/青建集團(tuán)股份公司施工方案山東省第23屆運動會綜合指揮中心工程輕鋼龍骨墻板施工方案(B—QL01)批準(zhǔn):審核:編制:青建集團(tuán)股份公司房建二分公司二O一二年四月目次一.工程概況···················································2二.施工準(zhǔn)備···················································21.材料準(zhǔn)備····················································22.主要機(jī)具····················································23.作業(yè)條件····················································24.施工工藝····················································35.質(zhì)量標(biāo)準(zhǔn)····················································96.施工試驗支配···············································107.平安生產(chǎn)、現(xiàn)場文明施工要求··································108.成品愛惜···················································109.工程質(zhì)量驗收···············································1010.主要工程質(zhì)量通病治理措施·································10

11.編制依據(jù)··················································1112.節(jié)點詳圖··················································11一.工程概況:本工程為濟(jì)寧綜合指揮中心輕鋼龍骨墻板安裝項目。其中輕鋼龍骨紙面石膏板120厚為設(shè)計基準(zhǔn),主要用于地上一般用房,如辦公室、會議室、備用房間等房間隔墻。雙面雙層內(nèi)填50厚巖棉(12+12+75+12+12)其中用于會議室等有隔聲要求的房間,要求空氣聲隔聲標(biāo)準(zhǔn)(A聲級)大于50dB。墻體的耐火極限應(yīng)滿足1小時。輕鋼龍骨埃特板(硅酸鈣板)隔墻120厚為設(shè)計基準(zhǔn),主要用于衛(wèi)生間、清潔間、淋浴間等有水的房間,雙面單層內(nèi)填50巖棉的做法(10+100+10),獨立的或者和衛(wèi)生間相鄰的開水間維護(hù)墻體運用硅酸鈣板隔墻。有水房間和無水房間之間的隔墻接受一面單層埃特板(硅酸鈣板)一面雙層紙面石膏板(10+100+12+12)。由于一、二層層超群過5米,按圖集《8BJ2-5(88J)墻身-輕鋼龍骨紙面石膏板(2007)》常規(guī)做法不能保證墻身穩(wěn)定性,等需等設(shè)計出特地加固方案,本方案僅適用二層以上部位的輕鋼龍骨隔墻的施工。二.施工準(zhǔn)備:1.材料準(zhǔn)備:1.1輕鋼龍骨:目前隔墻工程運用的輕鋼龍骨主要有支撐卡系列的通貫龍骨,品牌為龍牌或億博。輕鋼龍骨主件有沿頂沿地龍骨、加強龍骨、豎(橫)向龍骨、橫撐龍骨。輕鋼龍骨配件有支撐卡、卡托、角托、連接件、固定件、護(hù)角條、壓縫條等。輕鋼龍骨的配置應(yīng)符合設(shè)計要求。龍骨應(yīng)有產(chǎn)品質(zhì)量合格證。龍骨外觀應(yīng)表面平整,棱角挺直,過渡角及切邊不允許有裂口和毛刺,表面不得有嚴(yán)峻的污染、腐蝕和機(jī)械損傷。1.2緊固材料:M8膨脹螺栓、鍍鋅自攻螺絲(單層l2mm厚紙面石膏板/10mm硅酸鈣板用25mm長螺絲,兩層12mm厚紙面石膏板用35mm長螺絲)等,應(yīng)符合設(shè)計要求。1.3填充材料:50厚巖棉等按設(shè)計要求選用。

1.4紙面石膏板、埃特板(硅酸鈣板):紙面石膏板應(yīng)有產(chǎn)品合格證,品牌為龍牌、億博或者泰山。本工程接受12厚紙面石膏板和10厚埃特板(硅酸鈣板)。

1.5接縫材料:接縫膩子、玻纖帶(布)、108膠。

接縫膩子:抗壓強度>0.3MPa,抗折強度>1.5MPa,終凝時間>0.5h。

1.5.250mm中堿玻纖帶和玻纖網(wǎng)格布:

布重>80g/m2

斷裂強度:25mm×100mm布條,經(jīng)向>300N,緯向>150N。2.主要機(jī)具板鋸、電動剪、電動自攻鉆、電動無齒鋸、手電鉆、直流電焊機(jī)、刮刀、線墜、靠尺等。

3.作業(yè)條件

3.1主體結(jié)構(gòu)已驗收。

3.2室內(nèi)彈出+100cm標(biāo)高限制線。

3.3熟悉圖紙,并向作業(yè)班組作詳細(xì)的技術(shù)交底。

3.4依據(jù)設(shè)計圖和提出的備料支配,檢查隔墻全部材料,使其配套齊全。安裝各種系統(tǒng)的管、線盒及其他準(zhǔn)備工作已到位。

3.5主體結(jié)構(gòu)墻為磚砌體時,應(yīng)在隔墻交接處,按1000mm間距預(yù)埋防腐木磚。

3.6先作樣板墻一道,經(jīng)鑒定合格后再大面積施工。

4.施工工藝4.1工藝流程圖1輕鋼龍骨隔墻施工流程4.

2彈線、分檔

在隔墻和上、下及兩邊基體的相接處,應(yīng)按龍骨的寬度彈線。彈線清楚,位置精確。按設(shè)計要求,結(jié)合罩面板的長、寬分檔,以確定豎向龍骨、橫撐及附加龍骨的位置。圖2龍骨布置示意4.3踢腳部位處理

由于室內(nèi)三層以上地面建筑做法僅50,為了保證100高踢腳做法,取消地枕,在結(jié)構(gòu)面設(shè)置方鋼管將地龍骨抬起,在踢腳板高度范圍內(nèi)設(shè)防腐處理后的9厘板作為黏貼100高踢腳板的基層,詳圖3詳圖3踢腳線細(xì)部處理

4.

4沿頂、沿地固定龍骨

按彈線位置固定沿頂、沿地龍骨,可用M8*50膨脹螺栓固定,固定點間距600mm,龍骨對接應(yīng)平直。細(xì)部處理見圖3和圖4.圖4無吊頂房間隔墻頂部處理圖5有吊頂房間頂部處理

4.5固定邊框龍骨

沿彈線位置固定邊框龍骨,龍骨的邊線應(yīng)和彈線重合。龍骨的端部應(yīng)固定,固定點間距應(yīng)不大于1000mm,固定應(yīng)堅實。

邊框龍骨和基體之間,應(yīng)按設(shè)計要求安裝密封條。

4.6選用支撐卡系列龍骨時,應(yīng)先將支撐卡安裝在豎向龍骨的開口上,卡距為400~750mm,龍骨兩端的距離為25mm。

4.7安裝豎向龍骨應(yīng)垂直,其中衛(wèi)生間(貼面磚墻體)部位豎向龍骨間距300mm,其它房間豎向間距400mm

4.8選用通貫系列龍骨時,低于3000的隔墻宜安裝1道,3000-5000高的隔墻宜安裝2道,5000以上的宜安裝3道。

4.9罩面板橫向接縫處,如不在沿頂、沿地龍骨上,應(yīng)加橫撐龍骨固定板縫。

4.10門窗及轉(zhuǎn)角節(jié)點處,其他薄弱點為保證墻體穩(wěn)定性,需進(jìn)行加固處理。門框接受單獨方鋼管門框系統(tǒng),詳附圖:圖6門窗頂部龍骨連接構(gòu)造C75系列門框加固處理C100系列門框加固處理4.11對于特殊結(jié)構(gòu)的隔墻龍骨安裝(如曲面、斜面隔墻等),應(yīng)符合設(shè)計要求。

4.12電氣鋪管、安裝附墻設(shè)備

按圖紙要求預(yù)埋管道和附墻設(shè)備。要求和龍骨的安裝同步進(jìn)行,或在另一面石膏板封板前進(jìn)行,并實行局部加強措施,固定堅實。電氣設(shè)備專業(yè)在墻中鋪設(shè)管線時,應(yīng)避開切斷橫、豎向龍骨,同時避開在沿墻下端設(shè)置管線。

4.13龍骨檢查校正補強

安裝罩面板前,應(yīng)檢查隔斷骨架的堅實程度,門窗框、各種附墻設(shè)備、管道的安裝和固定是否符合設(shè)計要求。如有不堅實處,應(yīng)進(jìn)行加固。

4.14安裝石膏/埃特板(硅酸鈣板)罩面板

(1)紙面石膏板/埃特板(硅酸鈣板)宜豎向鋪設(shè),長邊(即包封邊)接縫應(yīng)落在豎龍骨上。曲面墻所用紙面石膏板/硅酸鈣板宜橫向鋪設(shè)。

(2)龍骨兩側(cè)的紙面石膏板/埃特板(硅酸鈣板)及龍骨一側(cè)的內(nèi)外兩層紙面石膏板應(yīng)錯縫排列,接縫不得落在同一根龍骨上。

(3)紙面石膏板/埃特板(硅酸鈣板)用自攻螺釘固定。沿紙面石膏板/硅酸鈣板周邊螺釘間距不應(yīng)大于200mm,中間部分螺釘間距不應(yīng)大于300mm,螺釘和板邊緣的距離應(yīng)為10~16mm。

(4)安裝紙面石膏板時,應(yīng)從板的中部向板的四邊固定,釘頭略埋入板內(nèi),但不得損壞紙面。釘眼應(yīng)用石膏膩子抹平。

(5)紙面石膏板/埃特板(硅酸鈣板)宜運用整板。如需對接時,應(yīng)緊靠,但不得強壓就位。

(6)隔墻端部的紙面石膏板/埃特板(硅酸鈣板)和四周的墻或柱應(yīng)留有3mm的槽口。施工時,先在槽口處加注嵌縫膏,然后鋪板,擠壓嵌縫膏使其和鄰近表層緊密接觸。圖8丁字墻墻細(xì)部處理圖8十字交叉墻細(xì)部處理圖7拐角墻細(xì)部處理(7)隔墻板的下端如用木踢腳板覆蓋,罩面板應(yīng)離地面20~30mm;用大理石、水磨石踢腳板時,罩面板下端應(yīng)和踢腳板上口齊平,接縫嚴(yán)密。

(8)鋪放墻體內(nèi)的玻璃棉、礦棉板、巖棉板等填充材料,和安裝另一側(cè)紙面石膏板/硅酸鈣板同時進(jìn)行,填充材料應(yīng)鋪滿鋪平。

4.15接縫及護(hù)角處理

(1)紙面石膏板/埃特板(硅酸鈣板)墻接縫做法有3種形式,即平縫、凹縫和壓條縫。一般做平縫較多,可按以下程序處理:

1)紙面石膏板/埃特板(硅酸鈣板)安裝時,其接縫處應(yīng)適當(dāng)留縫(一般3~6mm),并必需坡口和坡口相接,接縫內(nèi)浮土清除干凈后,刷一道50%濃度的108膠水溶液。

2)用小刮刀把WKF接縫膩子嵌入板縫,板縫要嵌滿嵌實,和坡口刮平。待膩子干透后,檢查嵌縫處是否有裂紋產(chǎn)生,如產(chǎn)生裂紋要分析緣由,并重新嵌縫。

3)在接縫坡口處刮約1mm厚的WKF膩子,然后粘貼玻纖帶,壓實刮平。

4)當(dāng)膩子起先凝固又尚處于潮濕狀態(tài)時,再刮一道WKF膩子,將玻纖帶埋入膩子中并將板縫填滿刮平。

5)陰角的接縫處理方法同平縫。

(2)陽角可按以下方法處理:

1)陽角粘貼兩層玻纖布條,角兩邊均拐過100mm,粘貼方法同平縫處理,表面亦用接縫膩子刮平。

2)當(dāng)有部位做金屬護(hù)角條時,按要求的部位、高度,先刮一層膩子,隨即用鍍鋅釘固定金屬護(hù)角條,并用膩子刮平。

4.16待板縫膩子干燥后,檢查板縫是否有裂縫產(chǎn)生,如發(fā)覺裂紋,必需圖8丁字墻墻細(xì)部處理圖8十字交叉墻細(xì)部處理圖7拐角墻細(xì)部處理5質(zhì)量標(biāo)準(zhǔn)

5.1主控項目

(1)骨架隔墻所用龍骨、配件、墻面板、填充材料及嵌縫材料的品種規(guī)格性能和木材的含水率應(yīng)符合設(shè)計要求。有隔聲、隔熱、阻燃、防潮等特殊要求的工程材料應(yīng)有相應(yīng)性能等級的檢測報告。

檢驗方法:視察;檢查產(chǎn)品合格證書、進(jìn)場驗收記錄、性能檢測報告和復(fù)驗報告。

(2)骨架隔墻工程邊框龍骨必需和基體結(jié)構(gòu)連接堅實,并應(yīng)平整、垂直、位置正確。

檢驗方法:手扳檢查、尺量檢查、檢查隱藏工程驗收記錄。

(3)骨架隔墻中龍骨間距和構(gòu)造連接方法應(yīng)符合設(shè)計要求。骨架內(nèi)設(shè)備管線的安裝、門窗洞口等部位加強龍骨應(yīng)安裝堅實、位置正確,填充材料的設(shè)置應(yīng)符合設(shè)計要求。

檢驗方法:檢查隱藏工程驗收記錄。

(4)骨架隔墻的墻面板應(yīng)安裝堅實。無脫層、翹曲、折裂及缺損。

檢驗方法:視察;手扳檢查。

(5)墻面板所用接縫材料和接縫方法應(yīng)符合設(shè)計要求。

檢驗方法:視察。

5.2一般項目

(1)骨架隔墻表面應(yīng)平整光滑、色澤一樣、干凈、無裂縫,接縫應(yīng)勻整、順直。

檢驗方法:視察;手摸檢查。

(2)骨架隔墻上的孔洞、槽、盒應(yīng)位置正確、套割吻合、邊緣整齊。

檢驗方法:視察。

(3)骨架隔墻內(nèi)的填充材料應(yīng)干燥,填充應(yīng)密實、勻整、無下墜。

檢驗方法:輕敲檢查;檢查隱藏工程驗收記錄。

(4)輕鋼龍骨紙面石膏板/硅酸鈣板罩面隔墻安裝的允許偏差和檢驗方法應(yīng)符合表5.4.4.2.(4)的規(guī)定。

表5.4.4.2.⑷輕鋼龍骨紙面石膏板/硅酸鈣板項次項目允許偏差(mm)檢驗方法1立面垂直度3用2m垂直檢測尺檢查2表面平整度3用2m靠尺和塞尺檢查3陰陽角方正3用直角檢測尺檢查4接縫凹凸差1用鋼直尺和塞尺檢查6.施工試驗支配

6.1各分項工程的檢驗批應(yīng)按下列規(guī)定劃分:

同一品種的輕質(zhì)隔墻工程每50間(大面積房間和走廊按輕質(zhì)隔墻的墻面30m2為一間)應(yīng)劃分為一個檢驗批,不足50間也應(yīng)劃分為一個檢驗批。

6.

2民用建筑輕質(zhì)隔墻工程的隔聲性能應(yīng)符合現(xiàn)行國家標(biāo)準(zhǔn)《民用建筑隔聲設(shè)計規(guī)范》GBJ118的規(guī)定。

6.3輕鋼龍骨紙面石膏板/硅酸鈣板罩面隔墻工程的檢查數(shù)量應(yīng)符合下列規(guī)定:

每個檢驗批應(yīng)至少抽查10%并不得少于3間;不足3間時應(yīng)全數(shù)檢查。

7平安生產(chǎn)、現(xiàn)場文明施工要求

7.1隔墻工程的腳手架搭設(shè)應(yīng)符合建筑施工平安標(biāo)準(zhǔn)。

7.2腳手架上搭設(shè)跳板應(yīng)用鐵絲綁扎固定,不得有探頭板。

7.3工人操作應(yīng)戴平安帽,骨架施工嚴(yán)格防火措施。

7.4施工現(xiàn)場必需工完場清。設(shè)專人灑水、打掃,不能揚塵污染環(huán)境。

7.5有噪聲的電動工具應(yīng)在規(guī)定的作業(yè)時間內(nèi)施工,防止噪聲污染、擾民。

7.6機(jī)電器具必需安裝觸電愛惜裝置。發(fā)覺問題立刻修理。

7.7遵守操作規(guī)程,非操作人員決不準(zhǔn)亂動機(jī)具,以防傷人。

7.8現(xiàn)場保持良好通風(fēng),但不宜有過堂風(fēng)。

8成品愛惜

8.1輕鋼骨架隔墻施工中,各工種間應(yīng)保證已安裝項目不受損壞,墻內(nèi)電線管及附墻設(shè)備不得碰動、錯位及損傷。

8.2輕鋼龍骨及紙面石膏板/硅酸鈣板入場時,存放運用過程中應(yīng)妥當(dāng)保管,保證不變形、不受潮、不污染、無損壞。

8.3施工部位已安裝的門窗、地面、墻面、窗臺等應(yīng)留意愛惜,防止損壞。

8.4已安裝好的墻體不得碰撞,保持墻面不受損壞和污染。

9工程質(zhì)量驗收

9.1施工時依據(jù)施工工藝,嚴(yán)格限制每一步質(zhì)量,做好自檢工作,并且會同監(jiān)理做好抽檢和驗評工作。

9.2檢驗批的合格判定應(yīng)符合下列規(guī)定:

(1)抽查樣本均應(yīng)符合主控項目的規(guī)定。

(2)抽查樣本的80%以上應(yīng)符合一般項目的規(guī)定。其余樣本不得存在影響運用功能或明顯影響裝飾效果的缺陷,其中有允許偏差的檢查項目,其最大偏差不得超過允許偏差的1.5倍。

9.3輕鋼龍骨紙面石膏板/硅酸鈣板罩面隔墻工程驗收時應(yīng)檢查下列文件和記錄:

(1)輕質(zhì)隔墻工程的施工圖、設(shè)計說明及其他設(shè)計文件。

(2)材料的產(chǎn)品合格證書、性能檢測報告、進(jìn)場驗收記錄和復(fù)驗報告。

(3)隱藏工程驗收記錄。

(4)施工記錄。

9.4輕鋼龍骨紙面石膏板/硅酸鈣板

溫馨提示

  • 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
  • 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。

評論

0/150

提交評論