文檔簡(jiǎn)介
1、青島市南軟件園G-1、G-2工程腳手架工程施工方案編制:審核:批準(zhǔn):青島建設(shè)集團(tuán)華友建設(shè)發(fā)展有限公司二四年七月目 次1. 工程概況·······································&
2、#183;····························22. 方案選擇····················
3、;················································23. 施工工藝
4、83;·················································
5、83;·················23.1 腳手架搭設(shè)工藝3.2 腳手架拆除工藝4. 施工方法···························
6、83;········································34.1 腳手架基礎(chǔ)4.2 懸挑槽鋼的支設(shè)4.3 腳手架搭設(shè)4.4 腳手架拆除5. 主要資源需求計(jì)劃·&
7、#183;·················································&
8、#183;·····56. 施工要求及安全技術(shù)措施·········································
9、3;·······56.1 施工要求6.2 安全技術(shù)措施7. 編制依據(jù)······································
10、183;····························108. 外腳手架計(jì)算書···················
11、183;·······································139.卸料鋼平臺(tái)方案········
12、83;·················································
13、83; 221. 工程概況青島市南軟件園G-1、G-2工程G-1地下2層,地上裙房2層,主樓22層; G-2地下2層,地上裙房2層,主樓20層;建筑高度G-1辦公樓80.5m,G-2辦公樓74.4m,地下一層及地上一層層高為4.5米,二層及其以上層高為3.3米??蚣艿目拐鸬燃?jí)為三級(jí),核心筒的抗震等級(jí)為二級(jí),地下室無(wú)上部主樓部分框架及砼墻的抗震等級(jí)為三級(jí),地下二層至地上三層為底部加強(qiáng)部位,四層及以上為非加強(qiáng)部位??拐鹪O(shè)防烈度為六度。2. 方案選擇2.1 本工程地下兩層,進(jìn)行地下二層施工時(shí),沿負(fù)二層外墻搭設(shè)落地式雙排鋼管扣件式腳手架,地下室外墻防水施工完畢后即拆除。詳見(jiàn)附圖一。2.2 16層采用落
14、地式雙排鋼管扣件式腳手架,高度為21m,詳見(jiàn)附圖二;7層及其以上采用懸挑雙排鋼管扣件式腳手架,懸挑梁選用18#槽鋼,每5層懸挑一次,共懸挑3次,每一懸挑腳手架的高度為16.5m。3. 工藝流程3.1 腳手架搭設(shè)工藝(1)地下室及16層落地式腳手架:準(zhǔn)備工作立桿底座立桿橫桿剪刀撐接頭鎖緊安裝連墻件鋪設(shè)腳手板立掛安全網(wǎng)上層立桿立桿連接銷橫桿; (2)7層及其以上懸挑式腳手架:準(zhǔn)備工作懸挑槽鋼的架設(shè)立桿橫桿剪刀撐接頭鎖緊安裝連墻件鋪設(shè)腳手板立掛安全網(wǎng)上層立桿立桿連接銷橫桿。3.2 腳手架拆除工藝密目網(wǎng)橫桿立桿剪刀撐連墻件4. 施工方法4.1 腳手架基礎(chǔ)地下室及16層外墻腳手架采用落地式雙排腳手架,腳
15、手架的地基應(yīng)夯實(shí),且有足夠的承載力。腳手架立桿設(shè)鋼底座,底座下為50mm厚的通長(zhǎng)木墊板,底座和墊板應(yīng)準(zhǔn)確地放在立桿的定位線上。4.2 懸挑槽鋼的支設(shè)7層及其以上采用懸挑式腳手架,每5層懸挑1次。懸挑結(jié)構(gòu)分為兩種情況:南北立面為18#槽鋼及14#鋼絲繩斜拉索,東西立面為18#槽鋼及48鋼管斜撐。用預(yù)埋在樓板中的20及16型圓鋼環(huán)將槽鋼卡住,并用硬木楔將槽鋼楔緊;在外挑槽鋼上與立桿對(duì)應(yīng)位置處各焊1根25mm、高120mm的鋼筋以固定立桿,斜拉索及斜撐對(duì)應(yīng)位置各焊1根25mm、長(zhǎng)120mm的鋼筋以固定斜撐。詳見(jiàn)附圖三。4.3 腳手架搭設(shè)4.3.1腳手架鋼管的搭設(shè)外腳手架采用雙排48×3.5
16、mm鋼管搭設(shè),立桿的橫距0.9m、縱距1.5m、橫桿的步距1.8m、內(nèi)立桿離墻300mm。腳手架必須設(shè)置縱、橫向掃地桿??v向掃地桿應(yīng)采用直角扣件固定在距底座上皮不大于200mm處的立桿上。橫向掃地桿用直角扣件固定在緊靠縱向掃地桿下方的立桿上。立桿與大橫桿的交點(diǎn)處設(shè)置小橫桿,小橫桿應(yīng)緊靠立桿用扣件與大橫桿扣牢。在腳手架外側(cè)立面的兩端各設(shè)置一道剪刀撐,沿高度方向連續(xù)設(shè)置剪刀撐,長(zhǎng)度方向剪刀撐間距15米。每組剪刀撐跨越5根立桿;剪刀撐鋼管的搭接長(zhǎng)度不小于1m,用3個(gè)扣件固定搭接鋼管;剪刀撐與橫向水平桿的伸出端或立桿相交處應(yīng)用旋轉(zhuǎn)扣件固定。4.3.2 連墻件的設(shè)置 本工程連墻件為剛性連接,按二步三跨設(shè)
17、置,其位置宜靠近主節(jié)點(diǎn),偏離主節(jié)點(diǎn)的距離不應(yīng)大于300mm。連墻件與建筑物的連接方式為:在外框梁上預(yù)埋25鋼筋地錨,其長(zhǎng)度500mm、外露長(zhǎng)度200mm。4.3.3腳手板的搭設(shè)本工程采用竹笆腳手板,每一懸挑單元(5層)設(shè)一作業(yè)層,并將該單元底層滿鋪腳手板作為防護(hù)層,防護(hù)層應(yīng)鋪滿內(nèi)立桿與混凝土墻之間的空間;自頂層的作業(yè)層計(jì),每隔12m滿鋪一層腳手板;作業(yè)層設(shè)防護(hù)欄桿和擋腳板。 鋪設(shè)竹笆板時(shí),在兩立桿間加二根縱向橫桿并與橫向水平桿連接,小橫桿應(yīng)在大橫桿的下面。作業(yè)層腳手板要鋪滿、鋪穩(wěn),離開墻面150mm。竹笆腳手板應(yīng)按其主竹筋垂直于縱向水平桿方向鋪設(shè),且采用對(duì)接平鋪,四個(gè)角用直徑1.2mm的鍍鋅鋼
18、絲固定在縱向水平桿上。4.3.4密目網(wǎng)的設(shè)置腳手架使用密目安全網(wǎng)全封閉。密目網(wǎng)設(shè)置在外排立桿的內(nèi)側(cè),用尼龍繩將密目網(wǎng)之間綁扎,并每隔250mm與腳手架環(huán)扣系牢。建筑物四周外挑安全平網(wǎng)。斜道的搭設(shè): 4.3.5.1斜道附著腳手架設(shè)置,人行道寬度不小于1m,坡度為1:3,拐彎處應(yīng)設(shè)置平臺(tái),其寬度不應(yīng)小于斜道寬度。4.3.5.2斜道兩側(cè)、平臺(tái)外圍和端部均應(yīng)按規(guī)范設(shè)置連墻件,每步應(yīng)加設(shè)水平斜桿,設(shè)置剪刀撐和橫向斜撐。4.3.5.3腳手板橫鋪時(shí),應(yīng)在橫向水平桿下增設(shè)縱向支托桿,縱向支托桿間距不應(yīng)大于500。4.3.5.4腳手板順鋪時(shí),接頭宜采用搭接,下面的板頭應(yīng)壓住下面的板頭。4.3.5.5拐彎處設(shè)平臺(tái)
19、,斜道和平臺(tái)按臨邊防護(hù)要求設(shè)1.2m高的防護(hù)欄及擋腳板,擋腳板高度不小于180mm;4.3.5.6斜道采用2030mm厚木腳手板,板面上每隔250mm300mm設(shè)置一根防滑木條,防滑木條厚度20mm。4.3.4 結(jié)構(gòu)挑架返上后樓層四周防護(hù)結(jié)構(gòu)樓板混凝土澆筑時(shí),在樓層四周沿框柱內(nèi)側(cè)邊緣線預(yù)埋22鋼筋地錨,間距1500。在結(jié)構(gòu)挑架返上后,根據(jù)地錨間距設(shè)置1500高立桿,并在立桿上設(shè)置三道水平桿,一道為掃地桿。防護(hù)桿與框柱間采用短鋼管和扣件連接牢固。4.4腳手架拆除4.4.1腳手架的拆除順序與搭設(shè)順序相反,須遵守先搭后拆,后搭先拆的原則,從腳手架頂端拆除其順序?yàn)椋喊踩W(wǎng)護(hù)身攔擋腳板腳手板小橫桿大橫桿
20、立桿連墻桿縱向支撐斜拉桿。4.4.2連墻桿應(yīng)在位于其上的全部可拆除桿件都拆除后方可拆除。5. 勞動(dòng)力需求計(jì)劃架子工:-22層階段11人,3層以上主樓階段14人。6. 施工要求及安全技術(shù)措施6.1 施工要求本工程腳手架的材料、搭設(shè)、使用及拆除均應(yīng)按照施工設(shè)計(jì)、國(guó)家相關(guān)的規(guī)范、規(guī)程及省、市有關(guān)文件的規(guī)定執(zhí)行。6.1.1 材料要求(1)腳手架鋼管采用48×3.5mm,鋼管的材質(zhì)使用力學(xué)性能適中、穩(wěn)定的Q235鋼,其質(zhì)量應(yīng)符合國(guó)家標(biāo)準(zhǔn)要求。禁止使用有明顯變形、裂紋和嚴(yán)重銹蝕的鋼管,嚴(yán)禁在鋼管上打孔。(2)扣件式腳手架采用可鍛鑄鐵制作的扣件,其質(zhì)量應(yīng)符合國(guó)家標(biāo)準(zhǔn)要求。腳手架采用的扣件,在螺栓檸
21、緊力距達(dá)65N·m時(shí),不發(fā)生破壞。嚴(yán)禁使用加工不合格、銹蝕和有裂紋的扣件,出現(xiàn)滑絲的螺栓必須更換。扣件活動(dòng)部位應(yīng)靈活轉(zhuǎn)動(dòng),夾緊鋼管時(shí),開口處的最小距離應(yīng)不小于5mm。(3)腳手板主要采用竹笆板和少量松木板,每塊質(zhì)量不應(yīng)大于30kg,其材質(zhì)應(yīng)符合現(xiàn)行國(guó)家標(biāo)準(zhǔn)的規(guī)定;松木板厚不應(yīng)小于50mm,兩端各設(shè)直徑為4mm的鍍鋅鋼絲箍2道。(4)安全網(wǎng):安全網(wǎng)采用經(jīng)國(guó)家指定監(jiān)督檢驗(yàn)部門監(jiān)定許可生產(chǎn)的廠家產(chǎn)品,同時(shí)應(yīng)具備監(jiān)督部門批量驗(yàn)證和工廠檢驗(yàn)合格證。安全網(wǎng)的力學(xué)性能應(yīng)符合GB572688安全網(wǎng)力學(xué)性能試驗(yàn)方法的規(guī)定,進(jìn)入現(xiàn)場(chǎng)后應(yīng)對(duì)安全網(wǎng)進(jìn)行模擬大型砂包沖擊試驗(yàn),立網(wǎng)采用安全網(wǎng)L1.8×
22、6的密目安全網(wǎng),平網(wǎng)采用P3×6的可密網(wǎng)。(5)進(jìn)場(chǎng)的鋼管、扣件、腳手板、安全網(wǎng)等材料,應(yīng)按規(guī)范的要求進(jìn)行檢查、驗(yàn)收。對(duì)不符合要求的材料,不允許使用;經(jīng)檢查合格的鋼管、扣件、腳手板應(yīng)分類堆放,堆放場(chǎng)地不得有積水。6.1.2 搭設(shè)要求6.1.2.1立桿(1)每根立在豎立桿時(shí),要注意桿件長(zhǎng)短搭配使用,立桿接頭除頂層可采用搭接外必須采用對(duì)接扣件實(shí)行對(duì)接接頭,搭接時(shí)的搭接長(zhǎng)度Ld1m,用不少于兩個(gè)旋轉(zhuǎn)扣件扣牢,扣件的外邊緣到桿端距離不小于100mm。(2)立桿接頭與相近大橫桿的距離不宜大于步高的三分之一,相鄰立桿接頭應(yīng)相互錯(cuò)開,不應(yīng)在同步高和同一跨距內(nèi),相鄰接頭的高度宜500mm。見(jiàn)下圖。(
23、3)凡落地架在立桿下統(tǒng)一墊通長(zhǎng)木方,并在立桿底部墊100×100厚5mm鋼板。(4)在腳手架立桿底端之上100150mm處一律設(shè)縱向和橫向掃地桿,橫向掃地桿在縱向掃地桿之下,并與立桿連接固定。當(dāng)立桿基礎(chǔ)不在同一高度時(shí),必須將高處的縱向掃地桿向低處延長(zhǎng)兩跨與立桿固定??窟吰律戏降牧U軸線到邊坡的距離不應(yīng)小于500,腳手架底層步距不應(yīng)大于2000。 (5)立桿頂端高出女兒墻上皮1000。6.1.2.2橫桿(1)大橫桿長(zhǎng)度不得小于三跨,并設(shè)置于立桿內(nèi)側(cè),大橫桿對(duì)立桿起約束作用,故立桿與大橫桿必須用直角扣件扣緊,不得遺漏。(2)大橫桿應(yīng)采用對(duì)接扣件連接,同一水平的和上下相鄰的兩根大橫桿的接頭
24、均應(yīng)相互錯(cuò)開,不得出現(xiàn)在同一跨間內(nèi),相鄰的水平間距應(yīng)500mm,接頭應(yīng)設(shè)置于距節(jié)點(diǎn)1/3跨度范圍內(nèi)。如下圖:(3)同一排大橫桿的水平偏差不大于該片腳手架總長(zhǎng)度的1/250且不大于50mm。(4)大橫桿接頭與相鄰立桿距離不大于立桿縱距的1/3。(5)小橫桿設(shè)置于大橫桿之上并用直角扣件固定在大橫桿上,小橫桿每個(gè)節(jié)點(diǎn)設(shè)置一根,在操作層每跨跨中加設(shè)一根用來(lái)支撐腳手板。(6)腳手架外側(cè)小橫桿伸出架子外皮100mm,內(nèi)側(cè)伸出立桿300mm。6.1.2.3拉接桿件(1)腳手架架體每層遇框架柱時(shí)必須與框架柱抱柱拉接,拉接點(diǎn)設(shè)置在結(jié)構(gòu)梁下第一道主節(jié)點(diǎn)處,同時(shí)在跨中樓板上予埋1道Ø48鋼管地錨,從地錨中
25、挑出拉接桿與架體拉接。(2)拉接桿件從架體第一道大橫桿開始設(shè)置。6.1.2.4剪刀撐在腳手架的外立面設(shè)置剪刀撐,。剪刀撐的斜桿與水平面的夾角為45度-60度之間,每道剪刀撐寬度不應(yīng)小于四跨,且不應(yīng)小于6米,搭設(shè)時(shí),將一根斜桿扣在立桿上,另一根扣在小橫桿的伸出部分上。(1)斜桿用扣件與腳手架扣緊的接頭兩端距腳手架節(jié)點(diǎn)不大于200mm,除兩端扣緊外,中間尚需增加24個(gè)扣結(jié)點(diǎn)。(2)斜桿的最下設(shè)一個(gè)連接點(diǎn)距腳手架最下端不宜大于500mm,以保證腳手架的穩(wěn)定。(3)剪刀撐的底部要插到腳手架的最下端,與立桿相交點(diǎn)必須加扣件的一定要加扣件。剪刀撐應(yīng)采取搭接方式,搭接長(zhǎng)度1000mm,并用不少于三個(gè)旋轉(zhuǎn)扣件
26、扣緊,兩端露出不少于100mm。6.1.2.5 腳手架的搭設(shè)除滿足上述要求外,還應(yīng)滿足下列要求: (1)腳手架的搭設(shè)作業(yè),必須在統(tǒng)一指揮下,嚴(yán)格按照規(guī)定的程序進(jìn)行。(2)按施工設(shè)計(jì)放線、鋪墊板、設(shè)置底座或標(biāo)定立桿位置;周邊腳手架應(yīng)從一個(gè)角部開始并向兩邊延伸交圈搭設(shè)。(3)腳手架必須配合施工進(jìn)度搭設(shè),一次搭設(shè)高度不應(yīng)超過(guò)相鄰連墻件以上二步;剪刀撐、斜桿等整體拉結(jié)桿件和連墻件應(yīng)隨搭升的架子一起及時(shí)設(shè)置;裝設(shè)連墻件及其他撐拉桿件時(shí),應(yīng)注意掌握撐拉的松緊程度,避免引起桿件和架體的明顯變形。 (4)腳手板采用對(duì)接平鋪時(shí),在對(duì)接處,與其下兩側(cè)支撐橫桿的距離應(yīng)控制在100mm200mm之間;腳手板采用搭接平
27、鋪時(shí),其搭接長(zhǎng)度不應(yīng)小于200mm,且應(yīng)在搭接段的中部設(shè)有支撐橫桿;鋪板嚴(yán)禁出現(xiàn)端頭超出支撐橫桿250mm以上未作固定的探頭板。(5)嚴(yán)禁將外徑48mm與51mm的鋼管混合使用;相鄰立桿的對(duì)接扣件不得在同一高度內(nèi)。(6)腳手架搭設(shè)中不得隨意改變構(gòu)架設(shè)計(jì)、減少桿配件設(shè)置和對(duì)立桿縱距作100mm的構(gòu)架尺寸放大。確有實(shí)際情況,需要對(duì)構(gòu)架作調(diào)整和改變時(shí),應(yīng)提交和請(qǐng)示技術(shù)主管人員解決。6.1.3 拆除要求本工程為結(jié)構(gòu)施工腳手架,隨著主體混凝土結(jié)構(gòu)的完成可按懸挑單元,逐單元自下至上拆除。落地式和每一懸挑單元腳手架拆除時(shí),應(yīng)符合下列規(guī)定:(1)腳手架拆除前應(yīng)檢查扣件連接、連墻件、支撐體系等是否符合構(gòu)造要求;
28、(2)拆除前須指派專人檢查架子上的材料、雜物等是否清理干凈,否則不許拆除。(3)腳手架的拆除順序與搭設(shè)順序相反,須遵守先搭后拆,后搭先拆的原則, 必須由上而下逐層拆除,嚴(yán)禁上下同時(shí)作業(yè);(4)連墻件必須隨腳手架逐層拆除,嚴(yán)禁先將連墻件整層或數(shù)層拆除后,再拆除腳手架;分段拆除高差小于2步,如高差大于2步,應(yīng)增設(shè)連墻件加固。(5)在拆除過(guò)程中,凡已松開連接的桿配件應(yīng)及時(shí)拆除,應(yīng)綁扎牢固或裝入容器內(nèi)運(yùn)走,避免誤扶和誤靠已松脫連接的桿件;拆除的腳手架桿,板應(yīng)分段放置,及時(shí)用塔吊運(yùn)至地面,并按指定地點(diǎn)堆放、外運(yùn)。(6)拆除過(guò)程中應(yīng)作好配合,協(xié)調(diào)工作,禁止單人進(jìn)行拆除較重桿件的拆除等危險(xiǎn)性作業(yè)。(7)拆除
29、腳手架時(shí)必須劃分安全區(qū),設(shè)警戒標(biāo)志,并設(shè)專人警戒。6.1.4 腳手架驗(yàn)收標(biāo)準(zhǔn)規(guī)定腳手架及其地基基礎(chǔ)應(yīng)按規(guī)范規(guī)定的時(shí)間階段和內(nèi)容進(jìn)行檢查與驗(yàn)收。其主要驗(yàn)收標(biāo)準(zhǔn)規(guī)定如下:(1)構(gòu)架尺寸符合規(guī)范及設(shè)計(jì)要求,個(gè)別部位的尺寸變化應(yīng)在允許的調(diào)整范圍之內(nèi)。(2)節(jié)點(diǎn)的連接可靠,扣件的擰緊程度應(yīng)控制在擰力矩達(dá)到4060N·m。(3)腳手架立桿的垂直度偏差應(yīng)1/300,且應(yīng)同時(shí)控制其最大垂直度偏差值:當(dāng)架高20m時(shí)為不大于50mm;當(dāng)架高20m時(shí)為不大于75mm。(4)縱向水平桿的水平偏差應(yīng)1/250,且全架長(zhǎng)的水平偏差值應(yīng)不大于50mm。(5)作業(yè)層鋪板、安全防護(hù)措施等均應(yīng)符合施工設(shè)計(jì)和規(guī)范要求。6
30、.1.5 荷載要求(1)施工荷載(作業(yè)層上人員、器具、材料的重量)的標(biāo)準(zhǔn)值,不得超過(guò)3 KN/m2;架板上施工設(shè)備單重不得大于1KN,使用人力在架上搬運(yùn)和安裝構(gòu)件的自重不得大于2.5KN。(2)腳手架僅滿足操作人員及隨身攜帶的操作工具的荷載,不得在腳手板上大量堆放材料、過(guò)重的設(shè)備。施工人員作業(yè)時(shí),盡量分散腳手架的荷載,嚴(yán)禁利用腳手架穿滑車做垂直運(yùn)輸及支撐大鋼模板。6.2 安全技術(shù)措施(1)腳手架搭設(shè)人員必須是經(jīng)過(guò)按現(xiàn)行國(guó)家標(biāo)準(zhǔn)特種作業(yè)人員安全技術(shù)考核管理規(guī)則(GB 5036)考核合格的專業(yè)架子工。上崗人員應(yīng)定期體檢,合格者方可持證上崗。(2)操作人員要嚴(yán)格遵守規(guī)章制度,加強(qiáng)規(guī)范管理,制止和杜絕
31、違章指揮和違章作業(yè)。加強(qiáng)防護(hù)措施,加強(qiáng)管理人員和操作人員的安全生產(chǎn)意識(shí)和自我保護(hù)意識(shí)。搭設(shè)腳手架人員必須戴安全帽、系安全帶,穿防滑鞋。(3)嚴(yán)格按照規(guī)范、設(shè)計(jì)要求和有關(guān)規(guī)定進(jìn)行腳手架搭設(shè)、使用、拆除,嚴(yán)厲制止亂搭、亂改、亂用等情況,確保腳手架構(gòu)架和防護(hù)設(shè)計(jì)達(dá)到承載可靠和使用安全的要求。作業(yè)層上的施工荷載應(yīng)符合設(shè)計(jì)要求,不得超載。不得將模板支架、纜風(fēng)繩、泵送混凝土和砂漿的輸送管等固定在腳手架上,嚴(yán)禁懸掛起重設(shè)備。(4)在腳手架使用期間,嚴(yán)禁拆除下列桿件:連墻件;主節(jié)點(diǎn)處的縱、橫向水平桿,縱、橫向掃地桿。(5)當(dāng)有六級(jí)及六級(jí)以上大風(fēng)、霧、雷雨和雪天應(yīng)停止腳手架搭設(shè)與拆除作業(yè)。雨、雪后上架作業(yè)應(yīng)有防
32、滑措施,并應(yīng)掃除積雪。(6)搭拆腳手架時(shí),地面應(yīng)設(shè)圍欄和警戒標(biāo)志,并派專人看守,嚴(yán)禁非操作人員入內(nèi)。(7)人員上下腳手架必須走設(shè)安全防護(hù)的人行通道和斜道,嚴(yán)禁攀爬腳手架上下。(8)在腳手架上進(jìn)行電、氣焊作業(yè)時(shí),必須有防火措施和專人看守。(9)腳手架應(yīng)按照施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范(JGJ46)的有關(guān)規(guī)定,采取接地和避雷的措施。(10)每日收工前應(yīng)清理架面,將架面上的材料物品堆放整齊,垃圾清運(yùn)出去;在任何情況下,嚴(yán)禁自架上向下拋擲材料物品和傾倒垃圾。(11)未盡事宜按照建設(shè)部、山東省及青島市有關(guān)建筑施工安全文件的要求進(jìn)行施工。7. 編制依據(jù)(1)招標(biāo)文件及答疑書、施工合同及我公司投標(biāo)承諾;(2
33、)工程設(shè)計(jì)圖紙、施工組織設(shè)計(jì)及相關(guān)的施工文件;(3)國(guó)家、部、省、市有關(guān)工程建設(shè)的法律、法規(guī);(4)集團(tuán)公司質(zhì)量、環(huán)境、安全衛(wèi)生認(rèn)證體系文件及有關(guān)管理規(guī)定;(5)現(xiàn)場(chǎng)條件、公司的施工管理制度和施工經(jīng)驗(yàn);(6)建筑施工手冊(cè)2003年第4版;(7)國(guó)家現(xiàn)行的規(guī)范、規(guī)程,主要包括:建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范JGJ130-2001建筑施工高處作業(yè)安全技術(shù)規(guī)范JGJ80-91建筑結(jié)構(gòu)荷載規(guī)范GB50009-20018. 腳手架承載力驗(yàn)算8.1落地式腳手架1.荷載計(jì)算A.一步一縱距的鋼管扣件重量NGK10.442KNB.腳手架一個(gè)立桿縱距的附設(shè)構(gòu)件及物品重量NGK24.185KNC.施工荷載標(biāo)準(zhǔn)
34、值QK3KN/m2D.防護(hù)欄桿水平活荷載標(biāo)準(zhǔn)值QK0.5KN/m2E.風(fēng)荷載W0.7µS.µs.wo=0.7×1.0×2.03×0.16224×0.77=0.16 KN/m2F.雪荷載取值0.3KN/m2G.腳手板取值0.3KN/m22、 驗(yàn)算單根鋼管允許搭設(shè)的最高高度 1. 由h1.8m H2h3.6m b1.05m 查表得Af48.491KN 2. NQK10.442KN NGK24.185KN 3. 由b1.05m L1.5m QK3.0KN/m2按 2層腳手架同時(shí)施工QK6KN/m2,查表得NGK12.6KN。 4. 將48.
35、491KN NGK1、NGK2 代入公式其中KA0.85 H(KA×48.491)1.30×(1.2×4.8151.4×12.6)×1.8/1.2×0.44239.7m 最大允許搭設(shè)高度HmaxH/(1+ H /100)39.7/(1+39.7/100)28.4m n128.4/1.815.7排 最高能搭設(shè)15排。 3、各桿件的內(nèi)力計(jì)算 A. 各桿件的內(nèi)力計(jì)算按三跨連續(xù)梁計(jì)算,計(jì)算彎距最不利位置位于大橫桿與小橫桿交接處。Mmax1/12 (q活q恒).b=1/12×(1.4×3.0)+1.2×(0.422
36、+40185+0.5+0.3×2+0.23) ×1.05彎距由兩根大橫桿承受Wn=5.08×103mm3Mmax/Wn0.5×106/5.08×10398.4N/mm 2f205N/mm2 大橫桿滿足要求C.小橫桿受力計(jì)算按簡(jiǎn)支梁計(jì)算力經(jīng)過(guò)2根大橫桿轉(zhuǎn)化成集中荷載傳遞給小橫桿,大橫桿距離立桿中心距約5cm。 Mmax1/2×1.4×3.0×1.051.2×(0.4424.185)/1.50.5×1.050.3×2×1.05×1.5×1.05 0.36KN&
37、#183;mMmax/Wn0.36×10 6 /5.08×10370.8N/mm 2f205N/mm2 小橫桿滿足要求。C. 小橫桿變形計(jì)算F1/2×1.4×3.0×1.051.2×(0.4424.185)/1.50.5×1.050.3×2×1.05×1.5 4.8KN W/b1.615×4800×10502/100×2.06×105×121900 1/2931/150 滿足要求D. 驗(yàn)算單根立管的局部穩(wěn)定 N1/2×1.2×
38、n1×NGK10.5×1.05/1.4×(1.2NGK21.4NQK)0.5×1.2×15×0.4420.5×1.05/1.4×(1.2×4.1851.4×1.2612.48KNh/i1800/15.78114 查表得0.489 由QK3.0KN/m2 得m55N/mm2 單根鋼管截面面積A=489mm2 N1/0.489Am12480/0.489×48955107.2N/mm2 KAKH·F0.85×0.661×205115.72N/mm2107.2N/
39、mm2 單立管安全。E. 驗(yàn)算整體穩(wěn)定(不考慮風(fēng)荷載影響) N1.2(NGK1NGK2)1.4NQK 1.2×(0.4424.185)1.4×12.6 30.618KN 計(jì)算值由b1.05M H12hA=2×3.6=7.2m 查表得h25x2 hA /b2×3.6/1.056.86oxhx25×6.86171.25 立桿為單鋼管KA0.85 KH1/(151.2/1000.661 (1/2N)/A30.618×103/0.242×4.893×10264.6N/mm2 KA1·KH·f0.85
40、215;0.661×205115N/mm264.64N/mm2 安全F. 抗風(fēng)驗(yàn)算 Nt1.4 hA·LA·W 1.4×3.6×6×0.232 6.12KN一個(gè)扣件的拉滑設(shè)計(jì)值為6KN6.12KN現(xiàn)場(chǎng)硬拉結(jié)可改為3×1.54.5m一道8.2.懸挑式腳手架 為適應(yīng)高層建筑分段搭設(shè)腳手架要求和配合施工等因素, 設(shè)計(jì)十一步架為一個(gè)懸挑段。在上段搭設(shè)時(shí),下段還承重上段搭設(shè)時(shí)的臨時(shí)荷載。設(shè)計(jì)荷載以十二步架為計(jì)算基數(shù)取值。荷載計(jì)算1)永久荷載,一步距腳手架結(jié)構(gòu)自重,取柱距1.5米,取每米0.249KNNGK=0.249KN/m2
41、5;19.8m=4.93KN2)施工荷載,考慮一層腳手架結(jié)構(gòu)施工荷載每跨施工荷載為 Ngk1=3kN/m2×1.5m×0.96m=4.32 KN腳手板荷載NQK2=0.24KN/m2×1.5m×0.96m×4=1.4KN3)風(fēng)荷載k=0.7·Z·S·0=0.7×1.5×0.1157×0.35=0.042KN/m2每跨風(fēng)荷載為0.04KN/m2×1.5m×19.8m=1.188 kN立桿穩(wěn)定性計(jì)算(按組合風(fēng)荷載計(jì)算)1)立桿軸向力NN=1.2Ngk+1.4×
42、0.85×NQK =1.2×4.93+1.4×0.85×6.9=15.852 KN每根立桿受力15.852KN/2=7.926KN2)值的計(jì)算= l0/ I = kµh /I 式中 k 為計(jì)算長(zhǎng)度附加系數(shù)(取k=1.155)µ 為計(jì)算長(zhǎng)度系數(shù),查表得µ=1.8I=1.58=1.155×1.8×180/1.58=236.85查表得,=1.3求A=489mm23)強(qiáng)度驗(yàn)算N/A=7.926×103/0.13×489=125.6<205 N/ mm2MW/W=1/10×0.8
43、5×1.4×2/W=0.85×1.4×0.04KN/m2×1.5 m×1.8 2m/10×5.08cm3=0.00488 KN/ mm2=4.88N/ mm2N/A+ MW/W=125.08 N/ mm2<205N/ mm2東立面和西立面無(wú)陽(yáng)臺(tái)處懸挑槽鋼結(jié)構(gòu)計(jì)算其中q為槽鋼自重按均布荷載考慮,18槽鋼自重:230N/m×1.52=349.6 N/m=0.35 KN/m支座反力RA=1.5N+5ql/8=1.5×7.926+5q×3/8=8.58 KNRB=-0.5N+3ql/8=-0.5&
44、#215;7.926+3q×3/8=-7.53 KN槽鋼挑梁計(jì)算強(qiáng)度驗(yàn)算按公式:V=MX/X WnõFMX=7.926KN×1.52M+7.926KN×0.33m+0.5×ql2=15.9 KN .M查得18槽鋼的截面抵抗距為Wn=137.9cm318槽鋼的抗壓強(qiáng)度設(shè)計(jì)值為f=215N/mm215.9 KN .M /0.96× 137.9 cm3= 120.105 N/mm2 <f 故安全。撓度驗(yàn)算按公式:=NL22/6EIl/400(懸臂梁I為懸伸長(zhǎng)度的2倍)N=7.926×2=15.852 KN, L2=0.81m
45、E=2.05×105N/ mm2I=1/12×BH3-(B-b)h3=1/12 ×7cm×18cm3-(7cm 0.9cm) × 16.6cm3 I=12920.7944 cm4/12=1076.732 cm4=(NL22/6EI) ×(3-L2/ L3)=15.852kN×0.81m×0.81m×0.81m /(6×2.05×105N/ mm2×1076.732 cm4)×(3-0.81/1.09)=1.435mmL/400=7.45 mm,故安全.驗(yàn)算懸挑梁錨固
46、鋼筋槽鋼懸挑梁計(jì)算簡(jiǎn)圖錨固點(diǎn)拉力R×l1=N×(l2+0.2),R=7.926×(0.81+0.2)/2.98=2.6 KN預(yù)埋錨固鋼筋吊環(huán)按兩個(gè)截面同時(shí)受力計(jì)算,每根鋼筋承受R/2=1.3 KN校核安全度,應(yīng)滿足AS/R/2 > 2 現(xiàn)場(chǎng)采用20錨固鋼筋,鋼材強(qiáng)度標(biāo)準(zhǔn)值S=240 KN/ mm2,AS=3.14×100 mm2×240 KN/ mm2=75360KN R/2=2.6/2=1.37 KN,故安全.東立面和西立面陽(yáng)臺(tái)處槽鋼下部采用鋼管斜支撐,鋼管大橫桿間距為1.5米。根據(jù)公式:N1L1+N2(L1-L2)=NXcosb(L1
47、+0.13) ( 2×2.51-1.09) ×7.926=NX×2.64cosbNX=15.33KN根據(jù)公式 H/i=150/1.58=95, 查表得ø=0.626根據(jù)公式N/ØA=15.33/0.626×0.489=50.07<205 故安全南北立面槽鋼挑梁計(jì)算根據(jù)公式:N1×L1+N2(L1-L2)=NXCOSb(L1+0.13) 7.926(2.64+0.33+0.96)+7.926×2.97=NX(4.06+0.13) COSb NX=54.68/ COSb×4.19=21.75KN取保險(xiǎn)細(xì)
48、數(shù)6,NX=6×21.75=130.5 KN查表選用6×19鋼絲繩,鋼絲繩直徑14mm,鋼絲0.9 mm,鋼絲總截面積72.49 mm2,鋼絲繩拉力134KN,抗拉強(qiáng)度1850N/ mm29. 卸料鋼平臺(tái)方案9.1施工準(zhǔn)備9.1.1技術(shù)準(zhǔn)備按施工規(guī)范和現(xiàn)場(chǎng)實(shí)際情況編制詳細(xì)的鋼平臺(tái)制作、安裝方案,并進(jìn)行受力計(jì)算,確保鋼平臺(tái)的結(jié)構(gòu)剛度、整體穩(wěn)定性,力求施工安全。施工操作人員在鋼平臺(tái)制作過(guò)程中及使用過(guò)程中,工長(zhǎng)及安全員應(yīng)對(duì)操作者及使用者進(jìn)行認(rèn)真詳細(xì)的技術(shù)交底,并監(jiān)督其操作過(guò)程按交底要求施工。材料準(zhǔn)備根據(jù)施工方案的要求配購(gòu)18、10槽鋼,鋼絲繩采用15規(guī)格。嚴(yán)禁用不合格的材料進(jìn)行平
49、臺(tái)制作。人員要求鋼料平臺(tái)的焊接制作應(yīng)由持有上崗證的電焊工按方案要求加工制作,焊縫的寬度及深度必須符合規(guī)范規(guī)定要求。鋼料平臺(tái)的安裝及提升工作應(yīng)由專業(yè)腳手架工操作,腳手架操作人員應(yīng)持有上崗證書。9.2、具體施工方法及措施.鋼料平臺(tái)的制作懸挑鋼料平臺(tái)結(jié)構(gòu)采用主梁、次梁及桁架組裝焊接的形式。主梁采用18槽鋼,次梁采用10槽鋼。根據(jù)方案部署,首先將18槽鋼相互焊接成矩形框狀, 10槽鋼作矩形框間次梁,次梁槽鋼頂面必須和主梁槽鋼的頂面緊貼焊接,主梁槽鋼和次梁槽鋼垂直相交焊接點(diǎn)的內(nèi)側(cè)應(yīng)用鋼板加焊三角形抗扭支撐,以減少邊框的受力后的扭曲應(yīng)力。每個(gè)焊接點(diǎn)應(yīng)沿頂面滿焊,且焊縫無(wú)氣孔、夾渣等缺陷。懸挑鋼平臺(tái)的主梁末
50、端擱置于建筑物邊梁上500,為防止鋼絲繩拉應(yīng)力的影響,因此在2根主梁18槽鋼后部下端各加焊一固定限位,限位采用400長(zhǎng)18槽鋼焊制。防止料臺(tái)往樓面反竄。斜拉鋼絲繩與鋼料平臺(tái)的拉接點(diǎn)采用12的鋼筋焊制成固定環(huán),固定環(huán)應(yīng)和主槽鋼焊牢。固定環(huán)每側(cè)設(shè)有1個(gè)。鋼料平臺(tái)主梁兩側(cè)設(shè)有兩道斜拉鋼絲繩。外側(cè)斜拉鋼絲繩從料臺(tái)主梁槽鋼底部繞過(guò),鋼絲繩在主梁槽鋼拉接端打彎,用最少三個(gè)鋼絲繩卡卡牢,繩卡且顛倒設(shè)置,鋼絲繩的彎頭末端均應(yīng)留有保險(xiǎn)彎。鋼平臺(tái)的斜拉繩與建筑物連接與結(jié)構(gòu)框架柱上。即將鋼絲鑲拼成鋼環(huán),然后用卡環(huán)固定。鋼絲繩固定的框架柱四周應(yīng)有保護(hù)棱角措施,防止棱角和鋼絲繩受損。鋼料平臺(tái)在外三側(cè)面設(shè)置防護(hù)欄桿,欄桿
51、的立桿采用48的腳手架鋼管固定與主梁槽鋼的頂面上,高度為950,立桿間距2000,然后在立桿上設(shè)置兩道水平拉桿,用扣件固定,最后在防護(hù)欄桿的內(nèi)側(cè)滿布竹膠板,以防掉物或起吊鉤掛。鋼料平臺(tái)的平面滿鋪50厚的木板,且用不低于8#鐵絲和料臺(tái)的桁架連接牢固,木板不得空頭、松動(dòng)。鋼料平臺(tái)加工制作完畢后,應(yīng)用防銹漆將焊接處刷油防銹。提升安裝完畢后應(yīng)由項(xiàng)目經(jīng)理、技術(shù)負(fù)責(zé)人、安全員等組織驗(yàn)收合格后方可投入使用。鋼料平臺(tái)的具體制作形式見(jiàn)附圖七。9.2.2鋼料平臺(tái)的安裝使用進(jìn)入標(biāo)準(zhǔn)層施工后,在該層頂板模板拆除前,先將該層樓面清理干凈,布置好料臺(tái)擱置位置,然后將鋼平臺(tái)用吊車吊至待拆樓板的擱置位置,注意吊裝時(shí)應(yīng)保持鋼料平臺(tái)的平穩(wěn)性,并保持外側(cè)比內(nèi)側(cè)高出100mm左右。鋼料平臺(tái)吊至安裝位置上空后,緩慢降落,使鋼平臺(tái)主梁擱置于樓面邊梁上,然后將斜拉鋼絲繩拉起,用鋼絲繩兜住框架柱后用卡環(huán)卡住主繩。鋼絲繩固定完畢后,將吊車吊鉤慢慢松開,檢查平臺(tái)是否保持穩(wěn)定,外側(cè)是否比內(nèi)側(cè)略高,主梁下端的限位是否卡住混凝土邊梁,并按圖進(jìn)行固定主梁擱置端,確定在各部位無(wú)誤后方可全部松開。鋼平臺(tái)吊裝后,檢查平臺(tái)和樓層之間的接觸處是否有空隙并封牢。鋼平臺(tái)每次安裝完畢后,應(yīng)在
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 石河子大學(xué)《應(yīng)急人力資源管理》2022-2023學(xué)年第一學(xué)期期末試卷
- 物業(yè)智能化解決方案
- 石河子大學(xué)《數(shù)學(xué)文化賞析》2021-2022學(xué)年第一學(xué)期期末試卷
- 石河子大學(xué)《口腔頜面外科學(xué)》2022-2023學(xué)年第一學(xué)期期末試卷
- 石河子大學(xué)《工程熱力學(xué)與傳熱學(xué)》2023-2024學(xué)年第一學(xué)期期末試卷
- 精神科新冠肺炎演練
- 沈陽(yáng)理工大學(xué)《數(shù)學(xué)建?!?023-2024學(xué)年第一學(xué)期期末試卷
- 沈陽(yáng)理工大學(xué)《液壓與氣動(dòng)技術(shù)》2022-2023學(xué)年第一學(xué)期期末試卷
- 沈陽(yáng)理工大學(xué)《電氣控制與PC技術(shù)》2022-2023學(xué)年期末試卷
- 沈陽(yáng)理工大學(xué)《場(chǎng)地設(shè)計(jì)》2021-2022學(xué)年第一學(xué)期期末試卷
- 自然拼讀法-圖文.課件
- 2024中國(guó)長(zhǎng)江電力股份限公司招聘高頻500題難、易錯(cuò)點(diǎn)模擬試題附帶答案詳解
- Unit 2 Travelling Around Listening and Speaking 教學(xué)設(shè)計(jì)-2024-2025學(xué)年高中英語(yǔ)人教版(2019)必修第一冊(cè)
- 電商主播考勤管理制度
- 2024-2030年中國(guó)礦泉水行業(yè)發(fā)展趨勢(shì)及發(fā)展前景研究報(bào)告
- 商業(yè)銀行貴金屬業(yè)務(wù)消費(fèi)者權(quán)益保護(hù)實(shí)施辦法
- 2024年新人教版七年級(jí)上冊(cè)道德與法治全冊(cè)教案
- 2024年秋新人教版七年級(jí)上冊(cè)數(shù)學(xué)教學(xué)課件 4.1 整式 第1課時(shí) 單項(xiàng)式
- 北師大版三年級(jí)數(shù)學(xué)上冊(cè)原創(chuàng)天天練
- 衢州江山市交投人力資源有限公司招聘筆試題庫(kù)2024
- 職業(yè)資格證書遺失補(bǔ)發(fā)申請(qǐng)表
評(píng)論
0/150
提交評(píng)論