文檔簡介
1、拱肋吊裝施工方案細則 校對:審批:目 錄一, 工程概況 二, 編制依據(jù)三, 吊裝施工前打算四, 吊裝工藝流程五, 質(zhì)量要求和技術(shù)要求六, 平安文明施工一, 工程概況福元路大橋主橋由兩個邊跨主橋及一個中跨主橋組成。每跨主縱梁沿縱向劃分為10個吊裝節(jié)段,其編號分別為G1G10節(jié)段。東拱(單片拱肋)序號節(jié)段編號單位B+CD+E1F1F21單個節(jié)段重量t365551.359.255252吊裝重量t91110.55525中拱(單片拱肋)序號節(jié)段編號單位B+CD+E1D+E2F1F21單個節(jié)段重量t365551.359.251.350.855252總重t91110.5102.15525西拱(單片拱肋)序號
2、節(jié)段編號單位B+CD+E2F1F21單個節(jié)段重量t365551.350.855253總重t91102.15525編制依據(jù):1, 長沙市福元路湘江大橋主橋主縱梁及主拱吊裝工藝設(shè)計2, 鋼結(jié)構(gòu)工程施工質(zhì)量驗收規(guī)范GB5020520013, 建筑鋼結(jié)構(gòu)焊接規(guī)程JGJ81914, 高層民用建筑鋼結(jié)構(gòu)技術(shù)規(guī)程JGJ99985, 建筑工程施工質(zhì)量驗收統(tǒng)一標準GB5030020016, 建筑施工高處作業(yè)平安技術(shù)規(guī)范JGJ80917, 建筑工程施工現(xiàn)場供用電平安規(guī)范GB50194938, 工程測量規(guī)范GB50026939, 建筑施工平安檢查標準JGJ959910, 鋼結(jié)構(gòu)高強螺栓連接的設(shè)計, 施工驗收規(guī)范JG
3、J829111, 其它相關(guān)現(xiàn)行國家標準, 規(guī)范和規(guī)程。三, 吊裝施工前打算1, 技術(shù)打算1.1, 依據(jù)圖紙和施工現(xiàn)場的實際狀況,對安裝人員進行吊裝前的技術(shù)交底,和部分吊裝工程材料及人員支配,做好充分打算,依據(jù)圖紙尺寸進行主縱梁和拱肋軸線定位。 1.2, 吊裝前的清理和設(shè)備檢修在主縱梁, 鋼拱吊裝前,施工人員要做好120T門吊周邊和鋼梁周邊的障礙物清理工作,確保吊裝施工順當進行。對運用的機械和檢測設(shè)備性能進行檢驗,保證在吊裝過程中設(shè)備工作狀態(tài)良好,運用功能齊全。四, 吊裝工藝流程鋼拱梁單元件在廠內(nèi)下料加工,并組裝成運輸節(jié)段運至橋位散裝拼裝場地,在散拼場組裝成吊裝節(jié)段,吊裝節(jié)段由平臺小車運至120
4、T門吊下,吊起上頂推平臺安裝。一孔鋼拱梁拼裝主要包括拱梁節(jié)點, 主縱梁, 端橫梁, 中橫梁, 小縱梁, 拱肋, 風撐, 臨時撐桿等。鋼拱梁拼裝依次:先梁后拱,主梁與拱肋采納左右對稱安裝,從每跨兩端向中間合攏的方式進行。主梁實行“雙主梁(分開)+橫梁”的安裝施工工藝。 鋼拱梁采納龍門吊結(jié)合支架法進行拼裝,總體拼裝依次實行“先梁后拱,從兩端向中間合攏”的方式,即主梁拼焊完成后,再拼裝鋼拱肋。第一孔鋼拱梁在拼裝平臺上完成拼裝后,即主梁拼焊完成后,再拼裝鋼拱肋。第一孔鋼拱梁在拼裝平臺完成拼裝后,安裝拱梁臨時撐桿。然后拆除拼裝平臺上梁段臨時支撐和拱肋支架,采納步履式頂推工藝將該孔鋼拱梁頂推出拼裝平臺,再
5、拼裝下一孔鋼拱梁,再將其頂推出拼裝平臺,最終拼裝第三孔鋼拱梁,三孔鋼拱梁拼裝全部完成后一起頂推至橋位。(一)拱肋吊裝1, 用龍門吊將G4節(jié)段運輸至安裝位置上方,緩慢落鉤;將G4節(jié)段下落至距安裝標高約500mm處;掛上纜風索及手拉葫蘆。 2, 通過手拉葫蘆調(diào)整G4節(jié)段的平面位置,平面位置偏差需限制在30mm之內(nèi),最大不超過50mm;將G4節(jié)段下放在臨時支座上;解開吊鉤;利用三項千斤頂調(diào)整G4節(jié)段平面位置與高程,滿意要求后固定纜風索。3, 重復步驟一步驟二,依次完成橫橋向, 順橋向?qū)ΨQ的其余兩個節(jié)段。4, 用與吊裝節(jié)段G4相同的方法與次序吊裝G3, G2節(jié)段(每個節(jié)段調(diào)位完畢后與G4節(jié)段臨時連接)
6、。G3節(jié)段定位完成后,起先定位G4, G3之間的風撐,并焊接,使得兩側(cè)的拱肋形成一個整體,提高整體的穩(wěn)定性。5, 用與吊裝節(jié)段G4相同的方法與次序吊裝G2節(jié)段(每個節(jié)段調(diào)位完畢后與G3節(jié)段臨時連接)。G2節(jié)段定位完成后,起先定位G2之間的風撐,并焊接。6, 在溫度相對穩(wěn)定的條件下,測量, 切割余量后吊裝單側(cè)G1節(jié)段(拱肋合攏段)。并安裝中間風撐。7, 拱肋節(jié)段吊裝驗算依據(jù)表拱肋節(jié)段長度劃分,吊裝時G3節(jié)段時應力, 變形最大,取G3節(jié)段進行應力, 變形驗算,驗算長度取34m,重量110t,分起吊狀態(tài)和就位狀態(tài)兩種工況。 起吊狀態(tài)按最不利狀況分析,簡化為單點起吊,吊點在節(jié)段正上方,其應力及變形結(jié)果
7、如下圖:應力云圖(單位:Mpa)位移云圖(單位:mm)由上述ANASYS電算結(jié)果可知,在起吊狀態(tài)節(jié)段端頭下?lián)希簇Q向變位)10.2mm,最大應力 56.8MPa。 就位狀態(tài)拱肋節(jié)段吊裝就位后,支座布置在拱肋兩端時為最不利工況,其應力及變形結(jié)果如下圖:應力云圖(單位:Mpa)位移云圖(單位:mm)由上述電算結(jié)果,拱節(jié)段在就位狀態(tài)時拱頂沉降(即豎向變位)8.3mm,最大應力 134MPa。(三)吊裝鋼絲繩選擇與計算1吊點的設(shè)置主拱最重的為主縱梁G3節(jié)段,總重接近115T。依據(jù)長沙市福元路湘江大橋主橋主縱梁及主拱吊裝工藝設(shè)計圖紙。索力最大389KN。選用直徑65mm的637鋼絲繩,鋼絲的強度極限值要
8、求為1700Mpa,查規(guī)范得鋼絲繩的破斷拉力總和為2665KN。表2 637鋼絲繩直 徑鋼絲總截面 積參考重量鋼絲繩公稱抗拉強度(N/ mm2)鋼絲繩鋼 絲14002000鋼絲繩破斷拉力總和(mm)(mm2)(/100m)kN (不小于)8.70.427.8826.2139.0043.2047.3051.5055.7011.00.543.5740.9660.9067.5074.0080.6087.1013.00.662.7458.9887.8097.20106.50116.00125.0015.00.785.3980.57119.50132.00145.00157.50170.5017.50.
9、8111.53104.8156.00172.50189.50206.00223.0019.50.9141.16132.7197.50213.50239.50261.00282.0021.51.0174.27163.3243.50270.00296.00322.00348.5024.01.1210.87198.2295.00326.50358.00390.00421.5026.01.2250.95235.9351.00388.50426.50464.00501.5028.01.3294.52276.8412.00456.50500.50544.50589.0030.01.4341.57321.1
10、478.00529.00580.50631.50683.0032.51.5392.11368.6548.50607.50666.50725.00784.0034.51.6446.13419.4624.50691.50758.00825.00892.0036.51.7503.64473.4705.00780.50856.00931.501005.0039.01.8564.63580.8790.00875.00959.501040.001125.0043.02.0697.08655.3975.501080.001185.001285.001390.0047.52.2843.47792.91180.
11、001305.001430.001560.0052.02.41003.80943.61405.001555.001705.001855.0056.02.61178.071107.41645.001825.002000.002175.0060.52.81366.281234.31910.002115.002320.002525.0065.03.01568.431474.32195.002430.002665.002900.00鋼絲繩容許拉力(平安荷載)按下式計算:S=Sb/k=pg/K=0.8226655=437.1KN其中:考慮鋼絲繩之間荷載不勻稱系數(shù),637鋼絲繩取0.82;pg鋼絲繩的破斷
12、拉力總和,查表得鋼絲繩強度極限為1700Mpa的65mm鋼絲繩的破斷拉力總和為2665KN;K鋼絲繩運用平安系數(shù),作為吊索無繞曲時取5。計算得:S=437.1KN389KN,滿意吊裝荷載的要求。2, 拱肋的拼裝調(diào)位拱肋拼裝調(diào)位的方法與主縱梁調(diào)位方法一樣。調(diào)位系統(tǒng)布設(shè)于拱肋橫隔板下方,調(diào)位系統(tǒng)布置圖見圖拱肋調(diào)位系統(tǒng)布置圖。圖拱肋調(diào)位系統(tǒng)布置圖五, 質(zhì)量要求和技術(shù)要求本工程施工中肯定依據(jù)鋼結(jié)構(gòu)工程質(zhì)量驗收規(guī)范和建筑工程規(guī)范的規(guī)定外,還必需做到以下幾點:1, 加強質(zhì)量管理措施,加強對施工人員的質(zhì)量意識,進一步提高全體人員對質(zhì)量的相識,實行工程質(zhì)量獎罰制度。 2, 加強建立質(zhì)量限制點,抓住關(guān)鍵部位,預防質(zhì)量通病發(fā)生,要
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 二零二五年度大米新品種研發(fā)與推廣合同4篇
- 2025年度商鋪租賃合同環(huán)保與節(jié)能條款規(guī)范2篇
- 二零二五年度智能交通標示牌系統(tǒng)集成與運營合同3篇
- 二零二五年度房地產(chǎn)項目存單質(zhì)押擔保合同4篇
- 二零二五年度農(nóng)產(chǎn)品冷鏈物流合同協(xié)議帶產(chǎn)地直供保障2篇
- 二零二五年度農(nóng)產(chǎn)品供應鏈質(zhì)押融資合同4篇
- 2025年度高效大棚種植項目承包合同4篇
- 二零二五年度企業(yè)財產(chǎn)重組分配合同2篇
- 2025年度創(chuàng)業(yè)園區(qū)場地租賃合同(含投資扶持)2篇
- 2025年度車牌號碼數(shù)據(jù)安全保護合同4篇
- 口腔醫(yī)學中的人工智能應用培訓課件
- 工程質(zhì)保金返還審批單
- 【可行性報告】2023年電動自行車項目可行性研究分析報告
- 五月天歌詞全集
- 商品退換貨申請表模板
- 實習單位鑒定表(模板)
- 六西格瑪(6Sigma)詳解及實際案例分析
- 機械制造技術(shù)-成都工業(yè)學院中國大學mooc課后章節(jié)答案期末考試題庫2023年
- 數(shù)字媒體應用技術(shù)專業(yè)調(diào)研方案
- 2023年常州市新課結(jié)束考試九年級數(shù)學試卷(含答案)
- 正常分娩 分娩機制 助產(chǎn)學課件
評論
0/150
提交評論