![鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房 投標(biāo)技術(shù)方案_第1頁(yè)](http://file4.renrendoc.com/view9/M03/1D/1D/wKhkGWdbnvaAIhrOAAIWagDxRIg117.jpg)
![鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房 投標(biāo)技術(shù)方案_第2頁(yè)](http://file4.renrendoc.com/view9/M03/1D/1D/wKhkGWdbnvaAIhrOAAIWagDxRIg1172.jpg)
![鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房 投標(biāo)技術(shù)方案_第3頁(yè)](http://file4.renrendoc.com/view9/M03/1D/1D/wKhkGWdbnvaAIhrOAAIWagDxRIg1173.jpg)
![鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房 投標(biāo)技術(shù)方案_第4頁(yè)](http://file4.renrendoc.com/view9/M03/1D/1D/wKhkGWdbnvaAIhrOAAIWagDxRIg1174.jpg)
![鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房 投標(biāo)技術(shù)方案_第5頁(yè)](http://file4.renrendoc.com/view9/M03/1D/1D/wKhkGWdbnvaAIhrOAAIWagDxRIg1175.jpg)
版權(quán)說(shuō)明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請(qǐng)進(jìn)行舉報(bào)或認(rèn)領(lǐng)
文檔簡(jiǎn)介
鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房投標(biāo)技術(shù)方案
目錄
L工程概況及特點(diǎn)................................................9
1.1建筑概況................................................9
1.2結(jié)構(gòu)概況................................................10
1.2.1基礎(chǔ)................................................10
1.2.2主體.................................................10
1.3安裝工程概況...........................................10
1.3.1概述.................................................10
1.3.2工程概況.............................................10
1.4工程特點(diǎn)...............................................11
1.4.1施T場(chǎng)地文明施T難度大...............................11
1.4.2工程特殊部位較多.....................................12
2.施工組織設(shè)計(jì)總體設(shè)想.........................................12
2.1工程建設(shè)目標(biāo)...........................................12
2.1.1質(zhì)量管理目標(biāo).........................................12
2.1.2工期管理目標(biāo).........................................12
2.1.3安全生產(chǎn)管理目標(biāo).....................................12
2.1.4文明施工管理目標(biāo)....................................12
2.2質(zhì)量控制重點(diǎn)..........................................12
3.施工部署....................................................13
3.1組織機(jī)構(gòu)...............................................13
3.1.1項(xiàng)目部的組織機(jī)構(gòu).....................................13
3.2強(qiáng)化項(xiàng)目管理..........................................14
3.2.1編制和實(shí)施項(xiàng)目管理實(shí)施計(jì)劃...........................14
3.2.2貫徹落實(shí)公司的規(guī)章制度...............................14
3.2.3逐層分解指標(biāo),明確責(zé)、權(quán)、利........................14
3.2.4嚴(yán)格執(zhí)行施工組織設(shè)計(jì).................................15
3.2.5執(zhí)行質(zhì)量進(jìn)度公開(kāi)制...................................15
3.2.6業(yè)主滿意.............................................15
3.3項(xiàng)目管理部職責(zé).........................................15
3.4項(xiàng)目管理部主要部門(mén)、崗位職責(zé)...........................16
3.4.1項(xiàng)目經(jīng)理.............................................16
3.4.2項(xiàng)目副經(jīng)理...........................................16
3.4.3項(xiàng)目總工程師.........................................17
3.4.4項(xiàng)目部的管理職責(zé).....................................17
3.5項(xiàng)目經(jīng)理長(zhǎng)駐現(xiàn)場(chǎng)措施...................................18
3.5.1建立請(qǐng)假制度.........................................18
3.5.2建立約束機(jī)制.........................................18
3.5.3實(shí)行項(xiàng)目經(jīng)理評(píng)分制....................................18
3.6勞務(wù)工資管理和發(fā)放措施................................19
3.7施工組織................................................19
3.7.1施工區(qū)、段劃分......................................19
3.7.2施工順序.............................................19
3.8資源酉已置...............................................21
3.8.1勞動(dòng)力安排計(jì)劃.......................................21
3.8.2工程投入的主要施工機(jī)械設(shè)備安排計(jì)劃..................22
3.8.3周轉(zhuǎn)材料配備.........................................24
3.8.4成品、半成品加工與組織.............................25
4.施工準(zhǔn)備...................................................26
4.1現(xiàn)場(chǎng)準(zhǔn)備...............................................26
4.1.1周邊環(huán)境的了解.......................................26
4.1.2場(chǎng)地平整.............................................26
4.2技術(shù)準(zhǔn)備...............................................26
4.2.1圖紙會(huì)審.............................................26
4.2.2施工組織設(shè)計(jì)和施工方案...............................27
4.3物資準(zhǔn)備...............................................27
4.3.1編制材料計(jì)劃.........................................27
4.3.2材料供應(yīng)商選擇.......................................27
4.3.3材料進(jìn)場(chǎng).............................................28
4.3.4材料檢測(cè).............................................28
4.4設(shè)備準(zhǔn)備...............................................29
4.4.1設(shè)備組織.............................................29
5.協(xié)調(diào)、配合及服務(wù)............................................29
5.1與設(shè)計(jì)院的協(xié)調(diào)配合.....................................29
5.2與監(jiān)理的協(xié)調(diào)配合.......................................29
5.3與業(yè)主協(xié)調(diào)配合.........................................30
5.4與質(zhì)檢站的協(xié)調(diào)配合.....................................30
5.5與公安部門(mén)的協(xié)調(diào)配合...................................30
5.6與業(yè)主指定分包單位的協(xié)調(diào)配合...........................30
5.7與社會(huì)各界的協(xié)調(diào).......................................30
5.7.1與地方安全部門(mén)的協(xié)調(diào)配合.............................30
5.7.2與地方環(huán)境監(jiān)測(cè)單位的協(xié)調(diào)配合.........................31
5.8內(nèi)部關(guān)系的協(xié)調(diào)配合.....................................31
5?9服務(wù)...................................................31
6.土建各分部分項(xiàng)工程主要施工方案...............................32
6.1施工測(cè)量...............................................32
6.1.1平面控制.............................................32
6.1.2垂直度控制...........................................33
6.1.3標(biāo)高抄測(cè).............................................33
6.1.4精度要求.............................................33
6.1.5沉降觀測(cè).............................................34
6.2基礎(chǔ)工程...............................................34
6.2.1基礎(chǔ)土方.............................................34
6.2.2基礎(chǔ)施工.............................................36
6.2.3基礎(chǔ)模板.............................................36
6.2.4基礎(chǔ)鋼筋工程.........................................37
6.2.5基礎(chǔ)混凝土..........................................38
6.3主體工程...............................................39
6.3.1模板工程.............................................39
6.3.2鋼筋工程.............................................43
6.3.3混凝土工程...........................................44
6.3.4砌體結(jié)構(gòu).............................................46
6.4保溫隔熱屋面...........................................50
6.4.1工藝流程.............................................50
6.4.2找平層...............................................50
6.4.3防水卷材施工.........................................50
6.4.4保溫層施工...........................................51
6.4.5細(xì)石砂面層施工.......................................52
6.5裝飾工程...............................................52
6.5.1室內(nèi)抹灰工程.........................................52
6.5.2外墻保溫層施工.......................................53
6.5.3乳膠漆墻面施工.......................................53
6.5.4油漆工程.............................................55
6.5.5門(mén)窗工程.............................................55
6.5.6欄桿安裝.............................................58
6.6樓地面工程.............................................58
6.6.1水泥細(xì)石碎樓地面.....................................58
6.7室外散水...............................................59
6.8腳手架工程.............................................59
6.8.1外腳手架.............................................59
6.8.2腳手架的防雷接地....................................62
6.8.3內(nèi)腳手架.............................................62
6.8.4安全防護(hù)架...........................................62
6.8.5腳手架拆除...........................................63
7,安裝各分部分項(xiàng)工程的施工方案.................................64
7.1給排水工程施工方案.....................................64
7.1.1預(yù)埋件的安裝.........................................64
7.1.2管道施工流程.........................................64
7.1.3PP—R管安裝...........................................65
7.1.4排水管安裝...........................................66
7.1.5UPVC管專(zhuān)用膠粘接.....................................67
7.1.6衛(wèi)生器具的安裝方法和要求.............................68
7.1.7消防系統(tǒng)的安裝方法和要求.............................69
7.1.8管道支架的安裝方法和要求.............................70
7.1.9管道試驗(yàn)與管道沖洗...................................70
7.1.10管道防腐與保溫......................................72
7.2電氣工程施工方案.......................................72
7.2.1電氣施工流程.........................................72
7.2.2土建配合階段.........................................72
7.2.3相接階段.............................................73
7.2.4系統(tǒng)調(diào)試.............................................85
&建筑節(jié)能及建筑保溫專(zhuān)項(xiàng)施工方案和措施.........................88
8.1.1外墻保溫專(zhuān)項(xiàng)施工方案和質(zhì)量保證措施...................88
一、基層墻體處理...........................................88
二、材料的準(zhǔn)備.............................................88
三、聚苯板的粘貼...........................................88
四、保溫板粘貼過(guò)程控制要點(diǎn).................................88
五、質(zhì)量檢驗(yàn):.............................................89
8.1.2屋面保溫專(zhuān)項(xiàng)施工方案和質(zhì)量保證措施...................91
9.重點(diǎn)、難點(diǎn)施工措施...........................................92
9.1.1測(cè)量放線采取的措施...................................92
9.1.2土方開(kāi)挖保證樁基質(zhì)量的施工措施......................92
9.1.3鋼筋保護(hù)層控制不嚴(yán)的防治措施.........................93
9.1.4為確保碎成型質(zhì)量,模板采取的施工措施...............93
10.確保工程質(zhì)量的技術(shù)組織措施..................................94
10.1質(zhì)量目標(biāo)..............................................94
10.1.1質(zhì)量管理目標(biāo)........................................94
10.1.2分部分項(xiàng)工程質(zhì)量管理目標(biāo)............................94
10.1.3工程觀感質(zhì)量管理目標(biāo)................................94
10.2質(zhì)量保證管理措施.....................................94
10.2.1質(zhì)量管理保證體系網(wǎng)絡(luò)................................94
10.2.2質(zhì)量管理制度......................................95
10.2.3編制質(zhì)量計(jì)劃、創(chuàng)優(yōu)措施..............................96
10.2.4施工過(guò)程質(zhì)量控制點(diǎn)................................96
10.3工程質(zhì)量技術(shù)措施......................................98
10.3.1施工組織設(shè)計(jì)審批制度................................98
10.3.2分部、分項(xiàng)工程技術(shù)交底、復(fù)核、隱蔽工程驗(yàn)收制度......98
10.3.3施工機(jī)械設(shè)備、監(jiān)視和測(cè)量設(shè)備的控制..................98
10.3.4原材料質(zhì)量保證措施.................................98
10.4主要分部分項(xiàng)工程質(zhì)量保證技術(shù)措施.....................99
10.4.1分部分項(xiàng)工程過(guò)程質(zhì)量控制措施.......................99
10.4.2基礎(chǔ)工程............................................99
10.4.3主體工程...........................................100
10.4.4裝修工程...........................................102
10.4.5屋面防水施工.......................................103
10.5工程質(zhì)量通病的防治措施.............................103
10.5.1目的...............................................103
10.5.2適用范圍...........................................103
10.5.3具體措施...........................................103
10.6采用質(zhì)量預(yù)控制的科學(xué)方法.............................106
10.7開(kāi)展QC小組活動(dòng)......................................107
10.7.1小組概況及活動(dòng)形式.................................107
10.7.2課題確定.........................................107
10.8計(jì)量管理...........................................108
11.確保安全生產(chǎn)的技術(shù)組織措施................................109
11.1安全管理目標(biāo).........................................109
11.2組織措施.............................................109
11.2.1施工現(xiàn)場(chǎng)安全組織.................................109
11.3安全保證計(jì)劃的編制..................................112
11.4施工過(guò)程控制........................................112
11.4.1人員培訓(xùn)..........................................112
11.4.2安全檢查..........................................112
11.4.3隱患整改..........................................113
11.4.4安全事故的處理....................................113
11.4.5現(xiàn)場(chǎng)急救.........................................113
1L4.6施工現(xiàn)場(chǎng)的安全要求................................114
11.5施工過(guò)程安全控制措施...............................115
11.5.1搭設(shè)腳手架安全要求...............................115
11.5.2洞口、臨邊的防護(hù)...................................115
11.5.3內(nèi)外交通管理保障措施...............................115
11.6消防管理............................................116
11.6.1組織措施...........................................116
11.6.2防火要求...........................................116
11.6.3消防設(shè)施的布置.....................................116
12.確保文明施工的技術(shù)組織措施................................117
12.1目標(biāo).................................................117
12.2現(xiàn)場(chǎng)文明施工管理.....................................117
12.2.1文明施工組織網(wǎng)絡(luò)...................................117
12.2.2文明施工崗位職責(zé)..................................117
12.2.3內(nèi)部溝通...........................................119
12.2.4場(chǎng)容場(chǎng)貌...........................................120
12.2.5施工現(xiàn)場(chǎng)標(biāo)化管理....................................120
12.3環(huán)保施工措施........................................122
12.3.1工作目標(biāo)...........................................122
12.3.2組織管理...........................................123
12.3.3工作制度...........................................123
12.3.4管理規(guī)定...........................................123
12.4組織保證措施........................................124
12.5技術(shù)保證措施........................................125
13.確保工期的技術(shù)組織措施.....................................126
13.1施工工期.............................................126
13.2施工進(jìn)度計(jì)劃.........................................126
13.3進(jìn)度保證措施.........................................126
13.3.1組織保證措施.......................................126
13.3.2勞動(dòng)力保證措施....................................127
13.3.3機(jī)械設(shè)備保證措施....................................127
13.3.4技術(shù)保證措施.......................................127
13.3.5周轉(zhuǎn)工具保證措施....................................127
13.3.6基礎(chǔ)工程階段保證措施...............................127
13.3.7主體工程階段保證措施...............................127
13.3.8裝飾工程階段保證措施...............................128
13.3.9水電安裝階段保證措施..............................128
13.3.10進(jìn)度計(jì)劃動(dòng)態(tài)控制措施..............................128
13.4進(jìn)度獎(jiǎng)罰措施.........................................129
13.5法定假期間保證措施....................................129
13.6農(nóng)忙期間保證措施......................................130
14.施工總平面布置.............................................131
14.1布置原則.............................................131
14.2生活區(qū)臨時(shí)設(shè)施布置..................................131
14.3臨時(shí)生產(chǎn)設(shè)施布置....................................131
14.3.1施工臨時(shí)用地圍護(hù)設(shè)置...............................131
14.3.2施工道路...........................................132
14.3.3攪拌臺(tái)設(shè)置........................................132
14.3.4鋼筋車(chē)間...........................................132
14.3.5現(xiàn)場(chǎng)辦公室.........................................133
14.3.6其它生產(chǎn)設(shè)施.......................................133
14.3.7施工區(qū)周邊環(huán)境的保護(hù)措施.........................133
14.3.8施工現(xiàn)場(chǎng)臨時(shí)用電方案...............................133
14.3.9施工現(xiàn)場(chǎng)臨時(shí)用水方案...............................134
15.新工藝、新技術(shù)、新材料的應(yīng)用...............................135
15.1新型模板.............................................135
15.2泵送碎...............................................135
15.3鋼筋直螺紋連接技術(shù)................................135
15.4激光測(cè)距儀、全站儀..................................135
15.5微機(jī)應(yīng)用.............................................135
16.季節(jié)性及夜間施工保證措施..................................136
16.1雨期及臺(tái)風(fēng)期施工措施...............................136
16.1.1管理措施...........................................136
16.1.2安全措施...........................................136
16.1.3技術(shù)措施.........................................136
16.2夜間施工措施.......................................137
16.3冬期施工技術(shù)措施.....................................137
16.3.1土方工程.........................................138
16.3.2鋼筋工程...........................................138
16.3.3碎工程.............................................138
16.4暑季施工措施.........................................138
17.降低工程成本技術(shù)措施......................................139
17.1主要技術(shù)節(jié)約措施.....................................139
17.2進(jìn)行技術(shù)經(jīng)濟(jì)分析,優(yōu)選施工方案.......................139
17.3提高勞動(dòng)生產(chǎn)率.......................................139
17.4節(jié)約材料消耗.........................................139
17.5提高機(jī)械設(shè)備利用率...................................139
編制依據(jù)
1.XX市XXXX有限公司二期建設(shè)工程招標(biāo)文件;
2.XX市XXXX有限公司一期建設(shè)工程設(shè)計(jì)圖紙;
3.XX市XXXX有限公司二期建設(shè)工程招標(biāo)答疑;
4.現(xiàn)行安全、文明施工的有關(guān)規(guī)定;
5,現(xiàn)場(chǎng)踏勘目測(cè)結(jié)果;
6.國(guó)家現(xiàn)行施工技術(shù)規(guī)范、規(guī)程、標(biāo)準(zhǔn)。
1.工程概況及特點(diǎn)
XX市XXXX有限公司二期建設(shè)工程,位于XX市XX區(qū)工業(yè)園區(qū)緯二路18
號(hào)。
本標(biāo)段施工內(nèi)容包括4#、5#廠房以及綜合樓土建、水電安裝工程。
建設(shè)單位:XX市XXXX有限公司
設(shè)計(jì)單位:XX市現(xiàn)代建筑設(shè)計(jì)研究院有限公司
1.1建筑概況
本標(biāo)段工程建筑面積約10854.38m;其中4#、5#廠房都為3595m",綜合
樓為3664.38m2。
建筑樓層:4#、5#廠房溝為兩層,綜合樓三層局部四層。
本工程設(shè)計(jì)基準(zhǔn)年限為50年,建筑主體結(jié)構(gòu)安全等級(jí)為二級(jí)?!?.000
為室內(nèi)地坪標(biāo)高,相當(dāng)于絕對(duì)標(biāo)高詳見(jiàn)總圖,室內(nèi)外高差廠房為150mm,綜合
樓為300mmo
建筑類(lèi)別及耐火等級(jí):耐火等級(jí)為二級(jí)
抗震設(shè)防烈度:六度。
結(jié)構(gòu)類(lèi)型:框架結(jié)構(gòu)體系。
地面做法:(廠房)地一:水泥砂漿地面;
地二:地磚地面;(用于衛(wèi)生間)
(綜合樓)水泥砂漿地面
樓面做法:(廠房)樓一:水泥砂漿樓面;
樓二:地磚樓面;(用于衛(wèi)生間)
(綜合樓)水泥砂漿樓面;
內(nèi)墻做法:(廠房)內(nèi)墻一:乳膠漆墻面
內(nèi)墻二:瓷磚墻面(用于衛(wèi)生間)
(綜合樓)乳膠漆墻面
外墻做法:(廠房)水泥砂漿抹灰,乳膠漆飾面;
(綜合樓)水泥砂漿抹灰,巖棉板保溫層,抗裂砂漿壓入一層
耐堿玻纖網(wǎng)格布,乳膠漆飾面;
頂棚做法:素水泥漿一道,混合砂漿抹灰,乳膠漆罩面;
門(mén)窗:塑鋼窗、防火鋼門(mén)安裝。
屋面做法:廠房為20厚1:3水泥砂漿找平層、40厚聚苯乙烯擠塑板、20厚1:3
水泥砂漿找平層、SBS改性瀝青防水卷材丁
綜合樓為最薄處30厚粉煤灰陶粒碎找坡層、40厚擠塑聚苯板、20
厚水泥砂漿找平層、刷一層基層處理劑、4厚高聚物改性瀝青防水卷材、50厚
C30細(xì)石碎,內(nèi)配中4@150雙向鋼筋。
1.2結(jié)構(gòu)概況
L2.1基礎(chǔ)
基礎(chǔ)碎墊層C10,獨(dú)立基礎(chǔ)、條形基礎(chǔ)廠房均采用C25泵送商品碎,綜合
樓均采用C30泵送商品稅。
L2.2主體
框架柱、梁、板:結(jié)構(gòu)強(qiáng)度等級(jí)為廠房C25、綜合樓C30泵送商品碎;
構(gòu)造柱:為C20非泵送商品碎;圈梁、過(guò)梁:為C20非泵送商品碎
砌體結(jié)構(gòu):-0.060以下采用MU20混凝土磚M10水泥砂漿砌筑;-0.060
以上外墻采用承重性砌塊,M7.5混合砂漿砌筑,內(nèi)墻采用碎空心砌塊,M5混
合砂漿砌筑,女兒墻采用碎空心砌塊,M7.5混合砂漿砌筑。
1.3安裝工程概況
1.3.1概述
本工程主要工作內(nèi)容為:給排水管道、電氣等工程的安裝。
1.3.2工程概況
A.給排水工程
包括給水系統(tǒng)、消火栓消防系統(tǒng)、排水系統(tǒng)、雨水系統(tǒng)等安裝;
給水系統(tǒng):本工程由市政管網(wǎng)供水
污水系統(tǒng):采用雨污分流制,糞便污水經(jīng)化糞池處理后與其它生活廢水
排入室外污水管網(wǎng);
雨水系統(tǒng):主樓采用重力流排水系統(tǒng)排至室外,與場(chǎng)地及道路雨水匯合
排入市政雨水管網(wǎng)。
室內(nèi)給水管采用PP-R管,熱熔連接;
消火栓消防管采用內(nèi)外熱浸熱鍍鋅鋼管,管徑大于等于DN100采用卡箍
連接,管徑小于DN100采用絲扣連接。
污水管采用UPVC排水管,粘接。
雨水管、冷凝水管采用UPVC塑料排水管,膠結(jié)。
B.電氣工程
包括配電設(shè)計(jì)、照明設(shè)計(jì)、防雷接地系統(tǒng);
電力配電系統(tǒng):
低壓配電電壓為380/300V三相四線制,采用放射式與樹(shù)干式相結(jié)合供電
方式;
照明系統(tǒng):
本工程電纜電線均采用阻燃電線電纜;
接地型式采用TN-C-S系統(tǒng),利用建筑物基礎(chǔ)主鋼筋作共同接地裝置。
防雷與接地:
防直擊雷:采用在屋頂明設(shè)避雷帶和其它地方暗設(shè)避雷帶組成混合接閃
器,引下線做法商品砂柱內(nèi)電焊成一體的四根不小于610的主筋作防雷引下
線。
所有接地均利用基礎(chǔ)及基礎(chǔ)梁中的鋼筋焊接溝通后連成一整體作為統(tǒng)一
接地體,形成共用接地系統(tǒng)。
1.4工程特點(diǎn)
1.4.1施工場(chǎng)地文明施工難度大
根據(jù)現(xiàn)場(chǎng)實(shí)地觀測(cè),本工程施工現(xiàn)場(chǎng)內(nèi),施工中要特別注重文明施工,
以最小的影響來(lái)確保場(chǎng)內(nèi)的正?;顒?dòng)。另外,現(xiàn)場(chǎng)臨建設(shè)施、材料堆放場(chǎng)地、
大型機(jī)械設(shè)備布置必須進(jìn)行合理的規(guī)劃和布局,施工順序也必須進(jìn)行全局的
策劃和組織,來(lái)保證場(chǎng)地受施工干擾最小。
L4.2工程特殊部位較多
本T.程屋面及衛(wèi)生間的防水處理等,都必須制定相應(yīng)的技術(shù)措施,確保
工程質(zhì)量符合設(shè)計(jì)與規(guī)范要求。
2.施工組織設(shè)計(jì)總體設(shè)想
2.1工程建設(shè)目標(biāo)
2.1.1質(zhì)量管理目標(biāo)
符合國(guó)家質(zhì)量驗(yàn)收標(biāo)準(zhǔn),一次性驗(yàn)收合格
2.1.1.1各分部工程質(zhì)量管理目標(biāo)
分部工程、分項(xiàng)工程一次性驗(yàn)收合格
2.1.1.2工程觀感質(zhì)量管理目標(biāo)
觀感評(píng)定:好
2.1.2工期管理目標(biāo)
工期:370個(gè)日歷天
2.1.2.1工程竣工管理目標(biāo)
工程竣工一次驗(yàn)收合格率100%
2.1.3安全生產(chǎn)管理目標(biāo)
2.1.3.1安全生產(chǎn)目標(biāo)
杜絕死亡、重傷事故
輕傷事故控制在5%。以內(nèi)
2.1.3.2安全生產(chǎn)過(guò)程目標(biāo)
事故隱患控制率在95%以上
整改率控制在100%
2.1.4文明施工管理目標(biāo)
2.1.4.1文明工地目標(biāo)
確?!笆屑?jí)文明工地二
2.2質(zhì)量控制重點(diǎn)
稅結(jié)構(gòu)施工
衛(wèi)生間防滲
屋面防水細(xì)部節(jié)點(diǎn)施工
平面及垂直度度控制
安裝與土建交叉施工的質(zhì)量控制
3.施工部署
3.1組織機(jī)構(gòu)
本工程采用公司、項(xiàng)目管理部二級(jí)管理模式。成立“XX市XXXX有限公司
二期建設(shè)工程項(xiàng)目經(jīng)理部”,代表公司進(jìn)行工程施工組織和管理,全面負(fù)責(zé)
整個(gè)工程的進(jìn)度、安全、質(zhì)量、成本控制四大指標(biāo),抓好優(yōu)質(zhì)服務(wù)及現(xiàn)場(chǎng)文
明施工等。
3.1.1項(xiàng)目部的組織機(jī)構(gòu)
在公司內(nèi)抽調(diào)一批具有較高專(zhuān)業(yè)知識(shí)和業(yè)務(wù)能力、經(jīng)驗(yàn)豐富的施工骨干
力量組成項(xiàng)目管理部的項(xiàng)目班子和管理層。項(xiàng)目部設(shè)項(xiàng)目經(jīng)理一名、項(xiàng)目總
工程師一名、項(xiàng)目副經(jīng)理一名,下設(shè)質(zhì)保部、技術(shù)部、工程部、物項(xiàng)部、經(jīng)
營(yíng)部、人勞部、財(cái)務(wù)部、安保部、資料室。
項(xiàng)目組織機(jī)構(gòu)網(wǎng)絡(luò)圖
項(xiàng)目經(jīng)理
項(xiàng)目總工程師項(xiàng)目副經(jīng)理
3.2強(qiáng)化項(xiàng)目管理
3.2.1編制和實(shí)施項(xiàng)目管理實(shí)施計(jì)劃
工程開(kāi)工前,項(xiàng)目經(jīng)理組織項(xiàng)目部相關(guān)管理人員編制項(xiàng)目管理實(shí)施規(guī)劃。
編制前,必須對(duì)施工合同和施工條件進(jìn)行分析,對(duì)項(xiàng)目管理目標(biāo)責(zé)任書(shū)
進(jìn)行分析。
在實(shí)施過(guò)程中,每隔一個(gè)月進(jìn)行一次檢查,必要時(shí)增加檢查頻率,發(fā)現(xiàn)
偏差,及時(shí)調(diào)整。確保本工程順利進(jìn)展。
3.2.2貫徹落實(shí)公司的規(guī)章制度
在項(xiàng)目施工過(guò)程中,必須貫徹執(zhí)行公司的各項(xiàng)規(guī)章制度,主要有:
《項(xiàng)目施工管理細(xì)則》
《項(xiàng)目施工質(zhì)量責(zé)任制》
《項(xiàng)目施工安全生產(chǎn)責(zé)任制》
《項(xiàng)目施工用戶滿意責(zé)任制》
《項(xiàng)目施工資金使用管理制度》
3.2.3逐層分解指標(biāo),明確責(zé)、權(quán)、利
項(xiàng)目開(kāi)工前,公司與項(xiàng)目經(jīng)理簽訂本項(xiàng)目承包合同,明確項(xiàng)目經(jīng)理及項(xiàng)
目部的責(zé)、權(quán)、利,項(xiàng)目部與項(xiàng)目管理人員及生產(chǎn)班組簽訂施工協(xié)議,分解
項(xiàng)目各項(xiàng)指標(biāo),明確參與施工人員的職責(zé)、權(quán)利及獎(jiǎng)勵(lì)和處罰,把績(jī)效與經(jīng)
濟(jì)收入掛鉤,進(jìn)一步強(qiáng)化職工的責(zé)任心、事業(yè)心,從而保證項(xiàng)目正常實(shí)施。
3.2.4嚴(yán)格執(zhí)行施工組織設(shè)計(jì)
施工組織設(shè)計(jì)經(jīng)公司總工和業(yè)主、監(jiān)理批準(zhǔn)后,必須嚴(yán)格執(zhí)行,任何人
不得隨意修改施工組織設(shè)計(jì)或不按施工組織設(shè)計(jì)施工,如需要修改施工組織
設(shè)計(jì),必須至少提前一周報(bào)請(qǐng)?jiān)瓕徟块T(mén)審批,經(jīng)批準(zhǔn)后方可按修改后的施
工組織設(shè)計(jì)執(zhí)行。
3.2.5執(zhí)行質(zhì)量進(jìn)度公開(kāi)制
工程開(kāi)工前,將工程質(zhì)量目標(biāo)、進(jìn)度計(jì)劃張貼上墻,施工過(guò)程中,根據(jù)
每一分部完成情況,填寫(xiě)對(duì)照表,找出原因,以便及時(shí)整改。
3.2.6業(yè)主滿意
通過(guò)強(qiáng)化項(xiàng)目管理,來(lái)達(dá)到工期短、質(zhì)量好、成本低及安全的目標(biāo),從
而最終生產(chǎn)出令業(yè)主滿意的產(chǎn)品。
3.3項(xiàng)目管理部職責(zé)
對(duì)公司總部負(fù)責(zé),向公司總部報(bào)告工程實(shí)施過(guò)程中的一切重大事宜;
負(fù)責(zé)工程項(xiàng)目的施工管理和各項(xiàng)工作的具體實(shí)施;
編制項(xiàng)目各項(xiàng)計(jì)劃,包括資金計(jì)劃和執(zhí)行機(jī)構(gòu)開(kāi)支預(yù)算;
編制項(xiàng)目質(zhì)量保證計(jì)劃和技術(shù)方案,并報(bào)公司審批后負(fù)責(zé)落實(shí)和實(shí)施;
編制項(xiàng)目安全文明施工組織管理方案,報(bào)公司審批后落實(shí);
做好現(xiàn)場(chǎng)生產(chǎn)組織管理工作,保證質(zhì)量、工期和安全目標(biāo)的實(shí)現(xiàn);
具體負(fù)責(zé)項(xiàng)目的各分部交驗(yàn)工作,以及竣工驗(yàn)收負(fù)責(zé)工程創(chuàng)優(yōu)的各項(xiàng)工
作;
3.4項(xiàng)目管理部主要部門(mén)、崗位職責(zé)
3.4.1項(xiàng)目經(jīng)理
3.4.1.1項(xiàng)目經(jīng)理的崗位職責(zé)
是項(xiàng)目管理部的法定代表人,與公司一道討論并決定承包項(xiàng)目部的一切
重大事宜,審核并批準(zhǔn)項(xiàng)目執(zhí)行機(jī)構(gòu)的各類(lèi)計(jì)劃、方案、報(bào)告和制度;
與公司經(jīng)理一道,牽頭負(fù)責(zé)項(xiàng)目管理部與業(yè)主和政府機(jī)構(gòu)的聯(lián)絡(luò)工作;
全面主持項(xiàng)目執(zhí)行機(jī)構(gòu)的日常工作,是項(xiàng)目實(shí)施過(guò)程的全職組織者和指
揮者;
決定項(xiàng)目的各種獎(jiǎng)勵(lì)分配方案并報(bào)公司備案;
擬訂項(xiàng)目執(zhí)行機(jī)構(gòu)組織和人員配制,提請(qǐng)公司聘任或解聘項(xiàng)目主要崗位
人員;
處理項(xiàng)目實(shí)施中的重大緊急事件,并及時(shí)向公司報(bào)告:
負(fù)責(zé)與業(yè)主、監(jiān)理、設(shè)計(jì)等的協(xié)調(diào)和溝通的組織領(lǐng)導(dǎo)工作;組織和領(lǐng)導(dǎo)
創(chuàng)優(yōu)工作。
3.4.1.2項(xiàng)目經(jīng)理的主要業(yè)績(jī)
項(xiàng)目經(jīng)理近幾年的主要業(yè)績(jī):見(jiàn)商務(wù)標(biāo)
3.4.2項(xiàng)目副經(jīng)理
3.4.2.1項(xiàng)目副經(jīng)理的崗位職責(zé)
落實(shí)項(xiàng)目質(zhì)量保證計(jì)劃、各類(lèi)施工技術(shù)方案、安全文明、施工組織管理
方案;
配合項(xiàng)目經(jīng)理,組織編制項(xiàng)目執(zhí)行機(jī)構(gòu)的勞資分配制度和其它管理制度;
配合項(xiàng)目經(jīng)理,組織編制項(xiàng)目實(shí)施的各類(lèi)進(jìn)度計(jì)劃、預(yù)算、報(bào)表;
協(xié)助項(xiàng)目經(jīng)理工作,具體負(fù)責(zé)項(xiàng)目基礎(chǔ)、土建、鋼結(jié)構(gòu)、裝修、機(jī)電等
施工生產(chǎn)的技術(shù)、質(zhì)量、安全、進(jìn)度的組織、控制和管理工作,以及協(xié)助項(xiàng)
目經(jīng)理分管計(jì)劃協(xié)調(diào)、安全文明、質(zhì)量保證、行政、保安等部門(mén)的工作;
具體負(fù)責(zé)項(xiàng)目質(zhì)量、工期,安全目標(biāo)的管理監(jiān)督工作;
配合項(xiàng)目經(jīng)理,管理經(jīng)營(yíng)部、財(cái)務(wù)部和物資采購(gòu)部的工作
負(fù)責(zé)工程的竣工交驗(yàn)工作;
在項(xiàng)目經(jīng)理的配合下,負(fù)責(zé)組織協(xié)調(diào)后方生產(chǎn)資源和技術(shù)服務(wù)的支持工
作;
協(xié)助總工程師進(jìn)行新材料、新技術(shù)、新工藝在本工程的推廣應(yīng)用和技術(shù)
總結(jié)工作
3.43項(xiàng)目總丁程師
3.4.3.1項(xiàng)目總工的崗位職責(zé)
協(xié)助項(xiàng)目經(jīng)理管理和領(lǐng)導(dǎo)技術(shù)部工作;
具體負(fù)責(zé)項(xiàng)目質(zhì)量保證計(jì)劃、各類(lèi)施工技術(shù)方案和安全文明施工組織管
理方案的編制及其檢查和落實(shí)工作;
負(fù)責(zé)總體和階段進(jìn)度計(jì)劃的編制、分解、協(xié)調(diào)和落實(shí)工作
負(fù)責(zé)項(xiàng)目質(zhì)量目標(biāo)、進(jìn)度、目標(biāo)、安全文明施工目標(biāo)和質(zhì)量獎(jiǎng)目標(biāo)的策
劃、組織、管理和落實(shí)工作;
組織相關(guān)部門(mén)和人員代表項(xiàng)目經(jīng)理部參與與業(yè)主、監(jiān)理或設(shè)計(jì)方等就施
工方案、技術(shù)、設(shè)計(jì)、質(zhì)量等方面的問(wèn)題的會(huì)議、討論或磋商;
主持施T組織設(shè)計(jì)和重大技術(shù)方案和測(cè)量方案的編制與修訂并負(fù)責(zé)把
關(guān);
組織進(jìn)度計(jì)劃的編制并監(jiān)督落實(shí),負(fù)責(zé)土建與水電安裝工作之間在進(jìn)度
安排方面的配合和協(xié)調(diào);
參與項(xiàng)目質(zhì)量策劃并督促技術(shù)方案和施工組織設(shè)計(jì)主要內(nèi)容的落實(shí)工
作;
對(duì)新技術(shù)、新工藝和新材料在本工程的推廣和使用進(jìn)行指導(dǎo);
協(xié)助項(xiàng)目經(jīng)理并組織創(chuàng)優(yōu)工作;
竣工圖、竣工資料、技術(shù)總結(jié)等工作的指導(dǎo)和審核;
負(fù)責(zé)組織對(duì)工人的崗前培訓(xùn)工作,并審查培訓(xùn)效果;
負(fù)責(zé)工程的技術(shù)資料整理工作
3.4.4項(xiàng)目部的管理職責(zé)
主要部門(mén)的崗位職責(zé)
3.4.4.1技術(shù)部
協(xié)助項(xiàng)目總工程師工作,負(fù)責(zé)項(xiàng)目施工的技術(shù)準(zhǔn)備工作;
編制項(xiàng)目質(zhì)量保證計(jì)劃、安全文明、施工方案。及時(shí)向總工返饋信息,
參與施工方案修訂工作。
具體負(fù)責(zé)現(xiàn)場(chǎng)總平面的布置方案及其調(diào)整方案;
協(xié)助安全文明施工、質(zhì)量體系運(yùn)行和爭(zhēng)創(chuàng)質(zhì)量獎(jiǎng)工作;
負(fù)責(zé)編制工程的物資需求計(jì)劃;
負(fù)責(zé)技術(shù)資料收集整理工作,項(xiàng)目階段交驗(yàn)和竣工交驗(yàn);
負(fù)責(zé)新技術(shù)、新材料、新工藝在本項(xiàng)目的推廣應(yīng)用和科技成果的總結(jié)工
作;
3.4.4.2質(zhì)保部
協(xié)助項(xiàng)目副經(jīng)理工作,負(fù)責(zé)項(xiàng)目的全面質(zhì)量管理;
參與編制項(xiàng)目質(zhì)量保證計(jì)劃,負(fù)責(zé)編制安全文明施工組織管理方案和管
理制度并監(jiān)督實(shí)施;
負(fù)責(zé)安全生產(chǎn)和文明施工的日常檢查、監(jiān)督、消除隱患等管理;
負(fù)責(zé)管理落實(shí)質(zhì)量記錄的整理存檔工作,協(xié)助項(xiàng)目總工程師進(jìn)行竣工資
料的編制工作;
負(fù)責(zé)項(xiàng)目質(zhì)量保證計(jì)劃并負(fù)責(zé)監(jiān)督實(shí)施、過(guò)程控制、日常管理;
負(fù)責(zé)項(xiàng)目全員質(zhì)量保證體系和質(zhì)量方針的培訓(xùn)教育工作;
負(fù)責(zé)分部分項(xiàng)工程工序質(zhì)量檢查和質(zhì)量評(píng)定工作;
負(fù)責(zé)質(zhì)量目標(biāo)的分解落實(shí),編制質(zhì)量獎(jiǎng)懲責(zé)任制度并負(fù)責(zé)日常管理;
負(fù)責(zé)工程創(chuàng)優(yōu)和評(píng)獎(jiǎng)的策劃、組織、資料準(zhǔn)備和日常管理工作;
3.5項(xiàng)目經(jīng)理長(zhǎng)駐現(xiàn)場(chǎng)措施
3.5.1建立請(qǐng)假制度
項(xiàng)目經(jīng)理若離開(kāi)現(xiàn)場(chǎng),在一天以內(nèi),應(yīng)以書(shū)面形式請(qǐng)假,經(jīng)現(xiàn)場(chǎng)總監(jiān)及
甲方代表批準(zhǔn),離開(kāi)前,必須將其工作交給現(xiàn)場(chǎng)副經(jīng)理代管,方可離開(kāi)。
3.5.2建立約束機(jī)制
資格預(yù)審文件和投標(biāo)文件中明確的項(xiàng)目經(jīng)理和技術(shù)員或施工員、質(zhì)量員、
安全員等不得擅自變更,如未經(jīng)發(fā)包人同意,開(kāi)工時(shí)或施工過(guò)程中變更,發(fā)
包人有權(quán)解除合同,并追究由此帶來(lái)的發(fā)包人一切損失。項(xiàng)目經(jīng)理本人每天
至少8小時(shí),每周不少于3天在本工程施工現(xiàn)場(chǎng)工作。且必須參加每周召開(kāi)
會(huì)例會(huì)(有事須請(qǐng)假)。
3.5.3實(shí)行項(xiàng)目經(jīng)理評(píng)分制
公司已建立項(xiàng)目經(jīng)理評(píng)分制,總共10分,根據(jù)評(píng)分進(jìn)行年度考核,作為
評(píng)選公司優(yōu)秀項(xiàng)目經(jīng)理及年終獎(jiǎng)的根本依據(jù),其中業(yè)主意見(jiàn)占5分,若業(yè)主
反映項(xiàng)目經(jīng)理無(wú)故或不請(qǐng)假就離開(kāi)現(xiàn)場(chǎng),每次扣0.5分。
3.6勞務(wù)工資管理和發(fā)放措施
我單位將嚴(yán)格遵守《中華人民共和國(guó)勞動(dòng)法》,認(rèn)真貫徹《關(guān)干切實(shí)解決
建筑業(yè)企業(yè)拖欠農(nóng)民工工資問(wèn)題的通知》文件精神,以及江蘇省和XX市《市
政府關(guān)于進(jìn)一步做好解決建設(shè)工程中拖欠工程款和拖欠民工工資工作的若干
意見(jiàn)》等一系列文件精神,切實(shí)做好此項(xiàng)工作。
無(wú)論工程款支付怎樣,我公司將按照下列措施執(zhí)行:
A.如果在工程款按合同支付情況下,將在每月30日全額支付勞務(wù)人員當(dāng)
月工資;
B.如果工程款未按合同支付時(shí),將在每月30日支付勞務(wù)人員生活費(fèi)850
元;
C.在節(jié)假日和學(xué)生開(kāi)學(xué)前,將支付勞務(wù)人員所完工程量的100%。
3.7施工組織
3.7.1施工區(qū)、段劃分
3.7.1.1施工區(qū)、段的劃分原則
整個(gè)標(biāo)段由二棟廠房和一棟綜合樓組成,施工時(shí),以各棟主體結(jié)構(gòu)施工
為主導(dǎo)工序。精心組織施工區(qū)域內(nèi),空間立體交叉有節(jié)奏流水作業(yè),做到工
序銜接緊密;安裝工程穿插于土建施工過(guò)程中,與土建工程施工交叉進(jìn)行。
3.7.1.2施工區(qū)、段劃分
按照設(shè)計(jì)圖中建筑物的布局,結(jié)合結(jié)構(gòu)的設(shè)計(jì)劃分施工區(qū)段,為保證工
期將整個(gè)標(biāo)段劃分成二大施工區(qū)域(4#及5#廠房、綜合樓),組織二班人馬,
進(jìn)行平行作業(yè)。以便各施工區(qū)內(nèi)部產(chǎn)生流水,縮短工期。
3.7.2施工順序
第一施工區(qū)(4#及5#廠房)一第二施工區(qū)(綜合樓)
3.7.2.2施工段的施工順序
按分部分項(xiàng)工程組織流水施工,其順序?yàn)椋憾ㄎ环啪€一土方開(kāi)挖一基礎(chǔ)
模板、鋼筋、商品碎一主體結(jié)構(gòu)模板、鋼筋、商品稅~砌體結(jié)構(gòu)一屋面防水
一門(mén)窗f內(nèi)裝飾一外裝飾f樓地面f安裝工程f室外一竣工
施工順序的穿插
主體結(jié)構(gòu)一層模板拆除后,即可穿插內(nèi)部結(jié)構(gòu)及安裝工程的施工,以減
少空間和時(shí)間上的損失,確保項(xiàng)目建設(shè)工期。每一個(gè)施工段均本著“先地下
后地上”、“先土建后安裝”“先主體后裝修”的原貝!組織施工。
每一階段都必須完成規(guī)定的工作內(nèi)容,為下一階段創(chuàng)造條件。
安裝工程的插入應(yīng)遵循的原則為:先土建后安裝,先主管后支管,在土建施
工主體時(shí),預(yù)留、預(yù)埋好預(yù)埋洞、預(yù)埋件。下部可穿插施工一些給水的施工,
土建室內(nèi)裝修的同時(shí),安裝全面進(jìn)入安裝階段。
3.8資源配置
3.8.1勞動(dòng)力安排計(jì)劃
根據(jù)本工程施工需要,由人勞部對(duì)作業(yè)人員從技能、責(zé)任心、工作經(jīng)驗(yàn)、
身體素質(zhì)、持證情況等方面選擇合格勞動(dòng)力,及時(shí)組織進(jìn)行施工,人勞部必須
在工程開(kāi)工前落實(shí)作業(yè)人員。特殊作業(yè)人員必須持有效證件方能上崗,持證率
100%,必要時(shí)進(jìn)行考試,做到好中選優(yōu)。
3.8.1.1勞動(dòng)力投入計(jì)劃
根據(jù)工程的結(jié)構(gòu)形式、建筑構(gòu)造和工作量及工期要求,編制勞動(dòng)力投入計(jì)
劃。
3.8.1.2勞動(dòng)力進(jìn)場(chǎng)計(jì)劃
根據(jù)施工進(jìn)度網(wǎng)絡(luò)計(jì)劃要求編制勞動(dòng)力投入計(jì)劃,按勞動(dòng)力投入計(jì)劃及時(shí)
組織作業(yè)人員進(jìn)入施工現(xiàn)場(chǎng)。
主要?jiǎng)趧?dòng)力投入計(jì)劃表
按工程施工階段投入勞動(dòng)力情況
工種基礎(chǔ)主體裝修、安裝
施工階段施工階段施工階段收尾階段
木工3050105
碎工3045205
瓦工15301510
抹灰工254010
鋼筋工303052
架子工420105
動(dòng)力司機(jī)4664
電工620206
油漆工004015
焊工4442
起重工3330
水工210106
調(diào)試工0004
普工15303015
合/p>
3.8.1.3人員培訓(xùn)教育
對(duì)參加施工的作業(yè)人員及時(shí)進(jìn)行進(jìn)場(chǎng)三級(jí)教育。
培訓(xùn)后進(jìn)行書(shū)面測(cè)試,合格后方可上崗作業(yè)。
3.8.2工程投入的主要施工機(jī)械設(shè)備安排計(jì)劃
根據(jù)本工程施工的結(jié)構(gòu)類(lèi)型特點(diǎn),配置合適的大、中、小型施工機(jī)械設(shè)備,
以滿足工程進(jìn)度的需要。
3.8.2.1垂直運(yùn)輸設(shè)備
現(xiàn)場(chǎng)設(shè)置2臺(tái)QTZ40固定式塔吊負(fù)責(zé)工程施工的垂直運(yùn)輸。同時(shí)負(fù)責(zé)鋼筋
原材和模板半成品的吊運(yùn)。
廠房主體碎施工到封頂、綜合樓主體碎施工到二層后在4#廠房和綜合樓附
近各安裝井架各一臺(tái),以滿足填充材料等小型材料上下。
為滿足施工及進(jìn)度要求,碎澆筑采用碎固定泵泵送。
3.8.2.2水平運(yùn)輸設(shè)備
?配備FC-1型機(jī)動(dòng)翻斗車(chē)1臺(tái),負(fù)責(zé)砂漿,碎及零星建材的運(yùn)輸。
?配備12t自卸車(chē)2輛,負(fù)責(zé)砂、石等建材的運(yùn)輸。
?樓層內(nèi)水平運(yùn)輸采用手推架子車(chē)。
3.8.2.3土方機(jī)械設(shè)備
配備履帶式反鏟挖土機(jī)0.5m3二臺(tái)進(jìn)行土方開(kāi)挖;在清槽施
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 8 古詩(shī)二首《登鸛雀樓》(說(shuō)課稿)-2024-2025學(xué)年統(tǒng)編版語(yǔ)文二年級(jí)上冊(cè)
- 2024-2025學(xué)年新教材高中生物 第一章 孟德?tīng)柖?第二節(jié) 孟德?tīng)枏膬蓪?duì)相對(duì)性狀的雜交實(shí)驗(yàn)中總結(jié)出自由組合定律說(shuō)課稿(1)浙科版必修2
- 2016七年級(jí)信息技術(shù)上冊(cè) 第9課 制作電子表格說(shuō)課稿 新人教版
- 二零二五年度析產(chǎn)協(xié)議范本:知識(shí)產(chǎn)權(quán)分配3篇
- 2023四年級(jí)語(yǔ)文下冊(cè) 第六單元 口語(yǔ)交際:朋友相處的秘訣(新學(xué)習(xí)單)說(shuō)課稿 新人教版
- 二零二五年度荒溝水域資源開(kāi)發(fā)承包合作協(xié)議
- 13人物描寫(xiě)一組《摔跤》說(shuō)課稿-2023-2024學(xué)年統(tǒng)編版語(yǔ)文五年級(jí)下冊(cè)
- 二零二五年度高端醫(yī)療影像設(shè)備租賃與維護(hù)一體化合同2篇
- 2024-2025學(xué)年新教材高中英語(yǔ) Unit 1 Knowing me Knowing you理解 課文精研讀說(shuō)課稿 外研版必修第三冊(cè)
- 2023一年級(jí)數(shù)學(xué)下冊(cè) 六 小小存錢(qián)罐-人民幣的認(rèn)識(shí)信息窗1 -認(rèn)識(shí)人民幣說(shuō)課稿 青島版六三制
- 《梅大高速茶陽(yáng)路段“5·1”塌方災(zāi)害調(diào)查評(píng)估報(bào)告》專(zhuān)題警示學(xué)習(xí)
- 2024年09月北京中信銀行北京分行社會(huì)招考(917)筆試歷年參考題庫(kù)附帶答案詳解
- 《大健康解讀》課件
- 2025年度交通運(yùn)輸規(guī)劃外聘專(zhuān)家咨詢協(xié)議3篇
- 2024年公司領(lǐng)導(dǎo)在新年動(dòng)員會(huì)上的講話樣本(3篇)
- 2025年中國(guó)濕度傳感器行業(yè)深度分析、投資前景、趨勢(shì)預(yù)測(cè)報(bào)告(智研咨詢)
- 人教版道德與法治二年級(jí)下冊(cè)《第一單元 讓我試試看》大單元整體教學(xué)設(shè)計(jì)2022課標(biāo)
- 聯(lián)合體三方協(xié)議合同模板
- 2024年3季度青島房地產(chǎn)市場(chǎng)季度簡(jiǎn)報(bào)
- 蘇東坡詞十首
- 2023年天津市文化和旅游局直屬事業(yè)單位招聘考試真題及答案
評(píng)論
0/150
提交評(píng)論