大橋建設(shè)工程
橋面系及附屬工程施工方案
(格式最終版)
編制單位:中建x局第一建設(shè)有限公司
編制人:
日期:2023.6
目錄
第一章編制依據(jù).............................................................................................................1
1.1編制依據(jù)...................................................................................................................1
1.2編制范圍...................................................................................................................1
1.3編制原則...................................................................................................................1
1.3.1確保工期.........................................................................................................1
1.3.2質(zhì)量控制.........................................................................................................2
1.3.3安全第一、預(yù)防為主......................................................................................2
1.3.4文明施工.........................................................................................................2
第二章工程概況.............................................................................................................2
2.1工程概況...................................................................................................................2
2.2技術(shù)標準...................................................................................................................2
2.3橋梁參數(shù)...................................................................................................................3
第三章施工安排.............................................................................................................3
3.1施工組織機構(gòu)...........................................................................................................4
3.2施工管理人員...........................................................................................................4
3.3項目管理目標...........................................................................................................6
第四章施工進度計劃.....................................................................................................6
4.1施工工期安排...........................................................................................................6
第五章施工準備與資源配置計劃...................................................................................6
5.1施工準備...................................................................................................................6
5.1.1技術(shù)準備.........................................................................................................6
5.1.2現(xiàn)場準備.........................................................................................................7
5.2資源配置...................................................................................................................8
5.2.1勞動力組織.....................................................................................................8
5.2.2機械設(shè)備.........................................................................................................8
5.2.3主要周轉(zhuǎn)材料準備..........................................................................................8
第六章施工方法及工藝要求..........................................................................................9
6.1金屬梁柱式護欄施工...............................................................................................9
6.1.1施工工藝流程.................................................................................................9
I
6.1.2金屬梁柱式護欄施工....................................................................................10
6.1.3質(zhì)量控制標準...............................................................................................11
6.2橋面鋪裝施工.........................................................................................................11
6.2.1施工工藝流程...............................................................................................11
6.2.2施工方法.......................................................................................................12
6.2.3實測項目.......................................................................................................19
6.3橋面防水層施工.....................................................................................................20
6.3.1施工材料技術(shù)參數(shù).......................................................................................20
6.3.2防水層施工...................................................................................................20
6.4橋頭搭板施工.........................................................................................................21
6.4.1施工工藝流程...............................................................................................21
6.4.2施工工藝及方法...........................................................................................21
6.5關(guān)鍵及特殊過程控制.............................................................................................23
第七章綠色施工措施...................................................................................................23
7.1環(huán)境保護及文明施工管理措施..............................................................................23
7.1.1環(huán)境保護及文明施工管理原則....................................................................23
7.1.2環(huán)境保護主要控制措施................................................................................23
7.2資源利用管理.........................................................................................................24
7.2.1資源利用管理目標.......................................................................................24
7.2.2資源利用管理機構(gòu)和職責(zé)分工....................................................................24
7.3“五節(jié)”實施措施......................................................................................................26
7.3.1節(jié)能措施.......................................................................................................26
7.3.2節(jié)材措施.......................................................................................................26
7.3.3節(jié)水措施.......................................................................................................26
7.3.4節(jié)地措施.......................................................................................................26
7.3.5人力節(jié)約措施...............................................................................................27
第八章工期保證措施...................................................................................................27
8.1工期保證體系.........................................................................................................27
8.2施工進度管理組織機構(gòu)和職責(zé)分工......................................................................28
8.3工期保證措施.........................................................................................................29
II
第九章質(zhì)量保證措施...................................................................................................30
9.1質(zhì)量目標.................................................................................................................30
9.2質(zhì)量管理的組織機構(gòu)和職責(zé)分工..........................................................................30
9.3質(zhì)量保證體系.........................................................................................................31
9.4質(zhì)量保證措施.........................................................................................................33
9.4.1組織措施.......................................................................................................33
9.4.2管理措施.......................................................................................................33
第十章安全文明施工措施............................................................................................33
10.1職業(yè)健康安全管理目標........................................................................................33
10.2建立安全組織機構(gòu),明確安全職責(zé)和權(quán)限........................................................33
10.3施工現(xiàn)場安全生產(chǎn)管理制度................................................................................35
10.3.1班前活動記錄.............................................................................................35
10.3.2機械設(shè)備管理制度.....................................................................................36
10.3.3特種作業(yè)持證上崗制度..............................................................................37
10.3.4安全設(shè)施、設(shè)備驗收制度..........................................................................37
10.4安全保證措施.......................................................................................................38
10.4.1施工人員安全保證措施..............................................................................38
10.4.2施工機械安全保證措施..............................................................................39
第十一章成品保護措施................................................................................................40
11.1成立成品保護管理機構(gòu)........................................................................................40
11.2一般規(guī)定...............................................................................................................40
11.3具體保護措施.......................................................................................................40
11.3.1橋面系工程成品保護..................................................................................40
11.3.2防水工程成品保護.....................................................................................41
第十二章應(yīng)急預(yù)案.......................................................................................................41
12.1危險源與風(fēng)險分析...............................................................................................41
12.2應(yīng)急組織機構(gòu)及職責(zé)...........................................................................................42
12.3預(yù)防與預(yù)警措施...................................................................................................44
12.4應(yīng)急響應(yīng)...............................................................................................................45
12.5信息發(fā)布...............................................................................................................47
III
12.6后期處置...............................................................................................................47
12.7保障措施...............................................................................................................48
12.8應(yīng)急救援路線.......................................................................................................50
第十三章新型冠狀病毒肺炎疫情防控預(yù)案..................................................................50
13.1風(fēng)險分析...............................................................................................................50
13.2防護及救援組織機構(gòu)及職責(zé)................................................................................51
13.3預(yù)防疫情防控措施...............................................................................................53
13.4監(jiān)測與預(yù)警...........................................................................................................54
13.5救援響應(yīng)...............................................................................................................55
13.6后期處置...............................................................................................................56
13.7救援保障...............................................................................................................57
IV
大橋建設(shè)工程橋面系及附屬工程施工方案
第一章編制依據(jù)
1.1編制依據(jù)
表1.1編制依據(jù)
序
類別文件名稱編號
號
1中華人民共和國安全生產(chǎn)法/
2法律法規(guī)、中華人民共和國環(huán)境保護法/
3行政文件建設(shè)工程質(zhì)量管理條例/
4新型冠狀病毒肺炎診療方案(試行第八版)
5公路橋涵施工技術(shù)規(guī)范JTG/T3650-2020
6混凝土結(jié)構(gòu)工程施工質(zhì)量驗收規(guī)范GB50204-2015
7建筑施工安全檢查標準JGJ59-2011
8組合鋼模板技術(shù)規(guī)范GB/T50214-2013
9鋼筋焊接及驗收規(guī)程JGJ18-2012
10行業(yè)規(guī)范公路橋梁伸縮裝置通用技術(shù)條件JT/T327-2016
11公路工程質(zhì)量檢驗評定標準第一冊土建工程JTGF80/1-2017
12公路瀝青路面設(shè)計規(guī)范JTGD50-2017
13公路工程施工安全技術(shù)規(guī)范JTGF90-2015
14公路瀝青路面施工技術(shù)規(guī)范JTGF40-2004
15公路交通安全設(shè)施施工技術(shù)規(guī)范JTG/T3671-2021
16設(shè)計文件淄博市孝婦河生態(tài)修復(fù)項目xx大橋建設(shè)工程圖紙
17其他xx大橋建設(shè)工程實施性施工組織設(shè)計
1.2編制范圍
本方案適用于淄博xx大橋建設(shè)工程橋面系及附屬工程施工。
1.3編制原則
施工方案應(yīng)滿足設(shè)計要求、技術(shù)標準、規(guī)范、規(guī)程并滿足施工現(xiàn)場實際施工需要。
以確保工程安全、優(yōu)質(zhì)、按期完成。
1.3.1確保工期
根據(jù)本工程的特點和要求,在保證質(zhì)量、安全可靠的前提下合理安排施工工序,優(yōu)
化施工組織,各工序緊密銜接,避免不必要的重復(fù)工作,以保證施工連續(xù)均衡有序地進
行,確保施工工期按計劃節(jié)點完成,力爭提前完成。
1
大橋建設(shè)工程橋面系及附屬工程施工方案
1.3.2質(zhì)量控制
確立質(zhì)量目標、制定創(chuàng)優(yōu)規(guī)劃、嚴格按照質(zhì)量體系運作,以工作質(zhì)量確保每道工序
和每項工程的工程質(zhì)量。
1.3.3安全第一、預(yù)防為主
確立安全工作目標、完善規(guī)章制度、層層簽訂安全生產(chǎn)責(zé)任狀,強化安全教育和安
全管理,狠抓現(xiàn)場各項規(guī)章制度、措施的落實,確保安全生產(chǎn)目標的實現(xiàn)。
1.3.4文明施工
堅持自始至終對施工現(xiàn)場的全過程進行嚴密監(jiān)控,以科學(xué)的方法實行動態(tài)管理,并
按動、靜結(jié)合的方法精心布置和規(guī)劃施工現(xiàn)場,保護周圍環(huán)境。嚴格施工管理,開展文
明施工活動,做到文明施工,爭創(chuàng)標準化施工現(xiàn)場。
第二章工程概況
2.1工程概況
表2.1工程概況
大橋建設(shè)工程橋面系及附屬
工程名稱工程性質(zhì)市政
工程
建設(shè)規(guī)模橋梁全長167.04工程地址山東省淄博市
橋梁跨徑組合為8×20m
裝配式預(yù)應(yīng)力混凝土簡支
項目承包范
建設(shè)單位空心板,橋面連續(xù);橋
圍
墩、橋臺采用柱式墩,樁
基礎(chǔ);橋梁全長167.04m
主要分包工
設(shè)計單位/
程
勘察單位質(zhì)量合格
合同
監(jiān)理單位工期自開工令下發(fā)后1000天
要求
總承包單位中建x局第一建設(shè)有限公司安全淄博市安全文明示范工地
工程主要功
橋梁
能
2.2技術(shù)標準
(1)設(shè)計基準期:100年
(2)安全等級:一級
(3)橋涵設(shè)計荷載:汽車荷載取城-A級,人群荷載取5kPa
2
大橋建設(shè)工程橋面系及附屬工程施工方案
(4)橋涵設(shè)計洪水頻率:1/100
(5)通航等級:孝婦河無通航要求
(6)橋梁所處環(huán)境類別:Ⅱ類環(huán)境
(7)橋梁設(shè)計使用年限:100年
(8)地震基本烈度:7度;地震動峰值加速度為0.1g。
(9)標準橫斷面:0.5m金屬梁柱式護欄+3.5m人行道+15m車行道+3.5m人行道
+0.5m金屬梁柱式護欄=23m
圖2.2上部結(jié)構(gòu)標準斷面圖
2.3橋梁參數(shù)
表2.3橋梁設(shè)計參數(shù)
梁板
序結(jié)構(gòu)物名跨徑角度橋長
樁號結(jié)構(gòu)物樁號長度
號稱(m)(°)(m)
(m)
K0+2
56.48
K0+256.48~K0+44*20+4*
1~K0+xx大橋9020167.04
23.5220
423.5
2
第三章施工安排
3.1施工組織機構(gòu)
為完成本工程任務(wù),加強項目施工標準化管理,確保工程建設(shè)工期、質(zhì)量、安全目
3
大橋建設(shè)工程橋面系及附屬工程施工方案
標,由項目經(jīng)理部總負責(zé),技術(shù)部、商務(wù)部、安全部、質(zhì)量部、工程部、測量部、物資
部、綜合辦公室、試驗室共9個職能部室配合,現(xiàn)場專業(yè)工程師進行管理及協(xié)調(diào)工作。
橋面系及附屬工程施工組織機構(gòu)如圖3.1:
項目經(jīng)理
生產(chǎn)經(jīng)理項目總工商務(wù)經(jīng)理
綜
技商安質(zhì)工物合試測
術(shù)務(wù)全量程資辦驗量
部部部部部部公室部
室
橋面系及附屬工
程施工隊伍
圖3.1橋面系及附屬工程施工組織機構(gòu)
3.2施工管理人員
施工管理人員配備見表3.2。
表3.2施工管理人員配置及職責(zé)
序號職務(wù)職責(zé)
1)負責(zé)項目施工、竣工驗收、試運行和保修等階段的組織實施、
指揮和管理工作。
1項目經(jīng)理
2)建立完善的項目運行管理體系,制定項目管理各項辦法和規(guī)章
制度,負責(zé)項目經(jīng)理部的各項管理工作。
1)全面負責(zé)橋面系和附屬工程施工現(xiàn)場的人員安排,材料、機械
設(shè)備的調(diào)動等施工組織工作。
2生產(chǎn)經(jīng)理
2)抓好施工中的質(zhì)量、安全、工期和現(xiàn)場管理工作,處理施工中
出現(xiàn)的具體問題。
4
大橋建設(shè)工程橋面系及附屬工程施工方案
序號職務(wù)職責(zé)
3)負責(zé)永久征地和臨時用地工作,提供可靠的征拆數(shù)據(jù)資料。
4)協(xié)助地方土地部門負責(zé)土地丈量、政策宣傳和處理工作,及時
掌握補償資金發(fā)放情況以及相關(guān)特殊問題的處理情況。
1)全面負責(zé)橋面系和附屬工程施工的技術(shù)管理工作。
2)組織解決施工中的關(guān)鍵技術(shù)和重大技術(shù)問題,負責(zé)新技術(shù)、新
4項目總工
工藝、新設(shè)備、新材料以及先進技術(shù)成果的應(yīng)用,有效開展技術(shù)管
理工作。
1)組織商務(wù)合同交底,組織招標工作。
2)組織報價審核、合同簽訂、合同管理及結(jié)算工作。
5商務(wù)經(jīng)理
3)掌握施工動態(tài),及時進行成本分析,為施工提供決策依據(jù);及
時組織和辦理索賠簽證工作,收回費用。
1)負責(zé)工程項目施工過程控制,負責(zé)施工進度管理。
2)負責(zé)工程技術(shù)調(diào)查、圖紙審核、現(xiàn)場核對、技術(shù)交底、變更設(shè)
計、技術(shù)創(chuàng)新、施工資料、技術(shù)總結(jié)、竣工文件編制等工作,解決
6技術(shù)部
施工技術(shù)疑難問題。
3)負責(zé)對新技術(shù)、新工藝、新材料、新設(shè)備“四新”成果和工法
進行研究、引進、吸收、推廣和應(yīng)用。
1)定期或不定期組織實施安全檢查,及時糾正違反安全生產(chǎn)規(guī)定
及違反施工程序、規(guī)程、規(guī)范行為,及時下發(fā)安全問題整改通知單,
7安全部責(zé)令有關(guān)單位和人員制定糾正和預(yù)防措施,并驗證其整改情況。
2)建立健全環(huán)保責(zé)任體系,制定環(huán)保、水保規(guī)劃及措施,并檢查
監(jiān)督貫徹落實情況。
1)指導(dǎo)QC小組活動,推薦QC小組參加上級成果鑒定與發(fā)布。負
責(zé)優(yōu)質(zhì)工程的申報和質(zhì)量情況反饋。
8質(zhì)量部
2)組織開展質(zhì)量評比,推廣先進經(jīng)驗,參與質(zhì)量事故調(diào)查處理,
提出改進意見并監(jiān)督落實。
1)負責(zé)物資采購和物資管理及制定項目物資管理辦法,檢查指導(dǎo)
和考核施工隊的物資采購和管理工作。
9物資部
2)根據(jù)業(yè)主的物資供應(yīng)方案,按時上報主要物資申請計劃,在現(xiàn)
場進行物資的驗收、現(xiàn)場物資信息的反饋,確保施工生產(chǎn)需要。
1)協(xié)調(diào)各部門之間的關(guān)系,促進各項工作順利進行。
10辦公室
2)負責(zé)工作、生活場所和辦公、生活設(shè)施、用品管理。
1)負責(zé)施工計劃制定、實施管理,按期上報各種報表,做好計劃
保障、調(diào)整工作。
2)負責(zé)對外合同的保管,完善內(nèi)部合同管理。
3)負責(zé)驗工計價、成本核算。
11商務(wù)部4)集中管理項目資金,做好資金預(yù)測,籌集資金,催收拖欠的工
程款,合理使用和調(diào)度資金,配合有關(guān)部門做好驗工計價與工程價
款的結(jié)算工作。
5)參與經(jīng)濟合同的簽訂,并嚴格執(zhí)行合同條款,杜絕失誤。
6)對項目各施工隊的財會工作進行檢查、監(jiān)督與指導(dǎo)。
1)負責(zé)檢驗、試驗、交驗及不合格品的檢驗控制,按檢驗評定標
13試驗室準對施工過程實施監(jiān)督并對檢驗結(jié)果負責(zé)。
2)負責(zé)現(xiàn)場各種原材料試件和混凝土試件的樣品采集和測試、檢
5
大橋建設(shè)工程橋面系及附屬工程施工方案
序號職務(wù)職責(zé)
驗及質(zhì)量記錄。
3)負責(zé)計量測試工作,負責(zé)檢驗、試驗設(shè)備的核定、校準及使用
管理工作。
1)負責(zé)按照項目部制定的施工組織設(shè)計和施工計劃,制定工區(qū)單
位工程施工組織計劃,合理組織資源,安排工序銜接,按期保質(zhì)完
14工程部
成項目部下達的生產(chǎn)任務(wù)。
2)負責(zé)現(xiàn)場的施工安全、質(zhì)量、環(huán)保及職業(yè)健康控制。
15測量部負責(zé)日常施工測量、精測任務(wù)以及相關(guān)的測量管理工作。
3.3項目管理目標
表3.3管理目標
序號項目管理目標名稱目標值
計劃施工日期:2022年3月10日~2022年4月29計劃工期:
1工期管理
51天
1)標段工程交工驗收的質(zhì)量評定:合格;
2質(zhì)量管理
2)竣工驗收的質(zhì)量評定:優(yōu)良。
3安全管理項目實施中無安全責(zé)任事故發(fā)生。
4成本控制合理控制施工成本,實現(xiàn)效益最大化。
嚴格落實綠色施工各項控制措施,施工現(xiàn)場揚塵、噪聲、污水、
廢棄物排放等控制指標符合國家和山東省環(huán)??刂茦藴?。逐步
5綠色施工
降低自然資源消耗,積極應(yīng)用“四新”技術(shù),維護生態(tài)環(huán)境,
促進社會、經(jīng)濟、生態(tài)可持續(xù)發(fā)展。
第四章施工進度計劃
4.1施工工期安排
橋面系及附屬工程計劃于2022年3月10開工,2022年4月29日全部完成,工期51
天。
第五章施工準備與資源配置計劃
5.1施工準備
5.1.1技術(shù)準備
1圖紙復(fù)核
熟悉施工圖紙并對圖紙進行復(fù)核,結(jié)合圖紙和實際情況進行施工方案的制定和各種
技術(shù)準備工作。
6
大橋建設(shè)工程橋面系及附屬工程施工方案
2入場安全教育
項目部組織有關(guān)技術(shù)、安全管理人員向施工隊長、班組長及所有橋面系及附屬工程
施工人員進行入場安全教育。
3施工技術(shù)、安全交底
項目總工程師組織有關(guān)技術(shù)、安全管理人員向施工隊長、班組長進行技術(shù)交底、安
全交底,再由專業(yè)工程師向所有橋面系及附屬工程施工人員進行技術(shù)交底、安全交底,
并履行簽字手續(xù)。
4測量準備
橋面系及附屬工程正式施工前,測量班進行放樣,并向監(jiān)理工程師報驗,形成測量
放樣資料。
5試驗準備
試驗室提前對混凝土配合比等進行試驗檢測,嚴格依照試驗數(shù)據(jù)確定使用材料,確
保達到設(shè)計要求。
對各種進場材料進行試驗檢測,確保進場材料合格。
5.1.2現(xiàn)場準備
1施工便道
按照施工便道方案布置好現(xiàn)場內(nèi)的道路,并結(jié)合周邊既有路網(wǎng)進出場。
2施工用水用電
施工用水采用經(jīng)檢驗合格的地表水和地下水相結(jié)合;施工用電從現(xiàn)場已形成的電網(wǎng)
提供。
3現(xiàn)場布置及臨時圍擋設(shè)置
道路交叉部位設(shè)置安全警示裝置,在車輛行駛的前方設(shè)置指示方向和減速慢行的標
志,施工區(qū)域進行封閉隔離,并安排專職人員進行管理。
施工現(xiàn)場設(shè)置相應(yīng)的安全警示標志,如必須戴安全帽、當(dāng)心觸電、禁止跨越、注意
安全、請勿靠近等警示牌及工藝流程圖、安全操作規(guī)程等圖表。
4臨時設(shè)施
施工隊伍進場后租用民房作為臨時設(shè)施,包括辦公室、食堂、宿舍、倉庫等,并由
項目部相關(guān)人員檢查驗收滿足要求后方可使用。
5交通組織措施
跨既有道路橋面系及附屬工程施工前應(yīng)做好交通組織措施,確保道路暢通和行車安
7
大橋建設(shè)工程橋面系及附屬工程施工方案
全。
5.2資源配置
5.2.1勞動力組織
表5.2.1勞動力配置計劃
序號工種名稱計劃人數(shù)
1普工50
2電工2
3測量工3
4木工10
5電焊工3
6鋼筋工10
7砼工10
8機操工10
5.2.2機械設(shè)備
表5.2.2機械設(shè)備配置
序號機械名稱型號規(guī)格數(shù)量
1砼罐車東風(fēng)8
2插入式震搗棒ZN5010
3木工電刨MIB2-80/13
4木工圓鋸MJ1043
5切槽機3
6交流電焊機BQ3-200-28
7灑水車SEQ51302
8平板振動器ZW-3.55
9汽車泵EM32/36-44
10混凝土磨光機HZM-806
11彎管機PDI-DW38CNC3
5.2.3主要周轉(zhuǎn)材料準備
表5.2.3主要周轉(zhuǎn)材料
序號材料名稱單位數(shù)量負責(zé)人
1木模板15mm厚m25000殷光建
2木枋20×10m3100殷光建
8
大橋建設(shè)工程橋面系及附屬工程施工方案
序號材料名稱單位數(shù)量負責(zé)人
3鋼管48.3×3.6t40殷光建
4鋼板12mm厚t15殷光建
5安全網(wǎng)m210000殷光建
6塑料布m2200殷光建
7泡沫板m500殷光建
88#槽鋼m700殷光建
9臨邊防護m400殷光建
第六章施工方法及工藝要求
6.1金屬梁柱式護欄施工
6.1.1施工工藝流程
施工準備
測量放線護攔板材料成型加工
法蘭立柱安裝護攔板材料進場驗收
立柱調(diào)整線形
護欄橫梁安裝采取補救措施
護欄橫梁線性調(diào)整返工
現(xiàn)場驗收清理現(xiàn)場
進行移交
圖6.1.1施工工藝流程
6.1.2金屬梁柱式護欄施工
一、施工方法
9
大橋建設(shè)工程橋面系及附屬工程施工方案
1、橋梁護欄制作與安裝施工要求
項目技術(shù)負責(zé)人熟悉圖紙、了解施工工藝及施工方法,對施工人員進行技術(shù)交底,
明確有關(guān)的技術(shù)資料及工程質(zhì)量要求。
熟悉施工工藝及有關(guān)技術(shù)文件,按施工計劃向安裝組進行施工任務(wù)交底,強調(diào)維護
大局利益完成任務(wù)的意識觀念。
安裝時應(yīng)按設(shè)計紙的水平標高和平面位置放線,注意欄桿與其它飾面工程的收口。
2、橋梁護欄成品制作工藝流程如下:
橋梁護欄工藝流程:甲方圖紙確認(包括規(guī)格、尺寸、顏色、安裝尺寸)→進料→放樣→
開料→酸洗磷化→表調(diào)→中和→水洗→焊接拼裝→半成品→細磨打砂→鍍鋅→整體調(diào)
正→靜電噴涂→烤漆→成品→檢驗→簡易包裝→運輸現(xiàn)場→通知甲方驗收→安裝(法蘭
蓋、膨脹螺栓連接、焊接)→檢查補漆→清理現(xiàn)場→報請甲方驗收→辦理移交手續(xù)→移交
甲方管理。
3、橋梁護欄安裝的工藝流程如下
搬運到位→彈控制線→定安裝位→校正固定→焊接→膨脹螺栓連接→自檢補漆→
完成安裝
4、橋梁護欄制作施工工藝要求:
焊接焊縫牢固可靠,承載構(gòu)件的結(jié)合部位要求為連續(xù)焊縫(滿
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024萬科物業(yè)合同范本涉及社區(qū)垃圾分類與回收利用3篇
- 2024年度托管班教師信息技術(shù)應(yīng)用能力提升聘用合同3篇
- 2024烏魯木齊房屋租賃合同:租客租后維修責(zé)任協(xié)議3篇
- 2024年地毯新產(chǎn)品推廣營銷合同范本3篇
- 新疆警察學(xué)院《測控系統(tǒng)設(shè)計基礎(chǔ)訓(xùn)練》2023-2024學(xué)年第一學(xué)期期末試卷
- 人教版凡爾賽-課件
- 2024年二級造價師考試題庫帶答案1
- 公司簽居間合同范例
- 打樁地基施工合同范例
- 銷售賣貨合同范例
- 新一代反洗錢監(jiān)測分析系統(tǒng)操作手冊all
- CCEA GC 11-2019 工程造價咨詢企業(yè)服務(wù)清單
- 農(nóng)業(yè)比較效益低的成因及應(yīng)對
- 2020年住房和城鄉(xiāng)建設(shè)行業(yè)人員繼續(xù)教育(八大員繼續(xù)教育)土建質(zhì)量員繼續(xù)教育考試題庫集
- 直觀教具在小學(xué)英語詞匯教學(xué)中的運用初探
- 《制冷設(shè)備原理與維修》期末試卷試題及參考答案
- 供水管道工程現(xiàn)場管理辦法
- 酒店委托管理模式下的財務(wù)治理
- 簡單員工考勤表
- 新年賀卡模板
- 國家開放大學(xué)《管理英語4》章節(jié)測試參考答案
評論
0/150
提交評論