版權說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權,請進行舉報或認領
文檔簡介
1、Fujian LNG Cooldown Presentation福建液化天然氣冷卻演示福建液化天然氣冷卻演示Option 4.方案方案4Cooldown Unloading System & T-0202冷卻卸載系統(tǒng)冷卻卸載系統(tǒng)&T-0202Cooldown Steps冷卻步驟冷卻步驟1. Displace Nitrogen from T-0202 & Unloading System Piping before cooldown冷卻前將氮氣抽離出T-0202和卸載系統(tǒng)管道2. Cooldown Unloading and T-0202 only僅冷卻卸載系統(tǒng)和T-02023. Displac
2、e LNG from unloading into T-0202將液化天然氣從卸載系統(tǒng)運至T-02024. Re-cooldown the facility with a second ship用另一艘船只再次冷卻設備Cooldown Description冷卻說明冷卻說明nDisplace the Nitrogen from T-0202 with vapor from the ship vaporizer用船只汽化器中的蒸汽置換T-0202中的氮氣nCooldown the Unloading and LP sendout systems with cold vapor from ship
3、用船上的冷蒸汽冷卻卸載和LP輸出系統(tǒng)nCooldown T-0202 until design temperature將T-0202冷卻至設計溫度nUnload all cargo into T-0202 將船上所有氣體卸載到T-0202nShip departs船只駛離nRecover unloading system LNG to T-0202將卸載系統(tǒng)中的液化天然氣運回T-0202Preparation準備階段準備階段nA valve lineup will be done for each step安排每一步的閥門開關順序nMonitoring of all cooldown inst
4、ruments will be on the DCS trends由集散控制系統(tǒng)監(jiān)視所有的冷卻設備nMonitoring of the unloading lines movement will be by a team of engineers將由一隊工程師監(jiān)視卸載管線作業(yè)nCommunication with the ship will be from the CBI focal point in the CCR與船只的聯(lián)系將由CBI中央控制室精英人員執(zhí)行Step 1: Nitrogen Displacement步驟步驟1:氮氣置換:氮氣置換nValve line up to direct
5、 the ship vapor to T-0202 bottom fill line.執(zhí)行閥門開關順序,引導船上蒸汽進入T-0202底部的充液管線nDirect the Nitrogen through the BOG system to the Flare Stack引導氮氣通過BOG系統(tǒng)進入火炬塔nControl the Tank pressure on 06-PV-0004控制06-PV-0004上的儲罐壓力nNitrogen target is 30%所需氮氣量為30nEstimated time for 12 hrs估計所需時間為12個小時Step 2: Unloading Syst
6、em Cooldown步驟步驟2:卸載系統(tǒng)冷卻:卸載系統(tǒng)冷卻nVapor Cooldown of the unloading system卸載系統(tǒng)的蒸汽冷卻 nCooldown will be controlled by the ship on instructions from the DCS operator冷卻作業(yè)由船只根據(jù)集散控制系統(tǒng)操作員的指令進行控制nCooldown rate will be 10 to 20 deg / hr冷卻速率為10-20/小時nCooldown can start during the Nitrogen displacement from T-0202在
7、氮氣抽離T-0202的期間可以開始冷卻nTarget temperature -100C at T-0202 riser T-0202立管目標溫度為-100nTime for this step.16 hrs.這一步所需時間為16個小時Step 3: Filling the Unloading Lines步驟步驟3:卸載管線充液:卸載管線充液nLNG can be introduced to the unloading arm when -100C is reached at T-0202 riser on 02-TIT-2021 / 02-TIT-2022當02-TIT-2021/02-TI
8、T-2022上的T-0202立管達到-100時,可以將液化天然氣裝入卸載臂nTwo ship stripping pumps can be started to fill the unloading system.啟動兩個船只掃艙泵對卸載系統(tǒng)進行充液nApproximate volume of LNG required 850m3 所需液化天然氣容積約為850m3nFilling rate 150 m3/hr from ship充液速率為每小時150m3nEstimated time for this step is. 10 hrs.這一步所需時間為10個小時Step 4: LNG Coold
9、own of T-0202步驟步驟4:T-0202的液化天然氣冷卻的液化天然氣冷卻nWhen LNG is detected at PIT on T-2020 riser the 02-HV-2002B on the tank must be closed.在T-2020立管上的PIT檢測到液化天然氣時必須關閉儲罐上的02-HV-2002BnOne stripping pump stopped and 02-HV-2001 Spray valve opened停止一臺掃艙泵,打開02-HV-2001噴射閥nSpray cooling of the tank can begin at 3 to
10、5C /hr.以每小時3到5的速度開始對儲罐進行噴淋冷卻nEstimated cooldown time is 50 hrs.估計冷卻時間為50個小時 nCooldown is finished when50 mm of LNG is measured on tank floor儲罐底上的液化天然氣達到50mm時結束冷卻.Step 5 Tank T-0202 Filling步驟步驟5:T-0202充液充液nFilling of the tank can begin when all floor thermocouple are reading -156C and at 50mm level當所
11、有的底面熱電偶讀數(shù)為-156并達到50mm時可以開始儲罐充液.nRequest the ship to start a cargo pump要求船只啟動裝卸油泵.nPumps can be started to the maximum limit of two unloading arms (8000m3/hr).可以以兩個卸載臂的最大速率(8000m3/hr)運轉(zhuǎn)油泵.nEstimated time for this step16 hrs. (depends on ship cargo size).估計所需時間為16個小時(取決于船只液量)Ship Departure船只駛離船只駛離nWhe
12、n cargo transfer is complete, the unloading arms can be disconnected following vendor procedure.充液完成后,可以根據(jù)供應商程序拆下卸載臂.nThe V-0102 Drain Drum emptied.排空V-0102干燥滾筒.nThe Unloading system LNG allowed to weather off.卸載系統(tǒng)使液化天然氣不受天氣影響.nThe unloading system purged by Nitrogen.用氮氣吹掃卸載系統(tǒng).Fig 1 Cooldown Diag. Overview圖圖1 冷卻圖總覽冷卻圖總覽Fig: 2 Nitrogen Displacement圖圖2:氮氣置換:氮氣置換LNG Vapor Cooldown液化天然氣蒸汽冷卻液化天然氣蒸汽冷卻Filling Unloading System卸載系統(tǒng)充液卸載系統(tǒng)充液Cooldown of T-0202T-0202冷卻冷卻Filling T-0202T-0202充液充液Displacing LNG to T-020
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經(jīng)權益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 部編初中歷史九上第6單元《資本主義制度的初步確立》考點測試
- 安健環(huán)體系抽考復習試題
- 七年級歷史與社會上冊說課稿(圖片版)第1單元第1課 我的家在哪里
- 婚禮音樂 課件
- 弱電設備出租合同范例
- PDCA循環(huán)法在提高ICU多重耐藥菌感染防控措施執(zhí)行率中的應用
- 工程型材購銷合同范例
- 大興機場商貿(mào)合同范例
- 小型裝修施工合同模板
- 工程竣工審計合同范例
- 部編(統(tǒng)編)人教版七年級語文上冊教學計劃(含教學進度表)
- 大棚鋼管購買合同協(xié)議書
- 2024年區(qū)人民法院公開招考聘用制司法輔助人員考試題及答案
- 特立帕肽治療骨質(zhì)疏松性骨折中國專家共識(2024版)解讀
- (完整版)新員工進場三級安全教育考核-試卷及答案
- 2024屆陜西省西安市西安交大附中中考四模數(shù)學試題含解析
- DB3305-T 104-2019環(huán)境污染責任保險風險評估技術規(guī)范
- GB/T 23132-2024電動剃須刀
- 門窗維修簡單合同范本(2024版)
- 糖尿病酮癥酸中毒
- 03D201-4 10kV及以下變壓器室布置及變配電所常用設備構件安裝
評論
0/150
提交評論