版權(quán)說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請進(jìn)行舉報或認(rèn)領(lǐng)
文檔簡介
1、軸系安裝工藝Procedure for shaft installationTCN124P-M012-GY03共 14 頁第 14 頁1.概述: General:1.1本工藝描述了57000DWT散貨船軸系各主要部件安裝以及主機(jī)定位的技術(shù)要求。 This procedure described the technical requirement of shaft components installation and M/E locating of 57000DWT BC. 1.2軸系主要部件包含有,4葉定距螺旋槳一支(直徑6000mm,重約16,347kg),螺旋槳軸1根(500×
2、6505,10211kg),中間軸1根(420×6006,7159kg),艉管裝置1套(3839kg),中間軸承一套(645kg),艉軸首尾密封裝置,軸接地裝置一套。 Main components of shaft include the following parts, one fixed pitch propeller with four blades (diameter 6000mm, weight 16,347kg), one propeller shaft(500×6505,10211kg), one intermediate shaft(420×60
3、06,7159kg), stern tube unit one set(3839kg), intermediate shaft bearing one set(645kg), fore and aft. shaft seal assembly, shaft grounding unit.1.3軸系的安裝工藝流程 Shaft system Installation sequence拉線(照光)艉管定位澆注環(huán)氧主機(jī)底角螺栓孔定位裝螺旋槳軸裝艏艉軸密封裝置安裝無鍵螺旋槳安放中間軸、主機(jī)。船下水后按軸系校中計算法定位軸系及主機(jī)。Pulling wire(Shaft sight)Locating ste
4、rn tube and chock fastLocating M/E holding down boltsInstall propeller shaftInstall shaft seal assemblyInstall propellerPut intermediate shaft and M/E. After vessel launching install and connect the shaft and M/E according to the shaft alignment calculation.注:船下水時,軸和主機(jī)作臨時固定,防止螺旋槳軸轉(zhuǎn)動。具體見“下水封槳封舵工藝”。No
5、te: Before launching fix the shaft and M/E temporarily, avoid turning of propeller shaft. Detail see “Procedure for fix rudder and propeller during launching”.1.4所有軸系零件均為外購成品,尺寸加工到位,在吊運(yùn)、安裝過程中要注意保護(hù)。在進(jìn)行吊裝前應(yīng)仔細(xì)檢查吊運(yùn)工具,如吊索、眼板、卸扣等應(yīng)安全可靠。All the components of shaft is finished production, please pay more att
6、ention during hoisting and installation. Check carefully handling tool before shaft hoist, such as halyard,eye plate, shackle should be safe and reliable.2.適用范圍: Range of application: 本工藝適用與12#57000DWT散貨船軸系安裝及主機(jī)定位施工。 This procedure is to be applied for instruct the shaft installation and M/E locatin
7、g for 12# 57000DWT bulk carrier. 3.參考資料: Reference documents: SC4439(ZS)G3-400-04 機(jī)艙布置圖 E/R Arrangement drawing SC4439(ZS)G3-425-01 推進(jìn)軸系布置圖 Shaft arrangement drawing SC4439(ZS)G3-230-02 舵系布置圖 Rudder arrangement drawing SC4439(ZS)-425-002-00 艉軸管總圖 General drawing of stern tubeSC4439(ZS)-420-001-00 主機(jī)
8、安裝圖 Installation drawing for M/ESC4439(ZS)-107-001 螺旋槳圖 Propeller drawing CB/T 4000-2005 中國造船質(zhì)量標(biāo)準(zhǔn) China Shipbuilding Quality Standard 4.工裝設(shè)備 Frock Equipment 激光經(jīng)緯儀、拉線架4套、鉛錘1只、重錘1只(25kg)、琴鋼絲(0.5mm)、鋼直尺、50m卷尺、常用鉗工工具等。 Laser instrument、 4 draw line frames、1 plumb、a heavy(25kg)、0.5mm steel wire、steel rul
9、er、50m tape ruler、normal locksmith tools etc. 5. 軸系精拉線條件: Shaft final draw wire preconditions:5.1機(jī)艙前壁(FR35)以后,主甲板以下主要結(jié)構(gòu)焊接工作已完成,火工矯正工作結(jié)束。機(jī)艙內(nèi)部的船體艙、柜的焊接打磨密性試驗(yàn)交驗(yàn)完畢。 Welding job of structures that after fore bulkhead (FR35) of E/R and below main deck almost finished, and the fire correction job finished.
10、 The structure tanks in E/R welding、grinding job and tightness test finished.5.2軸系區(qū)域內(nèi)主要輔機(jī)機(jī)座裝焊完成,除主機(jī)及舵機(jī)以外的大型設(shè)備(3t及以上)及底部單元等進(jìn)艙就位。In the area around shaft line, the auxiliary engine seat to be welded completely, all the big equipments (over 3 ton) and assembly units on position except M/E、steering gear
11、. 5.3 船體墊墩、支柱受力均勻、穩(wěn)定牢固,不允許隨意移動。 Frusta and support below structure bear even strength. Must be sure they are steady and without movement.5.4軸系精拉線要求在不受陽光曝曬及無急劇溫度變化情況下進(jìn)行,一般在晚間或陰天時進(jìn)行,以避免船體變形影響軸系中心線的正確性。Shaft draw wire job should be carried out on the condition of without sunshine and the temperature sh
12、arp change. Usually should carry out in evening or cloudly day, avoid hull deflection impact the shaft center line position.5.5 停止引起振動的作業(yè)與有嚴(yán)重噪聲干擾的作業(yè)。 Stop the vabriation and loud job.5.6 定位所用的激光經(jīng)緯儀以及測量工具應(yīng)經(jīng)相應(yīng)檢驗(yàn)部門校驗(yàn)合格。 The laser instrument and all the measure tools to be checked out by inspect dept. 6
13、. 軸系精拉線前的準(zhǔn)備: Preparation of shaft final draw wire:6.1實(shí)船基準(zhǔn)線的確定 Base line determine 6.1.1測量龍骨變形量,計算龍骨平均高度點(diǎn),作為船體實(shí)船基線。 Measure the deformation of keel calculate the even height of keel as the base line height.6.1.2測量實(shí)船中心線偏差量,并在尾封板及機(jī)艙前橫艙壁的區(qū)域塢底平面上勘劃出實(shí)船中線面的投影線,作為軸線在塢底平面的投影線。 Measure the actual center line
14、and mark the center line projection line on the dry dock below E/R area, the line is shaft line projection line.6.2軸系中心線的確定 Shaft center line determine6.2.1船體尾部理論軸中心面的確定 Stern part shaft center profile determinea,以中心線在塢底的延伸點(diǎn)為基準(zhǔn),調(diào)整激光經(jīng)緯儀”1”的軸線直至與船中心線重合。 Take the center line projection line on dock flo
15、or as benchmark adjust laser machinery No.1 until the axial line of laser crossed with benchmark.b,將激光經(jīng)緯儀“1”射出的光點(diǎn)延伸到尾部拉線架“B”上,并在垂直方向向上平移,同時測量此光點(diǎn)到塢底的垂直距離,當(dāng)測定的距離等于船體軸線到船臺的距離時(即:軸系中心線的高度為3300+外板厚度+塢墩高度),則此點(diǎn)為軸系中心線上一點(diǎn)。以此點(diǎn)作為參考點(diǎn)并打好樣沖點(diǎn),同時將激光經(jīng)緯儀旋轉(zhuǎn)180°將光點(diǎn)投射到后艉管支撐套后端面上,并打好樣沖,這樣就可初步確定軸系尾部理論面。 Extend the la
16、ser from No.1 machine on the wire frame “B” and move the laser point up, meantime measure the vertical distance form dock bottom to the laser point, during the distance same as shaft center line to dock bottom height stop movement, we can confirm that this point on the theory shaft center line. Take
17、 this point as benchmark and punch it on frame. Turn lasher head 180°and punch the lasher point on stern bossing aft. face, at present the stern shaft profile has been determined. 6.2.2機(jī)艙內(nèi)軸系中心線的確定 Shaft center line determine in E/Ra,在機(jī)艙Fr21附近位置設(shè)立一激光經(jīng)緯儀”2”,將光點(diǎn)延伸到船體外部的拉線架“B”,使之與拉線架上的樣沖點(diǎn)重合。 Arrang
18、e one laser machine “2” around Fr21 in E/R, extend laser on the wire frame B, until the laser point just superposed with the punch mark.b,調(diào)整激光經(jīng)緯儀2的位置,使之既能與船體尾柱上的樣沖點(diǎn)的連線相交,同時也能投影到艉部拉線架上的樣沖點(diǎn)上,然后將經(jīng)緯儀的位置固定。 Adjust laser head(2) position until the laser point crossed with the connect line between punch ma
19、rk on stern bossing aft. face, and the laser point also superposed with the punch mark on frame B, fix the laser machine position.6.2.3軸系中心線的延伸 Extend the shaft center linea,將激光經(jīng)緯儀2調(diào)轉(zhuǎn)1800,將光點(diǎn)延伸并投影在機(jī)艙FR31拉線架上,并確定光點(diǎn)位置,打好樣沖點(diǎn),這點(diǎn)與艉部拉線架上的樣沖點(diǎn)的連線即為理論軸線。 Turn lasher head(2)1800 extend lasher point on FR31 fr
20、ame A, and punch it. Then connection line between the punch point on frame A&B is the theory shaft center line.6.3根據(jù)船舶設(shè)計理論軸系中心線,在軸系艏艉端確定基準(zhǔn)點(diǎn),拉線時以此為基準(zhǔn)?;鶞?zhǔn)點(diǎn)坐標(biāo)分別為:艏點(diǎn)A(Fr31,CL±0,BL+3300),艉點(diǎn)B(Fr-5-2000,CL±0,BL+3300),見附圖。各基準(zhǔn)點(diǎn)在現(xiàn)場確定后報驗(yàn)船東船檢。 According to the theory shaft line position determine t
21、he fore and after datum mark. The coordinate of two datum marks is: Fore point A(Fr31,CL±0,BL+3300),Aft. point B(Fr-5-2000,CL±0,BL+3300), see attached drawing. Two datum marks point position should be confirmed by owner and surveyor. 6.4 通過艏艉基準(zhǔn)點(diǎn)拉線,檢查FR13#艙壁艉管孔的直徑理論值應(yīng)為900,并根據(jù)軸系理論中心線檢查此開孔的偏心
22、情況,在艙壁靠船首面劃出1130的檢驗(yàn)圓以及圓孔的正交十字線,用洋沖標(biāo)記。 Through the two datum mark points pull steel wire as shaft center line. According to this line check the stern tube hole on FR13# bulkhead, the theory diameter is900, check eccentricity of the hole, draw a1130 reference round and the cross line with punch mark.6
23、.5在軸系基準(zhǔn)點(diǎn)A后端,設(shè)立拉線架平臺,用來安放儀器和人員站立。 After the target A arrange one platform for the wire frame.6.6 艉管裝置在車間平臺時應(yīng)找正前后端面圓孔的中心,并劃十字線標(biāo)記。前后艉管端面十字線交叉點(diǎn)的連線即為艉管的理論中心線。完成后需交船東船檢認(rèn)可。 Find the center of fore and after hole of stern tube, and make cross line mark on the end surface. The two center point connect line i
24、s the theory center line of stern tube. The center point should confirmed by owner and surveyor.6.7艉管就位Install the stern tube 6.7.1按“艉管總圖(425-02-00)”將八只艉管調(diào)整螺栓預(yù)先布置到相應(yīng)位置處, 其中四只在艉柱中,另外四只安裝在FR13#艙壁船尾側(cè)。According to general drawing of stern tube(425-02-00), previously place eight stern tube adjustable bol
25、ts to relative position.The after four bolts in stern bossing, the other four installed on the aft. side of FR13# bulkhead.6.7.2按“艉管總圖(425-02-00)”焊好后艉柱上的兩個透氣管及一個注入管.注入管及透氣管均采用27X2.5無縫鋼管.鋼管上應(yīng)無任何油漆,油污等。According to general drawing of stern tube(425-02-00),weld two vent pipes on aft stern tube support
26、cover and one immit tube.Immit and vent tube all adopt27X2.5 seamless steel pipe. No any paint and dirty on steel pipe.6.7.3栓查艉管清潔, 艉柱內(nèi)表面及艉管外表面等與環(huán)氧樹脂接觸處(含澆注孔,透氣孔內(nèi)表面)均需清除鐵銹、油污、毛刺、焊渣、油漆和灰塵等。提交環(huán)氧服務(wù)工程師及船東檢查清潔度。 Check stern tube cleanness. Contact part of stern tube front & aft support cover inner fa
27、ce and stern tube outside face with epoxy resin(include spraying hole,vent hole inner face)need clean rust,oil dirty,burr,welding dregs,painting and dust.Submit epoxy service engineer and owner to check cleanness and can satisfy the requirement.6.7.4將艉管吊起送入艉柱中并向艏移動,在移動過程中注意保持艉管外表面和艉柱內(nèi)表面清潔,并用丙酮清洗?,F(xiàn)場需
28、由環(huán)氧服務(wù)工程師及船東監(jiān)控,當(dāng)?shù)竭_(dá)艉管裝置圖中所示位置時,重新檢查艉管外表面和艉柱內(nèi)表面清潔度,提交環(huán)氧服務(wù)工程師及船東檢查清潔度。 Hoisting the stern tube and move it to forward in stern bossing, during the transport please keep the surface cleanness and clean it use acetone. The chock fast service engineer and owner inspect on site, during the stern tube on pos
29、ition recheck the cleanness and submit to service engineer and owner check.6.7.5擰入艏艉處的調(diào)節(jié)螺栓將艉管撐起, 撤去起吊艉管所用的輔助工具。 Stern tube will be raised by screwing adjustment bolt of fore and after,and remove all auxiliary tools that sling stern tube.7. 拉線調(diào)整定位艉管: Draw wire and adjust the position of stern tube:7.
30、1在理論軸線前后端拉線架上用0.5mm琴鋼絲穿過前后艉軸管拉出理論軸線,鋼絲自由端掛25kg重錘。 Pull shaft line on wire frame use 0.5mm steel wire, at the aft. side hang a 25kg heavy. 7.2調(diào)節(jié)鋼絲線位置,使其穿過A和B兩個基準(zhǔn)點(diǎn),檢查確定后報驗(yàn)船東船檢。Adjust the steel wire until it through the two benchmark A and B, then submitted to ship owner and surveyor for approval.7.3用艏
31、艉調(diào)整螺栓精調(diào)艉管位置,使前后端艉管中心均在軸系理論中心線上(考慮撓度值)。并且調(diào)整艉管后端面距艉柱后端面距離為75mm,允許誤差±2mm。擰緊頂絲螺栓,固定艉管,報驗(yàn)船東船檢。 Adjust the stern tube position use the adjust bolts, until the stern tube target center on the shaft center line. And adjust the distance between stern tube after end to stern bossing end, the distance sho
32、uld be 75mm, the allowable tolerance is ±2mm. Fix the stern tube by the adjust bolts, submit to owner and surveyor check.琴鋼絲撓度計算公式如下:The deflection formula as following, Y = q·X·(L-X) / (0.99*2G)式中: Y鋼絲線上X一點(diǎn)撓度(m)In the formula: Y - the flexibility of point X on the steel wire (m).q鋼絲線
33、單位長度重量q/m,0.5mm鋼絲線取1.59g/mq-unit length weight of steel wire q/m, 1.59g.m per 0.5mm steel wire.X所求撓度點(diǎn)到基準(zhǔn)點(diǎn)距離(m)X-distance between calculation point to the benchmark(m)L鋼絲兩基準(zhǔn)點(diǎn)間的距離(m)L-the distance between the benchmark on steel wire(m).G鋼絲拉力(kg)G-pull strength on steel wire(kg).7.4檢查艉管與艉柱之間的最小間隙,采用動力泵
34、澆注環(huán)氧最小允許間隙為3mm. Check the clearance between stern tube and stern bossing, adopt the pump pouring chock fast the minimum clearance is 3mm.7.5檢查軸系中心線到主機(jī)基座面板的高度,此高度實(shí)際測量值應(yīng)在1135mm左右,檢查主機(jī)基座兩側(cè)的偏中情況,中心線到基座邊緣的距離應(yīng)為1095mm,若以上尺寸實(shí)測偏差過大需及時通知技術(shù)部門核對。 Check the vertical distance between shaft center line to M/E foun
35、dation top, measured distance should around 1135mm. Check the width from shaft center line to M/E foundation side, the width should be 1095mm. If the above result with big deviation please inform technical dept. in time. 7.6吊舵系中心線,檢查舵線與軸線的相交情況,以及舵線到艉管末端的距離,尺寸應(yīng)滿足“TCN124P-M012-GY01軸舵系初拉線工藝”中第10.3的要求。
36、Hang the rudder center line, check the relative position between rudder center line and shaft center line,and the distance between rudder line to stern tube end. The dimension should within the tolerance of item 10.3 in “TCN124P-M012-GY01 Preliminary alignment procedure for shaft & rudder”.7.7檢查
37、軸線到中間軸承基座面板的垂直高度(不包含墊塊高度),理論值為500mm,為保證活動墊塊的厚度50mm(按照設(shè)備說明書要求),垂直高度應(yīng)500mm且小515mm。 Check the vertical height between shaft center line to intermediate bearing seat face plate (not include pad height) theory value should be 500mm. In order to keep the moveable pad thickness 50mm(according to equipment
38、spec. requirement), the vertical height should 500mm and 515mm.7.8按照附圖尺寸確定主機(jī)滑油回油孔的開孔位置,開孔前應(yīng)檢查到貨主機(jī)油底殼上開孔尺寸是否與圖紙相符,確定無誤后方能開孔。 According to the attached drawing dimension determine the M/E LO return hole position, before open hole check the hole dimension on M/E follow attached drawing, after confirmed
39、 do the cut job.8. 安裝艉管總成加強(qiáng)板: Install the stern tube reinforcement plate:8.1艉管總成吊裝上船以后,先按照艉管總圖(SC4439(ZS)-425-02-00)將加強(qiáng)板(SC4439(ZS)-425-02-14)焊在艉管總成前端艉管座上。 After stern tube on position, according to stern tube general drawing (SC4439(ZS)-425-02-00) weld reinforcement plate on stern tube forward boss
40、ing.8.2按照圖紙將加強(qiáng)板與FR13艙壁焊接,按右圖所示,分段、對稱施焊。在焊接過程中必須打表隨時監(jiān)測焊接的變形情況,使得焊接完成時艉管艏艉部的中心仍在軸系中心線上,允許偏差0.50mm。According to the drawing weld the reinforcement plate on the FR13# bulkhead, symmetric weld as the right picture. Check and control the deformation during welding, keep the stern tube center still on the
41、shaft center line after weld, allowable deflection 0.50mm.9. 艉管總成的環(huán)氧澆鑄: Chock fast of stern tube:見艉管環(huán)氧澆注工藝。See stern tube chock fast procedure. 環(huán)氧澆注24h后,復(fù)核艉管總成的位置,將測量結(jié)果填入下檢驗(yàn)表中。 24 hours after chock fast recheck the position of stern tube, fill the result in the below list.偏差方向Direction位置Position上up下
42、Down左left右right尾管前中心Stern tube fore center尾管后中心Stern tube aft. center10. 主機(jī)底角螺栓孔定位開孔: Locating of M/E holding down bolts:10.1以A,B兩點(diǎn)為基準(zhǔn),用0.5mm鋼絲拉出軸系理論中心線,A點(diǎn)掛重25kg。 According to the A&B datum marks pull 0.5mm steel wire as the shaft center line, at A point hung a 25kg heavy.10.2在主機(jī)座槽中裝焊臨時支架,將軸系中心線
43、引至臨時支架上平面,并以此為基準(zhǔn)按照主機(jī)安裝圖中的尺寸,在兩側(cè)基座面板上劃出兩列主機(jī)地腳螺栓孔的中心連線,如下圖所示。 Install the temporary support in M/E seat groove as below drawing, mark the shaft center line projection on the support. According to the marked wire draw two arrange line of holding down bolts center connect line. As below drawing.10.3以艉管后
44、端面為基準(zhǔn)確定主機(jī)第6缸中心位置,沿鋼絲線向前測量,艉管后端面到6缸中心的理論距離為12325±1mm(該尺寸為理論值,實(shí)際尺寸待螺旋槳與螺旋槳軸在車間預(yù)壓后確定),采用吊線錘的方法找出主機(jī)第6缸中心投影點(diǎn),在臨時支架上穿過此點(diǎn)劃出與船中線的垂線,并延長與兩列主機(jī)地腳螺栓孔的中心連線相交。 Determine the No.6 cyl. center position measured from stern tube after end side, the theory distance should be 12325±1mm(the actual distance dec
45、ide by the propeller and propeller shaft pre-installation test result in workshop), use the plumb find out the projection point of No.6 cyl. center on temporary support. Through this point draw the vertical line with ship center line, and prolong the vertical line crossed with holding down bolts cen
46、ter connect line.10.4根據(jù)主機(jī)安裝圖,采用常規(guī)方法劃出主機(jī)全部地腳螺栓孔的中心位置,打硬記。然后對照主機(jī)安裝圖,采用縱向、橫向、以及對角測量的方法,反復(fù)校對,以確保全部地腳螺栓孔位置的準(zhǔn)確無誤。 According to engine installation drawing draw out the center position of all engine holding down bolts hole with punch mark. Then follow the engine installation drawing, measure each distance
47、from longitudinal、transverse and crossed direction, in order to ensure the correct position of all holding down bolts hole.10.5檢查艏、艉兩端螺栓孔中心對角間距,理論值應(yīng)為6436mm,允許偏差±2mm。復(fù)核全部螺栓孔的縱、橫向尺寸,縱向兩孔間誤差±0.5mm,橫向兩孔間誤差±1mm確保準(zhǔn)確無誤,縱向累積誤差±2mm。 Check the fore and after end bolts cross connect line le
48、ngth, theory distance should be 6436mm, allowable tolerance ±2mm. Recheck all the holding down bolts position, tolerance between two holes on longitudinal direction ±0.5mm, on the transverse direction ±1mm, cumulate tolerance on longitudinal direction ±2mm.10.6根據(jù)已劃好的底腳螺栓孔的中心點(diǎn),劃出全
49、部地腳螺栓孔的加工圓線46 mm、檢查圓線66mm,打硬記。 According to the marked center point of holding down bolt holes, draw the drilling hole 46 mm and reference round 66mm and marked on M/E seat.10.7加工出全部460+2.0mm的地腳螺栓孔,修除毛刺打磨光順。 Drill all the holding down bolts hole 460+2.0mm and grinding.10.8鉆孔作業(yè)后,須檢查主機(jī)機(jī)座下橫向加強(qiáng)板的位置,是否會影
50、響螺栓螺母的安裝。消除反面毛刺,以保證安裝時的良好貼合。 After drilling check the transverse reinforce plate below M/E seat plate, confirm whether the plate will impact install bolts and nuts. Remove the burr on the opposite side, ensure the nut surface M/E seat opposite side with good contact. 10.9回油管開孔時,應(yīng)核對主機(jī)油底殼與圖紙的正確性。 Befo
51、re open the return oil pipe hole on lube oil circulation tank must confirm the opening position on M/E sump bottom same as the drawing.11. 塞螺旋槳軸: Insert propeller shaft:11.1艉軸由機(jī)艙內(nèi)向艉管塞入,在裝軸之前,根據(jù)螺旋槳軸后端的螺紋,制造一個螺紋連接的導(dǎo)向帽,以免在塞軸的時候碰壞軸承內(nèi)的白合金。 Insert the propeller shaft into stern tube form E/R, during inser
52、t the propeller shaft the shaft end screw should covered by a smooth hat, avoid crashed with white metal bearing.11.2尾軸安裝前,艉管內(nèi)孔包括后軸承內(nèi)表面應(yīng)清潔,清潔程度要得到船東認(rèn)可,裝入時應(yīng)涂潤滑劑。 Before install the propeller shaft clean the shaft and bearing inner side and daub lube oil, the cleanness should confirmed by owner.11.3艉軸塞入時,首密封裝置及密封墊圈已套裝在尾軸上。 The forward shaft seal and the gasket should be move on shaft before insert shaft.11.4如下圖,在
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 圭亞那機(jī)場跑道安全改造施工方案
- 城市擋土墻基礎(chǔ)工程施工方案
- 遠(yuǎn)程醫(yī)療咨詢預(yù)約制度
- 零售企業(yè)員工晉升制度的創(chuàng)新實(shí)踐
- 鋁塑板墻面保溫施工方案
- 地鐵站臺加固施工方案
- 農(nóng)村農(nóng)產(chǎn)品直銷方案
- 石淋病護(hù)理隨訪方案
- 自動化測試工具開發(fā)驗(yàn)收方案
- 公共交通疫情防控運(yùn)營方案
- 《初中英語寫作》課件
- DB37-T 5202-2021 建筑與市政工程基坑支護(hù)綠色技術(shù)標(biāo)準(zhǔn)
- 牙科手機(jī)的清洗消毒、滅菌及保養(yǎng)課件
- 人音版二年級下冊音樂《小蜜蜂》課件
- 打印版醫(yī)師執(zhí)業(yè)注冊健康體檢表(新版)
- 湘教版八年級美術(shù)上冊工作計劃
- 高滲性非酮癥糖尿病昏迷培訓(xùn)課件
- 國開成本會計第15章綜合練習(xí)試題及答案
- 2022年陜西投資集團(tuán)有限公司招聘筆試題庫及答案解析
- 醫(yī)院產(chǎn)后出血的應(yīng)急演練腳本
- 基于實(shí)驗(yàn)驗(yàn)證并發(fā)現(xiàn)以太
評論
0/150
提交評論