項(xiàng)目專項(xiàng)施工方案
項(xiàng)目工程總承包(EPC)
高低壓配電施工方案
編制單位:中建八局第二建設(shè)有限公司
編制人:
審核人:
審批人:
編制日期:2023.11.19
-1-
項(xiàng)目專項(xiàng)施工方案
目錄
第一章編制說明.....................................................................................................................................1
1.1編制目的...................................................................................................................................1
1.2編制依據(jù)...................................................................................................................................1
第二章工程概況.....................................................................................................................................3
2.1建筑概況...................................................................................................................................3
2.2高低壓配電工程概況...............................................................................................................3
2.2.1供電電源...............................................................................................................................3
2.2.2變配電室位置.......................................................................................................................4
2.2.3負(fù)荷等級(jí).............................................................................................................................4
2.2.4備用電源...............................................................................................................................4
2.2.5其他電源...............................................................................................................................5
2.3項(xiàng)目主要施工條件...................................................................................................................5
2.3.1周邊電源情況.......................................................................................................................5
2.3.2場(chǎng)內(nèi)情況...............................................................................................................................5
2.3.3施工現(xiàn)場(chǎng)基礎(chǔ)設(shè)施狀況.......................................................................................................6
第三章施工準(zhǔn)備.....................................................................................................................................8
3.1施工技術(shù)準(zhǔn)備...........................................................................................................................8
3.2施工重點(diǎn)及難點(diǎn)分析...............................................................................................................8
3.3資源配置計(jì)劃.........................................................................................................................10
3.3.1勞動(dòng)力配置計(jì)劃...............................................................................................................10
3.3.2工程用原材料需要量計(jì)劃...............................................................................................11
3.3.3施工機(jī)具配置計(jì)劃.............................................................................................................11
3.3.4測(cè)量設(shè)備配置計(jì)劃...........................................................................................................12
-2-
項(xiàng)目專項(xiàng)施工方案
3.4施工進(jìn)度計(jì)劃.........................................................................................................................13
第四章主要分部分項(xiàng)工程施工方法...................................................................................................14
4.1高低壓盤、柜的安裝.............................................................................................................14
4.1.1工藝流程.............................................................................................................................14
4.1.2基礎(chǔ)驗(yàn)收.............................................................................................................................14
4.1.3高低壓盤、柜二次搬運(yùn).....................................................................................................16
4.1.4盤、柜就位組裝.................................................................................................................16
4.1.5盤、柜母線安裝.................................................................................................................18
4.1.6高壓柜小母線安裝.............................................................................................................19
4.1.7封閉式插接母線安裝.........................................................................................................19
4.1.8配電柜一、二次回路接線.................................................................................................22
4.2變壓器的安裝.........................................................................................................................24
4.2.1工藝流程.............................................................................................................................24
4.2.2基礎(chǔ)驗(yàn)收.............................................................................................................................24
4.2.3變壓器就位.........................................................................................................................25
4.2.4器身檢查.............................................................................................................................25
4.3高壓電纜敷設(shè).........................................................................................................................26
4.3.1工藝流程.............................................................................................................................26
4.3.2施工方法.............................................................................................................................26
第五章10KV設(shè)備的試驗(yàn)方法............................................................................................................29
5.1試驗(yàn)條件.................................................................................................................................29
5.2工藝流程.................................................................................................................................29
5.3試驗(yàn)前準(zhǔn)備工作.....................................................................................................................29
-3-
項(xiàng)目專項(xiàng)施工方案
5.4試驗(yàn)前檢查.............................................................................................................................30
5.5電力變壓器試驗(yàn).....................................................................................................................31
5.5.1工藝流程.............................................................................................................................31
5.5.2絕緣電阻測(cè)試.....................................................................................................................31
5.5.3變壓器直流電阻測(cè)試.........................................................................................................32
5.5.4組別、極性及變比測(cè)量.....................................................................................................32
5.5.5變壓器的工頻耐壓試驗(yàn).....................................................................................................33
5.6高壓開關(guān)柜試驗(yàn).....................................................................................................................34
5.6.1工藝流程.............................................................................................................................34
5.6.2絕緣電阻測(cè)試.....................................................................................................................34
5.6.3斷路器機(jī)械特性測(cè)試.........................................................................................................35
5.6.4斷路器回路電阻測(cè)試.........................................................................................................36
5.6.5高壓斷路器工頻耐壓試驗(yàn).................................................................................................36
5.6.6高壓隔離開關(guān)、絕緣子試驗(yàn).............................................................................................37
5.6.7電壓互感器、電流互感器調(diào)試.........................................................................................37
5.7母線、絕緣子實(shí)驗(yàn).................................................................................................................39
5.7.1高壓柜母線、絕緣子耐壓試壓.........................................................................................39
5.7.2高壓柜小母線絕緣試驗(yàn).....................................................................................................39
5.8避雷器、電纜試驗(yàn).................................................................................................................40
5.8.1避雷器試驗(yàn).........................................................................................................................40
5.8.2高壓電纜試驗(yàn).....................................................................................................................41
5.9試驗(yàn)后檢查.............................................................................................................................42
第六章10KV電氣設(shè)備調(diào)試及送電試運(yùn)行........................................................................................43
-4-
項(xiàng)目專項(xiàng)施工方案
6.110KV電氣設(shè)備的調(diào)試方法....................................................................................................43
6.1.1工藝流程.............................................................................................................................43
6.1.2裝置通電前檢查.................................................................................................................43
6.1.3整定值的輸入.....................................................................................................................43
6.1.4斷路器聯(lián)鎖調(diào)試.................................................................................................................44
6.1.5綜合保護(hù)裝置調(diào)試.............................................................................................................44
6.1.6小電流接地保護(hù)調(diào)試.........................................................................................................45
6.1.7PT、CT斷線保護(hù)調(diào)試........................................................................................................47
6.1.8變壓器信號(hào)回路檢查.........................................................................................................47
6.1.9備用電源自投調(diào)試.............................................................................................................48
6.2送電試運(yùn)行.............................................................................................................................49
6.2.1送電試運(yùn)行條件.................................................................................................................49
6.2.2送電前檢查.........................................................................................................................50
6.2.3受電設(shè)備絕緣電阻測(cè)量.....................................................................................................50
6.2.4送電操作.............................................................................................................................50
第七章施工質(zhì)量控制管理計(jì)劃...........................................................................................................51
7.1設(shè)備開箱檢查.........................................................................................................................51
7.1.1高低壓盤、柜的開箱檢查.................................................................................................51
7.1.2母線的開箱檢查.................................................................................................................53
7.1.3變壓器的開箱檢查.............................................................................................................53
7.1.4柴油發(fā)電機(jī)組的開箱檢查.................................................................................................54
7.2電氣設(shè)備安裝及電纜敷設(shè)、接線.........................................................................................54
7.3變配電設(shè)備調(diào)試.....................................................................................................................55
-5-
項(xiàng)目專項(xiàng)施工方案
第八章施工進(jìn)度控制管理計(jì)劃...........................................................................................................56
8.1進(jìn)度控制要點(diǎn).........................................................................................................................56
8.2進(jìn)度控制措施.........................................................................................................................56
8.3進(jìn)度控制方法.........................................................................................................................56
第九章成品保護(hù)措施...........................................................................................................................58
9.1成品保護(hù)管理制度.................................................................................................................58
9.2成品保護(hù)措施的制定.............................................................................................................59
9.3成品保護(hù)實(shí)施.........................................................................................................................59
9.4變配電工程成品保護(hù)措施.......................................................................................................60
第十章安全、消防管理措施...............................................................................................................62
10.1安全、消防管理目標(biāo)...........................................................................................................62
10.2安全施工管理體系...............................................................................................................62
10.3安全管理制度.......................................................................................................................63
10.4安全管理措施.......................................................................................................................66
第十一章環(huán)境保護(hù)及文明施工管理措施...........................................................................................71
11.1防止施工噪音污染措施.......................................................................................................71
11.2廢棄物管理...........................................................................................................................71
11.3材料設(shè)備的管理...................................................................................................................72
11.4現(xiàn)場(chǎng)場(chǎng)容...............................................................................................................................72
11.5料具管理...............................................................................................................................72
11.6機(jī)械管理...............................................................................................................................73
-6-
項(xiàng)目專項(xiàng)施工方案
第一章編制說明
1.1編制目的
本施工方案是為xx項(xiàng)目工程總承包(EPC)工程施工所編制的指導(dǎo)高低壓配電施工
用綱領(lǐng)性文件。目的是在經(jīng)濟(jì)上合理、技術(shù)上可靠的前提下,保質(zhì)、保量、保工期的按
時(shí)完成工程。
1.2編制依據(jù)
1以國家現(xiàn)行規(guī)范、標(biāo)準(zhǔn)、規(guī)程以及科學(xué)、合理、安全、高效節(jié)能、文明環(huán)保、針
對(duì)性、實(shí)用性為原則,編制本工程的施工,其內(nèi)容詳見表1.2-1。
表1.2-1規(guī)范圖集清單
序號(hào)類別規(guī)范、規(guī)程、圖集名稱編號(hào)
1國標(biāo)《電氣裝置安裝工程電氣設(shè)備交接試驗(yàn)標(biāo)準(zhǔn)》GB50150-2016
2國標(biāo)《電氣裝置安裝工程電纜線路施工及驗(yàn)收規(guī)范》GB50168-2018
3國標(biāo)《電氣裝置安裝工程接地裝置施工及驗(yàn)收規(guī)范》GB50169-2016
《電氣裝置安裝工程盤柜及二次回路
4國標(biāo)GB50171-2012
結(jié)線施工及驗(yàn)收規(guī)范》
5國標(biāo)《建設(shè)工程施工現(xiàn)場(chǎng)供用電安全規(guī)范》GB50194-2014
6國標(biāo)《機(jī)械設(shè)備安裝工程施工及驗(yàn)收通用規(guī)范》GB50231-2009
7國標(biāo)《電氣裝置安裝工程低壓電器施工及驗(yàn)收規(guī)范》GB50254-2014
8國標(biāo)《電氣裝置安裝工程電力交流設(shè)備施工及驗(yàn)收規(guī)范》GB50255-2014
《電氣裝置安裝工程爆炸和火災(zāi)危險(xiǎn)環(huán)境
9國標(biāo)GB50257-2014
施工及驗(yàn)收規(guī)范》
10國標(biāo)《建筑電氣工程施工質(zhì)量驗(yàn)收規(guī)范》GB50303-2015
11國標(biāo)《建筑節(jié)能工程施工質(zhì)量驗(yàn)收規(guī)范》GB50411-2019
12國標(biāo)《電氣裝置安裝工程母線裝置施工及驗(yàn)收規(guī)范》GB50149-2010
13企標(biāo)中建八局《施工組織設(shè)計(jì)編制與管理標(biāo)準(zhǔn)》ZJQ08-SGJB001-2017
14企標(biāo)中建八局《施工技術(shù)交底編制與管理標(biāo)準(zhǔn)》ZJQ08-SGJB002-2017
15企標(biāo)中建八局《建筑電氣工程施工技術(shù)標(biāo)準(zhǔn)》ZJQ08-SGJB303-2017
-1-
項(xiàng)目專項(xiàng)施工方案
2其他依據(jù)
1)現(xiàn)場(chǎng)踏勘資料:對(duì)施工現(xiàn)場(chǎng)及其周邊環(huán)境進(jìn)行踏勘所獲得的相關(guān)資料;
2)圖紙:xx項(xiàng)目工程總承包(EPC)工程設(shè)計(jì)圖紙;
3)企業(yè)施工能力:企業(yè)以往承建類似工程積累的豐富施工經(jīng)驗(yàn)及施工能力;
4)合同、招投標(biāo)文件、勘察文件、國家及地方法律法規(guī)政策規(guī)定;
5)我國現(xiàn)行的安全生產(chǎn)、文明施工、環(huán)保及消防等有關(guān)規(guī)定。
-2-
項(xiàng)目專項(xiàng)施工方案
第二章工程概況
2.1建筑概況
建筑工程概況如表2.1-1。
表2.1-1建設(shè)概況表
序號(hào)條款名稱說明與要求
1建設(shè)單位
2設(shè)計(jì)單位
3勘察單位
4監(jiān)理單位
5機(jī)電施工總承包單位
6
7建設(shè)地點(diǎn)
8計(jì)劃工期開工日期:2023-9-4,竣工日期:2023-5-22
9招標(biāo)要求質(zhì)量等級(jí)達(dá)到國家現(xiàn)行施工驗(yàn)收規(guī)范“合格”標(biāo)準(zhǔn)
2.2高低壓配電工程概況
設(shè)計(jì)范圍:10/0.4kV變配電系統(tǒng)。
2.2.1供電電源
2.2.2變配電室位置
一期工程設(shè)1個(gè)10kV高壓開閉所、3個(gè)變電所、1個(gè)柴油發(fā)電機(jī)房。
-3-
項(xiàng)目專項(xiàng)施工方案
2.2.3負(fù)荷等級(jí)
按照國家三級(jí)甲等兒童(綜合)醫(yī)院標(biāo)準(zhǔn)進(jìn)行設(shè)計(jì)。負(fù)荷分類如下:設(shè)計(jì)按按國
一級(jí)負(fù)荷中特別重要負(fù)荷:急診搶救室、產(chǎn)房、重癥監(jiān)護(hù)室、早產(chǎn)兒室、血液透析
室、手術(shù)室、術(shù)前準(zhǔn)備室、術(shù)后復(fù)蘇室、麻醉室、心血管造影檢查室等場(chǎng)所中涉及患者
生命安全的設(shè)備及照明用電;大型生化儀器、重癥呼吸道感染區(qū)的通風(fēng)系統(tǒng)。
一級(jí)負(fù)荷:急診搶救室、重癥監(jiān)護(hù)室、手術(shù)室、術(shù)前準(zhǔn)備室、術(shù)后復(fù)蘇室、麻醉室、
心血管造影檢查室場(chǎng)所中除去一級(jí)負(fù)荷中特別重要負(fù)荷的其他用電設(shè)備;急診診室、急
診觀察室及處置室、嬰兒室、內(nèi)鏡檢查室、影像科、放射治療室、核醫(yī)學(xué)室等場(chǎng)所的診
療設(shè)備和照明用電;
高壓氧倉、血庫、培養(yǎng)箱、恒溫箱的用電設(shè)備;病理科的取材室、制片室、鏡檢室
的用電設(shè)備;
百級(jí)潔凈度手術(shù)室空調(diào)系統(tǒng)用電;門診部、醫(yī)技部及住院部的走道照明;
計(jì)算機(jī)網(wǎng)絡(luò)系統(tǒng)用電、電子信息設(shè)備機(jī)房用電;變配電室用電、柴油發(fā)電機(jī)房用電;
一類高層普通電梯(客、醫(yī)梯)用電;排水(污)泵、生活水泵用電;
醫(yī)用氣體供應(yīng)系統(tǒng)中的真空泵、壓縮機(jī)、制氧機(jī)等設(shè)備及其控制與報(bào)警系統(tǒng)用電;
消防設(shè)備用電(火災(zāi)應(yīng)急照明及疏散指示標(biāo)志、防煙及排煙設(shè)施、自動(dòng)滅火系統(tǒng)、
消防水泵、消防電梯及其排水泵、電動(dòng)的防火卷簾與門窗以及閥門等)。
二級(jí)負(fù)荷:包括電子顯微鏡、影像科診斷用電設(shè)備;高級(jí)病房、肢體傷殘康復(fù)病房
照明用電;中心供應(yīng)室、空氣凈化機(jī)組用電;貴重藥品冷庫用電;太平柜用電;鍋爐房
用電;報(bào)告廳、科研實(shí)驗(yàn)化驗(yàn)室用電;普通扶梯用電;機(jī)械停車設(shè)備的用電負(fù)荷。
三級(jí)負(fù)荷:不屬于一、二級(jí)的負(fù)荷。如:病房、診室、普通辦公室用電、空調(diào)用電、
普通風(fēng)機(jī)、熱水器用電等。
-4-
項(xiàng)目專項(xiàng)施工方案
2.2.4備用電源
3。
2.2.5其他電源
本工程在一期地下一層設(shè)置了1臺(tái)1600kW快速自啟動(dòng)柴油發(fā)電機(jī)組作為備用電源,
為一級(jí)負(fù)荷中的特別重要負(fù)荷及部分一級(jí)負(fù)荷提供供電可靠性。機(jī)組并列運(yùn)行,供電電
壓為0.4kV,啟動(dòng)時(shí)間不大于15s。機(jī)組自帶并機(jī)控制屏,各控制屏的控制器之間通過
光纖進(jìn)行信息數(shù)據(jù)通訊。
2.3項(xiàng)目主要施工條件
2.3.1周邊電源情況
根據(jù)現(xiàn)場(chǎng)踏勘,項(xiàng)目現(xiàn)場(chǎng)在以北、草灘八路以東,周圍最近的電源點(diǎn)為尚稷路變電
站及農(nóng)場(chǎng)總公司變電站,供電方案10kV雙回路進(jìn)線擬從上述兩個(gè)變電站接入。
圖2.3-1項(xiàng)目所在位置及周邊情況
-5-
項(xiàng)目專項(xiàng)施工方案
2.3.2場(chǎng)內(nèi)情況
圖2.3-2項(xiàng)目場(chǎng)內(nèi)管網(wǎng)平面圖路
路
2.3.3施工現(xiàn)場(chǎng)基礎(chǔ)設(shè)施狀況路
路
1現(xiàn)場(chǎng)施工水源
-6-
圖2.2-2
圖2.2-2
圖2.2-2
項(xiàng)目專項(xiàng)施工方案
工程西南面處有泵房可供臨時(shí)用水。
2現(xiàn)場(chǎng)施工電源
場(chǎng)地外西南側(cè)有一處環(huán)網(wǎng)柜,供現(xiàn)場(chǎng)臨時(shí)施工用電
3現(xiàn)場(chǎng)變配電室供配電分區(qū)示意圖如下圖所示
圖2.3-3項(xiàng)目變配電室供配電分區(qū)示意圖
-7-
項(xiàng)目專項(xiàng)施工方案
第三章施工準(zhǔn)備
3.1施工技術(shù)準(zhǔn)備
1開工前仔細(xì)檢查、審核施工圖紙,參加施工圖交底會(huì)審,施工組設(shè)計(jì)已經(jīng)批準(zhǔn),
并向施工班、組下達(dá)安全、質(zhì)量、技術(shù)交底。
2現(xiàn)場(chǎng)檢查,建筑工程與建筑電氣安裝有關(guān)建筑物,混凝土強(qiáng)度預(yù)埋件、預(yù)留孔
洞、位置是否正確。
3管廊內(nèi)電纜支架是否安裝完畢,電纜井間電纜保護(hù)管是否暢通。
4施工技術(shù)文件滿足施工要求,有關(guān)的施工規(guī)范、規(guī)程、標(biāo)準(zhǔn)齊全。
5在高壓設(shè)備試驗(yàn)前,試驗(yàn)人員應(yīng)結(jié)合設(shè)備的說明書仔細(xì)閱讀,清楚設(shè)備的工作
原理繼電器控制各個(gè)環(huán)節(jié)之間的關(guān)系。
6試驗(yàn)人員應(yīng)根據(jù)設(shè)備原理圖和接線圖了解設(shè)備的外部和內(nèi)部接線情況,確定試
驗(yàn)設(shè)備線路在設(shè)備上的接駁點(diǎn)及試驗(yàn)設(shè)備的電壓電流等數(shù)據(jù)的參數(shù)并做好記錄,在經(jīng)過
工程技術(shù)人員的確認(rèn)后,方可接入試驗(yàn)設(shè)備。
7試驗(yàn)人員及調(diào)試人員必須持證上崗。
3.2施工重點(diǎn)及難點(diǎn)分析
3.2-1工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施
重點(diǎn)和
序號(hào)具體分析應(yīng)對(duì)措施
難點(diǎn)
本工程變配電系統(tǒng)共
首先做好各種資源的準(zhǔn)備及投入工作,深化設(shè)計(jì)、
有1個(gè)高壓總配電房,
報(bào)批報(bào)建、設(shè)備排產(chǎn)提前介入,確保各類資源的及
3個(gè)變配電房,1個(gè)發(fā)
工程體時(shí)供應(yīng),隨工程進(jìn)展作動(dòng)態(tài)調(diào)整,同時(shí)充分發(fā)揮組
1電機(jī)房,總計(jì)高低壓
量大織協(xié)調(diào)能力、資源集結(jié)和應(yīng)急能力強(qiáng)的企業(yè)優(yōu)勢(shì),
柜100余臺(tái),變壓器
全力以赴作好材料供應(yīng)工作,積極配合業(yè)主、監(jiān)理
10臺(tái),發(fā)電機(jī)組1臺(tái),
工程師工作,實(shí)現(xiàn)工程項(xiàng)目施工目標(biāo)。
體量巨大。
-8-
項(xiàng)目專項(xiàng)施工方案
1)抓好項(xiàng)目工期策劃工作,設(shè)置工期控制點(diǎn),采取
確實(shí)可行的工期保障措施,確保工期按照總進(jìn)度計(jì)
劃進(jìn)行。根據(jù)工期節(jié)點(diǎn)、倒排工期,與總包協(xié)調(diào),
及時(shí)提供作業(yè)面,同時(shí)自己積極創(chuàng)造作業(yè)面,實(shí)現(xiàn)
本工程工期緊張,變變配電工程盡早穿插施工,確保工期目標(biāo)的實(shí)現(xiàn)。
配電設(shè)備生產(chǎn)及安裝2)采用平行施工方式,按配電房進(jìn)行施工,配置充
2工期緊
工施的時(shí)間僅有3個(gè)足的施工資源,進(jìn)行動(dòng)態(tài)管理,合理流動(dòng)。施工高
月峰期投入勞動(dòng)力約40人,保證滿足工期需要。
5)當(dāng)出現(xiàn)工程重大變更、季節(jié)性施工等影響工程進(jìn)
度的因素時(shí),項(xiàng)目將采取積極的應(yīng)對(duì)措施,做好人
力、機(jī)械、材料等資源調(diào)配工作,合理安排施工程
序和時(shí)間,保證工期目標(biāo)實(shí)現(xiàn)。
1)首先進(jìn)行各子系統(tǒng)的單機(jī)調(diào)試和系統(tǒng)調(diào)試,成立
以項(xiàng)目經(jīng)理為組長的變配電調(diào)試小組,編制單機(jī)調(diào)
試、系統(tǒng)調(diào)試的程序、要求和系統(tǒng)參數(shù)指標(biāo)及調(diào)試
方案,報(bào)請(qǐng)同意后,由調(diào)試小組組織實(shí)施。
2)根據(jù)各子系統(tǒng)的工作原理,在系統(tǒng)全部完成前,
根據(jù)現(xiàn)場(chǎng)流水作業(yè)情況的安排,檢、測(cè)、調(diào)三個(gè)步
系統(tǒng)調(diào)本工程變配電系統(tǒng)設(shè)驟同步實(shí)施,實(shí)現(xiàn)早插入,分步實(shí)施。
3試難度備眾多,系統(tǒng)復(fù)雜,3)在本標(biāo)段機(jī)電安裝工程單機(jī)調(diào)試和系統(tǒng)調(diào)試基本
大調(diào)試工序多,難度大。完成之后,與業(yè)主、監(jiān)理單位、變配電系統(tǒng)分包單
位共同組成聯(lián)動(dòng)調(diào)試小組,確定相關(guān)專業(yè)責(zé)任人,
編制系統(tǒng)調(diào)試方案,各方密切協(xié)作,保證系統(tǒng)調(diào)試
一次成功。
4)調(diào)試所用的儀器儀表,均須經(jīng)國家或地方相關(guān)檢
測(cè)部門檢驗(yàn),并將檢驗(yàn)結(jié)果報(bào)備系統(tǒng)調(diào)試小組,批
準(zhǔn)后方可投入調(diào)試使用。
-9-
項(xiàng)目專項(xiàng)施工方案
1.質(zhì)量預(yù)控及檢測(cè)是保證工程質(zhì)量的一個(gè)重要手段。
項(xiàng)目部從收到施工圖開始,經(jīng)圖紙會(huì)審、編制項(xiàng)目
質(zhì)量計(jì)劃、施工組織設(shè)計(jì)、施工技術(shù)指導(dǎo)書、工序
質(zhì)量監(jiān)督檢查、分項(xiàng)分部工程質(zhì)量評(píng)定、單位工程
本工程合同質(zhì)量目標(biāo)質(zhì)量評(píng)定、竣工驗(yàn)收直至竣工后服務(wù),每一步程序、
為合格,公司內(nèi)控質(zhì)每一個(gè)環(huán)節(jié)都有專人負(fù)責(zé),專人檢查,層層把關(guān),
質(zhì)量要
4量目標(biāo)爭創(chuàng)“國家優(yōu)嚴(yán)格管理。同時(shí)接受業(yè)主、監(jiān)理單位的監(jiān)督及政府
求高
質(zhì)工程獎(jiǎng)”,施工質(zhì)質(zhì)量監(jiān)督機(jī)構(gòu)的監(jiān)督。
量要求高2.施工過程嚴(yán)格執(zhí)行自檢、互檢、專檢的“三檢制”
管理制度,上道工序檢驗(yàn)不合格不得進(jìn)入下道工序
施工。
3.強(qiáng)化質(zhì)量監(jiān)督,嚴(yán)格實(shí)行質(zhì)量否決權(quán),對(duì)不合格
分項(xiàng)、分部和單位工程必須返工處理。
3.3資源配置計(jì)劃
3.3.1勞動(dòng)力配置計(jì)劃
選用具有高壓施工資質(zhì)的專業(yè)勞務(wù)隊(duì)伍,明確試驗(yàn)調(diào)整、試運(yùn)行指揮者,操作者和
監(jiān)護(hù)人,專業(yè)施工及實(shí)驗(yàn)人員持證上崗。現(xiàn)場(chǎng)勞動(dòng)力需求表3.3-1。
表3.3-1勞動(dòng)力需求表
序號(hào)工種人數(shù)進(jìn)場(chǎng)時(shí)間備注
1電焊工42023年12月1日基礎(chǔ)找平、接地扁鋼焊接
高壓進(jìn)線電纜及室內(nèi)電纜敷設(shè),敷設(shè)
2其他工種302023年12月5日
完后退場(chǎng)
進(jìn)行電氣設(shè)備安裝及母線安裝,二次
3電工82023年12月10日
電纜敷設(shè)接線等工作
4高壓電工22023年1月5日高壓電纜頭制作
5高壓試驗(yàn)人員42023年1月10日高壓設(shè)備及電纜試驗(yàn)、調(diào)試
-10-
項(xiàng)目專項(xiàng)施工方案
3.3.2工程用原材料需要量計(jì)劃
根據(jù)現(xiàn)場(chǎng)施工進(jìn)度的要求提前排產(chǎn)各類設(shè)備及材料,保證各類原材料及設(shè)備的按時(shí)
供應(yīng)。工程原材料及設(shè)備需求表3.3-2。
表3.3-2工程原材料及設(shè)備需求表
序號(hào)設(shè)備名稱數(shù)量進(jìn)場(chǎng)時(shí)間備注
1高低壓配電柜1262023年12月15日設(shè)備基礎(chǔ)提前安裝完成
2變壓器102023年12月15日設(shè)備基礎(chǔ)提前安裝完成
3發(fā)電機(jī)12023年12月15日設(shè)備基礎(chǔ)提前安裝完成
4母線860米2023年1月5日相關(guān)設(shè)備安裝完成
5高壓電纜520米2023年1月5日相關(guān)設(shè)備安裝完成
3.3.3施工機(jī)具配置計(jì)劃
根據(jù)現(xiàn)場(chǎng)施工進(jìn)度的要去提前準(zhǔn)備施工機(jī)械,保證各類施工機(jī)械的按時(shí)供應(yīng)。主要
施工機(jī)械配置表如表3.3-3。
表3.3-3主要施工機(jī)械配備表
序號(hào)機(jī)具名稱型號(hào)數(shù)量備注
1液壓叉車3T1臺(tái)
2吊車16T1臺(tái)吊電纜盤
3汽車25T1輛電纜盤運(yùn)輸
4電纜支架2副電纜盤支撐
5鋼絲繩8T500米
6卷揚(yáng)機(jī)或柴油機(jī)8T1臺(tái)電纜牽引
7電纜滑輪直向25個(gè)
8對(duì)講機(jī)5對(duì)
9交流焊機(jī)380V1臺(tái)
10力矩扳手6把
-11-
項(xiàng)目專項(xiàng)施工方案
11墊鐵1mm若干
12水平尺400mm2把
13鋼卷尺50m1把
14穿線器50m1把
15液壓手推車2T2臺(tái)
16吊帶
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024-2030年中國安防電子行業(yè)市場(chǎng)供需趨勢(shì)發(fā)展戰(zhàn)略分析報(bào)告
- 2024年塔吊司機(jī)承包項(xiàng)目勞務(wù)合同3篇
- 2024-2030年中國太陽能發(fā)電系統(tǒng)設(shè)備商業(yè)計(jì)劃書
- 2024-2030年中國地面通信導(dǎo)航定向設(shè)備行業(yè)當(dāng)前經(jīng)濟(jì)形勢(shì)及投資建議研究報(bào)告
- 茅臺(tái)學(xué)院《圖形圖像信息處理進(jìn)階》2023-2024學(xué)年第一學(xué)期期末試卷
- 2024年權(quán)益保障:合同與財(cái)務(wù)制度
- 茅臺(tái)學(xué)院《電子測(cè)量原理》2023-2024學(xué)年第一學(xué)期期末試卷
- 馬鞍山師范高等??茖W(xué)?!吨型饣A(chǔ)教育比較》2023-2024學(xué)年第一學(xué)期期末試卷
- 2024年在線教育平臺(tái)軟件定制委托開發(fā)合同2篇
- 2024三輪汽車駕駛培訓(xùn)學(xué)校合作經(jīng)營協(xié)議3篇
- 2024年低壓電工復(fù)審取證考試題庫附答案(通用版)
- 新管徑流速流量對(duì)照表
- 咯血病人做介入手術(shù)后的護(hù)理
- 境外投資環(huán)境分析報(bào)告
- 《壓力平衡式旋塞閥》課件
- 物聯(lián)網(wǎng)與人工智能技術(shù)融合發(fā)展年度報(bào)告
- 婦產(chǎn)科醫(yī)生醫(yī)患溝通技巧
- 內(nèi)科學(xué)糖尿病教案
- 《高尿酸血癥》課件
- 微量泵的操作及報(bào)警處置課件查房
- 人教版小學(xué)數(shù)學(xué)四年級(jí)上冊(cè)5 1《平行與垂直》練習(xí)
評(píng)論
0/150
提交評(píng)論