項(xiàng)目專項(xiàng)施工方案
發(fā)展大廈工程
幕墻工程安全專項(xiàng)施工方案
編制單位:天石集團(tuán)有限公司
日期:
項(xiàng)目專項(xiàng)施工方案
目錄
第一章編制依據(jù)..........................................................................................................................................-1-
第二章工程概況..........................................................................................................................................-2-
2.1工程建設(shè)概況表................................................................................................................................................-2-
2.2幕墻設(shè)計(jì)概況....................................................................................................................................................-2-
2.3工程施工條件....................................................................................................................................................-4-
第三章施工安排..........................................................................................................................................-5-
3.1項(xiàng)目管理組織....................................................................................................................................................-5-
3.2項(xiàng)目管理目標(biāo)....................................................................................................................................................-5-
3.3各項(xiàng)資源供應(yīng)方式......................................................................................................................................-5-
3.3.1勞務(wù)資源安排一覽表...............................................................................................................................-5-
3.3.2機(jī)械設(shè)備采購供應(yīng)安排一覽表...............................................................................................................-5-
3.4施工流水段的劃分及施工工藝流程................................................................................................................-6-
3.4.1施工流水段的劃分...................................................................................................................................-6-
3.4.2施工工藝流程...........................................................................................................................................-7-
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對措施............................................................................................................-7-
第四章施工進(jìn)度計(jì)劃...................................................................................................................................-8-
第五章施工準(zhǔn)備與資源配置計(jì)劃..............................................................................................................-10-
5.1施工準(zhǔn)備計(jì)劃..................................................................................................................................................-10-
5.1.1技術(shù)準(zhǔn)備.................................................................................................................................................-10-
5.1.2現(xiàn)場準(zhǔn)備.................................................................................................................................................-10-
5.2資源配置計(jì)劃..................................................................................................................................................-11-
5.2.1施工機(jī)具配置計(jì)劃...................................................................................................................................-11-
5.2.2測量計(jì)量儀器配置計(jì)劃...........................................................................................................................-11-
5.2.3勞動力配置計(jì)劃.....................................................................................................................................-11-
5.2.4材料的運(yùn)輸方式.......................................................................................................................................-12-
第六章吊籃施工方法及工藝要求..............................................................................................................-13-
6.1吊籃選用方案....................................................................................................................................................-13-
項(xiàng)目專項(xiàng)施工方案
吊籃選用說明.....................................................................................................................................................-13-
6.1.2吊籃具體設(shè)置...........................................................................................................................................-13-
6.2施工工藝流程...................................................................................................................................................-14-
吊籃安裝工藝流程圖:.....................................................................................................................................-14-
吊籃安裝步驟.....................................................................................................................................................-14-
6.3施工要點(diǎn)...........................................................................................................................................................-17-
工作平臺安裝要點(diǎn)及注意事項(xiàng):.....................................................................................................................-17-
安全鎖、提升機(jī)及電器箱的裝安裝要點(diǎn)及注意事項(xiàng):.................................................................................-18-
穿鋼絲繩、重錘安裝要點(diǎn)及注意事項(xiàng):.........................................................................................................-19-
第七章臨時用電方案.................................................................................................................................-20-
7.1臨時用電設(shè)置原則............................................................................................................................................-20-
7.2配電線路形式選擇:........................................................................................................................................-20-
7.3配電箱各開關(guān)箱的選用....................................................................................................................................-20-
7.4臨時用電安全措施:.......................................................................................................................................-21-
7.5臨時用電布置圖...............................................................................................................................................-21-
第八章季節(jié)性施工安全措施........................................................................................................................-22-
8.1夏季高溫施工措施...........................................................................................................................................-22-
8.2雨季施工措施..................................................................................................................................................-25-
第九章安全管理計(jì)劃.................................................................................................................................-28-
9.1職業(yè)健康安全管理分解目標(biāo)..........................................................................................................................-28-
9.2安全管理組織機(jī)構(gòu)和職責(zé)分工......................................................................................................................-28-
安全管理組織機(jī)構(gòu)圖.........................................................................................................................................-28-
各級崗位安全生產(chǎn)責(zé)任制.................................................................................................................................-29-
9.3職業(yè)健康安全重大危險源..............................................................................................................................-31-
9.4安全生產(chǎn)管理制度..........................................................................................................................................-33-
9.6安全生產(chǎn)保證措施..........................................................................................................................................-34-
9.6.1安全施工的保證措施...............................................................................................................................-34-
9.6.2吊籃安全技術(shù)措施...................................................................................................................................-36-
吊籃日常檢查制度.............................................................................................................................................-37-
第十章環(huán)境管理計(jì)劃.................................................................................................................................-40-
10.1重大環(huán)境因素清單........................................................................................................................................-40-
10.2環(huán)境保護(hù)資源配置計(jì)劃................................................................................................................................-40-
10.3環(huán)境保護(hù)措施................................................................................................................................................-40-
項(xiàng)目專項(xiàng)施工方案
第十一章綠色施工管理計(jì)劃......................................................................................................................-41-
第十二章成品保護(hù)措施.............................................................................................................................-42-
第十三章應(yīng)急預(yù)案.......................................................................................................................................-43-
13.1高處墜落、物體打擊事故應(yīng)急救援預(yù)案......................................................................................................-43-
13.2食物中毒應(yīng)急預(yù)案..........................................................................................................................................-46-
13.3消防安全應(yīng)急預(yù)案..........................................................................................................................................-47-
13.4突遇暴風(fēng)雨施工措施......................................................................................................................................-49-
13.5其他突發(fā)情況的應(yīng)急措施..............................................................................................................................-50-
第十四章計(jì)算書和相關(guān)圖紙......................................................................................................................-56-
14.1ZLP630吊籃屋面安裝穩(wěn)定性驗(yàn)算..................................................................................................................-56-
14.21ZLP630吊籃17層樓面受力計(jì)算..................................................................................................................-59-
第十五章相關(guān)資質(zhì)證明文件........................................................................................................................-60-
15.1營業(yè)執(zhí)照.........................................................................................................................................................-60-
15.2安全生產(chǎn)許可證.............................................................................................................................................-61-
15.3資質(zhì)證書.........................................................................................................................................................-62-
15.4稅務(wù)登記證......................................................................................................................................................-64-
15.5吊籃檢測報告.................................................................................................................................................-65-
附件1吊籃平面布置圖.......................................................................................................................................-1-
附件2消防設(shè)施平面布置圖..............................................................................................................................-2-
附件3臨時用電平面布置圖...............................................................................................................................-3-
附件4幕墻用電系統(tǒng)圖.......................................................................................................................................-4-
附件五幕墻工程總進(jìn)度計(jì)劃.............................................................................................................................-5-
項(xiàng)目專項(xiàng)施工方案
第一章編制依據(jù)
序號類別文件名稱編號
1國家和行業(yè)頒布的有關(guān)現(xiàn)行規(guī)范及標(biāo)準(zhǔn)
2國家和行業(yè)頒布的有關(guān)現(xiàn)行規(guī)范及標(biāo)準(zhǔn)建質(zhì)〖2009〗87
關(guān)于印發(fā)《山東省建筑工程安全專項(xiàng)施工方案編制
3
國家行政審查與專家論證辦法》的通知
(中華人民共和國國務(wù)院
4文件建設(shè)工程安全生產(chǎn)管理?xiàng)l例令第393號)
建筑施工企業(yè)安全生產(chǎn)管理機(jī)構(gòu)設(shè)置及專職安全
5(建質(zhì)[2008]91號)
生產(chǎn)管理人員配備辦法
6建筑施工特種作業(yè)人員管理規(guī)定建質(zhì)[2008]75號
7濟(jì)南市建筑施工防火安全管理規(guī)定濟(jì)建質(zhì)安站字[2008]22號
濟(jì)南市建筑工程安全專項(xiàng)施工方案編制審查與專
8地方行政濟(jì)建質(zhì)安站字[2008]23號
文件家論證實(shí)施細(xì)則
關(guān)于印發(fā)《濟(jì)南市建筑施工高處作業(yè)吊籃安全管理
9暫行規(guī)定》的通知濟(jì)建質(zhì)安監(jiān)字[2012]4號
10《建筑幕墻》GB/T21086-2007
11《玻璃幕墻工程技術(shù)規(guī)范》JGJ102-2003
12《金屬與石材幕墻工程技術(shù)規(guī)范》JGJ133-2001
13《鋁合金門窗》GB/T8479-2008
14《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2012(2012年版)
15《建筑設(shè)計(jì)防火規(guī)范》GB50016-2014
16《施工現(xiàn)場臨時用電安全技術(shù)規(guī)范》JGJ46-2005
國家行業(yè)
17《墜落防護(hù)安全繩》GB24543-2009
規(guī)范
18《起重機(jī)鋼絲繩保養(yǎng)、維護(hù)、安裝、檢驗(yàn)和報廢》GB/T5972-2016
19《鋼結(jié)構(gòu)施工規(guī)范》GB50755-2012
20《鋼結(jié)構(gòu)焊接規(guī)范》GB50661-2011
21《高處作業(yè)吊籃》GB19155-2003
22《安全帶》GB6095-2009
23《鋼絲繩》GB/T5976-2006
24《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
25《建筑工程施工現(xiàn)場消防安全技術(shù)規(guī)范》GB50720-2011
26《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ130-2011
27技術(shù)規(guī)程《施工現(xiàn)場機(jī)械設(shè)備檢查技術(shù)規(guī)程》JGJ160-2016
28《建筑結(jié)構(gòu)可靠度設(shè)計(jì)統(tǒng)一標(biāo)準(zhǔn)》GB50068-2001
29《高處作業(yè)吊籃安裝、拆卸、使用技術(shù)規(guī)程》JB/T11699-2013
30合同山東xx發(fā)展大廈幕墻工程
31設(shè)計(jì)文件山東xx發(fā)展大廈幕墻工程施工圖-1-
項(xiàng)目專項(xiàng)施工方案
32其他山東xx發(fā)展大廈幕墻工程施工組織設(shè)計(jì)
第二章工程概況
2.1工程建設(shè)概況表
工程名稱工程性質(zhì)公共建筑(辦公、餐飲、公寓)
建設(shè)規(guī)模
26776.283717萬元工程地址
(造價)
總占地面
22169㎡總建筑面積93622.07㎡
積
建設(shè)單位項(xiàng)目承包范圍結(jié)構(gòu)地下二層、地上十九層
設(shè)計(jì)單位山東建大建筑規(guī)劃設(shè)計(jì)研究院
幕墻、輕鋼雨棚、鋼結(jié)構(gòu)采光頂、裝飾板墻面、室內(nèi)干掛石材、消防、通風(fēng)排
主要分包煙工程、空調(diào)風(fēng)系統(tǒng)、智能化、弱電系統(tǒng)、電源監(jiān)控、電氣火災(zāi)監(jiān)控及能耗監(jiān)
工程測系統(tǒng)、有線電視系統(tǒng)、會議室音視頻系統(tǒng)、空調(diào)節(jié)能系統(tǒng)、電梯工程、太陽
能系統(tǒng)、電力配電系統(tǒng)
勘察單位質(zhì)量確?!疤┥奖睜巹?chuàng)“國家優(yōu)質(zhì)工程獎”
監(jiān)理單位工期712日歷天
確?!吧綎|省建筑施工安全文明示范工
總承包單合同
安全地”責(zé)任事故死亡率為零,無傷亡事故、
位要求
無火災(zāi)事故。
質(zhì)量監(jiān)督綠色爭創(chuàng)“全國建筑業(yè)綠色施工示范工程”
單位施工確?!吧綎|省一星級綠色建筑評價標(biāo)識”
主樓主要作為山東xx置業(yè)有限公司唐冶地塊管理及各類辦公用房,輔樓為檔案
工程主要
用房、餐廳、調(diào)度中心、200人會議室及員工宿舍,裙房為主輔樓次要交通空間、
功能或用
食堂配套用房、餐廳包間、檔案辦公等房間,地下室主要功能為職工食堂、地
途
下停車庫、機(jī)電用房等。
幕墻分包
單位
幕墻工程
主要施工石材幕墻、玻璃幕墻、鋁板幕墻、鋁合金格柵、門窗、雨棚
范圍
2.2幕墻設(shè)計(jì)概況
1)幕墻結(jié)構(gòu)設(shè)計(jì)使用年限:不低于25年
抗震設(shè)防烈度:6度;
建筑耐火等級:地下1級、地上1級;
基本雪壓:0.35(KN/m2),基本風(fēng)壓:0.45(KN/m2)(50年一遇)。
-2-
項(xiàng)目專項(xiàng)施工方案
2)(1)幕墻系統(tǒng)一、干掛石材幕墻
本工程實(shí)體墻及構(gòu)造包柱采用干掛式石材幕墻,均采用背栓,膠縫為8mm;立柱為
90*60*5mm熱鍍鋅鋼管,橫梁為L50*5熱鍍鋅角鋼。
石材面板采用30mm霞紅色荔枝面花崗巖石材。
(2)幕墻系統(tǒng)二、構(gòu)件式玻璃幕墻
構(gòu)件式玻璃幕墻根據(jù)構(gòu)造及建筑效果的要求,主樓采用140*80系列隔熱明框鋁合金
型材,橫梁為60x70系列隱框橫梁,65*70明框橫梁。
鋁型材室外可視面氟碳噴涂處理(三涂二烤),室內(nèi)型材可視面粉末噴涂處理;玻璃
面板采用TP6+12A+TP6mm雙鋼化中空LOW-E玻璃,LOW-E膜位于朝向室內(nèi)的第二面。
(3)幕墻系統(tǒng)三、金屬幕墻
龍骨用50*50*5熱鍍鋅鋼方通,面板用3mm厚鋁單板。
(4)幕墻系統(tǒng)四、鋼結(jié)構(gòu)鋁板包邊雨棚
本工程主樓南立面鋼結(jié)構(gòu)鋁板包邊雨篷鋼梁采用H550x350x14x20和H550x250x10x16,
支撐橫梁采用H300X200X6X8和50x5mm鍍鋅方鋼管和50*5mm鍍鋅角鋼。面板采用3mm厚
鋁單板,表面氟碳噴涂,雨棚前端采用30mm厚石材。頂部防水采用2mm厚不銹鋼板。
本工程主樓北立面鋼結(jié)構(gòu)鋁板包邊雨篷鋼梁采用120*80*6熱鍍鋅矩形鋼和80*80*5
熱鍍鋅方鋼通,支撐橫梁50x5mm鍍鋅方鋼管和50*5mm鍍鋅角鋼。面板采用3mm厚鋁單板,
表面氟碳噴涂,雨棚前端采用30mm厚石材。頂部防水采用2mm厚不銹鋼板。
本工程其余位置鋁板包邊雨篷龍骨采用50*5mm鍍鋅角鋼。面板采用3mm厚鋁單板,
表面氟碳噴涂,頂部自由排水。
-3-
項(xiàng)目專項(xiàng)施工方案
(5)隔熱鋁合金門窗
本工程南北面入口設(shè)自動感應(yīng)門,采用15mm透明鋼化玻璃,其他位置為鋁合金隔熱
地彈門,采用6+12A+6Low-e鋼化中空玻璃。
(6)鋼結(jié)構(gòu)采光頂
本工程19層會議室上空設(shè)鋼結(jié)構(gòu)采光頂,龍骨采用120*80*6mm矩形鋼管和
80*80*5mm方鋼管,表面需噴涂防火涂料,玻璃采用8+12A+8(Low-e)+1.52pvb+8中空夾
膠鋼化玻璃。
2.3工程施工條件
1)主樓主體結(jié)構(gòu)、二次結(jié)構(gòu)施工完成,外墻清理完成,外腳手架拆除完成。
2)屋面除面層,已全部施工完成具備安裝吊籃條件。
3)建筑周邊道路通暢,消防設(shè)施到位。
4)臨電接駁箱由總承包二級配電箱引出,在主樓10層布置臨時用電,從總包(250A)
二級電箱內(nèi)引出,接入(250A)二級電箱,一次逐級退減至開關(guān)箱符合用電規(guī)范。
5)現(xiàn)場加工場地已同總承包單位對接落實(shí)。材料加工準(zhǔn)備;(由總承包劃分現(xiàn)場材
料堆放區(qū)、料場加工區(qū)布置臨時用電,搭設(shè)臨時加工棚,依據(jù)施工進(jìn)度計(jì)劃提供材料加工、
進(jìn)場計(jì)劃)。
6)施工圖紙確認(rèn)。
7)勞務(wù)人員準(zhǔn)備已到位。
-4-
項(xiàng)目專項(xiàng)施工方案
幕墻施工階段現(xiàn)場布置示意圖
第三章施工安排
3.1項(xiàng)目管理組織
xx發(fā)展大廈項(xiàng)目幕墻工程管理人員及職責(zé)分工
序號管理職務(wù)姓名職稱(資質(zhì))職責(zé)和權(quán)限
1項(xiàng)目經(jīng)理一級建造師全面管理
2技術(shù)負(fù)責(zé)人工程師技術(shù)管理
3安全員專職安全員安全文明管理
4材料員材料員證材料管理
5資料員資料員證資料管理
6質(zhì)檢員質(zhì)檢員證質(zhì)量管理
7施工員施工員證施工進(jìn)度管理
3.2項(xiàng)目管理目標(biāo)
項(xiàng)目管理目標(biāo)名稱目標(biāo)值
工期120天(以甲方開工令為準(zhǔn))
質(zhì)量目標(biāo)確?!疤┥奖睜巹?chuàng)國家優(yōu)質(zhì)工程獎
責(zé)任事故死亡率為零,無重大工傷事故、火
安全目標(biāo)災(zāi)事故和惡性中毒事件,輕傷頻率控制在
1.5‰以內(nèi)。
節(jié)能目標(biāo)執(zhí)行國家及濟(jì)南市規(guī)定
環(huán)保施工執(zhí)行國家及濟(jì)南市規(guī)定
3.3各項(xiàng)資源供應(yīng)方式
3.3.1勞務(wù)資源安排一覽表
序號工種人數(shù)
1大工60-80
2小工20-30
3電焊工10-20
4吊籃維修工2
5吊籃安裝拆卸人員6
6電工2
合計(jì)100-120
-5-
項(xiàng)目專項(xiàng)施工方案
3.3.2機(jī)械設(shè)備采購供應(yīng)安排一覽表
序號機(jī)具名稱型號提供方式電功率(kVA)需要量(臺)使用時間責(zé)任人
1電焊機(jī)BX-520-2自有250.64施工過程中
2手電鉆4300BV自有0.45KW20施工過程中
3沖擊鉆210-S43-2自有0.52KW20施工過程中
2
4打膠槍GRACO20自有/40施工過程中
5平臺據(jù)MAT-2自有1.5KW2施工過程中
6切割機(jī)JS-110自有2.5KW3施工過程中
7吊籃ZLP630自有1.5KW51施工過程中
3.4施工流水段的劃分及施工工藝流程
3.4.1施工流水段的劃分
主樓南北立面4-11軸外造型在17層有變化,按照兩個施工段施工(A1區(qū),A2區(qū)),
主樓2-4,11-13軸(B區(qū))設(shè)有施工電梯和塔吊,需延后施工,其他區(qū)域?yàn)镃區(qū)。
A2
C
B
B
A1
-6-
項(xiàng)目專項(xiàng)施工方案
3.4.2施工工藝流程
進(jìn)場準(zhǔn)備→吊籃搭設(shè)→施工放線→埋件安裝→石材幕墻主龍骨安裝→石材幕墻橫龍
骨安裝→石材幕墻龍骨滿焊及保溫安裝→玻璃幕主龍骨安→玻璃幕橫龍骨安裝→玻璃幕
隱蔽避雷安裝→玻璃幕墻面材安裝→石材幕墻安裝→玻璃幕墻開啟扇安裝→格柵百葉安裝
→幕墻打膠→拆除吊籃→腳手架搭設(shè)→雨棚安裝→玻璃門安裝→清洗幕墻→驗(yàn)收撤場
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對措施
序號重點(diǎn)和難點(diǎn)具體分析應(yīng)對措施責(zé)任人
1施工任務(wù)量本工程樓高76.5m,在樓周勞務(wù)隊(duì)伍選用與公司多
大邊需安裝51部吊籃,樓層年合作的公司,確保人員
較多高,安裝數(shù)量較多,落戶到位
2工期緊合同工期僅120天各作業(yè)面全面展開,做好
材料的準(zhǔn)備工程。
3外立面復(fù)雜南北立面造型原因,需進(jìn)做好吊籃安裝的安排,確
行二次安裝吊籃,影響施保能按時進(jìn)行吊籃轉(zhuǎn)移,
工進(jìn)度施工做好安排優(yōu)先施工
造型復(fù)雜處
-7-
項(xiàng)目專項(xiàng)施工方案
第四章施工進(jìn)度計(jì)劃
計(jì)劃2017年5月5日開工,2017年9月1日全部竣工,總工期120日歷日。。(詳
見附件網(wǎng)絡(luò)進(jìn)度計(jì)劃)
水發(fā)大廈幕墻工程總進(jìn)度計(jì)劃
序
號施工內(nèi)容工時開始日期完成日期
1進(jìn)場準(zhǔn)備19工作日2017年5月5日2017年5月22日
2主樓南北立面(4-11軸/1-16層)(A1)78工作日2017年5月21日2017年8月6日
3搭設(shè)吊籃5工作日2017年5月21日2017年5月25日
4放線4工作日2017年5月26日2017年5月29日
5石材提料5工作日2017年5月31日2017年6月4日
6石材埋板10工作日2017年5月30日2017年6月8日
7焊接主龍骨14工作日2017年6月5日2017年6月18日
8焊接副龍骨12工作日2017年6月15日2017年6月26日
9龍骨驗(yàn)收1工作日2017年6月25日2017年6月25日
10巖棉安裝9工作日2017年6月20日2017年6月28日
11安裝石材18工作日2017年6月29日2017年7月16日
12石材打膠8工作日2017年7月17日2017年7月24日
13雨棚放線3工作日2017年6月8日2017年6月10日
14雨棚打埋板4工作日2017年6月11日2017年6月14日
15雨棚龍骨安裝8工作日2017年6月15日2017年6月22日
16面材安裝7工作日2017年6月25日2017年7月1日
17雨棚打膠3工作日2017年7月2日2017年7月4日
18玻璃幕放線3工作日2017年5月26日2017年5月28日
19玻璃幕墻埋板10工作日2017年5月30日2017年6月8日
20玻璃幕龍骨安裝25工作日2017年6月9日2017年7月3日
21玻璃幕墻防火保溫安裝7工作日2017年6月27日2017年7月3日
22玻璃安裝23工作日2017年7月7日2017年7月29日
23玻璃幕開啟扇安裝11工作日2017年7月20日2017年7月30日
24玻璃幕打膠11工作日2017年7月20日2017年7月30日
25立面驗(yàn)收1工作日2017年7月31日2017年7月31日
26吊籃拆除6工作日2017年8月1日2017年8月6日
27主樓南北立面4-11軸/16-頂層(A2)35工作日2017年8月1日2017年9月4日
28搭設(shè)吊籃5工作日2017年8月1日2017年8月5日
29放線2工作日2017年8月4日2017年8月5日
-8-
項(xiàng)目專項(xiàng)施工方案
30打埋板4工作日2017年8月5日2017年8月8日
31主龍骨焊接5工作日2017年8月7日2017年8月11日
32副龍骨焊接5工作日2017年8月8日2017年8月12日
33龍骨驗(yàn)收1工作日2017年8月13日2017年8月13日
34巖棉安裝2工作日2017年8月11日2017年8月12日
35安裝石材7工作日2017年8月12日2017年8月18日
36石材打膠3工作日2017年8月17日2017年8月19日
37玻璃幕龍骨安裝11工作日2017年8月7日2017年8月17日
38防火安裝3工作日2017年8月18日2017年8月20日
39玻璃安裝6工作日2017年8月21日2017年8月26日
40玻璃幕窗打膠3工作日2017年8月27日2017年8月29日
41立面驗(yàn)收1工作日2017年8月30日2017年8月30日
42吊籃拆除5工作日2017年8月31日2017年9月4日
主樓南立面(2-4軸/1-頂層,12-13軸1-
43頂層)(B區(qū))30工作日2017年8月1日2017年8月30日
44搭設(shè)吊籃4工作日2017年8月1日2017年8月4日
45放線1工作日2017年8月5日2017年8月5日
46打埋板2工作日2017年8月6日2017年8月7日
47焊接主龍骨2工作日2017年8月8日2017年8月9日
48焊接副龍骨2工作日2017年8月10日2017年8月11日
49龍骨驗(yàn)收1工作日2017年8月11日2017年8月11日
50巖棉安裝3工作日2017年8月12日2017年8月14日
51安裝石材5工作日2017年8月15日2017年8月19日
52石材打膠1工作日2017年8月20日2017年8月20日
53玻璃幕玻璃安裝2工作日2017年8月21日2017年8月22日
54玻璃幕開啟扇安裝2
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2023年彎曲機(jī)粉末冶金制品項(xiàng)目融資計(jì)劃書
- 哈佛博弈論課件section
- 遼寧省盤錦市大洼區(qū)2023-2024學(xué)年七年級上學(xué)期期末考試數(shù)學(xué)試卷(含解析)
- 內(nèi)蒙古包頭市東河區(qū)2023-2024學(xué)年八年級上學(xué)期期末考試數(shù)學(xué)試卷(含答案)
- 養(yǎng)老院老人康復(fù)設(shè)施維修人員晉升制度
- 《個人納稅籌劃》課件
- 《員工獎勵與津貼》課件
- 《親親小動物主題墻》課件
- 掛靠租賃合同(2篇)
- 2024年牛羊養(yǎng)殖行業(yè)協(xié)會會員服務(wù)合同范本3篇
- 辦公樓消防改造工程環(huán)境保護(hù)措施
- 2023-2024學(xué)年高一下學(xué)期家長會 課件
- 溯源與解讀:學(xué)科實(shí)踐即學(xué)習(xí)方式變革的新方向
- 班克街教育方案
- 護(hù)理教育改革與創(chuàng)新研究
- 知識點(diǎn)總結(jié)(知識清單)-2023-2024學(xué)年人教PEP版英語六年級上冊
- 社會醫(yī)學(xué)課件第2章醫(yī)學(xué)模式-2024鮮版
- 《囚歌》教學(xué)課件
- 2024年日歷(打印版每月一張)
- 民法典銀行培訓(xùn)課件
- 四年級下冊數(shù)學(xué)單位換算題200道及答案
評論
0/150
提交評論