項(xiàng)目專項(xiàng)施工方案
中國建筑集團(tuán)有限公司
CHINASTATECONSTRUCTIONENGINEERINGCORPORATION
房建項(xiàng)目
夾層大型管道支吊架安裝施工方案
xx項(xiàng)目部
二〇二一年四月
1
項(xiàng)目專項(xiàng)施工方案
目錄
目錄............................................................................................................................................................1
第1章編制依據(jù)及說明..................................................................................................................4
1.1編制原則.................................................................................................................................4
1.2編制依據(jù).................................................................................................................................4
第2章工程概況.................................................................................................................................6
第3章工程重難點(diǎn)分析..................................................................................................................7
3.1重難點(diǎn)分析及解決方案..................................................................................................7
第4章施工準(zhǔn)備.................................................................................................................................9
4.1施工準(zhǔn)備工作流程............................................................................................................9
4.2人員、機(jī)械準(zhǔn)備.................................................................................................................9
4.3材料準(zhǔn)備.............................................................................................................................11
4.4技術(shù)準(zhǔn)備.............................................................................................................................11
第5章管線綜合排布及支架選型............................................................................................13
5.1管線綜合排布...................................................................................................................13
5.2支架選型與支架排布....................................................................................................13
5.3管道管托.............................................................................................................................18
第6章管道運(yùn)輸與管道安裝......................................................................................................19
6.1管道運(yùn)輸.............................................................................................................................19
6.2工藝流程:........................................................................................................................19
6.3管材、管件、附屬配件的檢驗(yàn).................................................................................20
1
項(xiàng)目專項(xiàng)施工方案
6.4管道支架制作安裝.........................................................................................................21
6.5管道下料及坡口加工方式...........................................................................................21
6.6管道安裝.............................................................................................................................22
6.7閥門安裝.............................................................................................................................23
第7章管道焊接..............................................................................................................................25
7.1施工一般要求...................................................................................................................25
7.2一般焊接程序...................................................................................................................25
7.3焊接工藝.............................................................................................................................26
7.4焊接檢驗(yàn).............................................................................................................................27
第8章管道試壓與清洗...............................................................................................................29
8.1管道系統(tǒng)試驗(yàn)前應(yīng)具備下列條件............................................................................29
8.2管道水壓試壓、水沖洗................................................................................................29
8.3管道系統(tǒng)試驗(yàn)應(yīng)注意的事項(xiàng)......................................................................................29
8.4管道清洗注意事項(xiàng).........................................................................................................30
第9章管道除銹、防腐施工......................................................................................................31
9.1除銹及污物的清除.........................................................................................................31
9.2防腐.......................................................................................................................................31
第10章質(zhì)量控制措施..................................................................................................................33
10.1質(zhì)量目標(biāo)及分解...........................................................................................................33
10.2主要質(zhì)量控制要點(diǎn).......................................................................................................33
10.3主要質(zhì)量通病防治方法.............................................................................................35
10.4人員及工器具管理.......................................................................................................36
2
項(xiàng)目專項(xiàng)施工方案
10.5標(biāo)識(shí)和可追溯性...........................................................................................................37
第11章質(zhì)量成品保護(hù)措施........................................................................................................39
11.1成品保護(hù)管理措施.......................................................................................................39
11.2專業(yè)成品保護(hù)措施.......................................................................................................39
第12章安全文明施工措施........................................................................................................41
12.1安全施工..........................................................................................................................41
12.2文明施工..........................................................................................................................42
3
項(xiàng)目專項(xiàng)施工方案
第1章編制依據(jù)及說明
1.1編制原則
為了光谷同濟(jì)兒童醫(yī)院項(xiàng)目夾層機(jī)電安裝工程施工的優(yōu)質(zhì)、快速、高效完成,同時(shí)便于
過程上中對(duì)工程質(zhì)量控制,針對(duì)夾層管廊特點(diǎn)和結(jié)合我公司類似工程施工經(jīng)驗(yàn),特編制夾層
通道機(jī)電安裝施工方案,旨在為光谷同濟(jì)兒童醫(yī)院項(xiàng)目機(jī)電安裝專業(yè)提供較完整的技術(shù)指導(dǎo)
性文件并規(guī)范化現(xiàn)場(chǎng)安全文明施工,同時(shí)為監(jiān)理、業(yè)主對(duì)本工程的施工方法、質(zhì)量、工程進(jìn)
度等各方面的詳細(xì)了解提供依據(jù)。
根據(jù)設(shè)計(jì)圖紙中各種管徑的排列形式,確定各支架的選型。由于設(shè)計(jì)中沒有對(duì)重型支架
材料規(guī)格明確規(guī)定,現(xiàn)根據(jù)規(guī)范及現(xiàn)場(chǎng)實(shí)際情況制定方案。重型支架采用優(yōu)質(zhì)槽鋼,以達(dá)到
安全、實(shí)用、美觀的效果。
1.2編制依據(jù)
1.主要技術(shù)文件
深化設(shè)計(jì)圖紙、設(shè)計(jì)變更及洽商記錄、技術(shù)規(guī)格書、規(guī)范圖集等技術(shù)文件。
2.主要標(biāo)準(zhǔn)及技術(shù)規(guī)范
類別名稱編號(hào)或文號(hào)
《給水排水管道工程施工及驗(yàn)收規(guī)范》GB50268-2008
《通風(fēng)與空調(diào)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50243-2016
國標(biāo)《建筑給排水及采暖工程施工質(zhì)量驗(yàn)收規(guī)范》GB50242-2002
《建筑節(jié)能工程施工質(zhì)量驗(yàn)收規(guī)范》GB50411-2014
《建筑材料及制品燃燒性能分級(jí)》GB8624-2019
《輻射供暖供冷技術(shù)規(guī)程》JGJ142-2012
JGJ174-2010
標(biāo)準(zhǔn)《多聯(lián)機(jī)空調(diào)系統(tǒng)工程技術(shù)規(guī)范》
《通風(fēng)管道技術(shù)規(guī)程》JGJ141-2017
4
項(xiàng)目專項(xiàng)施工方案
《金屬、非金屬風(fēng)管支吊架》08K132
《管道穿墻、屋面防水套管》01R409
《室內(nèi)動(dòng)力管道裝置安裝(熱力管道)》01R415
《室內(nèi)管道支吊架》05R417-1
圖集
《管道及設(shè)備保冷》98R419
《管道與設(shè)備保冷》98R419
《管道與設(shè)備保溫》98R418
《室內(nèi)熱力管道支吊架》95R402
5
項(xiàng)目專項(xiàng)施工方案
第2章工程概況
機(jī)電綜合管廊位于兒童醫(yī)院地下室夾層,夾層通道總長度為206米,最寬地方為10米,
高度為1.8m,最窄的地方為2.5m,高度為1.4m。水管2趟管徑為DN100,生活熱水管2趟
管徑為DN80,熱回水管有6趟管徑為DN50,材質(zhì)均采用304薄壁不銹鋼管及配套管件,連
接方式為承插氬弧焊接,管道工作壓力為1.6MPa;
消防供水管及噴淋水管管徑為DN150,材質(zhì)采用內(nèi)外熱鍍鋅鋼管及管件,連接方式為溝
槽卡箍連接,管道工作壓力為1.6MPa;
暖通管道系統(tǒng)龐大、繁雜,管徑大(如:DN300、DN250等),施工難度大。其中蒸汽
管道采用DN300的無縫鋼管,空調(diào)供回水管采用管徑DN150的無縫鋼管,連接方式為焊接,
管道工作壓力為1.6MPa;并且夾層管廊內(nèi)的空調(diào)管道需保溫。
動(dòng)力橋架包含500*200高壓電纜橋架一趟,800*200低壓電源電纜橋架一趟;
弱電500*200信息橋架一趟,消防500*150弱電橋架一趟。
還需要預(yù)留出1500*360的醫(yī)療氣體管線和軌道物流的施工區(qū)域。
夾層管道平面圖
6
項(xiàng)目專項(xiàng)施工方案
第3章工程重難點(diǎn)分析
3.1重難點(diǎn)分析及解決方案
序號(hào)重難點(diǎn)分析解決方案及措施
1、管道的運(yùn)輸:計(jì)算好管道用量,隨土建施工進(jìn)度,將管道及時(shí)
轉(zhuǎn)運(yùn)到夾層通道,利用卷揚(yáng)機(jī)以及炮車進(jìn)行運(yùn)輸。
管道管徑大,在夾
2、管道安裝:利用兩個(gè)5t手動(dòng)葫蘆吊裝配合安裝,安裝順序分為
層通道內(nèi)運(yùn)輸與
1安裝困難。施工空左側(cè)水管綜合支架與右側(cè)橋架綜合支架同時(shí)進(jìn)行。具體步驟為:
間狹小、密閉。
以6-7軸為基準(zhǔn),先制作好6-7軸交1-Y2~1-L兩側(cè)豎直端與橫端
支架,然后焊接形成整體支架,再將鋼管通過手動(dòng)葫蘆吊裝系統(tǒng)移
至6-7軸東夾層,從北向南依次施工。
1、支架采用優(yōu)質(zhì)槽鋼,對(duì)管道進(jìn)行滿水重量計(jì)算,力均分到每個(gè)
管道工程量大,系支架,根據(jù)材料力學(xué)進(jìn)行受力分析,得到支架承重最大彎矩點(diǎn),計(jì)
統(tǒng)復(fù)雜,支架用量
龐大,其中受力集算出支架受到的最大彎曲正應(yīng)力,同時(shí)對(duì)槽鋼進(jìn)行扭矩計(jì)算,確保
2
中,對(duì)支架材質(zhì)、支架安全可靠。
規(guī)格要求嚴(yán)格。
2、支架與墻面及地面的支撐點(diǎn)采用預(yù)埋鋼板的做法,確保支架的
穩(wěn)定性。
1、管道焊接:保證焊接質(zhì)量和焊接效率,防止返工。支架根據(jù)現(xiàn)
場(chǎng)情況逐一核實(shí)定位,保證排布不但要安全可靠,還要美觀;
管道系統(tǒng)嚴(yán)密性
2、安裝施工之前,對(duì)夾層管廊施工的管道進(jìn)行綜合排布,確保焊
3要求高,對(duì)于管道
接施工空間。
焊接要求高。
3、支吊架與鋼板焊接處需要滿焊,同時(shí)在250*250鋼板(10mm厚)
上打14號(hào)膨脹螺栓,螺栓對(duì)稱排布。
7
項(xiàng)目專項(xiàng)施工方案
1、對(duì)于標(biāo)高的復(fù)核與引線,根據(jù)土建放線,各施工部將土建所放
施工過程中對(duì)于
的標(biāo)高線引到同一軸線上進(jìn)行復(fù)核,復(fù)核誤差確保在5mm內(nèi)。
4管道與支架標(biāo)高
2、施工過程中利用水平儀放線確保安裝支架在同一直線上。
限制嚴(yán)格。
3、支架安裝過程中確保支架底部距地面凈空滿足設(shè)計(jì)要求。
8
項(xiàng)目專項(xiàng)施工方案
第4章施工準(zhǔn)備
4.1施工準(zhǔn)備工作流程
4.2人員、機(jī)械準(zhǔn)備
根據(jù)夾層通道空調(diào)水工程量合理安排勞務(wù)人員數(shù)量和機(jī)具設(shè)備臺(tái)班。
1.勞動(dòng)力計(jì)劃表
工期節(jié)點(diǎn)計(jì)劃
軸線時(shí)間節(jié)點(diǎn)
1-Y1~1-P交6-7軸3.1~3.31
1-P~1-D交8-10軸4.1~4.30
1-Y6~1-Y1交8-10軸4.10~4.30
B-1~B-10交B-A~B-C軸5.1~5.16
夾層通道勞動(dòng)力計(jì)劃表
2023年
工種
3.1-4.104.10-5.16
9
項(xiàng)目專項(xiàng)施工方案
焊工24
普工1212
管道工88
總計(jì)2222
2.主要機(jī)械需用計(jì)劃表
主要機(jī)械需用計(jì)劃表
序號(hào)機(jī)械或設(shè)備名稱型號(hào)規(guī)格數(shù)量額定功率生產(chǎn)能力用于施工部位
1手動(dòng)葫蘆5t/3t/2t4套5t/3t/2t設(shè)備吊裝
2臺(tái)鉆Z4116/2B2臺(tái)1kWφ405支架制作安裝
3沖擊鉆TE-255臺(tái)1.5kWφ25支吊架安裝等
4鋼管切割機(jī)CC4202臺(tái)1kW不銹鋼管斷管
φ16~
5液壓沖孔機(jī)SH-10(B)3臺(tái)2kW沖孔
104
6交直流電焊機(jī)BX3-30020臺(tái)2.5kW支架制作安裝
7電錘D16-222臺(tái)5kW支架制作安裝
8坡口機(jī)WS-200A5臺(tái)5.1kW鋼管坡口
600*500*75
94
電焊條烘干箱0臺(tái)焊條烘干
10電動(dòng)試壓泵3D-SY6臺(tái)6kW100kg管道試壓
11手動(dòng)試壓泵SY-256臺(tái)25kg管道試壓
12等離子切割機(jī)ACL31004臺(tái)3kW管道加工制作
13移動(dòng)腳手架1個(gè)管道加工
14臨時(shí)配電箱5套管道安裝
10
項(xiàng)目專項(xiàng)施工方案
4.3材料準(zhǔn)備
在正式安裝開始之前,所需的無縫鋼管、鍍鋅鋼管、槽鋼、波紋補(bǔ)償器等材料進(jìn)場(chǎng),并
經(jīng)過專業(yè)監(jiān)理工程師及業(yè)主的現(xiàn)場(chǎng)共同驗(yàn)收合格后方可使用,并做好相關(guān)檢查驗(yàn)收工作,達(dá)
到相關(guān)要求后方能安裝。
主要管材一覽表
專業(yè)系統(tǒng)名稱安裝位置管材型號(hào)長度/m
無縫鋼管DN300104
無縫鋼管DN250320
無縫鋼管DN200610
暖通系統(tǒng)夾層通道
無縫鋼管DN35070
無縫鋼管DN60050
無縫鋼管DN400331
不銹鋼管DN150200
不銹鋼管DN100120
給水系統(tǒng)夾層通道
不銹鋼管DN80250
不銹鋼管DN50700
消防系統(tǒng)夾層通道鍍鋅鋼管DN2001640
4.4技術(shù)準(zhǔn)備
1.圖紙會(huì)審工作
認(rèn)真熟悉圖紙、深刻理解設(shè)計(jì)意圖及設(shè)計(jì)要求,檢查設(shè)計(jì)圖紙和資料內(nèi)容是否符合有關(guān)
施工規(guī)范;設(shè)計(jì)圖紙是否齊全,圖紙本身及相互之間有無矛盾和錯(cuò)誤、圖紙與設(shè)計(jì)說明是否
一致,將所發(fā)現(xiàn)的問題在圖紙會(huì)審時(shí)提出,和業(yè)主、監(jiān)理、設(shè)計(jì)師等共同商定解決,形成紀(jì)
要。
11
項(xiàng)目專項(xiàng)施工方案
2.技術(shù)交底方案編制
夾層通道安裝工程正式施工之前,要針對(duì)相關(guān)施工內(nèi)容,編制詳盡的技術(shù)交底方案,方
案通過項(xiàng)目評(píng)審?fù)旰?,方可?duì)所有施工人員進(jìn)行交底,施工過程中嚴(yán)格按照技術(shù)交底內(nèi)容實(shí)
施。
12
項(xiàng)目專項(xiàng)施工方案
第5章管線綜合排布及支架選型
5.1管線綜合排布
1.系統(tǒng)綜合排布效果圖
管道綜合排布剖面圖
2.綜合布線依據(jù)
1.預(yù)先進(jìn)行排位規(guī)劃布置,對(duì)照現(xiàn)場(chǎng)土建、裝修作業(yè)等實(shí)際情況,以保證施工的可行性、
美觀性及實(shí)用性等。
2.最大限度地利用有限空間,管線的固定采用綜合支吊架。
3.預(yù)留施工過程中管道施工所需焊接空間,以及后期檢修所需空間。
4.保證空調(diào)水管、消防水管及給水管道開支管所需空間。
5.保證需保溫水管的保溫空間。
5.2支架選型與支架排布
支架梁的設(shè)計(jì)包括:支架梁的截面選取、支架梁的驗(yàn)算。根據(jù)設(shè)計(jì)圖紙中各種管徑的排
列形式,確定支架的寬度,設(shè)計(jì)中沒有對(duì)重型支架材料規(guī)格明確規(guī)定,根據(jù)規(guī)范及現(xiàn)場(chǎng)實(shí)際
情況制定方案,重型支架采用優(yōu)質(zhì)槽鋼制作。
以夾層1-Y1~1-P軸空調(diào)水管聯(lián)合支架為例:
13
項(xiàng)目專項(xiàng)施工方案
DN250空調(diào)水管選用無縫鋼管,取兩支架的間距L=6m;
1.對(duì)多個(gè)支架上的管道進(jìn)行受力分析
先分析DN250,含水米重:q1=107.66kg/m;運(yùn)行重量:q2=129.192kg/m;供回水管
道工作壓力為0.6MPa;
2.對(duì)橫向管道的支架受力分析
(1)內(nèi)力計(jì)算:桿端內(nèi)力值(乘子=1)
14
項(xiàng)目專項(xiàng)施工方案
--------------------------------------------------------------------------------------------
桿端1桿端2
-----------------------------------------------------------------------------
單元碼軸力剪力彎矩軸力剪力彎矩
--------------------------------------------------------------------------------------------
10.000000002547.284190.000000000.00000000-3912.31580-4095.09484
20.000000003412.57903-4095.094840.00000000-3047.02096-2998.42061
30.000000003181.19965-2998.420610.00000000-3278.40034-3290.02268
40.000000003241.42234-3290.022680.00000000-3218.17765-3220.28863
50.000000003231.91098-3220.288630.00000000-3227.68901-3207.62275
60.000000003209.73373-3207.622750.00000000-3249.86626-3328.02033
70.000000003307.95407-3328.020330.00000000-3151.64592-2859.09591
80.000000002937.24998-2859.095910.00000000-3522.35001-4614.39602
90.000000004644.82600-4614.396020.00000000-3106.69399-0.00000000
(2)算出各個(gè)支座反力與剪切力的結(jié)果如下所示:
得到每個(gè)支座最大剪力為:Fs(max)=4.64KN;
(3)再算出彎矩的結(jié)果如下所示:
得到最大彎矩為:M(max)=4614N·m
(4)查詢資料可得:D250無縫鋼管的抗彎截面模量為:Wx=937.61m3
(5)驗(yàn)證管道的彎曲正應(yīng)力:≤160MPa(滿足管道受彎曲要求)
3.固定支架垂直方向與水平方向受力分析
(1)垂直方向受力為F垂直=6*9*q1g/10=5.81KN
(2)水平方向的受力分析
考慮到管道與支架之間的摩擦力,摩擦力(木與鋼才的動(dòng)摩擦系數(shù)為0.2),
15
項(xiàng)目專項(xiàng)施工方案
為各支架對(duì)管道的合力,從而可以得到摩擦力f=0.2*5.81=1.162KN。
DN250管道搭設(shè)過程中需要架設(shè)DN250軸向內(nèi)壓式波紋補(bǔ)償器(吸收管道熱膨脹),向
廠家查詢補(bǔ)償器參數(shù)得知此波紋補(bǔ)償器的軸向剛度K=228N/mm,取無縫鋼管最大彈性型變
量L20mm;
可以算得彈性力為:;
管道內(nèi)部的內(nèi)推壓力為:;
將水平方向的力進(jìn)行矢量合成得到:F水平250=Fs+P1+f=10.2KN;
將水平方向的合力與最大支座反力進(jìn)行矢量合成,得F合=11.74KN
4.對(duì)單個(gè)支架進(jìn)行受力分析
每個(gè)管道對(duì)支架的合力都為F合=11.74KN。
所以截面最大彎矩為:Mmax=13053.8N·M
5.豎直端支架受力分析;
管道的運(yùn)行重量為:q2=129.192kg/m,14號(hào)槽鋼每米重量16.733kg/m,計(jì)算的整體重
量為W=129.192*6*4+16.733*3=3151kg。選用的14號(hào)Q235槽鋼抗拉強(qiáng)度為375~460MPa,
橫截面積M=2131.21mm2;計(jì)算得該支架豎直端的抗拉強(qiáng)度為:
W3151*10
P7.4MPa<375MPa,所以豎直端抗拉強(qiáng)度滿足要求;
M2*2131.21*106
6.槽鋼的選取
因?yàn)镸max=13053.8N·M;要滿足槽鋼
所受最大彎曲許用應(yīng)力不大于160MPa,
16
項(xiàng)目專項(xiàng)施工方案
(1)若選用14a槽鋼:>160MPa
(2)若選用14b槽鋼:<160MPa
(3)若選用16a槽鋼<160MPa
所以選用14號(hào)b型槽鋼。
以此類推,最后選擇支架的型號(hào)為:蒸汽管道支架、空調(diào)水管及消防水管支架全部采用14
號(hào)優(yōu)質(zhì)槽鋼。橋架綜合支架在管廊內(nèi)用12號(hào)優(yōu)質(zhì)槽鋼、架空區(qū)域采用10號(hào)優(yōu)質(zhì)槽鋼。綜合
給水管支架采用12號(hào)優(yōu)質(zhì)槽鋼。
7.膨脹螺栓的選取
查詢膨脹螺栓參數(shù)得此下表:
管道的運(yùn)行重量為:q2=129.192kg/m,14號(hào)槽鋼每米重量16.733kg/m,計(jì)算的整體重
量為W=129.192*6*4+16.733*3=3151kg。支架兩端鋼板上各使用4個(gè)膨脹螺栓,選用12號(hào)
國標(biāo)標(biāo)準(zhǔn)膨脹螺栓,最大承受重量G=8*2650=21200kg>W;所以可以選用12號(hào)膨脹螺栓。
17
項(xiàng)目專項(xiàng)施工方案
依據(jù)據(jù)施工規(guī)范中對(duì)支架間距得要求以及施工現(xiàn)場(chǎng)情況,對(duì)于支架排布,給排水及暖通
專業(yè)取支架間距為6m,橋架支架間距為2m。其簡化示意圖如下圖所示,取固定支架的間距
取60m,具體情況根據(jù)現(xiàn)場(chǎng)預(yù)留的伸縮縫來確定,對(duì)于波紋補(bǔ)償器的放置位置,距離固定支
架1m左右位置放置一個(gè)波紋補(bǔ)償器,固定支架之間全部采用活動(dòng)支架,活動(dòng)支架下端部用
木托墊起,上端部用抱箍進(jìn)行固定。
支架間距示意圖
5.3管道管托
管道管托示意圖如下所示,管道下端部用木托墊起來,上端部木托與下端部木托合并為
一個(gè)整體,然后用抱箍進(jìn)行緊固,最后用螺栓進(jìn)行固定。
18
項(xiàng)目專項(xiàng)施工方案
管道管托示意圖
19
項(xiàng)目專項(xiàng)施工方案
第6章管道運(yùn)輸與管道安裝
6.1管道運(yùn)輸
1.大口徑的蒸汽管道訂貨后,供貨時(shí)直接由場(chǎng)外運(yùn)至安裝現(xiàn)場(chǎng),并按照安裝位置需用的
數(shù)量依次卸貨,管道在運(yùn)輸和吊裝時(shí)要采取保護(hù)措施,尤其是不銹鋼管道,以保護(hù)管道(特
別是管端)不損壞和變形。管子運(yùn)至安裝現(xiàn)場(chǎng)后,吊車配合卸車。
2.空調(diào)水管道的安裝現(xiàn)場(chǎng)應(yīng)具備必要的運(yùn)輸通道,以保證貨到現(xiàn)場(chǎng)后能夠及時(shí)送入安裝
現(xiàn)場(chǎng)經(jīng)檢驗(yàn)后即時(shí)安裝。
3.大管徑的空調(diào)水管轉(zhuǎn)運(yùn)時(shí),利用2個(gè)5t的卷揚(yáng)機(jī)進(jìn)行牽引,將管道卸載到指定的地方。
6.2工藝流程:
管道安裝主要步驟有:
測(cè)量放線預(yù)制加工支架制作安裝管道安裝
管道清洗管道試壓
1.測(cè)量放線
管道安裝應(yīng)測(cè)量好管道坐標(biāo)、標(biāo)高、坡度線。管道安裝時(shí),應(yīng)復(fù)核水管的公稱壓力、等
級(jí)和使用場(chǎng)合。管道的標(biāo)識(shí)應(yīng)面向外側(cè),處于明顯位置。
2.預(yù)制加工
管材切割前,必須正確丈量和計(jì)算好所需長度,用記號(hào)筆在管表面畫出切割線。切割管
材必須使端面垂直于管軸線。管材切割應(yīng)使用管道切割機(jī),且根據(jù)不同材質(zhì)的管材進(jìn)行切割
片的跟換,不宜用鋼鋸鋸斷管材,在焊接前應(yīng)該進(jìn)行坡口打磨。管材與管件的連接必須清潔、
干燥、無油污。連接彎頭或三通等管件時(shí),應(yīng)注意管道的走向。宜先進(jìn)行預(yù)裝,校正好方向,
用墨線畫出軸向定位線。
3.支吊架制作安裝
20
項(xiàng)目專項(xiàng)施工方案
常用的管道支吊架按用途分為:固定支架、導(dǎo)向支架、活動(dòng)支架等。管道支吊架的布置
和類型應(yīng)滿足管道荷重、補(bǔ)償量及位移的要求,并注意減少管道的震動(dòng);另外,還必須考慮
管道的穩(wěn)定性、強(qiáng)度和剛度以及輸送介質(zhì)的溫度和工作壓力,并盡量簡便易于節(jié)約鋼材。管
道支架加工制作前應(yīng)根據(jù)管道的材質(zhì)、管徑大小等按標(biāo)準(zhǔn)圖集進(jìn)行選型。鋼管支吊架間距不
得大于規(guī)范要求。
支吊架與鋼板焊接處需要滿焊,同時(shí)在250*250鋼板(10mm厚)上打上4個(gè)12號(hào)膨
脹螺栓到稱重墻或梁上,螺栓對(duì)稱排布。
支架固定鋼板大樣圖
6.3管材、管件、附屬配件的檢驗(yàn)
21
項(xiàng)目專項(xiàng)施工方案
1.無縫鋼管、管件、閥門、焊材等必須具有材質(zhì)證明書或產(chǎn)品合格證書,并且需進(jìn)行檢
查、收集和整理歸檔。
2.按設(shè)計(jì)要求核對(duì)管子、管件、附屬配件的規(guī)格、材質(zhì)、型號(hào),并檢查其外面,不得有
裂紋、縮孔、氣泡、夾縫、折迭、重皮、毛刺、溝槽、傷痕等缺陷及銹蝕或凹陷超過壁厚的
負(fù)偏差。
3.閥門表面不得有粘砂、裂紋、縮孔等缺陷、開關(guān)應(yīng)靈活可靠,無卡澀現(xiàn)象。
6.4管道支架制作安裝
1.根據(jù)設(shè)計(jì)圖、夾層通道的尺寸,測(cè)量管架標(biāo)高。
2.根據(jù)支架標(biāo)準(zhǔn)圖進(jìn)行管道支架的下料、焊接制作,并按要求做好支架除銹、刷油與防
腐工作。
3.按設(shè)計(jì)及現(xiàn)場(chǎng)深化設(shè)計(jì)要求進(jìn)行支架安裝??照{(diào)水管道系統(tǒng)的管道支架安裝時(shí),應(yīng)按
照系統(tǒng)要求,從空調(diào)水供(回)水管道起,順著供水(回)方向依次安裝。管道分層布置時(shí),
應(yīng)先安裝上層管道支架及管道,然后再依次安裝中層及下層。這就要求確定支架制作和管道
安裝工序先后,完成支架及管道的正常安裝。
4.夾層通道式分層管道支撐安裝時(shí),應(yīng)考慮管道安裝時(shí)的吊裝方便,為此要求夾層通道
管道支撐安裝時(shí),先將管道運(yùn)至安裝點(diǎn),做好整體支架后再行安裝,否則需安裝的管道很難
順利吊裝到位。其安裝時(shí)需借助最上層管道支撐,待管道吊裝到管架上后再行安裝,以便于
管道正常吊裝。其他的依此類推進(jìn)行安裝。
6.5管道下料及坡口加工方式
1.根據(jù)施工平面圖和系統(tǒng)圖所標(biāo)注的規(guī)格、尺寸,再根據(jù)現(xiàn)場(chǎng)實(shí)際情況,空調(diào)水管單根
管道長度大約為6m,夾層通道大部分為直線段,以6m為基準(zhǔn)進(jìn)行焊接施工。需要加工切割
的管道提前加工預(yù)制完成再運(yùn)送至夾層安裝。
22
項(xiàng)目專項(xiàng)施工方案
2.坡口加工(坡口加工圖見焊接檢驗(yàn)部分)必須按照規(guī)范要求進(jìn)行,對(duì)口焊接角度為45
度,坡口間距為0-2mm,保證其型式正確、尺寸準(zhǔn)確,且宜采用機(jī)械方法。如采用氣割時(shí),
坡口面上的氧化熔渣、飛濺等物必須清理干凈,并將凹凸不平處修理平整。
6.6管道安裝
1.管道安裝前,必須將管道內(nèi)部清理干凈,管節(jié)應(yīng)按管道系統(tǒng)號(hào)和預(yù)制順序號(hào)進(jìn)行安裝。
每一段管道焊接完成后檢查管道內(nèi)部,不允許將施工工具遺漏在管道內(nèi)。
2.由于蒸汽管道口徑較大,在管道安裝前,首先制作好B-A~B-B軸東西兩側(cè)支架,這就
要求首先將管道通過手動(dòng)葫蘆移放到位,并且管托進(jìn)行預(yù)制,以盡量減少夾層通道內(nèi)作業(yè),
保證施工安全,提高施工機(jī)械利用率,加快施工進(jìn)度。
3.不銹鋼管材、管件應(yīng)統(tǒng)一歸類分開放置,不與碳鋼類材料混放,并采取防止鐵銹、雨
水等腐蝕措施。
4.不銹鋼管應(yīng)使用砂輪機(jī)切割或等離子切割機(jī)切割,坡口加工使用角向磨光機(jī)。
5.不銹鋼管道在組對(duì)預(yù)制過程中,避免使用鐵制工具敲擊管段,盡量增大地面預(yù)制量,
減少固定焊口的數(shù)量。
6.不銹鋼管應(yīng)用機(jī)械或等離子方法切割。當(dāng)用砂輪切割或修磨時(shí),應(yīng)有專用砂輪片。
7.不銹鋼管不準(zhǔn)直接與碳鋼支架接觸,應(yīng)在支架與管道之間墊入不銹鋼片、或不含氯離
子的塑料、橡膠墊片。
8.不銹鋼管道法蘭用的墊片應(yīng)用氯離子含量不超過50ppm的非金屬墊片。
9.管道連接時(shí)應(yīng)避免臟物的影響和氧化膜的破壞。
10.管道安裝時(shí),應(yīng)檢查法蘭密封面及密封墊片,不得有影響密封性能的劃痕、斑點(diǎn)等缺
陷。
23
項(xiàng)目專項(xiàng)施工方案
11.法蘭連接應(yīng)與管道同心,并應(yīng)保證螺栓自由穿入。法蘭間應(yīng)保持平行,其偏差不得大
于法蘭外徑的1.5%,且不得大于2mm。不得用強(qiáng)緊螺栓的方法消除歪斜。螺栓的安裝方向
應(yīng)一致。螺栓緊固應(yīng)對(duì)稱均勻操作。緊固后應(yīng)與法蘭緊貼,需加墊片時(shí),每個(gè)螺栓不應(yīng)超過
一個(gè)。法蘭連接時(shí)應(yīng)對(duì)接平行、緊密,與管道中心線垂直,墊片不應(yīng)使用雙層,螺母應(yīng)在同
一側(cè),螺桿露出的長度不應(yīng)大于螺栓直徑的1/2。
12.管子安裝平直度應(yīng)在距接口中心200mm處測(cè)量,當(dāng)管徑小于100mm時(shí),允許偏差
為1mm,當(dāng)管徑大于或等于100mm時(shí),允許偏差為2mm;但全長允許偏差均為10mm。
13.穿墻套管規(guī)格比管道的規(guī)格高兩檔。管道與套管之間的空隙應(yīng)采用不燃材料填充。
當(dāng)管道安裝工作有間斷時(shí),應(yīng)及時(shí)封閉敞開的管口。
15.與設(shè)備連接符合設(shè)計(jì)或工藝設(shè)備技術(shù)文件規(guī)定(如采用金屬軟管連接方式)。
16.管道安裝的允許偏差見下表規(guī)定:
項(xiàng)目允許偏差(mm)
室內(nèi)15
坐標(biāo)
室外25
室內(nèi)±15
標(biāo)高
室外±20
DN≤1002L‰最大50
水平管道平直度
DN>1003L‰最大80
立管鉛垂度5L‰最大50
成排管道間距15
交叉管的外壁或絕緣層間間距20
(注:L為管子有效長度)
摘自《工業(yè)金屬管道工程施工及驗(yàn)收規(guī)范》GB50235-97
6.7閥門安裝
1.按設(shè)計(jì)文件核對(duì)其型號(hào),并按介質(zhì)流向確定其安裝方向。在安裝前,均應(yīng)檢查閘板與
密封面是否清潔。安裝后,在無水條件下按照操作程序啟閉三次,以保證開啟靈活。對(duì)于電
24
項(xiàng)目專項(xiàng)施工方案
動(dòng)閥門、閘門的安裝,首先要弄清其工作原理,同時(shí)在安裝時(shí)請(qǐng)電氣專業(yè)的技術(shù)人員配合進(jìn)
行。
2.閥門安裝應(yīng)牢固、嚴(yán)密,與管道中心線同心,操作機(jī)構(gòu)靈活、準(zhǔn)確。各種閥門的性能、
結(jié)構(gòu)、材質(zhì)、防腐蝕以及各種技術(shù)參數(shù)均應(yīng)符合設(shè)計(jì)要求。
3.閥門應(yīng)在關(guān)閉狀態(tài)下安裝。安裝方位應(yīng)符合設(shè)計(jì)要求,操作方便,開關(guān)靈活。
4.閥門安裝前,應(yīng)作強(qiáng)度和嚴(yán)密性試驗(yàn)。試驗(yàn)應(yīng)在每批(同牌號(hào)、同型號(hào)、同規(guī)格)數(shù)量中
抽查10%,且不少于一個(gè)。對(duì)于安裝在主干管上起切斷作用的閉路閥門,應(yīng)逐個(gè)作強(qiáng)度和嚴(yán)
密性試驗(yàn)。閥門的強(qiáng)度和嚴(yán)密性試驗(yàn),應(yīng)符合下列規(guī)定:閥門的強(qiáng)度試驗(yàn)壓力為公稱壓力的
1.5倍;嚴(yán)密性試驗(yàn)壓力為公稱壓力的1.1倍;試驗(yàn)壓力在試驗(yàn)持續(xù)時(shí)間內(nèi)應(yīng)保持不變,且殼
體填料及閥瓣密封面無滲漏。
5.在安裝波紋補(bǔ)償器前,必須充分了解產(chǎn)品參數(shù)如伸縮量,是否在產(chǎn)地進(jìn)行了水壓試驗(yàn)
及預(yù)拉伸等后,再確定其具體的安裝方法。
6.管道上大型閥門或部件均應(yīng)加上獨(dú)立支撐,以免大型閥門及部件的重力對(duì)管道造成壓
力。
25
項(xiàng)目專項(xiàng)施工方案
第7章管道焊接
7.1施工一般要求
1.所有焊工合格證應(yīng)為有效證件,合格項(xiàng)目應(yīng)與從事項(xiàng)目相同。上崗前必須進(jìn)行現(xiàn)場(chǎng)模
擬考試,合格者方可以上崗。
2.施工現(xiàn)場(chǎng)應(yīng)備有符合規(guī)范要求的焊接材料貯存場(chǎng)所,烘干設(shè)備。并建立嚴(yán)格的保管、
烘干、發(fā)放制度,以防止錯(cuò)用和浪費(fèi)。
3.焊接設(shè)備的電流表、電壓表、氣體流量計(jì)等儀表儀器以及規(guī)范參數(shù)調(diào)節(jié)裝置應(yīng)定期檢
查。
4.電焊條(碳鋼焊條)應(yīng)在350℃溫度下,烘干1小時(shí),并放入保溫桶內(nèi)隨用隨取,保
證焊條溫度始終為120℃,且焊條不允許重復(fù)烘干,焊工應(yīng)使用小保溫桶將焊條運(yùn)到工地,
一次領(lǐng)用數(shù)量不宜超過2小時(shí)的使用量,并且要做到隨用隨取。
5.不銹鋼管的焊接采用氬弧焊,管內(nèi)充氬保護(hù),避免產(chǎn)生氧化腐蝕物,焊接前,將坡口
及其兩側(cè)20~30mm范圍內(nèi),清理干凈,然后再焊接。
6.不銹鋼管道安裝焊接前,在坡口端150mm范圍內(nèi)涂上白堊粉,防止在焊接時(shí)焊渣和飛
濺損傷管表面。
7.不銹鋼管的焊縫用涂刷法對(duì)焊縫及兩側(cè)部位酸洗。
7.2一般焊接程序
1.對(duì)管道質(zhì)量進(jìn)行檢查,焊縫坡口、間隙、錯(cuò)邊是否符合GB50236-98的三級(jí)焊縫標(biāo)準(zhǔn)。
2.按照焊接工藝卡所規(guī)定的焊接參數(shù)進(jìn)行施焊,若由于特殊原因需改變焊接工藝中某個(gè)
參數(shù),需報(bào)告工藝制訂人經(jīng)同意后方可改變。
3.焊接外觀質(zhì)量自檢:焊接缺陷(如飛濺、氣孔、焊渣)由焊工自己處理,做到誰焊、
誰負(fù)責(zé)、誰處理。
26
項(xiàng)目專項(xiàng)施工方案
4.焊縫質(zhì)量專檢:由焊接質(zhì)量檢查員或焊接工程師檢查并標(biāo)識(shí)。
7.3焊接工藝
本工程不銹鋼管采用氬弧焊接,無縫鋼管采用手工電弧焊。氬弧焊絲宜采用BOEAS2-1G
或BOEAS4-1G型號(hào)的焊絲。
1.氬弧焊工藝
1)焊槍噴嘴直徑為8mm,鎢極直徑為2.5mm,電極伸出長度為6mm。
2)管道焊接時(shí)管內(nèi)應(yīng)防止穿堂風(fēng)。
3)焊接時(shí)應(yīng)保持焊槍、焊絲與管口之間的相對(duì)位置,送絲可以采用斷續(xù)送進(jìn)和連續(xù)送進(jìn)
兩種方法,但要防止焊絲與高溫的鎢極接觸。噴嘴與工件的距離一般為10~15mm,焊槍可
作一點(diǎn)橫向擺動(dòng),焊絲應(yīng)均勻送入熔池,不要擾亂氣流,焊絲頭部應(yīng)始終放在氬氣保護(hù)區(qū)內(nèi)。
焊接終了時(shí),應(yīng)多加焊絲,然后慢慢拉開。
2.焊接前的準(zhǔn)備要求
1)焊條使用前應(yīng)進(jìn)行烘烤,現(xiàn)場(chǎng)應(yīng)指定專人負(fù)責(zé)烘烤焊條,并做好領(lǐng)用記錄。
2)焊條應(yīng)裝入保溫筒,隨用隨取。焊條隔夜必須收回保溫箱(并做好記錄),防止受潮
變質(zhì)。堿性焊條次日使用,還要重新烘烤,一般烘烤不得超過三次。
3)坡口加工必須按照規(guī)范要求進(jìn)行,保證其型式正確、尺寸準(zhǔn)確,且宜采用機(jī)械方法。
如采用氣割時(shí),坡口面上的氧化熔渣、飛濺等物體必須清理干凈,并將凹凸不平處修理平整。
4)接頭組對(duì)時(shí)一定要做到內(nèi)壁齊平,不得強(qiáng)力進(jìn)行,組對(duì)時(shí)錯(cuò)邊量不得超過壁厚的
10%,且不得超過1毫米。組對(duì)完成后的接頭應(yīng)及時(shí)進(jìn)行點(diǎn)固焊,所用焊接方法和材料與正
式施焊時(shí)相同。
3.焊接過程
1)本工程不銹鋼管采用氬弧焊接,無縫鋼管采用手工電弧焊。
27
項(xiàng)目專項(xiàng)施工方案
2)根據(jù)管道的材質(zhì)、規(guī)格、工作介質(zhì)及焊接時(shí)的環(huán)境溫度等情況,必要時(shí)在焊前對(duì)接頭
進(jìn)行預(yù)熱,其預(yù)熱溫度為100-200℃,預(yù)熱區(qū)域應(yīng)不小于距接頭150毫米的范圍,焊接完成
后,立即對(duì)接頭進(jìn)行熱處理。在熱處理時(shí),應(yīng)嚴(yán)格按照規(guī)范要求執(zhí)行,并及時(shí)作好記錄。
3)在正式焊接時(shí)必須按焊接工藝卡或焊接指導(dǎo)書執(zhí)行,不得任意變更。焊接時(shí)應(yīng)認(rèn)真操
作,仔細(xì)檢查,及時(shí)處理焊接缺陷。
4)多層多道焊時(shí),接頭應(yīng)錯(cuò)開,且應(yīng)逐層進(jìn)行檢查,經(jīng)自檢合格后,方可焊接次層,直
至完成。同時(shí)還應(yīng)特別注意接頭和收弧的質(zhì)量,收弧時(shí)應(yīng)將熔池填滿。
5)經(jīng)檢查需返修或補(bǔ)焊時(shí),應(yīng)有具體的返修或補(bǔ)焊工藝措施,需作熱處理的,在返修或
補(bǔ)焊后應(yīng)重做熱處理。
6)焊接過程中,還應(yīng)注意周圍環(huán)境的影響。不能有妨礙焊接工作的環(huán)境因素產(chǎn)生,否則,
應(yīng)采取有效措施予以防護(hù)。
7.4焊接檢驗(yàn)
1.焊接過程中應(yīng)時(shí)時(shí)對(duì)焊接質(zhì)量進(jìn)行檢查和檢驗(yàn),做好焊接質(zhì)量三級(jí)檢查驗(yàn)收工作。
2.焊接完成后對(duì)焊縫進(jìn)行外觀檢查,外觀檢查不合格的焊縫,不得進(jìn)入下一道工序,外
觀質(zhì)量合格標(biāo)準(zhǔn)為:
1)焊縫加強(qiáng)高為0-3毫米,寬度為坡口每側(cè)增寬約2毫米。
2)不允許有裂紋、未熔合、氣孔、夾渣。
3)根部未焊透的深度不大于厚度的10%且不大于1.5毫米,總長度不大于焊縫全長的
10%。
4)咬邊深度不大于0.5毫米,焊縫兩側(cè)總長不大于焊縫全長的20%。
5)內(nèi)凹不大于2毫米。
6)外觀檢查合格后及時(shí)作好記錄。
28
項(xiàng)目專項(xiàng)施工方案
3.焊縫坡口的基本型式與尺寸如下表所示:
坡口形式間隙鈍邊
坡口角度
圖示壁厚t(mm)(mm)(mm)
3-90-20-2650—750
bt
α9-260-30-3550—650
摘自《埋弧焊焊縫坡口的基本形式和尺寸》GB986-88
4.焊縫外觀質(zhì)量檢查:焊縫邊緣應(yīng)圓滑過渡到基本金屬表面,焊縫表面外觀質(zhì)量應(yīng)符合
下表要求。
接頭類別質(zhì)量要求
缺陷名稱Ⅰ級(jí)Ⅱ級(jí)
裂紋不允許
每50mm焊縫長度內(nèi)允許直徑≤0.3δ,
表面氣孔
且≤2mm≥氣孔2個(gè)
表面夾渣深≤0.1δ長≤0.3δ,且≤10mm
不加墊單面焊≤0.15δ,且≤1.5mm
未焊透
不允許缺陷總長在6δ焊縫長度內(nèi)不超過δ
深度≤0.5mm,焊縫兩側(cè)咬邊總長≤焊
咬邊
縫全長的10%
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024年度影視制作擔(dān)保合同6篇
- 2024年吊車施工進(jìn)度保障協(xié)議3篇
- 2024年度地坪漆施工原材料供應(yīng)及質(zhì)量控制合同3篇
- 2024年古建筑大門修復(fù)與安裝服務(wù)合同3篇
- 2024年度全面協(xié)議離婚書包括房產(chǎn)分割與子女教育安排條款3篇
- 2024年度奶茶店員工加班管理及勞動(dòng)合同3篇
- 2024年度洗滌行業(yè)環(huán)保達(dá)標(biāo)與驗(yàn)收合同范本3篇
- 2024年度旅游包車運(yùn)輸承包合同與導(dǎo)游服務(wù)配套3篇
- 2024年度知識(shí)產(chǎn)權(quán)金融服務(wù)及投資咨詢合同6篇
- 2024年影視制作實(shí)習(xí)生就業(yè)合同附影視后期制作培訓(xùn)協(xié)議3篇
- GB/T 1094.7-2024電力變壓器第7部分:油浸式電力變壓器負(fù)載導(dǎo)則
- 電大西方行政學(xué)說
- 2024-2025學(xué)年人教版數(shù)學(xué)七年級(jí)上冊(cè)期末復(fù)習(xí)卷(含答案)
- 2024年度中國PE、VC基金行業(yè)CFO白皮書
- 2023年南京市江寧區(qū)招聘教師考試真題
- 紀(jì)念毛同志誕辰131周年主題班會(huì)-緬懷偉大領(lǐng)袖奮斗新的征程課件
- 中南大學(xué)《物聯(lián)網(wǎng)原理及應(yīng)用》2022-2023學(xué)年第一學(xué)期期末試卷
- 機(jī)動(dòng)車檢測(cè)站新?lián)Q版20241124質(zhì)量管理手冊(cè)
- 大部分分校:地域文化形考任務(wù)一-國開(CQ)-國開期末復(fù)習(xí)資料
- 廣東省深圳市2023-2024學(xué)年高一上學(xué)期期末考試物理試題(含答案)
- 國家開放大學(xué)本科《公共部門人力資源管理》期末紙質(zhì)考試總題庫2025版
評(píng)論
0/150
提交評(píng)論