WEPEC
目 錄 ··············································· ···············································1、施工內(nèi)容概述·············································2、工藝流程················································· ································1、材料選擇·················································2、材料配制·················································3、基層處理要求及處理辦法···································4、施工方法·················································5、成品保護·················································6、耐酸磚塊材在施工中應(yīng)注意的事項······································································1、質(zhì)量保證組織措施·········································2、質(zhì)量保證技術(shù)標準·········································3、施工現(xiàn)場質(zhì)量管理體系················································································1、安全保證組織措施·········································2、安全保證技術(shù)措施·········································3、施工現(xiàn)場安全管理體系·····································
WEPEC
酸再生裝置尾氣達標治理項目—耐酸項目名稱瓷磚工程施工單位 審批單位設(shè)備運行單位安全
審
批
意
見質(zhì)量安全環(huán)保部
安全監(jiān)督處環(huán)保處生產(chǎn)技術(shù)部設(shè)備部主管處室設(shè)備部副部長設(shè)備部部長公司主管領(lǐng)導備注 、《建筑安裝工程質(zhì)量檢驗評定統(tǒng)一標準》;、《建筑防腐蝕施工設(shè)計規(guī)范》;、《工業(yè)建筑防腐蝕設(shè)計規(guī)范》;4、《磚板襯里設(shè)備技術(shù)條件》CD130A12-85;、設(shè)計施工圖紙、我公司多年從事類似工程經(jīng)驗 、施工內(nèi)容概述本工程主要內(nèi)容為在大連西太平洋石油化工有限公司W(wǎng)EPEC
酸再生裝置尾氣達標治理項目—耐酸瓷磚工程的施工,鋪貼面積200
㎡。、工藝流程舊基層處理→刷涂環(huán)氧樹脂打底料二道→環(huán)氧膠泥配制→環(huán)氧膠泥膠粘耐酸磚→表面缺陷修補、養(yǎng)護。 、材料選擇膠泥選用環(huán)氧樹脂膠泥,磚板選用工業(yè)防腐專用耐酸瓷磚。其中環(huán)氧樹脂膠泥由環(huán)氧樹脂、丙酮、石英粉、固化劑等組成。、材料配制:()環(huán)氧樹脂打底料、膠泥、配制:環(huán)氧樹脂打底料、膠泥配制時,可以把樹脂、稀釋劑、填料在攪拌機內(nèi)攪拌均勻,然后分到小的施工容器內(nèi),再加入固化劑,攪拌均勻使用。可以根據(jù)施工用量的大小隨時配用,配好的料在
個小時內(nèi)要用完。砂漿的配制要將樹脂、稀釋劑、填料、固化劑按比例一次加夠,攪拌均勻后使用,不間斷配制,每次均應(yīng)清理攪拌機械。配制前應(yīng)采用適當?shù)娜萜鲗⒏鞣N原料稱量好,一次加入,攪拌好而未使用的粘結(jié)料,不得加入任何物料,并需在初凝前用完。具體配制比例如下:()環(huán)氧樹脂膠泥施工配比:固化劑增塑劑填 料
名稱環(huán)氧樹脂
T
丙
酮石英粉或瓷粉
膠泥配比質(zhì)量比()冬季施工應(yīng)適當加大固化劑的用量,以加快硬化速度。、基層處理要求及處理辦法:
基層處理要求施工表面必須平整,無凹凸不平和蜂窩麻面,不允許裂縫存在。水泥砂漿、混凝土基層經(jīng)養(yǎng)護后,其基層表面20mm
深度內(nèi)水分含量不得超過
%,這時的基層外觀表現(xiàn)為:
表面均勻泛白,用手心按摸之無陰濕感覺,這樣的基層才能與防腐層緊密結(jié)合,若水分含量大時,需繼續(xù)進行干燥養(yǎng)護,或用蒸汽間接加熱干燥。
基層處理辦法混凝土基層如有凹凸不平或局部蜂窩麻面,可用:
水泥砂漿修平整,新補砂漿仍需充分硬化,干燥后再進行防腐層施工。在防腐層施工前,要用鋼絲刷清除基層表面的浮灰塵土,使表面粗粗平整,以增強基層與防腐層間的物理粘結(jié)力。然后,用軟毛刷或吸塵器等認真除去殘屑粉塵,不宜用潮濕拖把擦洗或吸塵。水泥砂漿、混凝土基層上若有油污,需局部用蘸有丙酮或乙醇的紗布團擦洗干凈。、施工方法:
底料刷涂在基層表面,應(yīng)均勻地刷涂打底料,不得有漏刷流掛等缺陷,自身養(yǎng)護不少于
小時,待第一次打底料初凝后將基層表面凹陷不表處用環(huán)氧膩子填平,隨即進行第二次打底料,二次打底的用料,要求及養(yǎng)護與每一次打底相同,二者的養(yǎng)護時間不少于
小時。、耐酸磚板鋪砌施工:
耐酸磚板施工時,應(yīng)刷涂一道環(huán)氧樹脂打底料,固化以后進行磚板鋪砌。
磚、板鋪砌前,應(yīng)事先清洗干凈,經(jīng)充分干燥,并防止塵土、油污沾染。鋪砌時,板的底面及其三邊要刮上環(huán)氧樹脂膠泥(擋磚的一邊不刮),隨刮隨鋪。
采用揉擠法施工:先將配制好的樹脂膠泥,按二分之一結(jié)合層厚度(結(jié)合層厚度
-6mm)鋪在環(huán)氧樹脂打底的基層上,隨即將刮有樹脂膠泥的板、磚,用力揉擠鋪上,并將磚板縫上擠出的多余膠泥用漆刀鏟除干凈,再用油漆刷蘸上少許丙酮洗除殘留漬斑。
平面鋪砌塊材、板材時,每鋪一塊,在待鋪的另一行用塊材擋住,以防滑動;立面鋪砌時,應(yīng)防止砌體受壓變形,每連續(xù)砌筑二層高度后應(yīng)稍停(約
分鐘),待樹脂膠泥初凝結(jié)牢后,再繼續(xù)往上砌筑,使鋪砌高度與膠泥的硬化時間相適應(yīng)。、成品保護:施工完畢的防腐項目,要進行合理保護,不得踩踏、雨淋、曝曬、污染,防腐蝕層未按規(guī)范要求養(yǎng)護合格,嚴禁投入使用。、耐酸磚塊材在施工中應(yīng)注意的事項:、氣候條件:
空氣相對濕度要求不大于,基面溫度要高于露點溫度
℃。對于空氣溫度和相對濕度的測量,要在現(xiàn)場進行。、在水泥砂漿、混凝土基層上用樹脂膠泥鋪塊材時,基層的表面應(yīng)均勻涂刷封底料。待固化后再進行塊材鋪砌。塊材結(jié)合層厚度,灰縫寬度和灌縫或勾縫的尺寸,均應(yīng)符合下表規(guī)定:結(jié)合層厚度、灰縫寬度和灌縫或勾縫的尺寸
0mm
塊材的鋪砌,除應(yīng)符合以上規(guī)范的要求外,尚應(yīng)符合下列規(guī)定:①
耐酸磚厚度不大于30mm
的石材的鋪砌,宜采用樹脂膠泥揉擠法施工;平面上鋪砌厚度大于30mm的石材,宜采用樹脂砂漿鋪砌、樹脂膠泥灌縫施工。②
結(jié)合層和灰縫的膠泥或砂漿應(yīng)飽滿密實,塊材應(yīng)防止滑移。③
當鋪砌塊材時,應(yīng)在膠泥或砂漿初凝前,將縫填滿壓實,灰縫的表面應(yīng)平整光滑。樹脂膠泥的灌縫與勾縫,應(yīng)在鋪砌砂漿塊材用的膠泥,砂漿固化后進行。勾縫前,灰縫應(yīng)清潔、干燥。勾縫時,宜分次進行,縫應(yīng)填滿密實,表面應(yīng)平整光滑。、質(zhì)量保證組織措施:
建立完善的項目質(zhì)量管理體系,各專業(yè)責任人員,按照質(zhì)量保證體系程序文件的要求,搞好材料的到貨檢驗、施工技術(shù)保證、質(zhì)量檢查、設(shè)備保障等日常工作,確保質(zhì)量體系的正常運行。
質(zhì)量保證體系人員按照公司質(zhì)量手冊開展日常工作,嚴格執(zhí)行本項目的質(zhì)量計劃。
實施質(zhì)量責任制由技術(shù)負責人、質(zhì)檢員、各班組長,對分項工程進一步細化、量化,各班組應(yīng)明確所干工序的質(zhì)量檢驗標準和評分標準,并由質(zhì)量檢查人員作現(xiàn)場記錄,并于當日將記錄結(jié)果匯總給項目經(jīng)理,交當日的生產(chǎn)會議評定,評定結(jié)果記錄在案。
落實、兌現(xiàn)質(zhì)量責任制:項目經(jīng)理定期召開由項目經(jīng)理、質(zhì)檢員、各班組長參加的質(zhì)量分析評比會議,對各班組所干工序的質(zhì)量檢查評定記錄進行綜合評定,評定結(jié)果直接和主要負責人的工資、獎金掛鉤,并作為年終評定的主要項目。
現(xiàn)場監(jiān)督指導和短期培訓相結(jié)合增強全員的質(zhì)量意識,質(zhì)量檢查員負責各施工班組的質(zhì)量意識教育和短期技術(shù)培訓,并配合業(yè)主,監(jiān)理和有關(guān)部門質(zhì)量檢查人員監(jiān)督檢查各班組按照施工規(guī)范和設(shè)計要求施工,做到一級抓一級,一級管一級,層層承包,分級負責。
自檢互檢和綜合檢查相結(jié)合現(xiàn)場施工各班組嚴格按照規(guī)范施工,作好自檢。各班組長配合質(zhì)檢員交叉檢查,質(zhì)檢員、各班組長聯(lián)合檢查,發(fā)現(xiàn)問題,追查責任,及時改進。、質(zhì)量保證技術(shù)標準:
基層含水率基層含水率不應(yīng)大于%,當基層處理面積在
平方米以下時,應(yīng)抽查三處,當在
平方米以上時,每增加
平方米抽查一處,不足平方米,按
平方米計。檢查辦法為砼表面空粘塑料布以沒有塑料布表面沒有水滴出現(xiàn)為合格。2.2
耐酸磚板面層:結(jié)合層和灰縫內(nèi)的樹脂膠泥應(yīng)飽滿密實,固化完全,粘接牢固,磚板和基層間無脫層。檢驗方法為:觀察和敲擊法。同時磚板的結(jié)合層和灰縫寬度應(yīng)符合下列標準:結(jié)合層厚度: 灰縫寬度:檢查方法是用尺測量。:耐酸磚錯縫及表面平整度:同層中縱縫(或橫縫)應(yīng)錯開板寬的,最小不得少于
;相鄰兩板高差不得大于
。、施工現(xiàn)場質(zhì)量管理體系:
經(jīng)部E部
管、安全保證組織措施:
確定以項目經(jīng)理為第一安全生產(chǎn)責任人,制定健全的安全生產(chǎn)責任制。并認真落實執(zhí)行,做到人人講安全,人人管安全,人人有責任。制定有效的安全教育培訓制度、安全檢查制度,并嚴格落實執(zhí)行,做好安全生產(chǎn)宣傳工作。
開工前必須對施工班組進行安全技術(shù)交底,并對全體施工人員進行健康、安全、環(huán)境教育。
堅持“安全第一,預防為主”的安全生產(chǎn)方針,始終把安全生產(chǎn)工作放在首要位置,納入項目部各級領(lǐng)導的議事日程,正確處理安全生產(chǎn)與效益、安全與進度、安全與質(zhì)量、安全與生產(chǎn)的辯證關(guān)系。
堅持教育為先導,認真抓好三級安全教育工作,提高職工的安全技術(shù)素質(zhì)和防范事故的能力,并經(jīng)考試合格后才能上崗,特殊工種必須取得相應(yīng)的安全操作證。
施工班組要在每天的班前生產(chǎn)會上,指出當天工作在安全上注意的事項,班組長的安全講話要有紀錄。
針對各施工環(huán)境制定相應(yīng)的安全技術(shù)措施和應(yīng)急措施。
按照國家規(guī)定,特殊作業(yè)人員必須經(jīng)培訓、考試,取得合格證才能上崗。
消防結(jié)合”的方針,建立、健全組織領(lǐng)導機構(gòu),落實消防安全責任制,保障消防通道、疏散通道、安全出口的暢通,配置足夠的消防設(shè)施和器材,設(shè)置消防安全標志,并定期檢查、維修,確保消防設(shè)施和器材的完好、有效。定期組織施工人員進行消防學習、培訓。
堅持安全事故上報、考核、和獎懲制度。對有章不循,違章作業(yè),玩忽職守,違反勞動紀律等給予扣款或行政處分,對在安全生產(chǎn)中表現(xiàn)突出的班組和個人給予表揚或獎勵。、安全保證技術(shù)措施:
做好現(xiàn)場的安全用電工作,施工現(xiàn)場臨時用電不許亂拉扯,使用
電源時,一定要接好地線,啟用前由電工進行檢查,防止觸電。
易燃、易爆和有毒材料不得堆放在施工現(xiàn)場,應(yīng)存放在專用庫房內(nèi),并設(shè)專人管理,
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 廈門土地租賃合同范例
- 中介合同合同范例范例
- 出售山頂平房合同范例
- 叉車司機聘用合同范例
- 廠房焊接施工合同范例
- 個人返利合同范本
- 華南租房合同范例
- 兄弟房產(chǎn)過戶協(xié)議合同范例
- 農(nóng)村房屋屋頂換新合同范例
- oem合作合同范例
- 市場營銷考試試題及答案(考試大全必備)
- 三年級下冊口算天天100題(A4打印版)
- 2021年大唐集團招聘筆試試題及答案
- DBJ53/T-39-2020 云南省民用建筑節(jié)能設(shè)計標準
- 2023年山東春季高考數(shù)學試題
- 初中 初一 勞動教育《舉辦一次家庭聚會》教學設(shè)計
- 人教版六年級上冊數(shù)學第六單元測試卷(百分數(shù)(一))
- 《基礎(chǔ)英語》課件 Unit 1 Thinking as a Hobby
- 雅思大作文資料_十大類題材_解析詳細_應(yīng)有盡有(最好全部打印后看_非常全)
- 小學綜合實踐食品添加劑
- 電氣消防設(shè)計說明專篇