




版權(quán)說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請進行舉報或認領(lǐng)
文檔簡介
1、PMPPreparationTraining,CostManagement,Chapter7,Project Cost Management,Resource Planning Cost Estimating Cost Budgeting Cost Control,Processes required to ensure the project is completed within the approved budget,Cost Management,7.1 Resource Planning,Planning,7.3 Cost Budgeting,7.4 Cost Control,Con
2、trolling,7.2 Cost Estimating,Resource Planning,Determining physical resources needed (i.e., material, equipment, and people) and what quantities of each should be used and when they would be needed to perform project activities,Resource Planning,Inputs Scope statement WBS Resource pool description O
3、rganizational policies Historical information Activity durations estimates,Tools Always scheduled to occur in the future,Work Packages Detailed, short-span tasks or material items; Required to accomplish the CA objectives; Typically for the near term,Control Account Elements,Cost Control,Performance
4、 Measurement Baseline (PMB),The plan against which actual performance can be compared Based on budgets assigned to scheduled segments of work Build PMB by summing the PV for all control accounts, by reporting period Budget at completion (BAC) Equal to the cumulative PV for the total project,Cost Con
5、trol,Time-Phased Budget,Performance Measurement Baseline (PMB),BAC,Cost Control,Work schedule to be accomplished,Planned Value (PV),Cost Control,Budgeted value of completed or in-process work,Performance Measurement Baseline,0,10000,20000,30000,40000,50000,60000,70000,80000,JANUARY,FEBRUARY,MARCH,AP
6、RIL,MAY,JUNE,JULY,CURRENT,EV,PV,PV,EV,JANUARY,0,0,FEBRUARY,2500,3600,MARCH,8000,8000,APRIL,13000,10000,MAY,42000,38000,JUNE,62000,JULY,70700,Earned Value,Cost Control,Actual Costs (AC),Actual expenditures for completed or in-process work,Cost Control,PV,EV,AC,JANUARY,0,0,0,FEBRUARY,2500,3600,6000,MA
7、RCH,8000,8000,8000,APRIL,13000,10000,8000,MAY,42000,38000,48000,JUNE,62000,JULY,70700,Schedule Variance,Comparing the EV, the amount originally budgeted for the work that has been completed or is in-process, to the PV, the amount budgeted for the work that was planned to have been accomplished SV =
8、EV PV A negative result means less work has been performed than was planned,Cost Control,SV Example,PV = $42,000 EV = $38,000 AC = $48,000 SV = EV PV = $38,000 $42,000 = - $4,000 SV% = SV / PV =- $4000 / $42,000 = - 0.095 = - 9.5%,Cost Control,Cost Variance,Comparing the amount originally budgeted f
9、or the work completed or in-process, the EV, to the actual costs of that work, the AC CV = EV AC A negative CV means more dollars were spent to accomplish the work than was planned,Cost Control,Cost Variance Example,PV = $42,000 EV = $38,000 AC = $48,000 CV = EV - AC = $38,000 $48,000 = - $10,000 CV
10、% = CV / EV = - $10,000 / $38,000 = - 26%,Cost Control,Performance Indices,Dfn: Cost- and schedule-performance efficiency calculations; expressed in $ Cost Performance Index (CPI) CPI = EV/AC Schedule Performance Index (SPI) SPI = EV/PV,Cost Control,CPI Example,PV = $42,000 EV = $38,000 AC = $48,000
11、 CPI = EV / AC = $38,000 / $48,000 = 0.79 $0.79 worth of work was actually done for each $1.00 spent,Cost Control,SPI Example,PV = $42,000 EV = $38,000 AC = $48,000 SPI = EV / PV = $38,000 / $42,000 = 0.90 $0.90 worth of work has been done for each $1.00 worth of work that was planned to be done,Cos
12、t Control,Estimate at Completion (EAC),Dfn: The managements assessment of the cost of the project at completion After variance analysis, the estimated cost at completion is determined,Cost Control,EAC Example,One methodology: EAC = BAC / CPI BAC = $80,000 CPI = 0.79 EAC = $80,000 / 0.79 = $101,265,C
13、ost Control,Variance at Completion,BAC = $80,000 EAC = $101,265 VAC = BAC EAC = $80,000 $101,265 = -$21,265 Based on past performance, project will exceed planned budget by $21,265,Cost Control,To Complete Performance Index (TCPI),Work Remaining / Cost Remaining TCPI = (BAC EV) / (EAC AC) = ($ 80,00
14、0 $ 38,000) / ($ 101,265 $ 48,000) = $ 42,000 / $ 53,265 = .79,Cost Control,Earned Value Examples,PVEVAC $1$1$1On scheduleOn cost $2$2$1On scheduleUnder cost $1$1$2On scheduleOver cost $1$2$2Ahead of scheduleOn cost $1$2$3Ahead of scheduleOver cost $1$2$1Ahead of scheduleUnder cost $3$2$1Behind sche
15、duleUnder cost $2$1$3Behind scheduleOver cost $2$1$1Behind scheduleOn cost,Cost Control,Example,PVEV ACEAC BAC 100125 75600 560 125100 100850 800 75 75 75700560 100 75 100570 600,Cost Control,Sample Cost Problem,BAC = $ 40k EV = $ 20k PV = $ 28k AC = $ 26k,Calculate % of Work Scheduled % of Budget S
16、pent % of Work Accomplished Cost Variance Schedule Variance,Cost Control,Sample Solution,Calculate % of Work ScheduledPV / BAC = $ 28K / $ 40K = 70 % % of Budget SpentAC / BAC = $ 26K / $ 40K = 65 % % of Work Accomplished EV / BAC = $ 20K / $ 40K = 50 % Cost VarianceEV AC = $ 20K $ 26K = - $ 6K Sche
17、dule Variance EV PV = $ 20K $ 28K = - $ 8K,Cost Control,Summary,Review Questions,Case 1,PV = $ 1,860 EV = $ 1,860 AC = $ 1,860,This is the ideal situation, where everything goes according to plan.,Case 2,PV = $ 1,900 AC = $ 1,700,In this Case, without Earned Value measurements, it appears were in go
18、od shape. Expenditures are less than planned.,Spending Variance = - $ 200,Case 2,PV = $ 1,900 EV = $ 1,500 AC = $ 1,700,But with EV measurements, we see.$400 worth of work is behind schedule in being completed; i.e., we are 21 percent behind where we planned to be.,SV = EV PV = - $ 400 SV % = SV / P
19、V x 100 = - 21 %,Case 2,PV = $ 1,900 EV = $ 1,500 AC = $ 1,700,In addition, we can see. “Actuals” exceed “Value Earned” (EV), i.e., $1,500 worth of work was accomplished but it cost $1,700 to do so. We have a $200 cost overrun (i.e., 13% over budget) .,CV = EV AC = - $ 200 CV % = CV / EV x 100 = - 1
20、3 %,Case 2,PV = $ 1,900 EV = $ 1,500 AC = $ 1,700,This means only 79 cents worth of work was done for each $1.00 worth of work planned to be done. And, only 88 cents worth of work was actually done for each $1.00 spent,SPI = EV / PV = $ 0.79 CPI = EV / AC = $ 0.88,Case 2,PV = $ 1,900 EV = $ 1,500 AC
21、 = $ 1,700,This is the worst kind of scenario, where all performance indicators are negative.,SV = - $ 400; SPI = 0.79 CV = - $ 200; CPI = 0.88,PV = $ 2,600 EV = $ 2,400 AC = $ 2,200,In this case there is bad news and good news.,Case 3,PV = $ 2,600 EV = $ 2,400 AC = $ 2,200,The bad news is that our
22、work efficiency is a bit low; were getting only 92 cents of work done on the dollar. As a result, we are behind schedule.,SPI = 0.92 SV = - $ 200; SV % = - 8 %,Case 3,PV = $ 2,600 EV = $ 2,400 AC = $ 2,200,The good news is that were under-running our budget. Were getting $1.09 worth of work done for
23、 each $1.00 were spending.,CV = + $ 200; CV % = + 8 % CPI = 1.09,Case 3,Case 4,PV = $ 1,700 EV = $ 1,500 AC = $ 1,500,In this case, the work is not being accomplished on schedule.,SV = - $ 200; SV % = - 12 % SPI = 0.88,Case 4,PV = $ 1,700 EV = $ 1,500 AC = $ 1,500,.but the cost of the work accomplis
24、hed is just as we budgeted.,CV = $ 0.00 CPI = 1.00,Case 5,PV = $ 1,400 EV = $ 1,600 AC = $ 1,400,A positive scenario; right? But is it because we are out-performing our learning-curve standards or because we planned too pessimistically?,Case 5,PV = $ 1,400 EV = $ 1,600 AC = $ 1,400,Here in this case
25、, we are getting work done at 114 percent efficiency.,SPI = 1.14 CPI = 1.14,Case 5,PV = $ 1,400 EV = $ 1,600 AC = $ 1,400,.work is ahead of schedule by 14 percent and under-running cost by 12.5%.,SV = + $ 200; SV % = + 14 % CV = + $ 200; CV % = + 12.5 %,Case 6,PV = $ 2,000 EV = $ 2,200 AC = $ 2,400,
26、In Case 6, work is being done efficiently, but a cost overrun is occurring.,SPI = 1.10 CV = - $ 200; CV % = - 9 %,Case 7,PV = $ 2,200 EV = $ 2,400 AC = $ 2,400,In Case 7, work is being done efficiently, and costs are right on target.,SPI = 1.09 CV = $ 0.00,Case 8,PV = $ 2,000 EV = $ 2,000 AC = $ 2,200,See if you can analyze this one!,Case 8,PV = $ 2,000 EV = $ 2,000 AC = $ 2,200,Were on schedule. But in order to be on schedule, its costing us $1.00 to do each 91-cents worth of work. Theres a $200 overrun as a result.,SV = $ 0.00 CV = - $ 200; C
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 基于保護動機理論的急性脂源性胰腺炎患者延續(xù)性護理方案的構(gòu)建與實施
- 2024年春八年級生物下冊 24.1 人口增長與計劃生育教學實錄 (新版)北師大版
- 2023七年級數(shù)學上冊 第5章 相交線與平行線5.2 平行線 3平行線的性質(zhì)教學實錄 (新版)華東師大版
- DB3713-T 257-2022 邦玉339高產(chǎn)栽培技術(shù)規(guī)程
- DB3708-T 22-2023 短季棉蒜后貼茬直播高效栽培技術(shù)規(guī)程
- 6一封信 (教學設(shè)計)2024-2025學年統(tǒng)編版語文二年級上冊
- 人工智能通識基礎(chǔ) 課件 第5章 人工智能的應用場景
- 5.2 一元一次方程的解法 教學設(shè)計 2024--2025學年北師大版數(shù)學七年級上冊
- 2024年四年級品社下冊《四大發(fā)明》教學實錄 滬教版
- 10愛心的傳遞者 (教學設(shè)計)統(tǒng)編版道德與法治三年級下冊
- 全省檢察機關(guān)公訴業(yè)務知識考試試卷
- 10KV開關(guān)柜教學講解課件
- 損傷疼痛病(軟組織損傷)中醫(yī)臨床路徑
- 航模隊第一講-飛機基本原理和彈射機制作
- 高速鐵路牽引供電系統(tǒng)課件
- 知名房地產(chǎn)抖音代運營方案
- 紅外線測溫技術(shù)方案
- 人教版八年級下冊英語全冊教案完整版教學設(shè)計含教學反思
- 煤礦探放水作業(yè)安全技術(shù)實際操作考試標準
- 銀行案件風險排查方案
- 德育主題班會 《遵義會議》教學課件
評論
0/150
提交評論