(biāo)準(zhǔn)、現(xiàn)行的國家及地方規(guī)范:
第三節(jié)投標(biāo)承諾
3.1工程質(zhì)量
嚴(yán)格按照IS0-9001質(zhì)量保證體系的管理要求和管理標(biāo)準(zhǔn)進(jìn)行本
工程的質(zhì)量管理,充分發(fā)揮我公司技術(shù)、質(zhì)量管理的優(yōu)勢,對質(zhì)量保
證體系、施工過程質(zhì)量管理制度、分部分項(xiàng)工程質(zhì)量保證措施、質(zhì)量
通病防治以及質(zhì)量管理等各方面做好嚴(yán)格、詳細(xì)的規(guī)定并貫徹實(shí)施。
我公司將強(qiáng)化對以上施工質(zhì)量控制關(guān)鍵程序的管理和控制,并根
據(jù)招標(biāo)文件所規(guī)定的質(zhì)量和技術(shù)要求,嚴(yán)格按照招標(biāo)文件所附施工技
術(shù)規(guī)范標(biāo)準(zhǔn)和上海市有關(guān)的技術(shù)、質(zhì)量規(guī)定,通過在工程施工過程中
強(qiáng)化質(zhì)量保證和控制體系、加強(qiáng)原材料質(zhì)量管理、過程質(zhì)量管理,確
保本工程質(zhì)量達(dá)到驗(yàn)收合格。
3.2工程進(jìn)度
本公司結(jié)合以前曾施工過的同類型工程的經(jīng)驗(yàn),通過優(yōu)化施工組
織設(shè)計(jì),投入足夠的勞動力及機(jī)械設(shè)備,通過方案優(yōu)化,確保工程在
230天之內(nèi)全部完工,比招標(biāo)文件要求的工期提前20天。
3.3安全施工
我公司承諾每位進(jìn)入現(xiàn)場的施工人員必須接受一次培訓(xùn),項(xiàng)目部
按區(qū)段設(shè)專職安全員二名,分別負(fù)責(zé)練塘段和朱家角段。每周一組織
對所有施工人員進(jìn)行上周工作講評,并布置下周工作注意事項(xiàng),確保
整個施工過程中重大安全事故為零。
3.4文明施工管理目標(biāo)
我公司承諾施工現(xiàn)場大臨設(shè)施嚴(yán)格按標(biāo)準(zhǔn)化搭設(shè),現(xiàn)場材料嚴(yán)格
按業(yè)主指定點(diǎn)堆放,確保周邊道路、河道交通暢通,施工現(xiàn)場必須有
防污染及防塵措施,確保施工現(xiàn)場達(dá)到文明工地標(biāo)準(zhǔn)。
3.5竣工資料
我公司將在本工程設(shè)置專職資料管理員,在施工過程中按照上海
市建委、市檔案局、市政局和甲方的有關(guān)文件規(guī)定,進(jìn)行竣工資料的
收集、整理和歸檔工作。當(dāng)工程具備竣工條件時,及時向業(yè)主提供完
整的,符合國家及質(zhì)量監(jiān)督站工程竣工驗(yàn)收規(guī)定的竣工驗(yàn)收報(bào)告、竣
工資料和竣工圖。
第四節(jié)技術(shù)標(biāo)編制原則
(1)遵守招標(biāo)文件、招標(biāo)補(bǔ)充文件條款的原則:在編制施工組織
設(shè)計(jì)文字說明及附表中,嚴(yán)格按照招標(biāo)文件的要求,嚴(yán)格貫徹《*******
原水管道擴(kuò)建工程》招標(biāo)文件及招標(biāo)補(bǔ)充文件的精神要求編制。
(2)遵守設(shè)計(jì)圖紙、文件和規(guī)范進(jìn)行編制的原則:編制施工組織
設(shè)計(jì)的過程中,嚴(yán)格遵守現(xiàn)行施工規(guī)范和質(zhì)量檢驗(yàn)標(biāo)準(zhǔn),遵守設(shè)計(jì)圖
紙的要求。
(3)堅(jiān)持實(shí)事求是,一切從實(shí)際出發(fā)的原則:施工組織設(shè)計(jì)的編
制,一切從本公司現(xiàn)有的實(shí)際施工能力、經(jīng)濟(jì)實(shí)力、技術(shù)水平出發(fā),
堅(jiān)持科學(xué)組織,合理安排,均衡生產(chǎn),確保高速度、高質(zhì)量、安全、
文明地完成*******原水管道擴(kuò)建工程項(xiàng)目建設(shè)。
(4)堅(jiān)持方案編制結(jié)合工程實(shí)際的原則:本技術(shù)標(biāo)的編制,一切
建立在對工程周邊環(huán)境、河道、道路交通、村莊狀況詳細(xì)調(diào)查研究、
對工程設(shè)計(jì)圖紙及設(shè)計(jì)要求仔細(xì)學(xué)習(xí)理解、對招標(biāo)文件深刻理解的基
礎(chǔ)上,同時考慮本工程線路長、沿線經(jīng)過的河道多及多種施工工藝等,
做到方案編制切合工程實(shí)際、有針對性、有目的性C
(5)一切從保障工程高速、優(yōu)質(zhì)、安全地完成,保證周邊地面道
路、鄉(xiāng)村道路、河道安全、交通通暢,保證地區(qū)環(huán)境的角度出發(fā)編制
本工程技術(shù)標(biāo)書的原則。
(6)堅(jiān)持積極推廣“四新”成果的原則:在各工序的施工中,對
于能夠提高工程質(zhì)量、進(jìn)度、降低成本的新技術(shù)、新工藝、新材料、
新設(shè)備,積極地采用推廣,提高工程施工的科技含量。
(7)堅(jiān)持專業(yè)化作業(yè)和綜合管理相結(jié)合的原則:施工組織方面,
發(fā)揮專業(yè)施工隊(duì)伍的優(yōu)勢,同時采用綜合管理手段,合理調(diào)配,達(dá)到
整體優(yōu)化,保證工程施工進(jìn)度、質(zhì)量、安全目標(biāo)全面實(shí)現(xiàn)的目的。
智建領(lǐng)航者
第二章施工部署
第一節(jié)施工部署總體安排
木工程線路長,工程范圍大、工期短,工程施工組織的過程中,
必須合理的劃分好施工區(qū)域及施工流程,施工前期由項(xiàng)目經(jīng)理組織施
工人員仔細(xì)踏勘現(xiàn)場,主要了解地下管線分布、河道深度與通航狀況、
地質(zhì)水文資料、魚塘現(xiàn)狀等。根據(jù)工程實(shí)際情況以及雨季月份安排好
各施工段。及早確定切合現(xiàn)場實(shí)際情況的施工方案,組織施工,確保
工程工期和質(zhì)量。
第二節(jié)施工段的劃分及施工總體流向
2.1施工區(qū)段的劃分
為確保工程施工總進(jìn)度,根據(jù)工程特點(diǎn),先按設(shè)計(jì)圖紙劃分兩大
塊,即練塘段和朱家角段,兩大塊內(nèi)再按施工專業(yè)劃分,即頂管施工
作業(yè)組、沉管施工作業(yè)組、管橋施工作業(yè)組、暗埋段施工作業(yè)組。由
于暗埋段路程長可再按長度及現(xiàn)場實(shí)際狀況再劃分若干施工區(qū),本工
程兩大塊暗埋段考慮各投入一支作業(yè)隊(duì)。
2.2施工總體流向
練塘段本工程前期階段可先考慮沿朱楓路及沈太路段施工,朱家角
智建領(lǐng)航者
智建領(lǐng)航者
段前期可施工沿沈磚路,上述區(qū)段由于就在路邊,可免去施工便道修
筑,而其余區(qū)段由于都是在農(nóng)田內(nèi),因此施工前期應(yīng)抓緊施工便道的
修筑。各區(qū)段內(nèi)各專業(yè)作業(yè)隊(duì)伍可平行展開。
在施工段內(nèi)有苗木影響施工,前期必須盡快測量定位,確定苗木
影響范圍,并書面通知業(yè)主。
第三節(jié)施工準(zhǔn)備
3.1施工現(xiàn)場平面布置說明
3.1.1施工用電
本工程業(yè)主提供電源300KW,但由于線路太長達(dá)到15.5KM,電纜
無法布置這么長,本工程主要用電是鉆孔灌注樁施工,鋼管的焊接及
夜間照明,頂管施工等。解決施工用電的方法是:
?配備四臺100KW的柴油發(fā)電機(jī),并配備1KM電纜;
?沿線向工廠企業(yè)借電;
3.1.2施工用水
本工程用水狀況基本同用電狀況,解決施工用水的方法是向周圍
工廠企業(yè)借水,施工用水主要用于頂管、管橋施工等,暗埋段相對用
的較少。經(jīng)過化驗(yàn)后在設(shè)計(jì)同意下也可考慮利用現(xiàn)有的河水。
智建領(lǐng)航者
智建領(lǐng)航者
3.1.3施工便道
管道在穿越農(nóng)田處需修筑便道,便道施工方法:素土上鋪筑500
厚建筑垃圾,用壓路機(jī)來回壓實(shí),便道寬度4m,兩側(cè)開挖好排水溝。
跨越河道時架設(shè)臨時軍用梁。
3.2施工大臨設(shè)施布置
大臨設(shè)施搭設(shè)位置考慮在靠近沈磚路或朱楓路一側(cè),具體位置待
中標(biāo)后確定,搭設(shè)臨時主要解決施工指揮辦公室、監(jiān)理及業(yè)主辦公室
等,并配備必要設(shè)施。項(xiàng)目部在現(xiàn)場配備若干車輛及自行車。
各區(qū)段施工人員食宿可就近解決,考慮可借用附近民宅作為住宿辦
公。
第四節(jié)施工進(jìn)度計(jì)劃
4.1施工進(jìn)度計(jì)劃表
本工程計(jì)劃開工日期暫定為2004年10月20日,實(shí)際開工日期按
批準(zhǔn)的開工報(bào)告或按照協(xié)定的開工日期為準(zhǔn),招標(biāo)文件要求工期為
250天,我公司自報(bào)工期230天,詳見施工進(jìn)度計(jì)劃表。
智建領(lǐng)航者
智建領(lǐng)航者
4.2施工進(jìn)度保證措施
本工程展開面大、占地范圍大,要確保施工進(jìn)度滿足合同規(guī)定的
期限,就必須做好圖紙、技術(shù)方案、組織管理、計(jì)劃調(diào)整、物資材料
供應(yīng)等方面的工作,我公司具有豐富的進(jìn)度管理經(jīng)驗(yàn),結(jié)合本工程的
實(shí)際情況,我們準(zhǔn)備從以下幾方面入手,控制本工程的施工總進(jìn)度:
4.2.1圖紙保證
將工程施工圖紙的設(shè)計(jì)工作規(guī)劃在總進(jìn)度控制的概念下,我公司
將委派專人主動與設(shè)計(jì)單位聯(lián)系,約定施工圖到位的時間,為施工創(chuàng)
造條件。
4.2施工技術(shù)保證
充分認(rèn)識本工程施工的難點(diǎn)、特點(diǎn),針對性的編制施工技術(shù)方案、
同土建施工單位接口等做好周全詳細(xì)的考慮,在此基礎(chǔ)上運(yùn)用新技術(shù)、
新工藝來縮短各個施工工序的施工周期,以科技保障施工進(jìn)度。
我司將本工程整體劃分為多個施工區(qū)。同時施工,配備充分的施
工技術(shù)管理力量、機(jī)械設(shè)備力量以保證施工工期。
做好季施工技術(shù)措施,制定針對雨季施工的針對性施工方案,避
免雨季施」:對工程進(jìn)度造成的影響。
工程正式開工前一周,做好施工組織設(shè)計(jì)、分項(xiàng)工程施工方案的
編制和審查工作,并在施工過程中貫徹實(shí)施、及時調(diào)整。
智建領(lǐng)航者
智建領(lǐng)航者
4.3編制合理的施工計(jì)劃
及時做好各項(xiàng)準(zhǔn)備工作,確定交通運(yùn)輸組織方案、進(jìn)度計(jì)劃及勞
動力供應(yīng)計(jì)劃、制定機(jī)械設(shè)備進(jìn)出場計(jì)劃以及材料供應(yīng)計(jì)劃。
組織和協(xié)調(diào)好本工程各施工段流水的銜接,確保工程按期完成。
編制合理的施工總進(jìn)度計(jì)劃及周、月、旬施工進(jìn)度計(jì)劃,確定工
程進(jìn)度控制關(guān)鍵節(jié)點(diǎn),在施工過程中按照實(shí)際進(jìn)度狀況進(jìn)行及時的調(diào)
整。
4.4施工組織保證
中標(biāo)后,我公司將在最短時間內(nèi)進(jìn)場,盡快熟悉工程情況,全面
了解影響工期的各方面因素。項(xiàng)目經(jīng)理部認(rèn)真研究并根據(jù)投標(biāo)書為藍(lán)
本,制定出詳盡的工期進(jìn)度計(jì)劃,與分包施工隊(duì)伍協(xié)調(diào),包括其施工
計(jì)劃的細(xì)化優(yōu)化。
由項(xiàng)目經(jīng)理主持召開每周一次的項(xiàng)目經(jīng)理部會議,對本工程施工
進(jìn)度、物資、勞動力、資金和設(shè)備進(jìn)行調(diào)度和平衡,解決施工過程中
的各類矛盾和問題,使本工程順利進(jìn)行。
項(xiàng)目經(jīng)理部以周計(jì)劃控制分部分項(xiàng)工程進(jìn)度,按計(jì)劃要求每周召
開一次平衡調(diào)度會,及時解決勞動力,施工材料、設(shè)備調(diào)度問題,確
保工程按計(jì)劃實(shí)施。
在本工程施工期間,按工程進(jìn)度需要,取消節(jié)假日、休息日,并
智建領(lǐng)航者
智建領(lǐng)航者
采用2?3班制晝夜施工方法來縮短工期,并配備足夠的勞動力。
加強(qiáng)施工組織管理,使各分部分項(xiàng)工序以最大限度進(jìn)行合理搭接,
保證施工流水能按計(jì)劃正常運(yùn)轉(zhuǎn)。前道工序施工為后道工序創(chuàng)造良好
環(huán)境,提高工作效率。
充分發(fā)揮我公司施工組織管理的優(yōu)勢,以總承包形式,組織多支
成建制的作業(yè)隊(duì),由項(xiàng)目經(jīng)理部分派管理人員按工序、分區(qū)域、流水
段交叉施工,進(jìn)行全過程監(jiān)控,確保工期目標(biāo)實(shí)現(xiàn)c
成立施工協(xié)調(diào)小組,加強(qiáng)與業(yè)主、周邊施工單位、有關(guān)政府部門
的協(xié)調(diào)工作,為保證本工程順利實(shí)施,提供有利條件。
4.5進(jìn)度計(jì)劃的落實(shí)與調(diào)整
制定的施工進(jìn)度計(jì)劃必須嚴(yán)格執(zhí)行,項(xiàng)H部將組織每周一次的生
產(chǎn)協(xié)調(diào)會,總結(jié)已完成的工作,并對下周的工作進(jìn)行規(guī)劃。充分聽取
各施工單位的意見,同時對各單位的進(jìn)度情況進(jìn)行考核與講評,
定期對工程進(jìn)度進(jìn)行檢查,對照總進(jìn)度計(jì)劃比較實(shí)際進(jìn)度是否提
前或滯后,如果發(fā)現(xiàn)某一工序進(jìn)度有滯后的現(xiàn)象,及時采取有力的措
施,如增加人力、物力和機(jī)具,搶回延誤的工期。
4.6物資資料與機(jī)械設(shè)備保證
為加快施工進(jìn)度,視施工進(jìn)度需要,組織設(shè)備、材料超常規(guī)投入,
配備足夠的設(shè)備和材料,保證工程施工順利進(jìn)行。
智建領(lǐng)航者
智建領(lǐng)航者
充分利用本公司的機(jī)械設(shè)備優(yōu)勢,調(diào)配、補(bǔ)充、租賃以滿足工程
需要,目前我公司已聯(lián)系、儲備了大量的施工機(jī)械,可滿足工程急需
串換要求,隨時可調(diào)運(yùn)現(xiàn)場,為加快工程進(jìn)度作有力保證。
我們將充分做好物資材料與機(jī)械設(shè)備的供應(yīng)計(jì)劃,充分利用現(xiàn)階
段人力市場資源,組織大量的勞動力,配備大量的機(jī)械設(shè)備用于本工
程施工,確保工程進(jìn)度。
根據(jù)所劃分的施工區(qū)域各自獨(dú)立組織流水施工,在材料的供應(yīng)上,
根據(jù)每一施工區(qū)域需用的施工機(jī)械和材料計(jì)劃,做好工程信息的收集、
反饋和調(diào)整,作到及時充足,并在施工過程中加以調(diào)整
4.7勞動力保證
根據(jù)方案實(shí)施要求及施工進(jìn)度和勞動力需求計(jì)劃,集結(jié)施工隊(duì)伍,
組織勞動力分批進(jìn)場,并建立相應(yīng)的領(lǐng)導(dǎo)體系和管理制度。
據(jù)工程項(xiàng)目需要,以本公司所使用的合格分包商作為評審和選擇
對象,并采用招標(biāo)形式選擇出合格的勞務(wù)施工隊(duì)伍,優(yōu)先選擇獲得優(yōu)
良工程的勞務(wù)分包。
項(xiàng)目總承包部按月對勞務(wù)分包商的作業(yè)簽發(fā)《合同履約單》,安排
施工任務(wù),并檢查監(jiān)督分包商作業(yè)隊(duì)的操作質(zhì)量,安全生產(chǎn)和現(xiàn)場用
料落手清,并提供證實(shí)資料,作出中途留退勞務(wù)分包商的決定。
4.8其他方面的保證
智建領(lǐng)航者
智建領(lǐng)航者
實(shí)施全過程質(zhì)量過程管理,降低一般質(zhì)量事故發(fā)生頻率,杜絕重
大質(zhì)量事故,減少質(zhì)量對進(jìn)度的影響。
抓好現(xiàn)場安全、消防、保衛(wèi)工作和衛(wèi)生工作,搞好文明施工,杜
絕重大安全事故和疫情的發(fā)生,保證工程順利進(jìn)行C
成立對外協(xié)調(diào)小組,各施工區(qū)域?qū)H藢谧骱脤ν鈪f(xié)調(diào)工作,減
少工程外部環(huán)境影響。
智建領(lǐng)航者
智建領(lǐng)航者
第五節(jié)機(jī)械設(shè)備勞動力計(jì)劃
5.1主要機(jī)械設(shè)備計(jì)劃表
額定功
機(jī)械或
序號規(guī)格型號數(shù)量率用途
設(shè)備名稱
(kW)
1反鏟挖土機(jī)DH-2804臺132挖土
2液壓頂管機(jī)200t2套頂管
3潛水鉆機(jī)LK-6502臺40鉆孔樁
BXs-300
4交流電焊機(jī)12臺23.4鋼管焊接等
-2A
5位攪拌機(jī)J3506臺3拌碎
6抓斗挖土機(jī)W10012臺沉井挖土
7蛙式夯土機(jī)HW-606臺2.8回填
8水泵JQB-471112臺2.2抽水
9挖泥船1只沉管
1
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 原油市場供需分析-洞察分析
- 幼兒急疹預(yù)防接種策略-洞察分析
- 體育賽事數(shù)據(jù)分析-洞察分析
- 梯度材料表面處理技術(shù)-洞察分析
- 腺病與慢性疼痛關(guān)系-洞察分析
- 水電安裝智能化產(chǎn)業(yè)鏈構(gòu)建-洞察分析
- 網(wǎng)絡(luò)博弈算法研究-洞察分析
- 消費(fèi)者需求變化與競爭-洞察分析
- 疫苗研發(fā)與養(yǎng)殖動物免疫-洞察分析
- 水下油氣管道風(fēng)險(xiǎn)評估-洞察分析
- 2024年秋季學(xué)期無機(jī)化學(xué)(藥)期末綜合試卷-國開(XJ)-參考資料
- 市場營銷試題(含參考答案)
- 2025年1月浙江省高中學(xué)業(yè)水平考試政治試卷試題(含答案解析)
- 專題1數(shù)列的通項(xiàng)公式的求法-高二上學(xué)期數(shù)學(xué)人教A版選擇性必修第二冊
- 工程建設(shè)安全專項(xiàng)整治三年行動實(shí)施方案
- 2025年中國帽子行業(yè)發(fā)展現(xiàn)狀、進(jìn)出口貿(mào)易及市場規(guī)模預(yù)測報(bào)告
- 工地高處墜落防范與措施方案
- 電氣工程及其自動化職業(yè)規(guī)劃課件
- 2023年新高考(新課標(biāo))全國2卷數(shù)學(xué)試題真題(含答案解析)
- 級配碎石拌和站建設(shè)方案詳細(xì)
- 水廠停水施工方案
評論
0/150
提交評論