




版權(quán)說(shuō)明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請(qǐng)進(jìn)行舉報(bào)或認(rèn)領(lǐng)
文檔簡(jiǎn)介
FdrationInternationaledesIngnieurs-conseilsInternationalFederationofconsultingEngineersInternationalevereinigungBeratenderIngenieureFederacinInternacionaldeIngenierosconsultores
Amendmentstothe
ConditionsofContractfor
UndergroundWorks
FIRST
EDITION2019
ISBN
978-2-88432-087-0
AmendmentsIssueNo1.–November2023
LISTOFAMENDMENTS
ThefollowingamendmentsaremadetotheFIDICConditionsofContractforUndergroundWorks,FirstEdition,2019,[ISBN978-2-88432-084-9](theEmeraldBook).
PagenumbersandlinesgivenbelowarereferencestopagenumbersandlinesastheyappearintheFIDICEmeraldBook,FirstEdition,2019.
Inaddition,severalminortypographicalerrorsandlayoutirregularitiesthathavealsobeencorrectedinthe2019publicationarenotlistedbelow.
AsaresultoftheamendmentmadetoSub-Clause1.1.21assetoutbelow,Sub-Clause1.1.21ofthe2019FirstEditionoftheEmeraldBookbecameSub-Clause1.1.56,and,therefore,Sub-Clausesnumber1.1.22to1.1.56hadtoberenumberedas1.1.21to1.1.55accordingly.Readersshouldnotethatthetextoftheamendment(s)madetotheserenumberedSub-ClausesdidnotmentionthenewnumbersintentionallyandthattheamendedtextoftheseSub-Clausesshouldbereadinconjunctionwiththerespectivenewnumber.
IssueNo.1–November2023.MinortypographicerrorswerercorrectedinMay2024
Coverpage:
Inthetextunderthemaintitle,replace“DisputeAvoidance/AdjudicationAgreement”with“DAABAgreement”.
Titlepage1:
Ontheright-handside,replace“DisputeAdjudication/AvoidanceAgreement”with“DAABAgreement”.
Delete1.1.58“LetterofAcceptance”–{unchanged}
12thunnumberedpage
add1.1.29DateofCompletion
13thunnumberedpage
Correctmistakeintitleof13.8“andContractPrice”Correctformatting20.2.4“FullydetailedClaim”
14thunnumberedpage
TypicalSequenceofPrincipalEventsDuringContractsforUndergroundWorks
Revisedwordingofpoint1&spellingof“adjustment”
1.TheTimeforCompletionistobestated(intheContractData)asanumberofdays,towhichisaddedanyExtensionofTimeunderSub-Clause8.5,andsubtractedoradded,asthecasemaybe,any
adjustmentofTimeforCompletionunderSub-Clause13.8.CorrectSCreference1.1.29“DateofCompletion”
GENERALCONDITIONS
Pageii
4.10
Addcommaafter“SiteData”-“UseofSiteData,oftheGeotechnicalBaselineReportandoftheGeotechnicalDataReport”.
Page1
Sub-Clause1.1.6:
Onthefirstlineafter“totheotherParty”,add“(excludingamattertobeagreedordeterminedundersub-paragraph(a)ofSub-Clause3.7[AgreementorDetermination])”.
Page1
Sub-Clause1.1.10:
Onthesecondlinereplace“asamendedby”with“and”.
Page2
Sub-Clause1.1.21:
Replace“Contractor’sKeyPersonnel”with“KeyPersonnel”.Sub-Clause1.1.21shallthereforebecomeSub-Clause1.1.56,andSub-Clausesnumber1.1.22to1.1.56shallberenumbered1.1.21to1.1.55accordingly.
Page3
Sub-Clause1.1.29:
Onthefifth/sixthlinereplace“DisputeAvoidance/AdjudicationAgreement”with“DAABAgreement”.
Page3
Sub-Clause1.1.30:
Onthesecondline,after“theEngineer”,add“underSub-Clause10.1[TakingOvertheWorksandSections]orthefirstparagraphofSub-Clause10.2[TakingOverParts]”.
?FIDIC2019–2023
2
Onthefourthandfifthlines,replace“ifSub-Clause10.2[TakingOverParts]”with“ifthesecondparagraphofSub-Clause10.2[TakingOverParts]”.
Page3Sub-Clause1.1.35:Replacethetextofthisdefinitionwith:
““Dispute”meansanysituationwhere:
“(a)onePartyhasmadeaClaim,ortherehasbeenamattertobeagreedordeterminedundersub-paragraph(a)ofSub-Clause3.7[AgreementorDetermination];
(b)theEngineer’sdeterminationunderSub-Clause3.7.2[Engineer’sDetermination]wasarejection(inwholeorinpart)of:
(i)theClaim(ortherewasadeemedrejectionundersub-paragraph
(i)ofSub-Clause3.7.3[Timelimits]);or
(ii)aParty’sassertion(s)inrespectofthematterasthecasemaybe;and
(c)eitherPartyhasgivenaNODunderSub-Clause3.7.5[DissatisfactionwithEngineer’sdetermination].”.
Page4Sub-Clause1.1.44:Onthefirstlineofthefirstparagraphadd“exceptional”before“eventor
circumstance”.
Page5Sub-Clause1.1.50:Replacethetextofthisdefinitionwith:
““GeneralConditions”meansthisdocumententitled“GeneralConditions”,aspublishedbyFIDIC.”
Page6Sub-Clause1.1.69:Replacealltextafter“whichis”onthesecondlinebythefollowing:“taken
overbytheEmployerunderthefirstparagraph,orusedbytheEmployeranddeemedtohavebeentakenoverunderthesecondparagraph,ofSub-Clause10.2[Taking-OverParts].”.
Page8Sub-Clause1.1.97:Onthesecond/thirdlinesreplace“inaccordancewiththeSpecial
Provisions”with“underClause12[TestsafterCompletion]”.
Page9Sub-Clause1.2:Deleteitems(k)and(l)
Page10Sub-Clause1.3:Onthefifthlineofthefirstparagraph,before“discharge,”,add
“disagreement,”.
Page11Sub-Clause1.5:Onthesecondlineofthefirstparagraph,after“Ifthereisanyconflict,
ambiguityordiscrepancy”andbeforethecomma,add:“inthedocuments”.
Onthefirstlineofthelastparagraph,replace“anambiguity”with“aconflict,ambiguity”.
Onthesecondlineofthelastparagraph,replace“theambiguity”with“theconflict,ambiguity”.
Onthethirdlineofthelastparagraph,replace“anambiguity”with“aconflict,ambiguity”.
Page12Sub-Clause1.9:Correctfontand/orboldformattingoftitle.
Inthethirdparagraph,add:
“and/orintheGeotechnicalBaselineReport”after“Employer’sRequirements”insub-paragraph(a)
andamendfirstbulletpointtoread:
?whenexaminingtheSite,theEmployer’sRequirementsand/ortheGeotechnicalBaselineReportbeforesubmittingtheTender;or
?FIDIC2019–20233
Replacethe5thparagraphwith:
“Ifitisagreedordetermined,undersub-paragraphs(a)and(b)above,thatthereisanerror,faultordefectthatanexperiencedcontractorwouldnothavediscovered:
Onthefirstlineofsub-paragraph(ii),replace“iftheContractor”with“iftherearenosuchmeasures,andthereforenoVariation,buttheContractor”.
Page15Sub-Clause1.15:Inthesecondparagraphattheendofthefirstsentenceadd“under”
after“otherthan”anddelete“under”insub-paragraphs(i)to(iv).
Page19Sub-Clause3.1:Insub-paragraph(b)delete“shallbe”.
Page20Sub-Clause3.2.2:Fourthparagraph–deletethecompletesecondsentence“Inperforming
thistask,theEngineershall......underSub-Clause3.7.3”
Page21Sub-Clause3.4:Onthesecond-lastlineofthelastparagraph,after“receivingthe
Contractor’sNotice,”add“bygivingaNotice”.
Page22Sub-Clause3.6:Onthesecondlineofthelastparagraphreplace“anentity”with“alegal
entity”.
Page22Sub-Clause3.7:Replacethesecondparagraphwith:
“WhenevertheseConditionsprovidethattheEngineershallproceedunderthisSub-Clause3.7toagreeordetermineeither:
(a)anymatter,asprovidedforinSub-Clauses1.9,4.7.3,10.2,11.2,13.3.1,13.5,13.8.1,14.4,14.5,14.6.3,15.3,15.6and18.5,identifyinginthesameSub-ClausethedateofcommencementofthecorrespondingtimelimitforagreementunderSub-Clause3.7.3[Timelimits];or
(b)anyClaim,
thefollowingprocedureshallapply:”.
Page23Sub-Clause3.7.3:Onthefirstlineofsub-paragraph(a)replace“(notaClaim)”with“under
sub-paragraph(a)ofSub-Clause3.7[AgreementorDetermination]”.Onthefirstlineofthelastparagraph,delete“agreementor”.
Onthefirstlineofsub-paragraph(ii)ofthelastparagraphafter“mattertobeagreedordetermined”add“undersub-paragraph(a)ofSub-Clause3.7[AgreementorDetermination]”.
Page26Sub-Clause4.2.1:Onthethirdlineofthelastparagraph,after“increaseordecreaseofthe
ContractPrice”,add“inonecurrency”.
Onthethirdlineofthelastparagraph,after“AcceptedContractAmount”,add“inthatcurrency”.
Page28Sub-Clause4.4:Onthesecondlineofthesecond-lastparagraphafter“theContractor
shallsubmit”,add“totheEngineer”.
Onthefourthlineofthesecond-lastparagraph,delete“totheEngineer”.
Page31Sub-Clause4.7.3:Onthefirstandsecondlinesofthelastparagraphreplace“If,under
sub-paragraph(b)above,anexperiencedcontractorwouldnothavediscoveredtheerror:”with:
“Ifitisagreedordetermined,undersub-paragraphs(a)and(b)above,thatthereisanerrorintheitemsofreferencethatanexperiencedcontractorwouldnothavediscovered:”.
?FIDIC2019–20234
Onthefirstlineofsub-paragraph(ii),replace“iftheContractor”with“iftherearenosuchmeasures,andthereforenoVariation,buttheContractor”.
Page35
Sub-Clause4.12:
InParagraph3inthefirstlineadd“physical”before“conditions”:
“Howevertheimpactontheprogressand/ortheCostofanyphysicalconditionsthataredescribedin.”
Page42
Sub-Clause5.1:
Inthelastparagraphadd“and/orintheGeotechnicalBaselineReport”after“Employer’sRequirements”inthefifthlineandcorrectthereferencetoSub-Clause1.9[ErrorsintheEmployer’sRequirementsand/orintheGeotechnicalBaselineReport].
Page54
Sub-Clause8.2.1:
Correctreferencefrom“BaselineSchedule”to“ScheduleofBaselines”.
Page54
Sub-Clause8.3:
Onthefirstandsecondlinesofthelastparagraph,replace“theProgramme”with“anyprogramme”.
Page56
Sub-Clause8.5:
Replacethethird-lastparagraphwith“WhenagreeingordeterminingeachEOT,theEngineershallreviewpreviousagreementsanddeterminationsofEOTunderSub-Clause3.7[AgreementorDetermination]andmayincrease,butshallnotdecrease,thetotalEOT.”.
Page61
Sub-Clause9.4:
Onthefirstlineofsub-paragraph(a),replace“order”with“instruct”.
Page62
Sub-Clause10.1:
Onthethirdlineofsub-paragraph(b),after“sub-paragraph(a)”,add“orsub-paragraph(b)(i)(asthecasemaybe)”.
Onthesecondlineofsub-paragraph(c),replace“provisional”with“final”.
Onthefirstlineofthethirdparagraph,replace“PartoftheWorksistakenover”with“Partistakenoverorisdeemedtohavebeentakenover”.
Page63
Sub-Clause10.2:
Onthefirstlineofthethirdparagraph,replace“theEngineerhasissuedaTaking-OverCertificateforaPart”with“aParthasbeentakenoverorisdeemedtohavebeentakenover”.
Onthefirstandsecondlinesofthefourthparagraph,replace“theEmployertakingoverand/orusingaPart”with“thetakingoverordeemedtakingoverofaPart”.
Inthelastparagraph:
-replacethefirstsentencewiththefollowing:“ForanyperiodofdelayafterthedatethataParthasbeentakenoverorisdeemedtohavebeentakenover,theDelayDamagesforcompletionoftheWorksortheSection(asthecasemaybe)inwhichthisPartisincludedshallbereduced.”;
-deletethesecondsentence:“Similarly,theDelayDamagesfortheremainderoftheSection(ifany)inwhichthisPartisincludedshallalsobereduced.”;
-replacethefourthsentencewiththefollowing:“TheEngineershallproceedunderSub-Clause3.7[AgreementorDetermination]toagreeordeterminethisreduction(and,forthepurposeofSub-Clause
3.7.3[Timelimits],thedatetheEngineerissuestheTaking-OverCertificateunderthefirstparagraphof,orreceivestheContractor’sNoticeunderthesecondparagraphof,thisSub-Clause(asthecasemaybe)shallbethedateofcommencementofthetimelimitforagreementunderSub-Clause3.7.3).”.
Page64
Sub-Clause10.4:
Onthesecondline,replace“PartoftheWorks”with“Part”.
?FIDIC2019–20235
Page65Sub-Clause11.3:Onthefourthlineofsub-paragraph(a),replace“matters”with“causes”.
Page72Sub-Clause13.2:Onthefirstlineofsub-paragraph(ii),replace“thirdparagraph”with
“fourthparagraph”.
Page78Sub-Clause13.8.1:Firstparagraphreplace“forthemeasurement”with“formeasurement”.
Deletethethirdparagraphandreplacewiththefollowing:
“TheEngineershall,within7daysafterreceivingthemeasurementrecordsfromtheContractor,giveaNoticetotheContractor:
(i)ofNo-objection(whichmayincludecommentsconcerningminormatterswhichwillnotsubstantiallyaffectthemeasurement);or
(ii)thatthemeasurementrecordsfail(totheextentstated)tocomplywiththeContract,withreasons.
IftheEngineergivesnoNoticewithinthisperiodof7days,theEngineershallbedeemedtohavegivenaNoticeofNo-objectiontothemeasurementrecords.
If,afterreceivinganEngineer’sNoticeunderthisSub-Clause,theContractordisagreeswiththeEngineer’samendments,theContractorshallgiveaNoticewithin14daystotheEngineersettingoutthereasonswhytheContractorconsiderstheamendedmeasurementsareinaccurate.AfterreceivingaContractor’sNoticeunderthisSub-Clause,unlessatthattimesuchmeasurementisalreadysubjecttothethirdparagraphofSub-Clause13.3.1[VariationbyInstruction],theEngineershall:
?proceedunderSub-Clause3.7[AgreementorDetermination]toagreeordeterminethemeasurement;and
?forthepurposeofSub-Clause3.7.3[Timelimit],thedatetheEngineerreceivestheContractor’sNoticeshallbethedateofcommencementofthetimelimitforagreementunderSub-Clause3.7.3).
Untilsuchtimeasthemeasurementisagreedordetermined,theEngineershallassessaprovisionalmeasurementforthepurposesofInterimPaymentCertificates.”
Page81Sub-Clause14.3:Initem(i)changethereferenceinthelastlinefrom(x)to(xi).
Page83Sub-Clause14.5:Onthefirstlineofthesecondparagraph,replace‘sub-paragraph(v)’
with“sub-paragraph(vi)”.
Page86Sub-Clause14.9:Insub-paragraph(b),delete“for”.
Onthefirstlineofthethirdparagraph,after“IPC”,add“,ortheFPC(asthecasemaybe),”.
Page89Sub-Clause14.13:Replacethelastparagraphwith“IftheContractorhasnotsubmitteda
dischargeunderSub-Clause14.12[Discharge]buthaseither:
(i)submittedaPartiallyAgreedFinalStatementunderSub-Clause14.11.2[AgreedFinalStatement];or
(ii)notdonesobut,totheextentthatadraftfinalStatementsubmittedbytheContractorisdeemedbytheEngineertobeaPartiallyAgreedFinalStatement,
theEngineershallproceedinaccordancewithSub-Clause14.6[IssueofIPC]toissueanIPC.”.
Page92Sub-Clause15.2.3:Onthesecondlineofsub-paragraph(a),replace“thisSub-Clause”with
“Sub-Clause15.2.2[Termination]”.
?FIDIC2019–20236
Page95Sub-Clause16.1:Thesentence“andsuchfailureconstitutesamaterialbreachofthe
Employer’sobligationsundertheContract”followingsub-paragraph(d)shouldnotbeindentedsoastobeclearthatitispartofsub-paragraph(d).
“(d)theEmployerfailstocomplywith:
(i)abindingagreement,orfinalandbindingdeterminationunderSub-Clause3.7[AgreementorDetermination];or
(ii)adecisionoftheDAABunder21.4[ObtainingDAAB’s
Decision](whetherbindingorfinalandbinding)
andsuchfailureconstitutesamaterialbreachoftheEmployer’sobligationsundertheContract,
theContractormay,notlessthan21daysafter...”
Page97Sub-Clause17.1:Onthefourthlineofthefirstparagraph,after“theissue”add“(ordeemed
issue)”.
Page98Sub-Clause17.2:Replacethetextofsub-paragraph(e)initsentiretywith“anyExceptional
Event;and/or”.
Insub-paragraph(f),after“anyactordefaultof”add“theEmployer,”.Inthesecond-lastparagraph:
-onthefirstline,replace“SubjecttoSub-Clause18.4[ConsequencesofanExceptionalEvent],if”with“If”.
-onthethirdline,replace“damage”with“l(fā)ossand/ordamage”.
-onthelastlineafter“[VariationbyInstruction]”,add:“and,inthecaseofsub-paragraph(e)above,shallbewithoutprejudicetoanyotherrightstheContractormayhaveunderSub-Clause18.4[ConsequencesofanExceptionalEvent]”.
Inthelastparagraph:
-onthefirstline,replace“l(fā)ossordamage”with“l(fā)ossand/ordamage”.
-onthelastline,replace“delays”with“delay”.Page100Sub-Clause18.1:Onthefirstlinebefore“event”add“exceptional”.
Page106Sub-Clause20.1:Onthefourthlineofsub-paragraph(c),delete“determination”.
Onthefourthlineofthelastparagraphreplace“butthe”with“exceptifanyofsub-paragraphs(a)to(c)ofSub-Clause21.4[ObtainingDAAB’sDecision]applies.The”.
Page107Sub-Clause20.2.2:Onthefourthlineofthelastparagraphreplace“[Fullydetailedclaim]”
with“[FullydetailedClaim]”.
Page108Sub-Clause20.2.4:Replacetheentiretextofthesecondparagraphwiththefollowing:“The
CostsclaimedunderthisSub-Clause20.2.4andrelatingtoExcavationandLiningWorksshallbecalculatedbyreferencetotheitemsofworkandcorrespondingunitratesintheBillofQuantities,totheextentthatsuchitemsofworkarecomparabletothoseatissueintheClaim;theitemsofworkshallbemeasuredasstatedunderSub-Clause13.8.1[ResponsibilityforMeasurement]”.
Onthefourthlineofthesecond-lastparagraphreplace“fullydetailedclaimshallinclude”with“fullydetailedClaimshallbesupplementedwith”.
Page109Sub-Clause20.2.5:Onthesixthlineofthesecondparagraphreplace“fullydetailedclaim”
with“fullydetailedClaim”.
?FIDIC2019–20237
Page112Sub-Clause21.2:Attheendofsub-paragraph(d)after“todoso,”add:
“,orbecausethetermsoftheDAABAgreement(includingtheamountofthemonthlyfeeorthedailyfee)cannotbeagreedwiththememberorreplacementwithin14daysafterhe/shehasbeenadvisedbythePartiesthattheyhaveagreedtohis/herappointment,”.
Inthefirstparagraphdeletethetextthatfollowssub-paragraph(d)andreplacewiththefollowing:
“then,unlessotherwiseagreedbytheParties,eitherorbothPartiesmayapplytothePresidentofFIDICorapersonappointedbythePresident,whoshallbetheappointingofficialundertheContract.Theappointingofficialshall,afterdueconsultationwithbothPartiesandafterconsultingtheprospectivemember(s)orreplacement:
-appointthemember(s)oftheDAABorthereplacement;and
-setthetermsoftheappointment,includingtheamountsofthemonthlyfeeandthedailyfeeforeachmemberorreplacement.
Selectionofthemember(s)orreplacementtobesoappointedshallnotbelimitedtothosepersonsnamedinthelistintheContractDataor,inthecaseofsub-paragraph(d)above,tothemember(s)orreplacementagreedbytheParties.Thisappointmentanditstermsshallbefinalandconclusive.”.
Onthesecondlineofthelastparagraph,delete“entityor”.
Page113Sub-Clause21.4:Onthethirdandfourthlinesreplace“andthefollowingprovisionsshall
apply”withafullstop“.”,andaddthefollowingtextasnewparagraphs:
“InadditiontothesituationdescribedinthedefinitionofDisputeunderSub-Clause1.1.34above,aDisputeshallbedeemedtohavearisenif:
(a)thereisafailureasreferredtoundersub-paragraph(b),oranon-paymentasreferredtoundersub-paragraph(c),ofSub-Clause
16.2.1[Notice];
(b)theContractorisentitledtoreceivefinancingchargesunderSub-Clause14.8[DelayedPayment]butdoesnotreceivepaymentthereoffromtheEmployerwithin28daysafterhisrequestforsuchpayment;or
(c)aPartyhasgiven:
(i)aNoticeofintentiontoterminatetheContractunderSub-Clause
15.2.1[Notice]orSub-Clause16.2.1[Notice](asthecasemaybe);or
(ii)aNoticeofterminationunderSub-Clause15.2.2[Termination],Sub-Clause16.2.2[Termination],Sub-Clause18.5[OptionalTermination]orSub-Clause18.6[ReleasefromPerformanceundertheLaw](asthecasemaybe);
andtheotherPartyhasdisagreedwiththefirstParty’sentitlementtogivesuchNotice;
whichDisputemaybereferredbyeitherPartyunderthisSub-Clause21.4withouttheneedforaNOD(andSub-Clause3.7[AgreementorDetermination]andsub-paragraph(a)ofSub-Clause21.4.1[ReferenceofaDisputetotheDAAB]shallnotapply).
WhereaDisputeistobereferredtotheDAABforitsdecision,thefollowingprovisionsshallapply.”.
?FIDIC2019–20238
Page113Sub-Clause21.4.1:Insub-paragraph(a)replace“ifSub-Clause3.7[Agreementor
Determination]appliedtothesubjectmatteroftheDispute”with“subjecttosub-paragraph(ii)ofSub-Clause3.7.3[Timelimits]andtheprovisionsofthesecondparagraphofSub-Clause21.4[ObtainingDAAB’sDecision]”.
APPENDIX–GENERALCONDITIONSOFDAABAGREEMENT
Page117Sub-Clause1.1:Replace“GeneralConditionsofDisputeAvoidance/Adjudication
Agreement”,inthetwoinstances,with“GeneralConditionsofDAABAgreement”.
Page118Sub-Clause4.1:Replacesub-paragraph(c)withthefollowing:
“(c)inthe5yearsbeforesigningtheDAABAgreement,nothavebeenemployedasaconsultantorotherwisebytheEmployer,theContractor,theEmployer’sPersonnelortheContractor’sPersonnel,exceptinsuchcircumstancesasweredisclosedinwritingtotheEmployerandtheContractorbeforetheysignedtheDAABAgreement(oraredeemedtohavedoneso);”.
Page121Sub-Clause9.1:Replacesub-paragraphs(b)(iv)and(b)(v)intheirentiretywiththefollowing:
“(iv)spentonpreparingandattendinghearings(and,incaseofathree-memberDAAB,attendingmeeting(s)betweentheDAABMembersinaccordancewithsub-paragraph(a)ofRule8.2oftheDAABRules,andcommunicatingwiththeOtherMembers);and
(v)spentonpreparingdecisions,includingstudyingwrittendocumentationandargumentsfromtheParties.”.
Insub-paragraph(c),replace“telephonecalls(andvideoconferencecalls,ifany,andinternetaccess)”with“internetaccess”.
Page122Sub-Clause9.2:Onthesecond-lastandlastlines,delete“(or,undertheContract,deemed
tohavebeensigned)”.
Page122Sub-Clause9.3:ReplacethetextofthisSub-Clauseinitsentiretywith:
“IftheDAABMemberhasbeenappointedbytheappointingofficial,theamountsoftheDAABMember’smonthlyfeeanddailyfee,underSub-Clause9.1above,shallbeasreferredtoundersub-paragraph(i)ofSub-Clause21.2[FailuretoAppointDAABMember(s)]oftheConditionsofContract.”.
Page123Sub-Clause9.6:Inthefirstparagraphreplacethenumberingofthethirdsub-paragraph
from“b”to“c”.
Page123Sub-Clause9.6(c):CorrectthereferencetoSub-Clause[DelayedPayments]to14.8.
Page123Sub-Clause9.7:Insub-paragraph(b),before“resign”,add“withoutprejudicetohis/her
otherrightsorremedies,”.
Page124Sub-Clause10.2:Onthefourthline,replace“notice”with“Notification”.
Page124Sub-Clause11.1:Onthesecondline,deletethetext:
“,orinthecaseofathree-memberDAABtheOtherMembersjointly,”.Onthefourthline,delete“ObjectionProcedure”.
Onthefourthandfifthlines,delete“ChallengeProcedure”.
Page125Clause12:Delete“2017”,delete“andArticle30”,anddelete“atAppendixVI”.
?FIDIC2019–20239
APPENDIX–DAABPROCEDURALRULES
Page126
Rule2.1:
Onthefourthandfifthlines,replace“bytelephoneorbyvideoconference”with“online”.
Page126
Rule3.2:
Onthesecondlinereplace“aface-to-facemeetingwiththeParties”with:
“anintroductorymeetingwiththeParties.Thedate,timeandtype(onlineorin-person)of,andagendafor,theintroductorymeetingshallbesetbytheDAABinconsultationwiththeParties”.
Page126
Rule3.3:
Onthefirstlinedelete“face-to-face”,andreplace“and/or”with“and”.Onthethirdlinereplace“and/orSite”with“andSite”.
Aftersub-paragraph(c)addanewparagraph:
“Eachsuchmeetingshallbeface-to-faceandeachSitevisitshallbein-person,unlessthe
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 年度服務(wù)合同范本
- epc工程廉政合同范本
- 保溫氈合同范本
- 合租經(jīng)營(yíng)協(xié)議合同范本
- 廠區(qū)維修電車合同范本
- 買房包干合同范例
- 原車主抵押合同范本
- 輪胎店銷售合同范本
- 醫(yī)療場(chǎng)所合作合同范本
- 勞動(dòng)作合同范例備案
- 國(guó)際標(biāo)準(zhǔn)《風(fēng)險(xiǎn)管理指南》(ISO31000)的中文版
- 幼兒園中班語(yǔ)言《猜燈謎》
- 煙花爆竹經(jīng)營(yíng)
- 射頻同軸電纜簡(jiǎn)介
- 2023-2024全球及中國(guó)企業(yè)組織活力報(bào)告(中文版)
- 現(xiàn)代自來(lái)水廠自動(dòng)化控制系統(tǒng)
- 2024年長(zhǎng)沙衛(wèi)生職業(yè)學(xué)院高職單招(英語(yǔ)/數(shù)學(xué)/語(yǔ)文)筆試歷年參考題庫(kù)含答案解析
- QB-T 5823-2023 工坊啤酒機(jī)械 發(fā)酵罐
- 紹興文理學(xué)院開(kāi)題報(bào)告模板
- 2021年古包頭市昆都侖區(qū)水務(wù)公司招聘考試試題及答案
- 體檢中心健康知識(shí)講座
評(píng)論
0/150
提交評(píng)論