項目專項施工方案
片區(qū)雨污分流(二期)工程施工
機(jī)械頂管專項施工方案
編制:
審核:
審批:
日期:
1
項目專項施工方案
目錄
第1章工程概況.................................................................................................1
1.1工程建設(shè)概況一覽表............................................................................1
1.2設(shè)計概況................................................................................................1
1.2.1中心街(北極宮大街-秦漢大道)............................................1
1.2.2中心街(吉元大街~北極宮大街)...........................................2
1.2.3涇干大街.....................................................................................2
1.2.4南環(huán)路.........................................................................................3
1.2.5先鋒大街.....................................................................................4
1.2.6北極宮大街.................................................................................5
1.2.7秦漢大道.....................................................................................5
1.2.8秦星路.........................................................................................6
1.2.9崇文大街.....................................................................................7
1.2.10興隆大街...................................................................................8
1.3地質(zhì)概況................................................................................................9
1.4地下水..................................................................................................10
1.5設(shè)計參數(shù)..............................................................................................10
1.6現(xiàn)狀管線調(diào)查......................................................................................11
1.6.1管線調(diào)查摸排...........................................................................11
1.6.2中心街與秦星路.......................................................................12
1.6.3秦漢大道...................................................................................12
1.6.4北極宮大街...............................................................................13
1.6.5先鋒大街...................................................................................13
1.6.6崇文大街...................................................................................13
1.6.7涇干大街...................................................................................13
1.6.8南環(huán)路.......................................................................................13
1.6.9興隆大街...................................................................................13
第2章編制依據(jù)...............................................................................................13
2.1施工平面圖..........................................................................................14
第3章施工計劃...............................................................................................16
3.1主要機(jī)械設(shè)備計劃..............................................................................16
3.2主要材料計劃......................................................................................17
3.3施工進(jìn)度計劃......................................................................................18
第4章施工工藝技術(shù).......................................................................................18
4.1施工部署..............................................................................................18
2
項目專項施工方案
4.1.1施工圍擋...................................................................................18
4.1.2功能區(qū)劃分...............................................................................19
4.1.3安全爬梯設(shè)置...........................................................................20
4.1.4變壓器設(shè)置...............................................................................21
4.2頂管工藝選擇......................................................................................22
4.2.1頂管工藝的適用性...................................................................22
4.2.2泥水平衡頂管工作井平面布置示意圖...................................22
4.2.3土壓平衡頂管工作井平面布置示意圖...................................23
4.2.4接收井平面布置示意圖...........................................................23
4.3設(shè)備安裝..............................................................................................23
4.3.1主要設(shè)備...................................................................................23
4.3.2高程、中線放樣.......................................................................23
4.3.3導(dǎo)軌安裝...................................................................................24
4.3.4頂力估算...................................................................................24
4.3.5后背墻施工...............................................................................27
4.3.6主頂泵站及千斤頂安裝...........................................................28
4.3.7洞口止水圈...............................................................................29
4.3.8機(jī)頭安裝...................................................................................29
4.4頂管施工工藝流程..............................................................................30
4.5泥水平衡頂管施工..............................................................................30
4.5.1泥水平衡頂管施工原理...........................................................30
4.5.2泥水平衡頂管示意...................................................................31
4.5.3泥漿池.......................................................................................31
4.5.4頂進(jìn)設(shè)備調(diào)試...........................................................................31
4.5.5機(jī)頭進(jìn)出洞措施.......................................................................33
4.5.6初始頂進(jìn)...................................................................................34
4.5.7頂進(jìn)...........................................................................................34
4.6土壓平衡頂管施工..............................................................................35
4.6.1土壓平衡頂管示意...................................................................35
4.6.2頂進(jìn)設(shè)備調(diào)試...........................................................................35
4.6.3初始頂進(jìn)...................................................................................36
3
項目專項施工方案
4.6.4頂進(jìn)...........................................................................................36
4.6.5頂進(jìn)測量...................................................................................37
4.6.6頂進(jìn)糾偏...................................................................................37
4.6.7注漿減阻...................................................................................37
4.6.8管縫處理...................................................................................39
4.6.9頂管結(jié)束后地面探測...............................................................39
4.6.10機(jī)頭進(jìn)出洞口.........................................................................39
4.7管周壓漿..............................................................................................39
4.7.1工后壓注漿...............................................................................39
4.8吊裝方案..............................................................................................41
4.8.1180T吊車參數(shù)...........................................................................41
4.8.275T吊車參數(shù).............................................................................41
4.8.3汽車吊吊裝使用情況...............................................................42
4.8.4汽車吊施工組織流程...............................................................42
4.8.5吊裝準(zhǔn)備工作...........................................................................43
4.8.6吊運(yùn)步驟...................................................................................43
4.8.7吊裝方法...................................................................................44
4.8.8機(jī)頭吊裝...................................................................................45
4.8.9構(gòu)件、鋼材卸車.......................................................................47
4.8.10D2800mm機(jī)頭吊裝驗算........................................................49
第5章施工安全保證措施...............................................................................50
5.1組織保障措施.....................................................................................50
5.1.1安全制度...................................................................................51
5.1.2建立安全管理制度...................................................................53
5.1.3安全生產(chǎn)責(zé)任制.......................................................................53
5.1.4安全教育制度...........................................................................53
5.1.5安全檢查制度...........................................................................54
5.1.6施工現(xiàn)場安全管理制度...........................................................54
5.1.7安全工程師跟班作業(yè)制度.......................................................54
5.1.8安全警示制度...........................................................................54
5.1.9落實事故處理報告制度...........................................................54
4
項目專項施工方案
5.1.10班前安全活動.........................................................................55
5.1.11持證上崗制度.........................................................................55
5.1.12安全早會、安全周會制度.....................................................55
5.1.13日常管理制度.........................................................................55
5.1.14安全管理措施.........................................................................56
5.2技術(shù)措施.............................................................................................58
5.2.1基坑安全...................................................................................58
5.2.2臨邊防護(hù)措施...........................................................................58
5.2.3吊裝安全防護(hù)措施...................................................................59
5.2.4頂管施工安全措施...................................................................61
5.2.5地下有限空間作業(yè)安全措施...................................................63
5.2.6地下管線保護(hù)安全措施...........................................................64
5.2.7預(yù)防行車道路沉降塌陷安全技術(shù)措施...................................65
5.2.8臨近建筑物沉降變形...............................................................67
5.2.9交通行車...................................................................................67
5.2.10臨時用電方案.........................................................................74
5.2.11監(jiān)控監(jiān)測措施........................................................................81
第6章施工人員及作業(yè)人員配備及分工.......................................................87
6.1施工管理人員......................................................................................87
6.2專職安全生產(chǎn)管理人員......................................................................88
6.3一般作業(yè)人員......................................................................................88
6.4特種作業(yè)人員.....................................................................................88
第7章一危大工程驗收要求...........................................................................89
7.1驗收內(nèi)容..............................................................................................89
7.2驗收標(biāo)準(zhǔn)..............................................................................................89
7.3驗收程序..............................................................................................89
7.4驗收人員..............................................................................................90
第8章應(yīng)急處置措施.......................................................................................90
8.1應(yīng)急指揮機(jī)構(gòu)及職責(zé)..........................................................................90
8.2事故風(fēng)險分析......................................................................................91
8.3應(yīng)急救援程序......................................................................................93
8.4應(yīng)急處置措施......................................................................................93
8.4.1機(jī)械傷害應(yīng)急措施...................................................................93
8.4.2高空墜落、物體打擊應(yīng)急措施...............................................93
8.4.3傾覆事故...................................................................................94
5
項目專項施工方案
8.4.4坍塌應(yīng)急措施...........................................................................95
8.4.5地下管線應(yīng)急措施...................................................................95
8.4.6交通事故...................................................................................98
8.4.7觸電應(yīng)急措施...........................................................................98
8.4.8中暑事故...................................................................................99
8.4.9火災(zāi)應(yīng)急措施.........................................................................100
8.5應(yīng)急物資準(zhǔn)備....................................................................................101
第9章附件.....................................................................................................101
9.1附件1:施工進(jìn)度橫道圖.................................................................102
9.2附件2危險性較大的分部分項工程驗收簽到表............................107
6
項目專項施工方案
第1章工程概況
1.1工程建設(shè)概況一覽表
xx片區(qū)雨污分流(二
期)工程施工
總規(guī)劃面積612公頃主要工程量新建雨水、污水及現(xiàn)狀道路拆除、恢復(fù)
原點(diǎn)大道(吉元大街一金柳北街)、涇干大街
(吉元大街一秦漢大道)、橋北一路、北當(dāng)
巷、中心街(吉元大街一秦漢大道)、南環(huán)路
(吉元大街一秦漢大道)、吉元大街、興隆大
街(涇干大街一南環(huán)路以南)、龍泉路、金柳
建設(shè)單位項目承包范圍
北路、體育路、鐵門街、北極宮大街(至文廟
廣場)、秦星路(涇干大街一中心街)、崇文
大街(原點(diǎn)大道—涇干大街)、崇文大街(涇
干大街一南環(huán)路)、秦漢大道(原點(diǎn)大道—南
環(huán)路)、先鋒大街(南環(huán)路―文教大道)
設(shè)計單位質(zhì)量達(dá)到國家現(xiàn)行施工驗收規(guī)范“合格”標(biāo)準(zhǔn)
勘察單位工期總工期500日歷天
合同無死亡事故,工傷頻率控制在西咸新區(qū)及涇
監(jiān)理單位要求安全河新城建筑施工安全管理規(guī)定的指標(biāo)要求范
圍內(nèi)。達(dá)到“西咸新區(qū)安全文明工地”標(biāo)準(zhǔn)
中國建筑第八工程局發(fā)表論文6篇,省級QC成果1項;工法2
總承包單位科技
有限公司篇
1.2設(shè)計概況
1.2.1中心街(北極宮大街-秦漢大道)
中心街(北極宮大街—秦漢大道)本次新建d600~d1500mm雨水管道,保
留現(xiàn)狀d400~d600mm合流管道用做污水管道。
中心街(秦星路—崇文大街)段,設(shè)計YD4--Ycw14井段,設(shè)計管徑
d1500mm,長度417.2m,最大埋深約為6.4m。設(shè)計采用頂管施工。
設(shè)計頂管工作井2座,分別為YD5、YD7,頂管工作井平面凈尺寸為9.0×
6.0m;設(shè)計頂管接收井2座,分別為YD4、YD6,頂管接收井平面尺寸為6.0×
5.0m。均為鋼筋混凝土結(jié)構(gòu)。
Ycw14為頂管接收井,已計入崇文大街設(shè)計范圍內(nèi)。YD8為頂管后反開挖
修建的檢查井。
1
項目專項施工方案
1.2.2中心街(吉元大街~北極宮大街)
中心街(吉元大街—竹林路)段,雨水管道單排敷設(shè),分別自東西兩側(cè)向中
間排入興隆大街規(guī)劃雨水管道中,設(shè)計管徑d600—d1350mm,設(shè)計長度
1045m。最終沿興隆大街排入涇河1#雨水排出口。
其中YA12-YA13井段設(shè)計管徑d1350mm,設(shè)計長度120m,埋深5.8m左右,
設(shè)計采用頂管施工。頂管工作井平面凈尺寸為9.0×5.0m,頂管接收井平面尺寸
為5.0×4.0m。均為鋼筋混凝土結(jié)構(gòu);
1.2.3涇干大街
涇干大街(北極宮大街-秦漢大道段)本次新建一段d600mm污水管道和一
段d1800mm-d2000mm雨水管道,保留現(xiàn)狀d1650mm合流管道做為雨水管道及
局部d800mm合流管道作為污水管道。
根據(jù)《涇河新城雨水專項規(guī)劃》,本次涇干大街(北極宮大街-秦漢大道)
設(shè)計范圍內(nèi)雨水管道單排敷設(shè),雨水管道由西向東下游秦漢大道規(guī)劃雨水管道。
最終分別通過3#雨水出水口排入現(xiàn)狀涇河。設(shè)計管徑d1800mm~d2000mm,長
度1877m。
涇干大街(北極宮大街-秦漢大道段)現(xiàn)狀大管徑d1500mm-d1650mm合流
管道做為分流改造后的雨水管道,現(xiàn)狀雨水口需進(jìn)行封堵處理,雨水通過新建雨
水口排入本次新建雨水管道,達(dá)到雨污分流改造的目的。
YC1~YC4井段設(shè)計管徑d1800mm,設(shè)計長度153.4m,最大埋深7.8m。YC4-
2
項目專項施工方案
YC10設(shè)計管徑d2000mm,設(shè)計長度589.8m,最大埋深7.2m,YC2-YC10井段設(shè)
計采用頂管施工。
設(shè)計頂管工作井4座,分別為YC3、YC5、YC7、YC9,頂管工作井平面凈尺
寸為8.0×6.0m;設(shè)計頂管接收井4座,分別為YC2、YC4、YC6、YC8;YC4、
YC6、YC8頂管接收井平面凈尺寸為6.0×5.0m,YC2頂管接收井平面凈尺寸為5.0
×6.5m。均為鋼筋混凝土結(jié)構(gòu)。
1.2.4南環(huán)路
南環(huán)路(北極宮大街-秦漢大道)本次新建d500~d1800mm雨水管道,保留
現(xiàn)狀d500mm合流管道做為污水管道。
根據(jù)《涇河新城雨水專項規(guī)劃》,本次南環(huán)路(北極宮大街-秦漢大道)設(shè)
計范圍內(nèi)雨水管道單排敷設(shè),雨水管道由西向東排入秦漢大道規(guī)劃雨水管道。最
終排入涇河3#雨水排出口。設(shè)計管徑d500~d1800mm,長度1804m。
南環(huán)路(北極宮大街-秦漢大道)現(xiàn)狀合流管道做為分流改造后的污水管道,
現(xiàn)狀雨水口需進(jìn)行封堵處理,雨水通過新建雨水口排入本次新建雨水管道,達(dá)到
雨污分流改造的目的。
YC21~YC27(Yqh25)井段設(shè)計管徑d1800mm,設(shè)計長度578.9m,最大埋深
7.0m。設(shè)計采用頂管施工。
設(shè)計頂管工作井3座,分別為YC22、YC24、YC26,頂管工作井平面凈尺寸
為8.0×6.0m;設(shè)計頂管接收井3座,分別為YC21、YC23、YC25,頂管接收井平
面凈尺寸為6.0×5.0m。均為鋼筋混凝土結(jié)構(gòu)。
3
項目專項施工方案
1.2.5先鋒大街
先鋒大街本次新建一段d800mm污水管道和兩段d1650mm-d2800mm雨水
管道,保留現(xiàn)狀d2400mm合流管道做為雨水管道。
根據(jù)《涇河新城雨水專項規(guī)劃》,本次先鋒大街(南環(huán)路-文教大道)設(shè)計
范圍內(nèi)雨水管道單排敷設(shè),雨水管道由北向南排入先鋒大街現(xiàn)狀雨水管道。最終
排入涇河2#雨水排出口。設(shè)計管徑d1650~d2800mm,長度830m。
先鋒大街(南環(huán)路-文教大道)現(xiàn)狀大管徑d2400mm合流管道做為分流改
造后的雨水管道,現(xiàn)狀雨水口需進(jìn)行封堵處理,雨水通過新建雨水口排入本次新
建雨水管道,達(dá)到雨污分流改造的目的。
Y2-Y6井段設(shè)計管徑d2800mm,設(shè)計長度430.5m,最大埋深8.3m。設(shè)計采
用頂管施工。
設(shè)計頂管工作井2座,分別是Y3、Y5,頂管工作井平面凈尺寸為9.0×
6.0m;接收工作井3座,分別是Y2、Y4、Y6,頂管接收井平面尺寸為6.0×
5.0m;結(jié)構(gòu)形式均為鋼筋混凝土結(jié)構(gòu)。
4
項目專項施工方案
1.2.6北極宮大街
北極宮大街現(xiàn)狀合流管道做為分流改造后的雨水管道,周邊用戶現(xiàn)狀排水管
道需采用d300mm的U-pvc管道連接至新建污水預(yù)埋管道,達(dá)到雨污分流改造的
目的。
W1~W13井段設(shè)計管徑d800mm,設(shè)計長度995.6m,最大埋深5.0m。設(shè)計
采用頂管施工。
設(shè)計頂管工作井6座,分別為W2、W4、W6、W8、W10、W12,頂管工作
井平面凈尺寸為8.0×6.0m;設(shè)計頂管接收井7座,分別為W1、W3、W5、W7、
W9、W11、W13,頂管接收井平面凈尺寸為5.0×4.0m。均為鋼筋混凝土結(jié)構(gòu)。
1.2.7秦漢大道
秦漢大道(涇干大街—中心街)本次新建d2400mm雨水管道,新建d800mm
污水管道,廢除d2000mm現(xiàn)狀合流管道。
秦漢大道(中心街—南環(huán)路)本次新建d2400mm雨水管道,保留現(xiàn)狀
d800mm合流管道用做污水管道。
根據(jù)《涇河新城雨水專項規(guī)劃》,本次秦漢大道(原點(diǎn)大道—南環(huán)路)設(shè)計
范圍內(nèi)雨水管道單排敷設(shè),雨水管道由北向南排入秦漢大道下游規(guī)劃雨水管道。
最終排入涇河3#雨水排出口。設(shè)計管徑d1650~d2400mm,長度1693m。其中,
秦漢大道(原點(diǎn)大道—涇干大街)、秦漢大道(中心街—南環(huán)路)兩段的現(xiàn)狀合
流管道用做分流改造后的污水管道,現(xiàn)狀雨水口需進(jìn)行封堵處理,雨水通過新建
雨水口排入本次新建雨水管道,達(dá)到雨污分流改造的目的。
5
項目專項施工方案
秦漢大道(中心街—南環(huán)路)現(xiàn)狀合流管道用做分流改造后的污水管道,現(xiàn)
狀雨水口需進(jìn)行封堵處理,雨水通過新建雨水口排入本次新建雨水管道,達(dá)到雨
污分流改造的目的。
秦漢大道(涇干大街—中心街)新建污水管道受下游接入現(xiàn)狀管道高程限制,
污水主管與現(xiàn)狀橫過路給水、熱力和現(xiàn)狀合流管有沖突位置,需將給水、熱力改
遷,該段新建雨水和污水管道后新建雨水口連接管,所以有沖突的橫過路合流管
可以拆除。拆改數(shù)量詳見PS-13污水工程數(shù)量表。
Yqh15—Yqh16井段雨水管道設(shè)計管徑d1800mm,設(shè)計長度120m,最大埋
深7.4m;Yqh16—Yqh25井段雨水管道設(shè)計管徑d2400mm,設(shè)計長度992m,最
大埋深7.6m;Yqh25—Yqh26井段雨水管道設(shè)計管徑d2600mm,設(shè)計長度31m,
最大埋深6.8m;均采用頂管施工。
設(shè)計頂管工作井6座,分別為Yqh15、Yqh17、Yqh19、Yqh21、Yqh23、
Yqh25,頂管工作井平面凈尺寸為9.0×6.0m;設(shè)計頂管接收井6座,分別為Yqh16、
Yqh18、Yqh20、Yqh22、Yqh24、Yqh26,頂管接收井平面尺寸為6.0×5.0m;均
為鋼筋混凝土結(jié)構(gòu)。
1.2.8秦星路
秦星路(涇干大街-中心街)本次新建d600~d1350mm雨水管道,保留現(xiàn)狀
d400mm合流管道做為污水管道。
根據(jù)《涇河新城雨水專項規(guī)劃》,本次秦星路(涇干大街-中心街)設(shè)計范
圍內(nèi)雨水管道單排敷設(shè),雨水管道由北向南排入中心街設(shè)計雨水管道。最終排入
涇河3#雨水排出口。設(shè)計管徑d600~d1350mm,長度613m。
6
項目專項施工方案
秦星路(涇干大街-中心街)現(xiàn)狀合流管道做為分流改造后的污水管道,現(xiàn)
狀雨水口需進(jìn)行封堵處理,雨水通過新建雨水口排入本次新建雨水管道,達(dá)到雨
污分流改造的目的。
YE6接入中心街YD4井段設(shè)計采用頂管施工;設(shè)計管徑d1350mm,設(shè)計長
度70.9m;最大埋深5.2m。
設(shè)計頂管工作井為YE6井,平面凈尺寸為7.0×5.0m;結(jié)構(gòu)形式為鋼筋混凝
土結(jié)構(gòu)。
1.2.9崇文大街
崇文大街(原點(diǎn)大道-涇干大街)本次新建d1500mm-d1650mm雨水管道,
保留現(xiàn)狀d500mm合流管道做為污水管道。
崇文大街(涇干大街—南環(huán)路)本次新建d600~d1650mm雨水管道,保留
現(xiàn)狀d500~d600mm合流管道用做污水管道。
根據(jù)《涇河新城雨水專項規(guī)劃》,本次崇文大街(原點(diǎn)大道-涇干大街)設(shè)
計范圍內(nèi)雨水管道單排敷設(shè),雨水管道由北向南排入涇干大街規(guī)劃雨水管道。最
終排入涇河3#雨水排出口。設(shè)計管徑d1500~d1650mm,長度755.34m。
本次崇文大街(涇干大街—南環(huán)路)設(shè)計范圍內(nèi)雨水管道單排敷設(shè),雨水管
道由北向南排入南環(huán)路規(guī)劃雨水管道。最終沿秦漢大道排入涇河3#雨水排出口。
設(shè)計管徑d600~d1650mm,長度940m。
崇文大街(原點(diǎn)大道—涇干大街)現(xiàn)狀合流管道做為分流改造后的污水管道。
現(xiàn)狀雨污水口處理措施:當(dāng)現(xiàn)狀雨水口無用戶污水接入時,應(yīng)將現(xiàn)狀雨水口予以
進(jìn)行封堵廢棄;當(dāng)現(xiàn)狀雨水口有用戶污水接入時,應(yīng)將雨水口用蓋板封閉,雨水
口予以保留利用。從而達(dá)到雨污分流改造的目的。
崇文大街(涇干大街—南環(huán)路)現(xiàn)狀合流管道用做分流改造后的污水管道,
7
項目專項施工方案
現(xiàn)狀雨水口需進(jìn)行封堵處理,雨水通過新建雨水口排入本次新建雨水管道,達(dá)到
雨污分流改造的目的。
崇文大街(原點(diǎn)大道—涇干大街)Y1-Y3井段設(shè)計管徑d1500mm,設(shè)計長度
98m,最大埋深6.0m;設(shè)計采用頂管施工,頂管工作井為Y2井,頂管工作井平
面凈尺寸為8.0×6.0m;頂管接收井為Y1井,頂管接收井平面凈尺寸5.0×
5.0m;均為鋼筋混凝土結(jié)構(gòu)。
崇文大街(涇干大街—南環(huán)路)Ycw13~Ycw14井段設(shè)計管徑d1350mm,設(shè)
計長度80m,最大埋深5.7m;Ycw14~Ycw16井段設(shè)計管徑d1650mm,設(shè)計長度
176m,最大埋深6.0m。設(shè)計采用頂管施工,頂管工作井Ycw13井的平面凈尺寸
為7.0×5.0m,頂管工作井Ycw15井的平面凈尺寸為8.0×6.0m;頂管接收井為
Ycw14、Ycw16井,頂管接收井平面凈尺寸為5.0×5.0m;均為鋼筋混凝土結(jié)構(gòu)。
1.2.10興隆大街
興隆大街(涇干大街-南環(huán)路)本次新建d1500~d2000mm雨水管道,保留
現(xiàn)狀d400mm合流管道做為污水管道。
北極宮大街(涇干大街—南環(huán)路)等路段現(xiàn)狀管徑較現(xiàn)狀大管徑管道改為雨
水管道,然后新建污水管道。
8
項目專項施工方案
Y1-Y10井段設(shè)計管徑d1500~d2000mm,設(shè)計長度1057.4m,最大埋深7.010m。
設(shè)計采用頂管施工,設(shè)計頂管工作井5座,分別為為Y1、Y3、Y5、Y7、Y9井,
工作井平面凈尺寸為8.0×6.0m;設(shè)計頂管接收井4座,分別為為Y2、Y4、Y6、
Y10井,頂管接收井平面尺寸為5.0×5.0m。結(jié)構(gòu)形式為鋼筋混凝土結(jié)構(gòu)。
1.3地質(zhì)概況
據(jù)據(jù)勘探報告,場地地層自上而下由人工處理水泥路面或瀝青路面
(Q4ml)、人工處理路基(Q4ml)、第四系全新統(tǒng)素填土(Q4ml)、沖洪積黃土
狀土(Q4al+pl)及圓礫(Q4al+pl)構(gòu)成,各層土的野外特征分述如下:
①人工處理水泥路面或瀝青路面(Q4ml):黑色或灰色,由瀝青或水泥混凝
土作面層的路面。層厚0.15~0.20m,層底埋深0.15~0.20m,層底標(biāo)高
396.40~414.73m。
②人工處理路基(Q4ml):黃褐色,濕,可塑狀態(tài)。由粘性土、白灰組成。
層厚0.35~1.00m,層底埋深0.50~1.20m,層底標(biāo)高395.90~414.14m。
③素填土(Q4ml):黃褐色,濕,硬塑狀態(tài)。以粘性土為主,局部可見植物
根系,含少量白灰渣、結(jié)核、碎磚屑等。層厚0.60~2.90m,層底埋深
1.20~3.60m,層底標(biāo)高395.00~412.98m。
④黃土狀土(Q4al+pl):黃褐色,濕,硬塑狀態(tài)。針狀孔隙,含氧化鐵,偶
9
項目專項施工方案
見蝸牛殼碎片。層厚4.90~18.20m,層底埋深7.50~20.00m,層底標(biāo)高
384.01~406.88m。
⑤圓礫(Q4al+pl):雜色,濕~飽和,中密狀態(tài)。以花崗巖、石英巖為主,呈
亞圓形,分選性差,一般粒徑5-6cm,最大10cm,中粗砂及粘性土充填。顆粒
組成為20~200mm占21.3%,2.0~20mm占43.8%,0.5~2.0mm占12.7%,
0.25~0.5mm占10.0%,0.075~0.25mm占7.1%,<0.075mm占5.1%。該層未揭
穿,揭露最大厚度9.30m。
1.4地下水
根據(jù)勘測報告,各勘探點(diǎn)中量測的穩(wěn)定水位為10.40~17.10m,相應(yīng)標(biāo)高為
386.20~390.34m,地下水屬潛水類型,地下水水位變化較大,地下水水位年變
幅可按2m考慮。地下水補(bǔ)給形式主要為涇河地下徑流、大氣降水和地表水滲入
補(bǔ)給,排泄方式以徑流排泄、人工開采及蒸發(fā)消耗為主。
1.5設(shè)計參數(shù)
序類管徑長度工作井
道路井段管頂覆土施工工藝
號別mmm深度
中心街
雨YD4-YD7-5.97~6.4
1(北極宮-D1500417.23.65~4.35泥水平衡頂進(jìn)
水Ycw144
秦漢)
中心街
雨YA12-5.99~7.4
2(北極宮-D1350120.03.62~4.32泥水平衡頂進(jìn)
水YA138
吉元)
雨
YC2-YC4D1800153.45.0~6.42.42~2.82泥水平衡頂進(jìn)
水
3涇干大道
雨
YC4-YC10D2000589.85.6~7.82.8~5.0土壓平衡頂進(jìn)
水
YC21-
雨5.57~7.8
4南環(huán)路YC26-D1800578.92.79~5.05泥水平衡頂進(jìn)
水3
Yqh25
雨6.42~9.3
5先鋒大街Y2-Y6D2800430.53.3~5.26土壓平衡頂進(jìn)
水4
10
項目專項施工方案
北極宮大污4.72~6.4
6W1-W13D800995.63.5~2.9人工頂進(jìn)
街水4
雨Yqh15-7.04~7.4
D18001205.06~5.45泥水平衡頂進(jìn)
水Yqh163
7雨Yqh16-
秦漢大道D24009923.1~5.0土壓平衡頂進(jìn)
水Yqh25
雨Yqh25-
D2600317.6~7.83.8~3.9人工頂進(jìn)
水Yqh26
雨5.45~5.9
8秦星路YE16-YD4D135070.93.6~3.8人工頂進(jìn)
水1
雨5.84~6.9
Y1-Y3D1500983.5~4.3人工頂進(jìn)
水2
雨Ycw13-
9崇文大街D1350806.3~7.14.14.2~人工頂進(jìn)
水Ycw14
雨Ycw14-6.50~6.9
D16501763.2~3.87泥水平衡頂進(jìn)
水Ycw164
雨1057.
10興隆大街Y1-Y10D20006,6~7.513.4~4.8土壓平衡頂進(jìn)
水4
1.6現(xiàn)狀管線調(diào)查
1.6.1管線調(diào)查摸排
1、在施工準(zhǔn)備階段,根據(jù)住建局組織的管線交底會議了解的管線特征和情況,
應(yīng)走訪當(dāng)?shù)厝罕姾陀嘘P(guān)機(jī)構(gòu),核對管線分布圖,了解是否還有其他管線,并組織
人員將各種管線的功能、平面位置、埋深、管線走向等管線特征繪制于施工平面
圖上,形成管線分布圖,詳細(xì)記錄各管線的產(chǎn)權(quán)單位、聯(lián)系人聯(lián)系電話、意外處理
措施,并會知參加施工的有關(guān)人員。
2.進(jìn)場施工前,對施工現(xiàn)場進(jìn)行詳細(xì)的調(diào)查,摸排,做好地下管線、文物的保護(hù)
工作。
3、動工前,項目經(jīng)理應(yīng)組織工程施工人員進(jìn)行技術(shù)安全交底會,將各種管
線的詳細(xì)情況對施工班組人員機(jī)械作業(yè)人員做詳細(xì)說明,并針對管線的保護(hù)措
施進(jìn)行交底。施工機(jī)械作業(yè)人員應(yīng)服從工地管理人員的安排有責(zé)任向有關(guān)人員詳
細(xì)了解地下管線的情況。
4、施工準(zhǔn)備階段或該分項工程動工前,還應(yīng)根據(jù)了解到的各種管線的特征結(jié)
11
項目專項施工方案
合本部分的施工范圍進(jìn)行。
(1)管線探測儀探測;
(2)人工開挖探坑,詳細(xì)、徹底的印證和明確各種管線的特性特征,在管線分布
圖上進(jìn)行標(biāo)注,同時采取可行措施在施工現(xiàn)場予以標(biāo)注明示。特別是在機(jī)械挖土
前,必須將可能預(yù)見的在動工范圍內(nèi)的各種管線用人工挖坑探明,否則不得使用機(jī)
械作業(yè)。溝槽開挖前必須做好原有管道(管線)得探測和遷移工作,進(jìn)行所施工部
位的管線調(diào)查。查清有無地下管線通過,先用管線探測儀進(jìn)行探測,對儀器探測出
有管線的部位或根據(jù)調(diào)查資料顯示可能有管線的位置再利用人工開挖探槽進(jìn)一
步證明,槽坑應(yīng)比溝槽深0.5m。在開挖探槽時,由人工用鐵楸開挖,以免損傷管線。
如有異常需書面報告監(jiān)理工程師,經(jīng)處理方案批準(zhǔn)后方可施工,以確保不損壞管線。
5.施工管理人員是現(xiàn)場管線保護(hù)的直接責(zé)任人。發(fā)生事故應(yīng)按照有關(guān)規(guī)定
及時_上報,同時應(yīng)采取有力措施協(xié)助有關(guān)單位做好保護(hù)和搶救工作,防止發(fā)生人
員傷亡和制止事故的擴(kuò)大。事故的處理應(yīng)按照“三不放過”的原則和公司《程序文
件》的要求進(jìn)行。
6、在已探明各種管線結(jié)構(gòu)的上下、左右分別50cm、5
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024-2030年中國安防電子行業(yè)市場供需趨勢發(fā)展戰(zhàn)略分析報告
- 2024年塔吊司機(jī)承包項目勞務(wù)合同3篇
- 2024-2030年中國太陽能發(fā)電系統(tǒng)設(shè)備商業(yè)計劃書
- 2024-2030年中國地面通信導(dǎo)航定向設(shè)備行業(yè)當(dāng)前經(jīng)濟(jì)形勢及投資建議研究報告
- 茅臺學(xué)院《圖形圖像信息處理進(jìn)階》2023-2024學(xué)年第一學(xué)期期末試卷
- 2024年權(quán)益保障:合同與財務(wù)制度
- 茅臺學(xué)院《電子測量原理》2023-2024學(xué)年第一學(xué)期期末試卷
- 馬鞍山師范高等??茖W(xué)?!吨型饣A(chǔ)教育比較》2023-2024學(xué)年第一學(xué)期期末試卷
- 2024年在線教育平臺軟件定制委托開發(fā)合同2篇
- 2024三輪汽車駕駛培訓(xùn)學(xué)校合作經(jīng)營協(xié)議3篇
- 2024年低壓電工復(fù)審取證考試題庫附答案(通用版)
- 新管徑流速流量對照表
- 咯血病人做介入手術(shù)后的護(hù)理
- 境外投資環(huán)境分析報告
- 《壓力平衡式旋塞閥》課件
- 物聯(lián)網(wǎng)與人工智能技術(shù)融合發(fā)展年度報告
- 婦產(chǎn)科醫(yī)生醫(yī)患溝通技巧
- 內(nèi)科學(xué)糖尿病教案
- 《高尿酸血癥》課件
- 微量泵的操作及報警處置課件查房
- 人教版小學(xué)數(shù)學(xué)四年級上冊5 1《平行與垂直》練習(xí)
評論
0/150
提交評論